Professional Documents
Culture Documents
HDD Procedure For Road Closure
HDD Procedure For Road Closure
HDD Procedure For Road Closure
ID-PRC-09
PROCEDURE FOR
TRENCHLESS INSTALLATION METHOD
(JALAN HAJI ABDUL MANAN: CH0.0C-CH96.0C)
PROCEDURE FOR TRENCHLESS INSTALLATION METHOD
Doc. No. ID-PRC-09 Rev. No. 1
Date: 13-01-2022 Page : 2 of 15
TABLE OF CONTENTS
SECTION PAGE
Cover Page 1
Table of Contents 2
1.0 Introduction 3
1.1 Scope
1.2 Definitions
2.0 General 3
3.0 Personnel 4
1.0 INTRODUCTION
1.1 Scope
1.2 Definitions
2.0 GENERAL
Pipeline construction which related to road crossings, water way crossing and
underground crossing shall be installed in accordance with drawings or proposed
HDD procedure which have been approved by CLIENT and in manner, which
satisfies all requirements of the authorities having jurisdiction over the crossing.
Impact on users of the roads shall be minimised and the safety of the roads shall not
be adversely affected.
CONTRACTOR shall obtain all permits necessary for all crossings when requuired.
Prior to commencement of work, a joint survey will be carried out together with the
client to finalise and confirm the crossing alignment.
3.0 PERSONNEL
CONTRACTOR shall employ only qualified personnel to perform the works under
safe conditions.
CONTRACTOR shall use only appropriate plant and equipment. All such plant shall
be in good condition.
Subject to the approval of CLIENT and the relevant authority, CONTRACTOR may
use one of the following methods of installation.
Boring or Jacking
Horizontal Directional Drilling ( HDD )
When the pilot casing has emerged at the opposite end of the
bore, the boring or jacking equipment shall be removed and
the carrier pipe temporarily held to the pilot casing. The pipe
shall then be advanced through the bore until the carrier pipe
is in the desired position, allowing adequate free pipe
(minimum 3 metres) for tie-ins and for inspection of pipe
surface. The pilot casing shall then be removed for re-use on
subsequent crossings.
PROCEDURE FOR TRENCHLESS INSTALLATION METHOD
Doc. No. ID-PRC-09 Rev. No. 1
Date: 13-01-2022 Page : 6 of 15
5.2.2.3 Backfilling
The drill profile shall be designed with a minimum depth of 2.0 meters
from the existing ground level. The depth will also be depending on
authorities requirements.
Two mixing tanks will be used for bentonite mixing. One will act as
standby tank while the other one is being discharge.
When the drilling fluid at the 1st tank is nearly empty, the discharge
valve of the 1st tank will be closed. At the same time, the discharge valve
for the 2nd tank will be opened. Through this practice, continuous
consumption of the bentonite can be achieved.
Before re-mixing of bentonite into the empty tank, the tank will be
cleaned by flushing with water.
PROCEDURE FOR TRENCHLESS INSTALLATION METHOD
Doc. No. ID-PRC-09 Rev. No. 1
Date: 13-01-2022 Page : 9 of 15
i. SITE PREPARATION
The 1st length of the drill rod guided by the drill head will be
rotated and jacked into the ground without any bending. Bending will be
started during the 2nd rod of drilling.
When the end of the 1st drill rod reach the jaw of the rig, one
rod is considered drilled into the ground and the 2nd rod is then attached to
the end tail of the 1st rod. Bending will made at the 2nd rod drilling.
PROCEDURE FOR TRENCHLESS INSTALLATION METHOD
Doc. No. ID-PRC-09 Rev. No. 1
Date: 13-01-2022 Page : 10 of 15
Through out the forward run phase, the location and direction
of the drill is monitored at every 4.57 meters interval (length of 1 drill rod).
When the particular drill rod has achieved the zero bending
state, the location shall be marked as the exit point for the HDD pipes
during pulling stage. The entry point for HDD pipes shall be marked
whereby the drill rod is still subjected to zero bending (0 degree pitch).
If the drill head strays off the course, the locator technician
shall inform the drilling operator via two ways radio communication. The
operator will make the required adjustment until the drill head gets back to
the original course.
Upon completion of the pilot drill, ground level along the actual
pilot drill alignment will be taken at an interval of each drill rod. All the
readings of this ground level shall be incorporated in the HDD profile
drawings and will be converted and referred from the datum levels as per
the survey drawing.
Once the drill head reaches the exit point, it is removed and a
fluid jet reamer is attached and the back reaming operation is reversed
from the exit pit towards the entry pit.
PROCEDURE FOR TRENCHLESS INSTALLATION METHOD
Doc. No. ID-PRC-09 Rev. No. 1
Date: 13-01-2022 Page : 11 of 15
During the back reaming activity, drill rods are extracted from
the entry point (at rig machine). In order to maintain a string inside the
tunnel during the hole enlargement, drill rods are jointed up at the exit pit
until the reamer reaches the entry pit.
Once the reamer and towing head reach to the exit pit, the
reamer and swivel beacon will be dismantled. The towing head will be cut
out and the pipes will then be properly sealed.
Site area will then be cleaned from any dumped and unused
material.
PROCEDURE FOR TRENCHLESS INSTALLATION METHOD
Doc. No. ID-PRC-09 Rev. No. 1
Date: 13-01-2022 Page : 14 of 15
The work shall be completed and affected road shall be reopen to the public
within the time frame agreeable by CLIENT and Related Authority. If the work
cannot be completed due to certain circumstances, CONTRACTOR shall cut
the pipe and the affected road shall be clean up and reopen to the public
within the time frame.
i. Calculation for combined stress for HDD stress analysis shall not
exceed 40% of SMYS.
ii. Reaming work shall only commence after actual drawing and stress
analysis has been approved by SEC representative.
iii. Pipe pulling shall not proceed unless swivel beacon is attached
utilized.
iv. Entry and exit pit shall be trial pit to minimum depth of 2m
The supervisor shall be responsible for the site safety. He shall be reporting
to the main contractor’s site representative in the event of an
accident/incident happens. Safety measures to be implemented are as
follows: -
i. Prior to any site excavation, a survey of the site shall be carried out to
determine the presence (if any) of buried third party cables or services.
ii. Warning signs and colored bunting shall be erected at the location of
overhead power cables.
iii. Warning signs (DANGER KEEP AWAY), shall be erected at all site of
excavation.
iv. Workers will be equipped with PPE.
v. Fire extinguisher will be provided at job site.
PROCEDURE FOR TRENCHLESS INSTALLATION METHOD
Doc. No. ID-PRC-09 Rev. No. 1
Date: 13-01-2022 Page : 15 of 15
vi. Traffic cones and wall barrier (if necessary) to be provided where
working at busy public traffic area.