Professional Documents
Culture Documents
Module 4. Soil Compaction
Module 4. Soil Compaction
Module 4. Soil Compaction
1. Earthwork must not create slope stability problems (i.e., landslides). This is especially important in hilly
and mountainous areas, since the level building pads or road alignments created by the earthwork
are possible only because nearby areas are made steeper and thus less stable.
2. Fills must have sufficient shear strength to support both their own weight and external loads, such as
foundations or vehicles. Lack of sufficient strength can produce landslides, bearing capacity failures,
and rutting of pavements.
3. Fills must be sufficiently stiff to avoid excessive settlement. Soft fills permit foundations to settle
excessively, thus damaging buildings, and often produce undesirable changes in surface drainage
patterns.
4. Fills must continue to satisfy requirements 2 and 3, even if they become wet.
5. Some fills, such as the core of earth dams or liners for sanitary landfills, must have a sufficiently low
hydraulic conductivity1 to restrict the flow of water. Others, such as aggregate base material below
pavements, must have a high hydraulic conductivity to drain water away from critical areas.
6. In areas prone to frost heave (a heaving that occurs when the ground freezes), it is sometimes
desirable to have fills made of soils that are not frost-susceptible.
EARTHWORK
CONSTRUCTION METHODS ANO EOUIPMENT
Design engineers need to have a good understanding of construction methods and equipment, because
the way something is built often has a significant impact on how it must be designed. This is especially true
for geotechnical engineers, because we are usually involved in both the design and construction phases
of a project.
➢ Moisture Conditioning
The soil must be at the proper moisture content before it
is compacted. Soils that are too wet or too dry will not
compact well. Usually the moisture content is not correct
and needs to be adjusted accordingly. If the soil is too
dry, this is usual! y done by spraying it with a water truck,
as shown in Figure. A bulldozer or other equipment is then
used to mix the soil so the water is uniformly distributed.
➢ Compaction
The next step is to compact the lift.
Compaction is the use of equipment to
compress soil into a smaller volume, thus
increasing its dry unit weight and improving
its engineering properties. The solids and
water are virtually incompressible, so
compaction produces a reduction in the
volume of air. Three phase diagrams showing the changes in soil as it moves
from its natural location to a compacted fill.
EARTHWORK
The necessary compaction of subgrades of roads, earth fills, and embankments may be obtained by
mechanical means. The equipment that are normally used for compaction consists of
➢ In cohesionless sands and gravels, vibrating type equipment is effective in producing densities up to
100 percent of modified Proctor. Where densities are needed in excess of 100 percent of modified
Proctor such as for base courses for heavy duty air fields and highways, rubber tired rollers with tire
loads of 130 kN and above and tire pressure of 1000 kN/m2 can be used to produce densities up to 103
to 104 percent of modified Proctor.
SOIL COMPACTION STANDARDS AND ASSESSMENT
For geotechnical engineers, soil compaction is one of the most important parts of earthwork
construction. Compaction improves the engineering properties of the fill in many ways, including:
❑ Increased shear strength, which reduces the potential for slope stability problems, such as landslides,
and enhances the fill' s capacity for supporting loads, such as foundations.
❑ Decreased compressibility, which reduces the potential for excessive settlement.
❑ Decreased hydraulic conductivity, which inhibits the flow of water through the soil. This may be
desirable or undesirable, depending on the situation.
❑ Decreased void ratio, which reduces the amount of water that can be held in the soil, and thus helps
maintain the desirable strength properties.
❑ Increased erosion resistance, which helps maintain the ground surface in a serviceable condition
Proctor Compaction Test
During the 1930s, Mr. R. R. Proctor, an engineer with the City of Los Angeles, developed a method of
assessing compacted fills that has since become a nearly universal standard (Proctor, 1933). This method
consists of compacting the soil in the laboratory to obtain the maximum dry unit weight, (𝜸𝒅 )𝒎𝒂𝒙 then
requiring the contractor to achieve at least some specified percentage of this value in the field. The
original version of the laboratory test is now known as the standard Proctor test, while a later revision is
called the modified Proctor test. The dry unit weight achieved in the field is determined using several
types of field density tests.
SOIL COMPACTION STANDARDS AND ASSESSMENT
Standard Proctor Test (ASTM designation D-698)
SOIL COMPACTION STANDARDS AND ASSESSMENT
Standard Proctor test procedure
l. Obtain a bulk sample of the soil to be used in the compacted fill and
prepare it in a specified way.
2. Place some of the prepared soil into a standard 1/30 ft3 (9.44x10-4 m3 )
cylindrical steel mold until it is about 40 percent full. This mold is shown
in Figure
3. Compact the soil by applying 25 blows from a special 5.5-lb (2.49-kg)
hammer that drops from a height of 12 in (305 mm).
4. Place a second layer of the prepared soil into the mold until it is about
75 percent full and compact it using 25 blows from the standard
hammer.
5. Place the third layer of the prepared soil into the mold and compact it
in the same fashion. Thus, we have applied a total of 75 hammer blows.
6. Trim the sample so that its volume is exactly 1/30 ft3, then weigh it. The
unit weight, , is thus:
SOIL COMPACTION STANDARDS AND ASSESSMENT
When using English units, is expressed in lb/ft3 • With SI units, use kN/m3 , which requires
converting kg to kN (1 kN = 102.0 kg).
7. Perform a moisture content test on a representative portion of the compacted sample, then compute
the dry unit weight, 𝛾𝑑 .
8. Repeat steps 2-7 three or four times, each with the soil at a different moisture content.
❑ Before drawing the compaction curve, it is best to first draw two other curves:
One representing S = 100% (sometimes called the zero air voids curve), and the other representing
S= 80%, as shown in Figure. These two curves can be developed using the equation,
and are intended to help us draw the Proctor compaction curve. The S= 100% curve represents an
upper limit for the Proctor data, for it is impossible to have S> 100%. The S= 80% curve should go nearly
through the peak in the Proctor curve. In addition, the right limb of the Proctor curve should be slightly
to the left of S = 100%, because compaction does not remove all of the air.
Problem 1
A Proctor compaction test has been performed on a soil sample . The test results were as follows:
SOIL COMPACTION STANDARDS AND ASSESSMENT
The mass of the compaction mold was
2.031 kg. The moisture content tests
were performed on small portions of the
compacted soil samples.
a. Compute 𝛾𝑑 and 𝑤 for each data
point and plot these results
b. Develop and plot curves for S= 80%
and S= 100% using a specific gravity
of 2.69.
c. Using the data from steps a and b,
draw the Proctor compaction curve
and determine (𝛾𝑑 )𝑚𝑎𝑥 and 𝑤𝑜 .
Solution 1
a. Computations for data point no. 1:
b. Using the equation, solve values of 𝛾𝑑 in the range of test data from step a and compute the
corresponding values of 𝑤 for S= 80% and 100%:
SOIL COMPACTION STANDARDS AND ASSESSMENT
c. Plot the data points from part a and the curves from
part b, then draw the compaction curve as shown in
Figure.
Answers
SOIL COMPACTION STANDARDS AND ASSESSMENT
Problem 2
A proctor compaction test was conducted on a soil sample, and the following observations were made
Water content, percent 7.7 11.5 14.6 17.5 19.7 21.2
Mass of wet soil, g 1739 1919 2081 2033 1986 1948
If the volume of the mold used was 950 cm3 and the specific gravity of soils grains was 2.65, make
necessary calculations and draw, (i) compaction curve and (ii) 80% and 100% saturation lines
Solution 2
From the known mass of the wet soil sample and volume of the mold, wet density or wet unit weight is
obtained by the equations,
Then from the wet density and corresponding moisture content, the dry density or dry unit weight is
obtained from,
Thus for each observation, the wet density and then the dry density are calculated and tabulated as
follows:
SOIL COMPACTION STANDARDS AND ASSESSMENT
Water content, percent 7.7 11.5 14.6 17.5 19.7 21.2
Mass of wet sample, g 1739 1919 2081 2033 1986 1948
Wet density, g/cm3 1.83 2.02 2.19 2.14 2.09 2.05
Dry density, g/cm3 1.70 1.81 1.91 1.82 1.75 1.69
Dry unit weight kN/m3 16.7 17.8 18.7 17.9 17.2 16.6
Hence the compaction curve, which is a plot between the dry unit weight and moisture content can be
plotted as shown in the Fig. The curve gives,
Maximum dry unit weight, MDD = 18.7 kN/m3 Optimum moisture
content, OMC = 14.7 percent
For drawing saturation lines, make use of Eq.,
where, Gs = 2.65, given, S = degree of saturation 80% and 100%, w = water content, may be assumed
as 8%, 12%, 16%, 20% and 24%.
Hence for each value of saturation and water content, find 𝛾𝑑 , and tabulate:
Water content, percentage 8 12 16 20 24
𝛾𝑑 kN/m3 for S = 100% 21.45 19.73 18.26 17.0 15.69
𝛾𝑑 kN/m3 for S = 80% 20.55 18.61 17.00 15.64 14.49
With these calculations, saturation lines for 100% and 80% are plotted, as shown in the Fig. Also the
saturation, corresponding to MDD = 18.7 kN/m3 and OMC = 14.7% can be calculated as,
SOIL COMPACTION STANDARDS AND ASSESSMENT
Test Procedure
A soil at a selected water content is placed in five layers into a mold of given dimensions, with each
layer compacted by 25 or 56 blows of a 10 Ib (4.54 kg) hammer dropped from a height of 18 in. (457
mm) subjecting the soil to a total compactive effort of about 56,250 ft-lb/ft3 (2700 kN-m/m3 ).
SOIL COMPACTION STANDARDS AND ASSESSMENT
The resulting dry unit weight is determined. The procedure is repeated for a sufficient number of water
contents to establish a relationship between the dry unit weight and the water content for the soil. This
data, when plotted, represents a curvilinear relationship known as the compaction curve or moisture-dry
unit weight curve. The value of the optimum water content and maximum dry unit weight are
determined from the compaction curve as shown in Fig.
SOIL COMPACTION STANDARDS AND ASSESSMENT
Problem 3
A small cylinder having volume of 600 cm3 is pressed into a recently compacted fill of embankment filling
the cylinder. The mass of the soil in the cylinder is 1100 g. The dry mass of the soil is 910 g. Determine the
void ratio and the saturation of the soil. Take the specific gravity of the soil grains as 2.7.
Water content,
Once the maximum dry unit weight has been established for the soil being used in the compacted fill, we
can express the degree of compaction achieved in the field by using the relative Compaction, CR:
SOIL COMPACTION STANDARDS AND ASSESSMENT
where:
Most earthwork specifications are in terms of the relative compaction, and require the contractor to
achieve at least a certain value of CR . For example, if a certain soil has (𝛾𝑑 )= 120 lb/ft3 and the
project specifications require CR = 90%, then the contractor must compact the soil until 𝛾𝑑 =108 lb/ft 3
A comparison among the three compaction quality control tests is shown in Table 5.2.
SOIL COMPACTION STANDARDS AND ASSESSMENT
SOIL COMPACTION STANDARDS AND ASSESSMENT
Problem 4
A sand cone test has been performed in a compacted fill made with the soil described in Problem 1. The
test results were as follows:
Initial mass of sand cone apparatus = 5.912 kg
Final mass of sand cone apparatus = 2.378 kg
Mass of soil recovered from hole= 2.883 kg
Moisture content of soil from hale = 7.0%
Density of sand = 1300 kg/m3
Vo1ume of cone below valve = 1.114 x 103 m3
The project specifications require a relative compaction of at least 90%.
Compute 𝛾𝑑 and 𝐶𝑅 and determine whether the project specifications have been met. If not, suggest a
course of action.
Solution 4
SOIL COMPACTION STANDARDS AND ASSESSMENT
Conclusion and Recommendation The relative compaction is less than the required 90%, so the
specifications have not been met. This may be at least partially due to the low moisture content, which
is well below optimum. Suggest ripping the soil, adding water, mixing, and recompacting.
Problem 5
A balloon-type apparatus is sued to determine an in-place unit weight for a soil (field density test). The
volume of the test hole determined by reading the water level graduations on the apparatus cylinder
before and after digging the test hole is 0.000708 m3. The wet weight of soil obtained from the test hole is
1410 g. The soil sample was dried on a field stone and weighs 1237 g.
a. Compute the water content of the tested soil.
SOIL COMPACTION STANDARDS AND ASSESSMENT
b. Compute the in-place dry unit weight of the tested soil.
c. Determine the percentage of compaction for the test result if the soil is part of a compacted earth fill
whose maximum unit weight (from laboratory compaction tests) is 18.57 kN/m3.
Solution 5 𝛾𝑚𝑜𝑖𝑠𝑡
𝛾𝑑𝑟𝑦 =
a. water content of the tested soil 1+𝑤
19.54 𝑘𝑁/𝑚3
1410 − 1237 𝛾𝑑𝑟𝑦 = = 17.14 𝑘𝑁/𝑚3
𝑤= = 0.14𝑥100% = 14% 1 + 0.14
1237
c. Percentage of compaction
b. In-place dry unit weight of the
tested soil 17.14(100)
% 𝑜𝑓 𝑐𝑜𝑚𝑝𝑎𝑐𝑡𝑖𝑜𝑛 =
1410 3
18.57
𝜌𝑚𝑜𝑖𝑠𝑡 = = 1991.5 𝑘𝑔/𝑚
0.000708 % 𝑜𝑓 𝑐𝑜𝑚𝑝𝑎𝑐𝑡𝑖𝑜𝑛 = 92.3%
3
1991.5 𝑘𝑔/𝑚 (9.81𝑘𝑁/𝑚 )3
3
𝛾𝑚𝑜𝑖𝑠𝑡 = = 19.54 𝑘𝑁/𝑚
1000 𝑘𝑔/𝑚3
Problem 6
During construction of a soil embankment, a sand cone in-place density test was performed in the field.
The following data were obtained:
1. Weight of sand used to fill test hole and funnel of sand-cone device = 867 g.
2. Weight of sand to fill funnel = 319 g.
SOIL COMPACTION STANDARDS AND ASSESSMENT
3. Unit weight of sand = 98.0 lb/ft3.
4. Weight of wet soil from the test hole = 747 g.
5. Moisture content of soil from test hole as determined by Speedy Moisture Tester = 13.7 %
Calculate the dry unit weight of the compacted soil.
Solution 6
Weight of sand used in test hole = weight of sand to fill test hole and funnel – weight of sand to fill funnel
Weight of sand used in test hole = 867 g – 319 g = 548 g
548 𝑔
453.6 𝑔/𝑙𝑏
Volume of test hole = = 0.0123 𝑓𝑡 3
98.0 𝑙𝑏/𝑓𝑡 3
747 𝑔
453.6 𝑔/𝑙𝑏
Wet unit weight of soil in-place= = 133.9 𝑙𝑏/ 𝑓𝑡 3
0.0123 𝑓𝑡 3
𝛾 133.9 𝑙𝑏/𝑓𝑡 3
𝛾𝑑 = 𝛾𝑑 = = 117.8 𝑙𝑏/𝑓𝑡 3
1+𝑤 1 + 0.137
3 𝑓𝑡 3 𝑙𝑏 1𝑇
c. 𝑊𝑠 = 𝑉𝛾𝑑 = (190 𝑦𝑑 3 ) 1 𝑦𝑑
(108 𝑡3
) 2000 𝑙𝑏
= 277 T
𝑊 = 𝑊𝑠 1 + 𝑊 = 277 T 1 + 0.091 = 302 T Answer
𝑙𝑑 3 𝑓𝑡 3
d. (𝑊𝑠 )𝑓𝑖𝑙𝑙 = (𝛾𝑑 )𝑓𝑖𝑙𝑙 (𝑉𝑓𝑖𝑙𝑙 ) = (114 𝑓𝑡 3 )(11,500 𝑦𝑑 3 = 35.4𝑥106 𝑙𝑏
1 𝑦𝑑
the weight of water to be added is the required increase in the moisture content, ∆𝑤 times the dry weight:
(𝑊𝑠 )𝑎𝑑𝑑𝑒𝑑 = ∆𝑤 𝑊𝑠 = 0.128 − 0.091 35.4𝑥106 𝑙𝑏 = 1.31𝑥106 lb
Volume of water to be added = 8 229 cu.m. a. Compute the volume of soil if taken from
Volume of water to be added in liters borrow pit C
= 8 229 000 L b. Compute the transportation cost of the
Problem 9 soil if taken at borrow pit B
An earth dam requires 1 million cu.m. of soil c. Which borrow pit would be the most
compacted to a void ratio of 0.80. In the vicinity of economical?
the proposed dam, three borrow pits were identified Solution 9
as having suitable materials. The cost of purchasing
a. Volume of soil from borrow pit C:
the soil and the cost of excavation are the same
EARTHWORK QUANTITY COMPUTATIONS
𝑉𝑐 1 + 𝑒𝑐 𝑉𝑐 1 + 1.5
= = = Borrow Volume Transportation Cost
𝑉 1+𝑒 1 𝑥 106 1 + 0.80 Pit Needed (Php)
(m3)
𝑉𝑐 = 1 388 888 𝑚3
A 1 555 555 1 555 555(0.60)= 933,333.00
b. Transportation const of soil if taken from borrow
pit B: B 1 055 555 1 055 555(1.00)=1,055,555.00
𝑉𝐵 1 + 0.9 3
C 1 388 888 1 388 888(0.75)=1,041,666
= = 1 055 555 𝑚
1(106 ) 1 + 0.80
Transportation cost = 1 055 555 (1) Most economical borrow pit is A
▪ The settlement problems with these deep fills stem from the following characteristics and processes:
EARTHWORK QUANTITY COMPUTATIONS
o The fills are very heavy, and thus induce large compressive stresses in the lower parts of the fill and in
the underlying soils.
o Loose natural soils were usually removed before placement of the fills, but these removals often were
not as extensive as they should have been.
o Although the fills were typically placed at a moisture content near optimum, they slowly became
wetter due to the infiltration of water from rain, irrigation, broken utility pipelines, and other sources.
o The wetting of the lower portions of the fill and the underlying natural soils often caused them to
compress, causing settlements that varied with the fill thickness. When such fills were placed in old
canyons, the thickness often changed quickly over short distances, thus causing large differential
settlements (i.e., differences in settlements) over short distances.
o If the fill was made of expansive soils, the wetting caused heaving in the upper zones, which
sometimes offset the compression of the underlying fill, and other times aggravated the differential
settlements.
These effects may be evaluated by conducting an appropriate laboratory testing program using the
proposed fill soils, then performing special analyses to predict the Iong-term settlements (Noorany,
Sweet, and Smith, 1992). Based on the results of such a testing and analysis program, we can develop a
design to keep fill settlements within tolerable limits.