Week - 1 : Assessment
• Tasks :
– Fit-Gap analysis Fit Gap Analysis document
– Scope Validation and Revisit Effort estimate
• Work Product
– Fit Gap Analysis document
– Scope Validation and
7
• Tasks
• Conduct Functional Design Workshops
• Conduct Technical Design Workshops
• Conduct Design Review
• Design – RICE objects, Dimensions, Interfaces
• Work Product
• Functional Design
• Technical Designs
• Approved Designs
• Inventory of Objects, Customizations & Interfaces changes
9
• Tasks
• Build & Unit Test
– Development
– Prepare Test cases
– Test Plans
– Release Documents
• Work Product
• Unit Test Cases & results
• SIT Plan & Test Cases
10
• Initial Configuration
– Setup Applications
– Prepare Validation Scripts
– Conduct Configuration Validation Workshops
– Update Setup Documentation
– Update Business Process Model
11
• Tasks
• Launch Prototype 1
• Unit Test (establish dimensions, meta data and other core design)
• Add Calculations
• Data integration – data loads, transformations
• Data interfaces – reports, forms, task lists
• System Integration Testing – Data Validation, SIT, Fix SIT Defects, Prepare
Data Validation reports, SIT Test Results
12
Work Products
• SIT Defect and resolution logs
• SIT test results
• SIT completion Report
• Data Validation report
13
Week – 11 : UAT