PROJECTWISE FINANCIAL PROGRESS (STATEMENT- I)

Quarterly Progress Report for the Quarter Ending SEPT 2021


Name of Project :- Kasola (St.) Taluka - Mangrulpir Distt- Washim ( Rs. in Crores )

Expen- Quarterwise Target and Achievement in 2021-22 Quarter


Expenditure in
diture Target Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending Ending
Sr. Updated Balance 2021-22 up to
Component of Project upto for 2021- June 21 Sept 21 Dec 21 March 22 Cumulative Remarks
No. Cost Cost SEPT -21
March 22 Expenditure
(8+10+12+14)
2021 Target Achieved Target Achieved Target Achieved Target Achieved (Col 4+15)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work --

1 Land Acquisition 3.59 3.59 -- -- -- -- -- -- -- -- -- -- -- 3.59

2 Earthwork 4.75 4.75 -- -- -- -- -- -- -- -- -- -- -- 4.75

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.39 0.39 -- -- -- -- -- -- -- -- -- -- -- 0.39

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --
2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --
3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --
D Miscelleneous 0.22 0.22 -- -- -- -- -- -- -- -- -- -- -- 0.22

E ETP 0.65 0.04 0.61 -- -- -- -- -- -- -- -- -- -- 0.04

Total 9.60 8.99 0.61 -- -- -- -- -- -- -- -- -- -- 8.99


Name of Project :- Kupta (St.) Taluka - MANORA Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Quarter
Cost diture Cost for 2021- 2021-22 up to
Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending Ending
Sr. upto 22 SEPT -21
Component of Project June 21 Sept 21 Dec 21 March 22 Cumulative
No. March (8+10+12+14)
Expenditure
2021
Target Achieved Target Achieved Target Achieved Target Achieved (Col 4+15)
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 4.03 4.03 -- -- -- -- -- -- -- -- -- -- -- 4.03

2 Earthwork 7.87 7.43 0.44 0.44 -- -- -- -- 0.44 -- 7.43

3 Concrete 0.21 0.21 -- -- -- -- -- -- -- -- 0.21

B Canal System 0.60 0.60 -- -- -- -- -- -- -- -- 0.60

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.50 0.23 0.27 0.26 -- -- -- -- 0.26 -- 0.23

E ETP 1.50 -- 1.50 -- -- -- -- -- -- -- --

Total 14.71 12.50 2.21 0.70 -- -- -- -- -- -- 0.70 -- -- 12.50


Name of Project :-Dhamni (St.) Taluka - KARANJA Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 12.31 12.31 -- -- -- -- -- -- -- -- -- 12.31

2 Earthwork 4.99 4.99 -- -- -- -- -- -- -- -- -- 4.99

3 Concrete 0.13 0.13 -- -- -- -- -- -- -- -- -- 0.13

B Canal System 0.57 0.57 -- -- -- -- -- -- -- -- -- 0.57

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous -- -- -- -- -- -- -- -- -- -- -- --

E ETP 0.84 -- 0.84 0.40 -- -- -- -- -- 0.40 -- --

Total 18.84 18.00 0.84 0.40 -- -- -- -- -- -- 0.40 -- -- 18.00


Name of Project :- Chandhai (St.) Taluka - Mangrulpir Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 5.03 5.03 -- -- -- -- -- -- -- -- -- 5.03

2 Earthwork 4.36 4.36 -- -- -- -- -- -- -- -- -- 4.36

3 Masonry -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.71 0.71 -- -- -- -- -- -- -- -- -- 0.71

5 Gate (For Barrages) -- -- -- -- -- -- -- -- -- -- -- --

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.05 0.05 -- -- -- -- -- -- -- -- -- -- -- 0.05

E ETP 0.58 -- 0.58 -- -- -- -- -- -- -- -- -- -- --

Total 10.73 10.15 0.58 -- -- -- -- -- -- -- -- -- -- 10.15


Name of Project :- Gaiwal (St.) Taluka - KARANJA Distt- WASHIM ( Rs. in Crores )

Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 17.13 17.13 -- -- -- -- -- -- -- -- -- 17.13

2 Earthwork 6.17 6.17 -- -- -- -- -- -- -- -- -- 6.17

3 Masonry -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 2.50 2.50 -- -- -- -- -- -- -- -- -- 2.50

B Canal System -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.80 -- 0.80 0.80 -- -- -- -- -- 0.80 -- --

E ETP 1.14 -- 1.14 -- -- -- -- -- -- -- -- --

Total 27.74 25.80 1.94 0.80 -- -- -- -- -- -- 0.80 -- -- 25.80


Name of Project :- Hiwara (St.) Taluka - Manora Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 4.73 4.73 -- -- -- -- -- -- -- -- -- 4.73

2 Earthwork 4.74 4.74 -- -- -- -- -- -- -- -- -- 4.74

3 Masonry -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.65 0.65 -- -- -- -- -- -- -- -- -- 0.65

5 Gate (For Barrages) -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.53 0.53 -- -- -- -- -- -- -- -- -- 0.53

E ETP 1.53 -- 1.53 -- -- -- -- -- -- -- -- --

Total 12.18 10.65 1.53 -- -- -- -- -- -- -- -- -- -- 10.65


Name of Project :- Chorad (St.) Taluka - Mangrulpir Distt- Washin ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 4.62 4.58 0.04 -- -- -- -- -- -- -- -- -- -- 4.58

2 Earthwork 5.02 5.02 -- -- -- -- -- -- -- -- -- -- -- 5.02

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.60 0.60 -- -- -- -- -- -- -- -- -- -- -- 0.60

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.49 0.37 0.12 -- -- -- -- -- -- -- -- -- -- 0.37

E ETP 0.32 -- 0.32 -- -- -- -- -- -- -- -- -- -- --

Total 11.05 10.57 0.48 -- -- -- -- -- -- -- -- -- -- 10.57


Name of Project :- Belmandal (St.) Taluka - KARANJA Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 6.92 6.41 0.51 -- -- -- -- -- -- -- -- -- -- 6.41

2 Earthwork 3.68 3.68 -- -- -- -- -- -- -- -- -- -- -- 3.68

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.41 1.41 -- -- -- -- -- -- -- -- -- -- -- 1.41

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.21 0.05 0.16 -- -- -- -- -- -- -- -- -- -- 0.05

E ETP 0.53 -- 0.53 -- -- -- -- -- -- -- -- -- -- --

Total 12.75 11.55 1.20 -- -- -- -- -- -- -- -- -- -- 11.55


Name of Project :Jogaldari (St.) Taluka - Mangrulpir Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 3.13 3.13 -- -- -- -- -- -- -- -- -- -- -- 3.13

2 Earthwork 6.92 6.92 -- -- -- -- -- -- -- -- -- -- -- 6.92

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.17 1.17 -- -- -- -- -- -- -- -- -- -- -- 1.17

5 Gates (for barrages) -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.22 0.22 -- -- -- -- -- -- -- -- -- -- -- 0.22

E ETP 0.81 0.05 0.76 -- -- -- -- -- -- -- -- -- -- 0.05

Total 12.25 11.49 0.76 -- -- -- -- -- -- -- -- -- -- 11.49 --


Name of Project :- Sarsiboth-2 (St.) Taluka - Mangrulpir Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 3.18 3.18 -- -- -- -- -- -- -- -- -- -- -- 3.18

2 Earthwork 2.19 1.98 0.21 -- -- -- -- -- -- -- -- -- -- 1.98

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 2.50 2.50 -- -- -- -- -- -- -- -- -- -- -- 2.50

5 Gate (For Barrages) -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.72 0.71 0.01 -- -- -- -- -- -- -- -- -- -- 0.71

E ETP 0.44 -- 0.44 -- -- -- -- -- -- -- -- -- -- --

Total 9.03 8.37 0.66 -- -- -- -- -- -- -- -- -- -- 8.37


Name of Project :- Sudi (St.) Taluka - Malegaon Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending 2021-22 up to Quarter Ending
Sr. upto 22 SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
(Col 4+15)
2021 Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17
A Head Work

1 Land Acquisition 2.82 2.53 0.29 -- -- -- -- -- -- -- -- -- -- 2.53

2 Earthwork 3.63 3.63 -- -- -- -- -- -- -- -- -- -- -- 3.63

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.59 0.59 -- -- -- -- -- -- -- -- -- -- -- 0.59

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Miscellaneoue -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.41 0.05 0.36 -- -- -- -- -- -- -- -- -- -- 0.05

E ETP 0.41 -- 0.41 -- -- -- -- -- -- -- -- -- -- --

Total 7.86 6.80 1.06 -- -- -- -- -- -- -- -- -- -- 6.80


Name of Project :- Surkhandi (Storage) M.I. Project Taluka :- Washim Distt. :- Washim
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending 2021-22 up to Quarter Ending
Sr. upto 22 SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
(Col 4+15)
2021 Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 3.811 3.811 -- -- -- 0.0045 -- -- -- -- -- -- 0.00 Rs.


3.82
0.0045 is paid for Adv. fees.

2 Earthwork 4.50 4.33 0.17 0.16 -- -- -- -- -- -- 0.16 -- -- 4.33

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 3.64 1.55 2.10 1.26 -- -- -- -- -- -- 1.26 -- -- 1.55

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.70 0.63 0.07 -- -- -- -- -- -- -- -- -- -- 0.63

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 12.65 10.32 2.34 1.42 -- 0.00 -- -- -- -- 1.42 -- 0.00 10.32


Name of Project :- Dharpimpri (Storage) M.I. Project Taluka :- Malegaon Distt. :- Washim
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 2.58 2.57 0.01 -- -- -- -- -- -- -- -- -- -- 2.57

2 Earthwork 4.10 4.05 0.05 -- -- -- -- -- -- -- -- -- -- 4.05

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.20 1.15 0.05 -- -- -- -- -- -- -- -- -- -- 1.15

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.46 0.45 0.01 -- -- -- -- -- -- -- -- -- -- 0.45

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 8.34 8.22 0.12 -- -- -- -- -- -- -- -- -- -- 8.22


Name of Project :- Yeota (St.) Taluka - KARANJA Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 4.58 4.58 -- -- -- -- -- -- -- -- -- -- -- 4.58

2 Earthwork 5.21 5.21 -- -- -- -- -- -- -- -- -- -- -- 5.21

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.54 0.54 -- -- -- -- -- -- -- -- -- -- -- 0.54

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous -- -- -- -- -- -- -- -- -- -- -- -- -- --

E ETP 0.60 -- 0.60 -- -- -- -- -- -- -- -- -- -- --

Total 10.93 10.33 0.60 -- -- -- -- -- -- -- -- -- -- 10.33


Name of Project :- Bramha (St.) Taluka - Washim Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 2.32 1.64 0.68 -- -- -- -- -- -- -- -- -- -- 1.64

2 Earthwork 5.22 5.22 -- -- -- -- -- -- -- -- -- -- -- 5.22

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.48 0.48 -- -- -- -- -- -- -- -- -- -- -- 0.48

5 Gate (For Barrages) -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 3.05 1.13 1.92 -- -- -- -- -- -- -- -- -- -- 1.13

E ETP 0.75 -- 0.75 -- -- -- -- -- -- -- -- -- -- --

Total 11.82 8.47 3.35 -- -- -- -- -- -- -- -- -- -- 8.47


Name of Project :- Bhildongar (St.) Taluka - Manora Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 1.26 1.23 0.03 -- -- -- -- -- -- -- -- -- -- 1.23

2 Earthwork 4.12 4.12 -- -- -- -- -- -- -- -- -- -- -- 4.12

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.14 0.14 -- -- -- -- -- -- -- -- -- -- -- 0.14

5 Gate (For Barrages) -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 0.18 0.15 0.03 -- -- -- -- -- -- -- -- -- -- 0.15

E ETP 0.27 -- 0.27 -- -- -- -- -- -- -- -- -- -- --

Total 5.97 5.64 0.33 -- -- -- -- -- -- -- -- -- -- 5.64


Name of Project :- Wakad (St.) Taluka - Risod Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 66.16 65.07 1.09 1.01 0.89 0.89 -- -- -- -- 0.12 -- 0.89 65.97
Rs. 0.8939 cr. transfere

2 Earthwork 15.26 15.05 0.21 -- -- -- -- -- -- -- -- -- -- 15.05

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 3.14 3.1420 -- -- -- -- -- -- -- -- -- -- -- 3.14

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue -- -- -- -- -- -- -- -- -- -- -- -- -- --

E ETP 2.16 -- 2.16 -- -- -- -- -- -- -- -- -- -- --

Total 86.72 83.26 3.46 1.01 0.89 0.89 -- -- -- -- 0.12 -- 0.89 84.16
Name of Project :- Koyali (St.) Taluka - Risod Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 8.30 8.30 -- -- -- -- -- 0.04 -- -- -- -- 0.04 8.34

2 Earthwork 8.54 8.54 -- -- -- -- -- -- -- -- -- -- -- 8.54

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.15 1.15 -- -- -- -- -- -- -- -- -- -- -- 1.15

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 0.28 0.05 0.23 -- -- -- -- -- -- -- -- -- -- 0.05

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 18.27 18.04 0.23 -- -- -- -- 0.04 -- -- -- -- 0.04 18.08


Name of Project :- Wadgaon (St.) Taluka - KARANJA Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 6.93 6.93 -- -- -- -- -- -- -- -- -- -- -- 6.93

2 Earthwork 17.76 17.58 0.18 0.18 0.18 0.15 -- -- -- -- -- -- 0.15 17.73

3 Masonry 3.07 3.07 -- -- -- -- -- -- -- -- -- -- -- 3.07

4 Concrete 0.86 0.85 0.01 0.01 -- -- 0.01 -- -- -- -- -- -- 0.85

B Canal System -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 0.50 -- 0.50 0.31 -- -- -- -- -- -- 0.31 -- -- --

E ETP 1.23 -- 1.23 -- -- -- -- -- -- -- -- -- -- --

Total 30.35 28.43 1.92 0.50 0.18 0.15 0.01 -- -- -- 0.31 -- 0.15 28.58 --
Name of Project :- Chaktirth (St.) Taluka - Malegaon Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 6.14 5.77 0.37 0.15 -- -- 0.15 0.04 -- -- -- -- 0.04 5.81

2 Earthwork 30.84 27.15 3.69 0.20 -- -- 0.20 -- -- -- -- -- -- 27.15

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 3.37 2.85 0.53 0.15 -- -- 0.15 -- -- -- -- -- -- 2.85

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 0.72 -- 0.72 -- -- -- -- -- -- -- -- -- -- --

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 41.07 35.76 5.31 0.500 -- -- 0.50 0.04 -- -- -- -- 0.04 35.80


Name of Project :- Kinkhed (St.) Taluka - KARANJA Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 5.55 5.55 -- -- -- -- -- -- -- -- -- -- -- 5.55

2 Earthwork 9.47 8.97 -- -- -- -- -- -- -- -- -- -- -- 8.97

3 Masonry 0.01 0.01 -- -- -- -- -- -- -- -- -- -- -- 0.01

4 Concrete 0.13 0.13 -- -- -- -- -- -- -- -- -- -- -- 0.13

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 0.52 -- 0.52 -- -- 0.18 -- -- -- -- -- -- 0.18 0.18

E ETP 0.99 -- 0.99 -- -- -- -- -- -- -- -- -- -- --

Total 16.67 14.66 1.51 -- -- 0.18 -- -- -- -- -- -- 0.18 14.84 --


Name of Project :- Kukasa (St.) Taluka - Risod Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 42.39 36.42 5.97 1.42 -- -- -- 0.14 -- -- 1.42 -- 0.14 36.56

2 Earthwork 12.73 9.33 3.40 0.58 -- -- -- -- -- -- 0.58 -- -- 9.33

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.55 1.49 0.06 -- -- -- -- -- -- -- -- -- -- 1.49

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 1.21 -- 1.21 -- -- -- -- -- -- -- -- -- -- --

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 57.88 47.24 10.64 2.00 -- -- -- 0.14 -- -- 2.00 -- 0.14 47.38


Name of Project :- SONGAWHAN BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 12.08 11.67 0.41 -- -- -- -- -- -- -- -- -- -- 11.67

2 Earthwork 7.15 7.15 -- -- -- -- -- -- -- -- -- -- -- 7.15

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 17.31 14.50 2.81 -- -- -- -- -- -- -- -- -- -- 14.50

5 Gates (for barrages) 19.47 19.36 0.11 -- -- -- -- -- -- -- -- -- -- 19.36

B Canal System No Canal -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation NO -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 9.40 1.51 7.89 3.00 0.32 0.32 -- -- 1.00 -- 1.68 -- 0.32 1.83

E ETP 4.96 -- 4.96 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 70.37 54.19 16.18 4.00 0.82 0.32 -- -- 1.00 -- 2.18 -- 0.32 54.51
Name of Project :- TANKA BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 4.14 3.66 0.48 -- -- -- -- 0.13 -- -- -- -- 0.13 3.79

2 Earthwork 3.87 2.23 1.64 -- -- -- -- -- -- -- -- -- -- 2.23

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 29.71 29.71 -- -- -- -- -- -- -- -- -- -- -- 29.71

5 Gates (for barrages) 21.19 21.19 -- -- -- -- -- -- -- -- -- -- -- 21.19

B Canal System No canal -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscellaneoue 10.07 9.67 0.40 3.00 0.35 0.35 -- -- 1.00 -- 1.65 -- 0.35 10.02

E ETP 5.73 -- 5.73 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 74.71 66.46 8.25 4.00 0.85 0.35 -- 0.13 1.00 -- 2.15 -- 0.48 66.94
Name of Project :- ADGAON BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 2.96 1.74 1.22 0.50 -- -- -- -- 0.50 -- -- -- -- 1.74

2 Earthwork 4.00 3.78 0.22 -- -- -- -- -- -- -- -- -- -- 3.78

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 23.55 23.55 -- -- -- -- -- -- -- -- -- -- -- 23.55

5 Gates (for barrages) 19.99 18.37 1.62 -- -- -- -- -- -- -- -- -- -- 18.37

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 9.11 3.87 5.24 3.00 1.18 1.18 -- -- 1.00 -- 0.82 -- 1.18 5.05

E ETP 4.85 0.13 4.72 0.50 0.25 -- -- -- -- -- 0.25 -- -- 0.13

Total 64.46 51.44 13.02 4.00 1.43 1.18 -- -- 1.50 -- 1.07 -- 1.18 52.62
Name of Project :- JAIPUR BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 19.50 19.39 0.11 0.11 0.04 0.04 0.07 0.24 -- -- -- -- 0.28 19.67

2 Earthwork 7.68 7.68 -- -- -- -- -- -- -- -- -- -- -- 7.68

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 22.99 22.99 -- -- -- -- -- -- -- -- -- -- -- 22.99

5 Gates (for barrages) 28.63 28.63 -- -- -- -- -- -- -- -- -- -- -- 28.63

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 4.37 3.89 0.48 2.89 -- -- -- -- 1.00 -- 1.89 -- -- 3.89

E ETP 6.08 -- 6.08 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 89.25 82.58 6.67 4.00 0.54 0.04 0.07 0.24 1.00 -- 2.39 -- 0.28 82.86
Name of Project :- DHILLI BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 5.89 5.21 0.68 0.68 -- -- 0.30 -- 0.38 -- -- -- -- 5.21

2 Earthwork 5.05 4.56 0.49 -- -- -- -- -- -- -- -- -- -- 4.56

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 28.80 27.99 0.81 -- -- -- -- -- -- -- -- -- -- 27.99

5 Gates (for barrages) 26.80 25.02 1.78 -- -- -- -- -- -- -- -- -- -- 25.02

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 11.01 5.01 6.00 2.32 0.27 0.27 -- -- 1.00 -- 1.05 -- 0.27 5.28

E ETP 6.18 -- 6.18 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 83.73 67.79 15.94 4.00 0.77 0.27 0.30 0.00 1.38 -- 1.55 -- 0.27 68.06
Name of Project :- KOKALGAON BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 4.60 2.71 1.89 0.89 -- -- -- -- 0.89 -- -- -- -- 2.71

2 Earthwork 7.10 4.96 2.14 -- -- -- -- -- -- -- -- -- -- 4.96

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 20.53 20.45 0.08 -- -- -- -- -- -- -- -- -- -- 20.45

5 Gates (for barrages) 20.98 20.44 0.54 -- -- -- -- -- -- -- -- -- -- 20.44

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 15.41 2.12 13.29 2.11 1.24 1.24 -- -- -- -- 0.87 -- 1.24 3.36

E ETP 5.10 -- 5.10 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 73.72 50.68 23.04 4.00 1.74 1.24 -- -- 0.89 -- 1.37 -- 1.24 51.92
Name of Project :- RAJGAON BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 2.68 1.30 1.38 1.38 -- -- 1.00 -- 0.38 -- -- -- -- 1.30

2 Earthwork 3.60 3.12 0.48 -- -- -- -- -- -- -- -- -- -- 3.12

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 24.00 23.66 0.34 -- -- -- -- -- -- -- -- -- -- 23.66

5 Gates (for barrages) 16.56 16.32 0.24 -- -- -- -- -- -- -- -- -- -- 16.32

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D MIscelleneous 10.21 9.82 0.39 1.62 0.24 0.24 -- -- 1.38 -- -- -- 0.24 10.06

E ETP 4.63 -- 4.63 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 61.68 54.22 7.46 4.00 0.74 0.24 1.00 -- 1.76 -- 0.50 -- 0.24 54.46
Name of Project :- UKALI BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 12.73 11.74 0.99 0.99 -- -- -- 0.20 0.40 -- 0.59 -- 0.20 11.94

2 Earthwork 7.11 7.08 0.03 -- -- -- -- -- -- -- -- -- -- 7.08

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 40.61 40.61 -- -- -- -- -- -- -- -- -- -- -- 40.61

5 Gates (for barrages) 22.82 22.92 (--)0.10 -- -- -- -- -- -- -- -- -- -- 22.92

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D MIscelleneous 6.25 0.62 5.63 2.01 0.23 0.23 -- -- 1.00 -- 0.78 -- 0.23 0.85

E ETP 7.30 -- 7.30 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 96.82 82.97 13.85 4.00 0.73 0.23 -- 0.20 1.40 -- 1.87 -- 0.43 83.40
Name of Project :- JUMDA BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 5.44 2.95 2.49 1.49 -- -- -- 1.45 1.00 -- 0.49 -- 1.45 4.40

2 Earthwork 6.44 2.83 3.61 -- -- -- -- -- -- -- -- -- -- 2.83

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 24.28 24.28 -- -- -- -- -- -- -- -- -- -- -- 24.28

5 Gates (for barrages) 18.66 17.56 1.10 -- -- -- -- -- -- -- -- -- -- 17.56

B Canal System 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 9.57 4.65 4.92 1.51 0.18 0.18 -- -- 1.00 -- 0.33 -- 0.18 4.83

E ETP 5.00 -- 5.00 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 69.39 52.27 17.12 4.00 0.68 0.18 -- 1.45 2.00 -- 1.32 -- 1.63 53.90
Name of Project :- GANESHPUR BARRAGE Taluka - WASHIM Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 4.66 2.91 1.75 0.75 -- -- -- -- -- -- 0.75 -- -- 2.91

2 Earthwork 4.23 2.52 1.71 -- -- -- -- -- -- -- -- -- -- 2.52

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 24.53 23.65 0.88 -- -- -- -- -- -- -- -- -- -- 23.65

5 Gates (for barrages) 18.39 16.14 2.25 -- -- -- -- -- -- -- -- -- -- 16.14

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

E Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 9.07 1.32 7.75 2.25 1.46 1.46 -- -- 0.79 -- -- -- 1.46 2.78

E ETP 4.81 -- 4.81 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 65.69 46.54 19.15 4.00 1.96 1.46 -- -- 0.79 -- 1.25 -- 1.46 48.00
Name of Project :- WARUD BARRAGE Taluka - RISOD Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 5.30 2.30 3.00 1.00 -- -- 1.00 0.02 -- -- -- -- 0.02 2.32

2 Earthwork 6.25 6.06 0.19 -- -- -- -- -- -- -- -- -- -- 6.06

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 20.08 17.12 2.96 -- -- -- -- -- -- -- -- -- -- 17.12

5 Gates (for barrages) 16.99 16.56 0.43 -- -- -- -- -- -- -- -- -- -- 16.56

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 9.27 6.81 2.46 2.00 0.98 0.98 -- -- 1.02 -- -- -- 0.98 7.79

E ETP 4.59 -- 4.59 1.00 0.50 -- -- -- -- -- 0.50 -- -- --

Total 62.48 48.85 13.63 4.00 1.48 0.98 1.00 0.02 1.02 -- 0.50 -- 1.00 49.85
Name of Project :- Palaskhed Taluka - Risod Distt- Washin ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 20.26 19.80 0.46 0.46 0.46 0.46 -- -- -- -- -- -- 0.46 20.26
Rs. 0.4644 cr. is paid to

2 Earthwork 13.97 13.85 0.12 0.12 0.12 0.60 -- 1 -- -- -- -- 1.71 15.56

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.76 1.76 0.00 -- -- -- -- 0.0891 -- -- -- -- 0.09 1.85

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 0.47 0.20 0.27 0.27 -- -- -- -- -- -- 0.27 -- -- 0.20

2 Earthwork 0.82 0.32 0.50 0.50 -- -- -- -- -- -- 0.50 -- -- 0.32

3 Structure 1.18 0.18 1.00 1.00 -- -- -- -- -- -- 1.00 -- -- 0.18

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites 3.00 1.74 1.26 1.26 -- -- -- -- -- -- 1.26 -- -- 1.74

3 Compensation 13.99 13.99 -- -- -- -- -- -- -- -- -- -- -- 13.99

D Miscelleneous 1.09 0.44 0.65 0.65 -- -- -- -- -- -- 0.65 -- -- 0.44

E ETP -- -- -- -- -- -- -- -- -- -- -- -- --

Total 56.54 52.28 4.26 4.26 0.58 1.07 -- 1.20 -- -- 3.68 -- 2.27 54.54
Name of Project :- Undri Taluka -Karanja Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 23.00 22.87 0.13 0.13 -- -- -- 1.31 0.13 -- -- -- 1.31 24.18

2 Earthwork 3.33 3.33 -- -- -- -- -- -- -- -- -- -- -- 3.33

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.71 0.71 -- -- -- -- -- -- -- -- -- -- -- 0.71

5 Gates (for barrages) -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 2.62 2.62 -- -- -- -- -- -- -- -- -- -- -- 2.62

2 Earthwork 0.91 0.91 -- -- -- -- -- -- -- -- -- -- -- 0.91

3 Structure 0.80 0.80 -- -- -- -- -- -- -- -- -- -- -- 0.80

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 3.37 3.37 -- -- -- -- -- -- -- -- -- -- -- 3.37

E ETP 2.06 1.31 0.75 -- -- -- -- -- -- -- -- -- -- 1.31

Total 36.80 35.92 0.88 0.13 -- -- -- 1.31 0.13 -- -- -- 1.31 37.23


Name of Project :- Zodga Taluka - Karanja Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 27.00 26.17 0.83 -- -- -- -- -- -- -- -- -- -- 26.17

2 Earthwork 9.00 4.66 4.34 2.50 -- -- -- -- -- -- 2.50 -- -- 4.66

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 2.00 0.80 1.20 -- -- -- -- -- -- -- -- -- -- 0.80

5 Gates (for barrages) -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 1.66 1.66 -- -- -- -- -- -- -- -- -- -- -- 1.66

2 Earthwork 1.16 1.16 -- -- -- -- -- -- -- -- -- -- -- 1.16

3 Structure 0.53 0.53 -- -- -- -- -- -- -- -- -- -- -- 0.53

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 4.32 4.32 -- -- -- -- -- -- -- -- -- -- -- 4.32

E ETP 1.250 -- 1.25 -- -- -- -- -- -- -- -- -- -- --

Total 46.92 39.30 7.62 2.50 -- -- -- -- -- -- 2.50 -- -- 39.30


Name of Project :- Mizapur Taluka - Malegaon Distt- Washin ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 27.00 27.00 -- -- -- 0.04 -- 4.34 -- -- -- -- 4.38 31.38


Rs. 0.0436 cr. Paid for l

2 Earthwork 8.70 8.66 0.04 0.02 -- -- -- -- -- -- 0.02 -- -- 8.66

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.38 0.34 0.04 -- -- -- -- -- -- -- -- -- -- 0.34

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 2.79 1.01 1.78 0.20 -- -- -- -- -- -- 0.20 -- -- 1.01

2 Earthwork 2.93 0.25 2.68 0.10 -- -- -- -- -- -- 0.10 -- -- 0.25

3 Structure 1.25 0.43 0.82 0.18 -- -- -- -- -- -- 0.18 -- -- 0.43

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites 2.37 2.37 -- -- -- -- -- -- -- -- -- -- -- 2.37

3 Compensation 7.82 7.82 -- -- -- -- -- -- -- -- -- -- -- 7.82

D Miscelleneous 0.63 0.03 0.60 -- -- -- -- -- -- -- -- -- -- 0.03

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 53.87 47.92 5.95 0.50 -- 0.04 -- 4.34 -- -- 0.50 -- 4.38 52.30
Name of Project :- GONDEGAON Taluka - MANORA Distt- WASHIM ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 16.00 15.23 0.77 -- -- -- -- -- -- -- -- -- -- 15.23

2 Earthwork 11.02 11.02 0.00 -- -- -- -- -- -- -- -- -- -- 11.02

3 Masonry 0.43 0.43 -- -- -- -- -- -- -- -- -- -- -- 0.43

4 Concrete 1.70 1.70 -- -- -- -- -- -- -- -- -- -- -- 1.70

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 1.25 1.02 0.23 0.230 -- 0.05 0.23 -- -- -- -- -- 0.05 1.07

2 Earthwork 4.65 3.25 1.40 1.400 -- -- 0.50 -- 0.400 -- 0.500 -- -- 3.25

3 Structure 4.54 2.96 1.58 1.580 -- -- 0.50 -- 0.580 -- 0.500 -- -- 2.96

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.39 0.22 0.17 0.17 -- -- -- -- -- -- 0.170 -- -- 0.22

E ETP 0.48 -- 0.48 -- -- -- -- -- -- -- -- -- -- --

Total 40.46 35.83 4.63 3.380 -- 0.05 1.23 -- 0.98 -- 1.17 -- 0.05 35.88 --
Name of Project :- Kawthal Taluka - Mangrulpir Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work --

1 Land Acquisition 10.91 6.38 4.53 -- -- -- -- -- -- -- -- -- -- 6.38

2 Earthwork 6.96 5.25 1.71 0.77 -- -- -- -- -- -- 0.77 -- -- 5.25

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.95 0.80 0.15 -- -- -- -- -- -- -- -- -- -- 0.80

5 Gates (for barrages) -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 1.04 1.04 -- -- -- -- -- -- -- -- -- -- -- 1.04

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 PDN 4.63 -- 4.63 4.63 -- -- -- -- -- -- 4.63 -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 1.75 0.55 1.20 -- -- -- -- -- -- -- -- -- -- 0.55

E ETP 1.53 0.31 1.22 -- -- -- -- -- -- -- -- -- -- 0.31

Total 27.77 14.33 13.44 5.40 -- -- -- -- -- -- 5.40 -- -- 14.33 --


Name of Project :- Mairaldoh Taluka - Malegaon Distt- Washin ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 8.11 7.36 0.75 -- -- 0.04 -- 0.024 -- -- -- -- 0.06 7.42


Rs. 0.0368 paid for layin

2 Earthwork 8.95 8.65 0.30 -- -- -- -- -- -- -- -- -- -- 8.65

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.34 1.31 0.03 -- -- -- -- -- -- -- -- -- -- 1.31

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure 0.60 0.41 0.19 -- -- -- -- -- -- -- -- -- -- 0.41

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.93 -- 0.93 -- -- -- -- -- -- -- -- -- -- --

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 19.93 17.73 2.20 -- -- 0.04 -- 0.02 -- -- -- -- 0.06 17.79


Name of Project :-Khadki Taluka - Malegaon Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 6.65 6.65 -- -- -- -- -- -- -- -- -- -- -- 6.65

2 Earthwork 4.93 4.93 -- -- -- -- -- -- -- -- -- -- -- 4.93

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 0.50 0.50 -- -- -- -- -- -- -- -- -- -- -- 0.50

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 2.23 1.17 1.06 0.66 -- -- -- -- -- -- 0.66 -- -- 1.17

2 Earthwork 0.46 0.35 0.11 0.11 -- -- -- -- -- -- 0.11 -- -- 0.35

3 Structure 1.99 0.47 1.52 1.00 -- -- -- -- -- -- 1.00 -- -- 0.47

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.22 0.05 0.17 -- -- -- -- -- -- -- -- -- -- 0.05

E ETP 0.43 -- 0.43 0.250 -- -- -- -- 0.10 -- 0.15 -- -- --

Total 17.41 14.12 3.29 2.02 -- -- -- -- 0.10 -- 1.92 -- -- 14.12


Name of Project :- Swasin Taluka - Mangrulpir Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 43.50 38.37 5.13 -- -- -- -- -- -- -- -- -- -- 38.37

2 Earthwork 8.50 7.80 0.70 0.70 -- -- -- -- 0.25 -- 0.45 -- -- 7.80

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 6.00 4.12 1.88 1.00 0.50 0.43 -- -- 0.50 -- -- -- 0.43 4.55

5 Gates -- -- -- -- -- -- -- -- -- -- -- -- -- --

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 PDN 5.26 -- 5.26 4.87 -- -- 0.70 0.40 3.00 -- 1.17 -- 0.40 0.40

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 2.70 2.20 0.50 -- -- -- -- -- -- -- -- -- -- 2.20

E ETP 3.11 0.73 2.38 -- -- -- -- -- -- -- -- -- -- 0.73

Total 69.07 53.22 15.85 6.57 0.50 0.43 0.70 0.40 3.75 -- 1.62 -- 0.83 54.05 --
Name of Project :- Kuttardoh M.I. Project Taluka :- Malegaon Distt. :- Washim
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 3.40 3.38 0.02 -- -- 0.01 -- 0.08 -- -- -- -- 0.09


Rs. 0.0119cr. is3.47
paid to farmer as per Hon'ble Co

2 Earthwork 7.98 7.76 0.22 -- -- -- -- -- -- -- -- -- -- 7.76

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 2.09 1.97 0.12 -- -- -- -- -- -- -- -- -- -- 1.97

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 0.59 0.37 0.22 -- -- -- -- -- -- -- -- -- -- 0.37

2 Earthwork 0.86 0.78 0.08 -- -- -- -- -- -- -- -- -- -- 0.78

3 Structure 1.48 1.28 0.20 -- -- -- -- -- -- -- -- -- -- 1.28

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation sites -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 0.63 0.63 -- -- -- -- -- -- -- -- -- -- -- 0.63

E ETP -- -- -- -- -- -- -- -- -- -- -- -- --

Total 17.03 16.17 0.86 -- -- 0.01 -- 0.08 -- -- -- -- 0.09 16.27


Name of Project :- Wadiraitala Taluka - Risod Distt- Washin ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 24.71 18.75 5.96 2.23 -- 0.02 -- 0.551 2 -- -- -- 0.57 19.32
Rs. 0.0176 cr. payment

2 Earthwork 14.68 13.95 0.73 -- -- -- -- -- -- -- -- -- -- 13.95

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 1.01 0.87 0.14 -- -- -- -- -- -- -- -- -- -- 0.87

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 14.33 0.31 14.02 14.02 -- -- -- -- 7 -- 7 -- -- 0.31

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 1.63 -- 1.63 -- -- -- -- -- -- -- -- -- -- --

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 56.36 33.88 22.48 16.25 -- 0.02 -- 0.551 9.23 -- 7.02 -- 0.57 34.45
Name of Project :- Jaipur M.I. Project Taluka :- Washim Distt. :- Washim
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 54.68 52.96 1.72 0.08 -- 0.00 -- -- -- -- 0.08 -- 0.00 52.96

2 Earthwork 58.06 57.02 1.04 -- -- -- -- -- -- -- -- -- -- 57.02

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 17.00 17.00 -- -- -- -- -- -- -- -- -- -- -- 17.00

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 0.30 -- 0.30 -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation sites -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 9.42 4.90 4.52 -- -- -- -- -- -- -- -- -- -- 4.90

E ETP -- -- -- -- -- -- -- -- -- -- -- -- --

Total 139.46 131.88 7.58 0.08 -- 0.00 -- -- -- -- 0.08 -- 0.00 131.88


Name of Project :- Wara Jahagir Taluka - Washim Distt- Washin ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 28.89 25.27 3.62 2.82 2.02 2.02 -- 0.0941 -- -- 0.80 -- 2.12 27.39

2 Earthwork 58.92 56.90 2.02 0.10 -- -- -- -- -- -- 0.10 -- -- 56.90

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 8.240 8.24 -- -- -- -- -- -- -- -- -- -- -- 8.24

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 10.17 0.01 10.16 2.00 -- -- -- -- -- -- 2.00 -- -- 0.01

2 Earthwork 8.51 -- 8.51 4.00 -- -- -- -- -- -- 4.00 -- -- --

3 Structure 4.44 -- 4.44 3.07 -- -- -- -- -- -- 3.07 -- -- --

C Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 5.67 1.09 4.58 -- -- -- -- -- -- -- -- -- -- 1.09

E ETP -- -- -- -- -- -- -- -- -- -- -- -- --

Total 124.84 91.51 33.33 11.99 2.02 2.02 -- 0.09 -- -- 9.97 -- 2.12 93.63
Name of Project :- Pangrabandi Taluka - Malegaon Distt- Washim ( Rs. in Crores )
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 32.18 21.80 10.38 2.30 2.30 2.30 -- 1.58 -- -- -- -- 3.88 25.68
Rs. 2.3014 is payment o

2 Earthwork 70.79 70.79 0.00 -- -- -- -- -- -- -- -- -- -- 70.79

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 9.750 6.01 3.74 0.84 -- -- 0.400 -- 0.440 -- -- -- -- 6.01

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition 14.55 5.59 8.96 6.06 -- -- -- -- 4.03 -- 2.03 -- -- 5.59

2 Earthwork 15.53 -- 15.53 5.06 -- -- -- -- 3.00 -- 2.06 -- -- --

3 Structure 2.95 -- 2.95 2.95 -- -- -- -- 0.95 -- 2.00 -- -- --

C Rehabilitation 0.00 -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation Sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 3.84 -- 3.84 -- -- -- -- -- -- -- -- -- -- --

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 149.59 104.19 45.40 17.21 2.30 2.30 0.40 1.58 8.42 -- 6.09 -- 3.88 108.07
Name of Project :- Umari M.I. Project Taluka :- Manora Distt. :- Washim
Updated Expen- Balance Target Quarterwise Target and Achievement in 2021-22 Expenditure in Remarks
Cost diture Cost for 2021- 2021-22 up to Quarter Ending
Sr. upto 22 Ist Quarter Ending IInd Quarter Ending IIIrd Quarter Ending IVth Quarter Ending SEPT -21 Cumulative
Component of Project June 21 Sept 21 Dec 21 March 22
No. March (8+10+12+14) Expenditure
2021 (Col 4+15)
Target Achieved Target Achieved Target Achieved Target Achieved
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17

A Head Work

1 Land Acquisition 8.96 7.16 1.80 0.50 0.10 0.10 0.20 -- 0.20 -- -- -- 0.10 7.26

2 Earthwork 7.74 3.85 3.89 3.00 0.50 0.50 0.50 -- 1.00 -- 1.00 -- 0.50 4.35

3 Masonry -- -- -- -- -- -- -- -- -- -- -- -- -- --

4 Concrete 10.00 -- 10.00 7.01 -- -- 3.51 3.13 2.00 -- 1.50 -- 3.13 3.13

B Canal System -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Land Acquisition -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Earthwork -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Structure -- -- -- -- -- -- -- -- -- -- -- -- -- --

E Rehabilitation -- -- -- -- -- -- -- -- -- -- -- -- -- --

1 Families Displaced -- -- -- -- -- -- -- -- -- -- -- -- -- --

2 Rehabilitation sites -- -- -- -- -- -- -- -- -- -- -- -- -- --

3 Compensation -- -- -- -- -- -- -- -- -- -- -- -- -- --

D Miscelleneous 2.70 1.51 1.19 -- -- -- -- -- -- -- -- -- -- 1.51

E ETP -- -- -- -- -- -- -- -- -- -- -- -- -- --

Total 29.40 12.52 16.88 10.51 0.60 0.60 4.21 3.13 3.20 -- 2.50 -- 3.73 16.25