Professional Documents
Culture Documents
DEME 3-Day General Principles of Contract Management Training Presentation
DEME 3-Day General Principles of Contract Management Training Presentation
MANAGEMENT
Training to DEME
Workshop Objectives
Demonstrate how you can improve the DEME Group’s contractual and
commercial position in both the pre-contract and post-contract phases of
projects.
On day 3, to:
Explain the philosophy of the main FIDIC standard forms of contract and
what their use means.
Q: What is a Contract?
Understanding the clients’ needs and the opportunities and risks involved
Issuing and/or receiving requests for extra payment and additional time
A: No. Why?
A: No. Why?
Q: Who is involved in managing a contract?
Days 1 and 2
1. Tender stage
2. Procurement and Sub-Contracting
3. Contracts (Construction contracts and Letters Of Intent)
4. Setting up the project
5. Planning and Progress
6. Financial issues
7. Management of Change and Variations
8. Dispute resolution
Day 3
FIDIC introduction
Overview of differences between different standard forms
Specific requirements of FIDIC contracts
Comparison with other standard forms
1. Tender Stage
This includes:
Technical requirements
Type and scope of works (i.e. dredging, design and build)
Timing and timescale
Legal considerations
Type of contractual relationship (i.e. main contract, sub contract)
Applicable terms and conditions
Commercial aspects
Method of valuing works (i.e. lump sum, re-measurable)
Guarantees and payment conditions
How is this achieved?
O & R REGISTER
Description
Contracting Risks (1 of 2)
1. Extent of the scope of work
2. Safety provisions
5. Liabilities
Contracting Risks (2 of 2)
1. Clarity of the contract wording and provisions (no discrepancies)
2. Wording and provisions that can be easily understand by all
concerned
3. Document submittals at, or just after commencement
4. Condition precedent clauses (‘ontbindende voorwaarden’)
5. Notice requirements
6. Requirement for record keeping
7. Change process
8. Claims process
ORM
Other requirements:
Safety provisions
The phrase ‘back to back with the main contract’? If so, what
does it mean?
‘Back to back’
Article 3.1 says that ‘Subcontractor shall be deemed to have full knowledge
of the provisions of the Main Contract...
Contractor shall (if requested) make available a copy of the Main
Contract.
Article 3.2 says ‘Subcontractor shall carry out and complete Subcontract
Works so that no act or omission of the Subcontractor shall result in
any breach of the Main Contract by the Contractor.
Article 3.3 says ‘to the extent that such obligations and liabilities relate to
the Subcontract Works, the Subcontractor shall perform the obligations
and assume the liabilities of the Contractor under the Main Contract.’
An example of Main Contract Wording …
Article 15 (c) says that ‘Contractor must make all the terms and conditions
of Contract (as far as the same are applicable ) terms and conditions of
Subcontract and must not permit any alteration of the Subcontract without
the prior written consent of Company and must enter into a Subcontract
with the Subcontractor accordingly.’
Terms and Conditions for a Sub-Contract - 2
All can work but in all cases, the parts of the main contract
relevant to the subcontract need identifying (and possibly
revising), and then be incorporated into the subcontract.
3. Contracts
a Contract is an agreement,
which should be based
upon the mutual understanding
that was built up
in the tender stage.
Contractual Agreement
You receive a Purchase Order from the prospective client that does
not expressly refer to the offer.
The Purchase Order includes certain terms and has on the back of
the document, the prospective client’s general terms and conditions.
The first general term and condition says that “acceptance of this
order constitutes unconditional acceptance of these conditions”.
Type of industry:
Type of payment:
Dredging
Lump sum
Energy
Target price
Building
Unit rates / re-measurement
Industrial
Reimbursable
Infrastructure
Type of arrangement:
Employer & contractor
Contractor & subcontractor
Turnkey
Design & build
Contract Requirements
The start of the procurement process (where there are long lead in
times) or the start of engineering or mobilisation needs to happen
so the required completion date(s) will be met
− Did Employer (to be) start its procurement process too late?
− Is it however, now in your interest to start?
− If works starts, you must ensure the basis upon which it does
so is defined in writing
Various Options
“As you know from our meeting this morning, we have just received a letter of intent from
[X] for the [Y] project, which includes your [equipment].
In our turn, we are pleased to confirm that it is our intention to enter into a sub contract
with [you] for your [equipment], this will be generally be on the basis of the Sub Contract
document that we discussed this morning (ref…)
We also agreed that we would incorporate your final comments on the draft Sub Contract
and that you would provide details of the Advance Payment Bond, on-demand Performance
Bond and insurance that you can offer.
The main contract commencement date is…
Please acknowledge receipt.”
Consider what this letter is saying and what your response would be
Part 2
“This is to place a letter of intent (LOI) for [W] works to [X] ... by [Y] … strictly in
accordance with the following terms and conditions and to give an authorisation to
proceed immediately with the engineering, procurement and manufacturing in
accordance with this requisition.”
Sections then cover matters including:
Scope and Price
Payments Terms
Delivery Terms and Date
Contract Documents
Etc.
Consider what this letter is saying and what your response would be
4. Setting up the Project
Now, Contract is signed – we’re in a risky stadium !
Why?
It involves:
− Knowledge Transfer Checklist to be populated
− Knowledge Transfer Meeting to be held according to template
Knowledge Transfer Meeting - Template
Tender-project transition
• Hand Over
Checklist
aims to
structure the
hand over
between TM and
PM
• Hand over
checklist will be
part of updated
PMM
• Signed by
AM/TM/PM
Knowledge Transfer Process - 2
It involves:
− Knowledge Transfer Checklist to be populated
− Knowledge Transfer Meeting to be held according to template
− Responsible, Accountable, Consulted, Informed (RACI) table to be
populated and kept up to date
RACI Table
1Project Responsible & Assign ORM 'point of contact' for project Project Manager Project Manager ORM department
Accountable PM p.p.
Knowledge Transfer Meeting Define attendees Project Manager Project Manager
PM p.p.
Knowledge Transfer Meeting Sign Knowledge Transfer Checklist Project Manager Project Manager ORM department
Tender Manager Tender Manager
O&R Register Update/manage O&R Register Project Manager Project Manager ORM department (SC)
PM p.p.
Work budget Create/update work budget Project Manager Project Manager AD/BU/GM
PM p.p. Area Controller
Contingency budget Create/update contingency budget Project Manager Project Manager AD/BU/GM
PM p.p. Area Controller
Primary Kick-Off Meeting Define attendees Project Manager Project Manager DRIVE department
PM p.p.
Primary Kick-Off Meeting Organize/prepare Primary Kick-Off meetings Project Manager Project Manager
PM p.p.
Primary Kick-Off Meeting Define mitigation strategies for O&R Project Manager Project Manager DRIVE department
PM p.p.
Operational Action log Create/update operational action log Works Manager Project Manager DRIVE department DRIVE (SC)
All action holders (SC)
Operational staff (SC)
Non-operational Action log Create/update non-operational action log Finance Manager Project Manager Relevant supporting Core Project Management
departments Team (SC)
Knowledge Transfer Process - 3
Design &
Engineering
Opportunity Planning
& Risk
Contracts
Review your contract to identify obligations and the need for project-specific
systems?
Deliverables
Planning submittals
Discrepancies
Notices
Payments
It should:
− Reflect the Contract requirements (the Baseline)
And remember:
No planning → no deviation →
no variation → no compensation
Critical Path
Calculates float.
The Critical Path - Shortest route between work and the pub
Critcal Path Analysis - 1
New Wall
No Activity Time (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Excavate the trench
2 Pour the foundation
3 Raise the brickwork
4 Place the coping
5 Complete
6
7
8
Link Activity
Critcal Path Analysis - 2
New Wall
No Activity Time (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Excavate the trench
2 Pour the foundation
3 Raise the brickwork
4 Place the coping
5 Complete
6
7
8
New Wall
No Activity Time (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Excavate the trench
2 Pour the foundation
3 Raise the brickwork
4 Place the coping
5 Complete
6 Design
7 Order concrete
8 Order bricks
New Wall
No Activity Time (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Excavate the trench
2 Pour the foundation
3 Raise the brickwork
4 Place the coping
5 Complete
6 Design
7 Order concrete
8 Order bricks
Critcal Path Analysis - 5
New Wall
No Activity Time (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Excavate the trench
2 Pour the foundation
3 Raise the brickwork
4 Place the coping
5 Complete
6 Design
7 Order concrete
8 Order bricks
Critcal Path Analysis - 6
New Wall
No Activity Time (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Excavate the trench
2 Pour the foundation
3 Raise the brickwork
4 Place the coping
5 Complete
6 Design
7 Order concrete
8 Order bricks
Critcal Path Analysis - 7
New Wall
No Activity Time (days) 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
1 Excavate the trench
2 Pour the foundation
3 Raise the brickwork
4 Place the coping
5 Complete
6 Design
7 Order concrete
8 Order bricks
Total Float
Exercise 3 – Planning
Please refer to next slide for instruction
and hand out for doing the exercise
Instruction for Exercise 3
050
(safety should be planned into a project)
Chock car wheels 1 min When you are
060
070
Find car jack & wheel brace
Loosen wheel nuts
2
6
min
min
alone
080 Position jack 3 min
090 Raise car 4 min
100 Remove wheel nuts 1 min 110
120
Remove wheel
Install spare wheel
1
1
min
min
When you have
130 Replace wheel nuts 1 min a friend helping
140 Tighten wheel nuts 2 min
150 Lower car 1 min
160 Final tighten wheel nuts 2 min
170 Remove jack 1 min
180 Stow jack, wheel brace & punctured wheel 2 min When you have
190 Remove chocks 1 min
200 Wipe hands 1 min two friends
210 Complete 0
helping
Solution 1: When you are alone
Legend :
Project : Wheel Change Current Plan
Date : 1 Jan 2015
Prepared by : Superplan
Solution 2: When you are with a Friend
Legend :
Project : Wheel Change Driver Passenger
Date : 1 Jan 2015
Prepared by : Superplan
Solution 3: When you are with two Friends
Legend :
Project : Wheel Change Driver Passenger
Date : 1 Jan 2015
Prepared by : Superplan 2nd Passenger
Resource Planning and Critcal Path
Legend :
Project : Wheel Change Driver Passenger
Date : 1 Jan 2015
Prepared by : Superplan 2nd Passenger Critical path
Driver
Passenger
2nd Passenger
Networked Planning
zoek blokkeer
blokken de wielen
40 2 50 1
trek plaats
wielbouten wieldop
170 2 190 1
verwijder
blokken/st
210 1
Progress Reporting
Involves:
Making a report
For this, you will require details from your Subcontractors but who
should report in the context of their Contract with you.
Contractor’s Progress Records and Monitoring
− Correspondence
− Effects of changes
Cost plus
Feasibility
Financial circumstances
Political aspects
Legal / contractual
Early days of Project execution
Approvals
Relationships
Consultants’ performance
Access to works
Payment
Method of working
Sequence of working
Design
Use of Subcontractors
The Subcontractor can ‘change’
Method of working
Sequence of working
Manning levels
Price of work
Design
In Construction / Engineering projects:
‘change’ means what?
Involves awareness
5 steps
Step 1
Management of change
What types?
As an example …
5) Instructed variations.
8) Force Majeure.
Allowable and foreseeable Changes - issues
In the case of instructed Variations, further relevant details are often contained
elsewhere and can include:
Progress updates
Cost reports
Management of change
Notices must state the event and be clear it’s notice of a potential
claim
Why?
What type?
Change
Direct Indirect
Valuation of Change
Valuation rules will normally apply – money is value or cost plus profit;
And a ‘Claim’?
Simply, a request for reimbursement, from one party to another, of the money
and / or time consequences flowing from an event that the contractor was not
required to anticipate.
Valuation rules will normally again apply – money mainly cost or cost and
profit; time either prospective or respective.
Money impact
Valuation of Claims for compensation
beyond Contract
And again:
An Extension of Time:
‘Ownership’ of float
Effect of concurrency
Activity 1 2 3 4 5 6 7 8 9 10 11
ACTIVITY A
Original
ACTIVITY B Completion
ACTIVITY C
Why Delay?
Delay analysis techniques
Activity 1 2 3 4 5 6 7 8 9 10 11
ACTIVITY A Event
Original
ACTIVITY B Completion
ACTIVITY C
Estimate of Delay
Delay analysis techniques
Activity A
Activity B
Activity C
Activity D
Activity E
Completion
A. As-Planned V As-Built Method - 2
Activity A
Activity B
Activity C
Activity D
Activity E
Completion
A. As-Planned V As-Built Method - 3
Activity A
Activity B
Activity C
Activity D
Activity E
Completion
A. As-Planned V As-Built Method - 4
Activity A
Activity B
Activity C
Activity D
Activity E
Completion
(extension of time)
(contractor culpable)
A. As-Planned V As-Built Method - 5
Advantages
− Simple to understand
− Transparent
− Does not require a networked programme
− Relies upon actual progress
Disadvantages
− Subjective assessment of critical delays
− Depends also on opinion
− Requires as-built programme
B. Impacted As-Planned Method - 1
Activity A
Activity B
Activity C
Activity D
Activity E
Completion
B. Impacted As-Planned Method - 2
Activity A
Activity B
Activity C Delaying event
Activity D
Activity E
Completion
B. Impacted As-Planned Method - 3
Activity A
Activity B
Activity C Delaying event
Activity D
Activity E
Completion Impacted completion date
(extension of time)
B. Impacted As-Planned Method - 4
Advantages
− Quick
− Simple to carry out and understand
− Transparent
− As-built programme not required
− Can demonstrate acceleration and mitigation
Disadvantages
− Theoretical conclusions
− Requires a reasonable and robust as-planned programme
− Ignores actual progress
− Can hide concurrent delay
Delay Analysis Methods
Consider:
Contract conditions
Records available
Time available
Applicable law
Value of dispute
Most practical and common sense approach in circumstances
Delay Analysis Techniques
From SCL Delay and Disruption Protocol, 2nd edition paragraph 11.5
Exercise 4 - Case Study
‘The Delayed Project’
Please refer to next slide for instrcutions
and the hand out for the exercise itself
Instruction for Exercise 4
Contractual entitlement
Narrative / story
Apportionment
1. The contract
2. The records
3. The facts
1 2 3 4 5 6 7 8 9 10 11 12 13 14
Planned
1 STEEL FRAME Completion
Sub-Contractor A
200T CRANE
Main Contractor
Approved Programme
Step 5 – The Scott Schedule
To be populated meticulously –
a highly valuable tool at any stage
Event Description Brief Facts Clause Notice Relevant Activity Period of
No Ref Docs Affected Delay
1 Design Fault The connection 26.4(ii) Letter MOM Act 4.AG 2 wks
to Access detail for the 10.10.01 31.10.01
Gallery upper part of Drg 201 rev A
the gantry was dated
identified as 27.10.01
being Progress
underspecified report
on 10.10.01. 30.11.01
The engineer
was
immediately
notified. A
revised drawing
was issued on
22.10.01 and
the works
proceeded on
24.10.01.
Step 5 – The Scott Schedule
of events
1 Design Fault The connection 26.4(ii) Letter MOM Act 4.AG 2 wks
to Access detail for the 10.10.01 31.10.01
Gallery upper part of Drg 201 rev A
the gantry was dated
identified as 27.10.01
being Progress
underspecified report
on 10.10.01. 30.11.01
The engineer
was
immediately
notified. A
revised drawing
was issued on
22.10.01 and
the works
proceeded on
24.10.01.
CAUSE
EFFECT
8. Dispute Resolution
Dispute Avoidance – the basics 1
Work procedures
(e.g. internal - external communication, document management, ….)
Agree records
(“what do we accept to be substantiation if needed ?”)
Non-Binding
Negotiation us
Mediation us with help
Conciliation us with more help
Mini trial us with even more help
Expert determination them
Adjudication them
Binding
Arbitration them
Litigation them
If there are no further questions:
Mark Castell – Regional Managing Director Ernst Jan de Jong – Senior Consultant
mark.castell@drivertrett.com ernst.dejong@drivertrett.com
www.drivertrett.com
Days 1 and 2
Tendering
Procurement and sub-contracting
Construction contracts and letters of intent
Setting up the project
Planning & progress
Financial issues
Management of change
Dispute resolution
Day 3
FIDIC introduction
Overview of differences between different standard forms
Specific requirements of FIDIC contracts
Comparison with other standard forms
2
Introduction to FIDIC
3
FIDIC
Fédération Internationale des Ingénieurs-Conseils
Tendering procedures
Model Agreements
Standard Forms of Contract
7
General principles of FIDIC Standard Forms of
Contract - 1
10
CURRENT FIDIC MAIN STANDARD FORMS OF CONTRACT
Yellow book:
Plant and
Design-Build
Contract
Silver book:
EPC/Turnkey
Contract
Gold book:
DBO Contract
WHEN DO YOU USE WHICH STANDARD FORM?
Employer
Straightforward project ? Design ?
< € 500K or < 6 months no yes
no
yes
Contractor design
yes Ongoing
operation
? no
yes
Confirm your
understanding 1
16
EXERCISE
19
The Blue book
20
GENERALLY – BLUE BOOK
FIDIC produces the General Conditions (15 clauses) and does not
anticipate separate Particular Conditions to be used (however notes for
guidance are included).
23
FORMATION OF A CONTRACT – BLUE BOOK
24
FORMATION OF A CONTRACT – BLUE BOOK
25
FORMATION OF A CONTRACT – BLUE BOOK
26
BLUE BOOK GENERAL CONDITIONS
Clause 5 - Design
Clause 12 - Default
Clause 1 includes:
Pay those fees and other charges stated in the Contract Data
(sub-clause 1.6)
GENERALLY – BLUE BOOK
Contractor is responsible for its design “which shall be fit for the
intended purpose as specified in the Contract, or where no purposes
are specified, fit for their ordinary purposes” (sub-clause 5.2).
GENERALLY – BLUE BOOK
Provision for Taking Over for any completed part of the Works “...the
Employer shall not occupy or use any part of the Works prior to the
issue of a Taking-Over Certificate for that part of the Works” (sub-
clause 8.3)
Only the Engineer (or delegated assistants) can vary the Works
(sub-clause 10.1).
42
GENERALLY – RED BOOK
“...We offer to execute and complete the Works and remedy any defects therein,
in conformity with this Tender ... for the sum of [amount of money]...”
“We agree to abide by this Tender until [date] and it shall remain binding upon
us and may be accepted at any time before that date.”
“If this offer is accepted, we will provide the specified Performance Security,
commence the Works as soon as reasonably practicable after the Commencement
Date and complete the Works in accordance with the above-named documents
within the Time for Completion.”
“Unless and until a formal Agreement is prepared and executed, this Letter of
Tender, together with your written acceptance thereof, shall constitute a
binding contract between us.”
45
FORMATION OF A CONTRACT – RED BOOK
46
RED BOOK GENERAL CONDITIONS
47
GENERALLY – RED BOOK
Clause 1 includes:
Definitions (sub-clause 1.1).
Note; don’t forget the communications rules at sub-clauses 1.3 and 1.4
Unless the Engineer notifies otherwise, the Contractor shall adopt these
revised methods, which may require increases in the working hours and / or
in the numbers of Contractor’s Personnel or Goods, at the risk and cost of
the Contractor…
If these revised methods cause the Employer to incur additional costs, the
Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these
costs to the Employer, in addition to delay damages (if any) under Sub-
Clause 8.7 below.”
55
GENERALLY – RED BOOK
Provision for Taking Over for any completed part of the Works
“...the Employer shall not use any part of the Works unless and
until the Engineer has issued of a Taking-Over Certificate for that
part..” (sub-clause 10.2)
Only the Engineer (or delegated assistants) can vary the Works
(sub-clause 13.1).
Variations is a defined term.
Value engineering provisions are at sub-clause 13.2
61
GENERALLY – YELLOW BOOK
The purpose
The scope
The design
Other technical criteria
GENERALLY – YELLOW BOOK
64
GENERALLY – YELLOW BOOK (AS RED BOOK)
Clause 1 includes:
Definitions (sub-clause 1.1).
Note: don’t forget the communications rules at sub-clauses 1.3 and 1.4
Unless the Engineer notifies otherwise, the Contractor shall adopt these
revised methods, which may require increases in the working hours and / or
in the numbers of Contractor’s Personnel or Goods, at the risk and cost of
the Contractor…
If these revised methods cause the Employer to incur additional costs, the
Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these
costs to the Employer, in addition to delay damages (if any) under Sub-
Clause 8.7 below.”
73
GENERALLY – YELLOW BOOK (MAINLY AS RED BOOK)
Provision for Taking Over for any completed part of the Works
“...the Employer shall not use any part of the Works unless and
until the Engineer has issued of a Taking-Over Certificate for that
part..” (sub-clause 10.2)
Only the Engineer (or delegated assistants) can vary the Works
(sub-clause 13.1).
Variations is a defined term.
Value engineering provisions are at sub-clause 13.2
79
GENERALLY – SILVER BOOK (AS YELLOW BOOK)
The purpose
The scope
The design
Other technical criteria
GENERALLY – SILVER BOOK (AS YELLOW BOOK)
82
Clause 20 – Claims, Disputes and Arbitration
GENERALLY – SILVER BOOK (AS YELLOW BOOK)
Clause 1 includes:
Definitions (sub-clause 1.1).
Note; don’t forget the communications rules at sub-clauses 1.3 and 1.4
Contractor to design and construct the Works so they are fit for
the purposes for which the Works are intended as defined in the
Contract (sub-clause 4.1).
Unless the Employer notifies otherwise, the Contractor shall adopt these
revised methods, which may require increases in the working hours and / or
in the numbers of Contractor’s Personnel or Goods, at the risk and cost of
the Contractor…
If these revised methods cause the Employer to incur additional costs, the
Contractor shall subject to Sub-Clause 2.5 [Employer’s Claims] pay these
costs to the Employer, in addition to delay damages (if any) under Sub-
Clause 8.7 below.”
91
GENERALLY – SILVER BOOK (AS YELLOW BOOK)
97
EXERCISE
Appendix to
Employer’s Tender
Contractor design Lump Sum Representative
Particular
Conditions
Valuation project
Re-measurable Lump Sum Lump Sum
specific
101
EXERCISE
102
EXERCISE - ANSWERS
Sub-Clause 1.6 [Contract Agreement] says that the Employer and Contractor
shall enter into a Contract Agreement within 28 days of the Contractor receiving
the Letter of Acceptance.
Sub-Clause 4.2 [Performance Security] states that the Contractor shall provide to
the Employer Performance Security.
Sub-Clause 4.3 [Contractor’s Representative] provides for the Contractor to
appoint a Representative who will have the authority to act for the Contractor
(including issuing and receiving communications).
A detailed time programme (and separate report) under sub-clause 8.3
[Programme].
If Sub-Clause 14.4 [Schedule of Payments] applies and the Contract does not
contain a schedule of payments, the Contractor shall submit to the Engineer
within 42 days of the Commencement Date, non-binding estimates of the
expected payments during each quarterly period.
If Sub-Clause 14.2 [Advance Payment] applies, the Contractor shall provide to
the Employer an advance payment guarantee.
Sub-Clause 18.1 [General Requirements for Insurances] requires that the
relevant insuring Party shall provide to the other Party evidence that the
insurances have been effected, copies of policies and evidence of payment of
premiums; and give notice of such to the Engineer.
EXERCISE - ANSWERS
The ‘things’ that the Contractor should expect to receive from the
Employer and/or his representative within say 28 days of Contract
Award:
• Sub-Clause 1.6 [Contract Agreement] says that the Employer and Contractor
shall enter into a Contract Agreement within 28 days of the Contractor
receiving the Letter of Acceptance.
• Sub-Clause 2.1 [Right of Access to Site] says that the Employer shall give the
Contractor right of access to, and possession of parts of the Site as stated in
the Appendix to Tender.
• Sub-Clause 3.2 [Delegation by the Engineer] allows the Engineer to assign
duties and / or delegate authority to Assistants; this would include authority
to communicate with the Contractor on certain matters.
• Not less than 7 days notice of the Commencement Date (sub-clause 8.1).
• If Sub-Clause 14.2 [Advance Payment] applies, the Employer shall pay the
advance payment in accordance with Sub-Clause 14.7 [Payment].
• Sub-Clause 18.1 [General Requirements for Insurances] requires that the
relevant insuring Party shall provide to the other Party evidence that the
insurances have been effected, copies of policies and evidence of payment of
premiums; and give notice of such to the Engineer.
Some particular concepts of
FIDIC standard forms
105
Subcontracting
106
FIDIC requires a Contractor to obtain consent to sub-contract works
109
Variations – Blue Book
110
Valuation of variations – Blue Book
111
Variations – Yellow Book
Clause 13.1 does not set out the types of changes that can be made i.e.
authority for variations
112
Procedure – Yellow Book
Clause 3.3 states that the Contractor must comply with all instructions
from the Engineer
113
Valuation of variations – Yellow Book
114
Claims
Blue Book Clause 10.6 – Employer’s claims
116
Yellow Book Clause 2.5 – Employer’s claims
117
Yellow Book Employer’s claims
118
Blue Book Clause 10.3 – Early Warning
119
Blue Book Contractor’s claims
Clause 10.5 - Engineer to check, consult and agree time and cost
effects, or determine.
120
Blue Book Clause 6.1 – Defined Risks
121
Yellow Book Clause 20.1 – Contractor’s claims
122
Yellow Book Clause 20.1 – Contractor’s claims
123
Yellow Book Clause 20.1 – Contractor’s claims
124
Yellow Book Contractor’s claims
125
FIDIC Exercise –
identifying the
changes
126
Dispute resolution
Resolution of Disputes under Blue Book
128
Resolution of Disputes under Yellow Book
129
YELLOW BOOK TYPICAL SEQUENCE OF DISPUTE EVENTS
ENVISAGED IN CLAUSE 20
131
Second editions of the Red, Yellow and Silver books
are published in 2017
Why?
Contractor not liable for defects or damages >2 years after DNP;
Notices must state it’s a notice and make reference to the relevant
sub-clause.
TIME ISSUES
All activities to be logic linked, showing early and late start and finish
dates, float and critical path,
Must also show holiday periods, right of access dates, key delivery dates.
138
IN OVERVIEW
Employer Engineer
Owner
Contractor
Company
Charterer
Contractor
General principles of contract management
Workshop Objectives
Demonstrate how you can improve the DEME Group’s contractual and
commercial position in both the pre-contract and post-contract phases of
projects.
On day 3, to:
Explain the philosophy of the main FIDIC standard forms of contract and what
their use means.
142
IF THERE ARE NO FURTHER QUESTIONS:
Mark Castell – Regional Managing Director Ernst Jan de Jong – Senior Consultant
mark.castell@drivertrett.com ernst.dejong@drivertrett.com
www.drivertrett.com