DAILY UPDATE OF PILING WORK FOR THE PROJECT "CONSTRUCTION OF SH

SL NO LOCATION TOTAL NO OF PILES DATE PILE NO AS PER


AS PER DESIGN DESIGN

1 13 July 2021 16

2 16 July 2021 12

3 18 July 2021 15

4 20 July 2021 25 & 11

5 22 July 2021 14 & 29

6 25 July 2021 10

7 27 July 2021 30 & 9

8 28 July 2021 13

9 29 July 2021 26

10 30 July 2021 4
11 01 August 2021 31 & 8

12 03 August 2021 7 & 27

proposed bow
32 nos (1200 mm dia
string girder
& 28M depth below
13 bridge over NH 05 August 2021 32
bottom of pile cap)
bypass

14 07 August 2021 3

15 09 August 2021 28 & 2

16 10 August 2021 24 & 1

17 11 August 2021 20 & 6

18 12 August 2021 23

19 13 August 2021 5

20 14 August 2021 19 & 22

21 15 August 2021 -

22 16 August 2021 23
23 17 August 2021 21

24 18 August 2021 18

25 20 August 2021 17

TOTAL NO OF PILES PILE NO AS PER


SL NO LOCATION DATE
AS PER DESIGN DESIGN

1 13 August 2021 26/P1

2 14 August 2021 25/P1,26/P2

3 15 August 2021 -

4 16 August 2021 23/P2,25/P2

5 17 August 2021 22/P1,26/P3

6 18 August 2021 22/P2,23/P4,25/P3

7 19 August 2021 26/P4,27/P2

8 20 August 2021 25/P4,

21/P1,22/P3,23/P1
9 21 August 2021
, 24/P5,27/P1
48 NOS ( 1200 MM
proposed
dia & 27 M depth
roundabout
below bottom of pile
portion(P20-P27)
cap )
48 NOS ( 1200 MM
proposed
dia & 27 M depth
roundabout
10 below bottom of pile 22 August 2021 26/P6
portion(P20-P27) cap )

21/P2,23/P6,
11 23 August 2021
24/P6,25/P5,27/P4

12 24 August 2021 26/P5,22/P4

27/P3,23/P3,24/P3,2
13 25 August 2021
5/P6,21/P3

22/P5, 21/P4,23/P5,
14 26 August 2021
24/P4

15 27 August 2021 27/P6,21/P5,22/P6,2


4/P1

16 28 August 2021 20/P5,21/P6,27/P5

18 31 August 2021 24/P2,20/P3

19 01 September 2021 20/P4

20 02 September 2021 20/P6

21 05 September 2021 20/P2

22 07 September 2021 20/P1


23 08 September 2021

08 December 2021 23/P7

09 December 2021 23/P8, 21/P7

10 December 2021 21/P8

TOTAL NO OF PILES PILE NO AS PER


SL NO LOCATION DATE
AS PER DESIGN DESIGN

84 NOS (1200MM dia


proposed viaduct
& 29.5 M depth
1 portion( P1 L/R - 11 September 2021 8R/P2,
below bottom of pile
P7 L/R)
cap)

12 September 2021 7R/P5,


16 September 2021 8R/P1,

18 September 2021 8R/P3, 7R/P6

19 September 2021 6R/P6

20 September 2021 8R/P4,

21 September 2021 7R/P3,6R/P5, 5R/P1,

22 September 2021 8R/P6,7R/P4, 4R/P6,

23 September 2021 6R/P4, 4R/P5,

24 September 2021 8R/P5,


26 September 2021 8L/P5

28 September 2021 8L/P6

29 September 2021 8L/P3

30 September 2021

01 October 2021 8L/P4

02 October 2021 6R/P3

03 October 2021 8L/P1,7R/P1,6R/P1

04 October 2021 8L/P2,7R/P2


05 October 2021 6R/P2, 7L/P6

06 October 2021 7L/P6, 7L/P5

07 October 2021 7L/P5, 6L/P6

08 October 2021 7L/P4

09 October 2021 6L/P4,7L/P3

10 October 2021 5R/P5, 4L/P6

11 October 2021 5R/P6, 7L/P2, 6L/P3

12 October 2021 4L/P5, 6L/P1


13 October 2021 5R/P3

14 October 2021 4L/P4

15 October 2021 3R/P5, 6L/P2, 7L/P1

16 October 2021

17 October 2021 5R/P4, 3R/P4, 4L/P3

18 October 2021 3R/P3, 2R/P4

19 October 2021 5L/P5, 4L/P2,

20 October 2021
21 October 2021 5L/P3, 4L/P1, 2R/P3

22 October 2021 3R/P2, 3L/P2

23 October 2021 5L/P6

4R/P3, 3R/P1, 5L/P4,


24 October 2021
3L/P1

2L/P6, 3L/P4, 4R/P4,


25 October 2021 5L/P1

26 October 2021 2R/P5, 3L/P3, 5L/P2,

27 October 2021 3L/P5, 4R/P1,

28 October 2021 3L/P6,


29 October 2021 4R/P2

30 October 2021

31 October 2021

01 November 2021 9R/P5

02 November 2021 9R/P6

03 November 2021

04 November 2021

05 November 2021
06 November 2021 9L/P2

07 November 2021 9L/P1

08 November 2021

09 November 2021 9L/P4

10 November 2021 9L/P3

11 November 2021 9L/P6

12 November 2021 9L/P5

13 November 2021 AL/P1


14 November 2021

15 November 2021 9R/P3

16 November 2021 2R/P1

17 November 2021 9R/P4, A1L/P4

18 November 2021 A1R/P2, 9R/P2

19 November 2021 A1R/P3

A1R/P4, 9R/P1,
20 November 2021
2R/P2

21 November 2021
22 November 2021 13R/P6, 14R/P6

23 November 2021 14R/P5, 13R/P5

24 November 2021 10R/P3

25 November 2021

26 November 2021 13L/P2, 14R/P4

27 November 2021 13R/P4, 10R/P4

14R/P3, 13L/P1,
28 November 2021
11R/P2

29 November 2021 10R/P1, 13R/P3

13L/P4, 15R/P6,
30 November 2021
10R/P2

01 December 2021 13R/P1,14R/P2

02 December 2021 10L/P6, 13L/P3


03 December 2021 14R/P1

04 December 2021

07 December 2021 10L/P4, 13L/P6

08 December 2021 15R/P5

09 December 2021 15R/P4,

10 December 2021 13L/P5, 15R/P3

11 December 2021 14L/P6, 14L/P5

12 December 2021 16L/P1, 10L/P1

13 December 2021 14L/P4, 16L/P3,

14 December 2021 15R/P1,

15 December 2021 14L/P3

16L/P5, 15R/P2,
16 December 2021
14L/P2

17 December 2021 15L/P5,

18 December 2021 10L/P2

19 December 2021 16L/P2

20 December 2021 15L/P6, 16L/P4

22 December 2021 15L/P3, 16L/P6


23 December 2021 15L/P4

24 December 2021 5R/P7, 3R/P7

25 December 2021 2L/P2, A1L/P3, 3R/P8

26 December 2021 5R/P8

TOTAL NO OF PILES PILE NO AS PER


SL NO LOCATION DATE
AS PER DESIGN DESIGN

proposed viaduct 48NOS(1200MM dia


1 portion( P8 L/R - & 27M depth below
P11 L/R) bottom of pile cap )
ECT "CONSTRUCTION OF SHREE SETU AT PURI" AS ON 01.09.2021
NO OF PILES CUMULATIVE 7 days cube 28 days cube PCC OF PILE RCC OF PILE CAP
COMPLETED NO OF PILES test date test date CAP
COMPLETED

1 1 20.7.21 10.8.21

1 2 23.7.21 13.8.21

1 3 25.7.21 15.8.21

2 5 27.7.21 17.8.21

2 7 29.7.21 19.8.21

1 8 1.8.21 22.8.21

2 10 3.8.21 24.8.21

1 11 4.8.21 25.8.21

1 12 5.8.21 26.8.21

1 13 6.8.21 27.8.21
2 15 8.8.21 29.8.21

2 17 10.8.21 31.8.21

1 18 12.8.21 2.9.21

1 19 14.8.21 4.9.21

2 21 16.8.21 6.9.21

2 23 17.8.21 7.9.21

2 25 18.8.21 8.9.21

1 26 19.8.21 9.9.21

1 27 20.8.21 10.9.21

1 28 21.8.21 11.9.21

- -
NO WORK DUE TO
- INDEPENDENCE DAY

1 29 23.8.21 13.9.21
1 30 24.8.21 14.9.21

1 31 25.8.21 15.9.21

1 32 27.8.21 17.9.21

CUMULATIVE
NO OF PILES NO OF PILES IN
NO OF PILES REMARKS
COMPLETED PROGRESS
COMPLETED

1 1 20.8.21 10.9.21

2 3 21.8.21 11.9.21

NO WORK DUE TO
INDEPENDENCE DAY
- -

2 5 23.8.21 13.9.21

2 7 24.8.21 14.9.21

3 10 25.8.21 15.9.21

2 12 26.8.21 16.9.21

1 13 27.8.21 17.9.21

5 18 28.8.21 18.9.21
1 19 29.8.21 19.9.21

5 24 30.8.21 20.9.21

2 26 31.8.21 21.9.21

5 31 1.9.21 22.9.21

4 35 2.9.21 23.9.21

4 39 3.9.21 24.9.21

3 42 4.9.21 25.9.21

2 44 7.9.21 28.9.21

1 45 8.9.21 29.9.21

1 46 9.9.21 30.9.21

1 47 12.9.21 3.10.21

1 48 14.9.21 5.10.21
PIT conducted on 26
nos piles at
roundabout

1 49

2 51

1 52

CUMULATIVE
NO OF PILES NO OF PILES IN
NO OF PILES REMARKS
COMPLETED PROGRESS
COMPLETED

Approved by tce on
1 1 18.9.21 9.10.21
20.08.21

1 2 19.9.21 10.10.21
1 3 23.9.21 14.10.21

2 5 25.9.21 16.10.21

PCC OF P20 at
1 6 26.9.21 17.10.21 roundabout

1 7 27.9.21 18.10.21

PCC of P26 at
3 10 28.9.21 19.10.21 roundabout

3 13 29.9.21 20.10.21

2 15 30.9.21 21.10.21

PCC of P-24 at
1 16 1.10.21 22.10.21 roundabout
1 17 3.10.21 24.10.21

1 18 5.10.21 26.10.21

1 19 6.10.21 27.10.21

0 19

1 20 8.10.21 29.10.21 short pile by 1.8 M.

1 21 9.10.21 30.10.21 crane operation


starts

3 24 10.10.21 31.10.21

2 26 11.10.21 1.11.21
1 27 12.10.21 2.11.21

2 29 13.10.21 3.11.21

2 31 14.10.21 4.11.21

1 32 15.10.21 5.11.21

2 34 16.10.21 6.11.21

2 36 17.10.21 7.11.21

3 39 18.10.21 8.11.21

2 41 19.10.21 9.11.21
1 42 20.10.21 10.11.21

1 43 21.10.21 11.11.21

3 46 22.10.21 12.11.21

0 46

3 49 24.10.21 14.11.21

2 51 25.10.21 15.11.21

2 53 26.10.21 16.11.21

0 53
3 56 28.10.21 18.11.21

2 58 29.10.21 19.11.21

1 59 30.10.21 20.11.21

4 63 31.10.21 21.11.21

4 67 1.11.21 22.11.21

3 70 2.11.21 23.11.21

2 72 3.11.21 24.11.21

1 73 4.11.21 25.11.21 pile cap PCC P8R


PLE CAP P20
1 74 5.11.21 26.11.21
ROUNDABOUT

74

74 pile cap PCC P7R

PLE CAP P27


1 75 8.11.21 29.11.21
ROUNDABOUT

1 76 9.11.21 30.11.21 pile cap PCC P6R

76

76

76 PILE CAP P26


1 77 13.11.21 4.12.21

1 78 14.11.21 5.12.21

78 15.11.21 6.12.21 PILE CAP P25

1 79 16.11.21 7.12.21

1 80 17.11.21 8.12.21

1 81 18.11.21 9.12.21 PILE CAP P24

1 82 19.11.21 10.12.21

1 83 20.11.21 11.12.21
83

1 84 22.11.21 13.12.21

1 85 23.11.21 14.12.21

PILE CAP P22


2 87 24.11.21 15.12.21
CASTED

2 89 25.11.21 16.12.21

1 90 26.11.21 17.12.21 P6L PCC

3 93 27.11.21 18.12.21

93
2 95 29.11.21 20.12.21

2 97 21.12.21

1 98 1.12.21 22.12.21

98 23.12.21

2 100 24.12.21

2 102 25.12.21

3 105 26.12.21

2 107 27.12.21

3 110 28.12.21

2 112 29.12.21

2 114 30.12.21
2 116 31.12.21

P8R PILE CAP


116 1.1.22
CASTING

2 118 4.1.22 P8L

1 119 5.1.22

1 120 6.1.22

P7R PILE CAP


2 122
CASTING

2 124

2 126

2 128

P6R PILE CAP


1 129
CASTING

1 130

3 133

1 134

1 135 P9L

1 136

2 138

2 140
1 141 P4L

2 143

3 146

1 147

CUMULATIVE
NO OF PILES NO OF PILES IN
NO OF PILES REMARKS
COMPLETED PROGRESS
COMPLETED
HSDL
6R

7R
8R
4R/P1,
4R/P6
Shree Setu Via Duct Piling status as on 24.09.21

Pile Group Pile Group


Piles completed Piles completed
(Approved) (Approved)
1R 1L
2R 2L
3R 3L
4R 2 4L
5R 1 5L
6R 3 6L
7R 4 7L
8R 6 8L
9R 9L
10R 10L

Total = 16 0

Pile group Pile group


8R 8L
7R 7L P1, P2, P3,P5, P6,
6R 6L P1, P3, P4, P6,
5R P4, P3, P6, P5, 4 5L P5,
4R 1 4L P2, P3, P4, P5, P6,
2R P4, 1
3R P3, P4, P5, 3

Pile group 120 Pile group

8R P1,P2,P6, P4, P3, 5 8L P2, P1, P4, P3, P6, P5,

P5, P2, P1, P4,


7R 6 7L P1, P2, P3,P5, P6,
P3, P6,

P4, P1, P2, P3,


6R 6 6L P1, P3, P4, P6,
P5, P6,

P1, P4, P3, P6,


5R 5 5L P5, P2, P1, P4, P6, P3
P5,
P5,P6, P2, P1, P4,
4R 6 4L P2, P3, P4, P5, P6, P1,
P3
2R P4, P5, P6, P3, 4 2L
P3, P4, P5, P1,
3R 5 3L P5, P3, P4, P1, P2,
P2,

Pile group 74 Pile group


5R 5L P2, P1, P4, P6, P3
4R P2, P1, P4, P3 4 4L
2R P5, P6, P3, 3 S
3R P1, P2, 2 3L P5, P3, P4, P1, P2,

Pile group 65 Pile group

8R P1,P2,P6, P4, P3, 5 8L P2, P1, P4, P3, P6, P5,

P5, P2, P1, P4,


7R 6 7L P1, P2, P3,P5, P6,
P3, P6,

6R P4, P1, P2, P3, 6 6L P1, P3, P4, P6,


P5, P6,
P1, P4, P3, P6,
5R 5 5L P5, P2, P1, P4, P6, P3
P5,
P5,P6, P2, P1, P4,
4R P3 6 4L P2, P3, P4, P5, P6, P1,

2R P4, P5, P6, P3, 4 2L


P3, P4, P5, P1,
3R 5 3L P5, P3, P4, P1, P2,
P2,
2R P2, P1, 2 2L
9R P1, P2, P4, P3, 4 9L P5
10R P2, P1, P4, P3, 4 10L P6, P3,
11R P2, 1 11L
12R 12L
P1, P2, P3, P4,
13R 6 13L P4, P1, P2,
P5, P6,
P1, P2, P3, P4,
14R 6 14L
P5, P6,
15R P6, 1 15L
A1R P4, P2, P3, P3, 4 A1L P4, P1,
98.4 15744

43.4 30380

32
5R/P4,
3R/P2,
6 3R/P4, 8L/P1,7R/P1,6R/P1
3L/P2
4L/P3
3R/P3,
5 5L/P6 8L/P2,7R/P2
2R/P4

4R/P3,
3R/P1, 5L/P5,
4 6R/P2, 7L/P6
5L/P4, 4L/P2,
3L/P1

6 7L/P6, 7L/P5

6 7L/P5, 6L/P6

7L/P4
5 6L/P4,7L/P3

5R/P5, 4L/P6
5R/P6, 7L/P2, 6L/P3
4L/P5, 6L/P1
5R/P3
4L/P4
3R/P5, 6L/P2, 7L/P1

5R/P4, 2R/P4, 3R/P3,P4,P5, 7L/P1,P2, 5L/P5,


4L/P2,P3,P4, 8R/P2,P3, 7R/P6, 6R/P3

40

1
2