Professional Documents
Culture Documents
0 Main Summary
0 Main Summary
0 Main Summary
Previous Value
Initial Contract This Bill Value of Upto Date Value
Sr.No Name of School of Work
Cost (PKR) Work Done of Work Done
Done(PKR)
1
GPS Riali Chalhana 13,870,234 12,488,692 150,387 12,639,079
2
BPS Chalhana Riali 12,294,377 10,509,997 116,390 10,626,386
3
BPS Semari 12,360,977 7,199,002 182,973 7,381,976
4
GPS Kashi Rah Jura 12,617,132 6,261,972 268,899 6,530,871
5 Contingency
500,000 - -
6 Price Adjustment
4,752,815 (1,781,151) 2,971,664
Certified
Prepared By Project Ma
Contractor: M/S Kashif Shafique Khawaja
Amount
Certifed by
Remarks
Consultant
(This Bill)
150,387
116,390
182,973
268,899
718,649
(1,781,151)
(1,062,502)
(53,125)
(1,009,377)
2,368,845
2,007,499
3,366,967 3,366,967
Certified By:
Project Manager
Assistant Engineer
IsDB Assisted Projects