Professional Documents
Culture Documents
Code of Practice For Installation AND Observation of Cross Arms For Measurement of Internal Vertical Movement in Earth Dams
Code of Practice For Installation AND Observation of Cross Arms For Measurement of Internal Vertical Movement in Earth Dams
Is 7500:2000
Indian Standard
C) BIS 2000
FOREWORD
This Indian Standard ( First Revision ) was adopted by theBureau of Indian Standards, after the draft finalized by
the Hydraulic Structures-Instrumentation Sectional Committee had been approved by the Water Resources Division
Council.
Generally the more important field observations made on the behaviour of earth dams are those of settlement of
embankment and measurements of internal pore pressure. These provide a record of field performance and furnish
information that would enable future designs to be based on realistic conditions. Vertical movement devices
provide a means of determining volume change within the embankment and settlement of foundations, and identify
zones of excessive and uneven settlement which may lead to stabi Iity problem and cracking. The cross arm installation
especially permits the measurement of consolidation within any desired lift or lifts of embankment both during, and
after construction. Consideration governing the choice and location of this instrument is given in IS 7436
( Part 1 ) :1-993 ‘Guide for types of measurements for structures in river valley projects and criteria for choice and
location of measuring instruments: Part 1 For earth and rock-fill dams’.
This standard was first published in 1974. A revision of this standard has been taken up to incorporate certain
changes found necessary in the standard in the light of comments received from the users. The major changes in
this revision are inclusion of paragraphs on general guidance, maintenance and advantages and limitations of the
mechanical type of installation. However, these provisions for electrical type of installation shall be considered for
inclusion as soon as text for the same is prepared and finalized.
In the formulation of this standard due weightage has been given to international co-ordination among the
standards and practices prevailing in different countries in addition to relating it-to the practices in the field in this
country. As per USBR Publication ‘Embankment Dam Instrumentation Manual, Jan 1987’, mechanical type of cross
arms is not being used in that country because other instruments that are easier to install and monitor have been
developed.
For the purpose of deciding whether a particular requirement of this standard is complied with, the final value,
observed or calculated expressing the result of a test or analysis, shall be rounded off in accordance with IS 2: 1960
‘Rules for rounding off numerical values ( revised)’. Thenumber of significant places retained in the rounded off
value should be the same as that of the specified value in this standard.
IS 7500:2000
Indian Standard
CODE OF PRACTICE FOR INSTALLATION AND
OBSERVATION OF CROSS ARMS FOR MEASUREMENT
OF INTERNAL VERTICAL MOVEMENT IN EARTH DAMS
( First Revision)
1
Is 7500:2000
~$,.
w
a
—
t
HEMP
OR O AKUM
HEMP OR OAKUM
4. ‘1
.,
CROSS ARM
=“,
II flREOUIRED EXCAVATION
I ‘ L____
k
l------
I i -7
w’
II /
/
EXCAVATION OF
l..
[
ROCK LINE ~
65
1t
---- 1-.1i
I
I MEASURl Nr3 POINT= 100mm@ MIN HOLE
.,
&j J
NOTE — As each cross arm unit is placed, determine the elevations of all cross arms installed.
FIG. 1 TYPICAL INSTALLATION OF CROSS ARM, MeChaniCal. T)’tw FOR 3000 mm SPACING — Gt;NI:RAi.
2
1S 7500:2000
,,
\4fMlNELEvATION
P’;’
-,,,$JEXCA
VAT’;, ,
cIF \ “ o
u-l
I
Ln
\ EMBANKMENT i
\ BEFORE BEGIN-
I NING EXCAVATION
\ FOR CROSSARM
\
\
\
\ 1
,1 POWER COMPACTED
‘1 f
EARTHFILL
\ OAKU~ -/ i- I
\
d
I
I
0
I
OAKUM OR I m
N
I I ,
2 LUQS,
50mm
‘EM’
@ PIPE
\
‘AcK’NGl\
I
I
I
‘--t
I
I
I o
In
----1i
DEPRESSION AROUND
PIPE FORMED BY PIPE
,0,,,>,
The details of reading scale with adaptor used for Any suitable device as described in IS 6935. The
lowering the torpedo are given in Fig. 4. If torpedo measuring .devices should be kept clean and free of
is attached to calibrated stainless steel aircraft cable, grit. It is suggested that each type of instrument
reading scale may be suitably modified for aircraft be disassembled, in so far as practicable, and cleaned
cable. following completion of readings. The tape should
be carefully inspected for kinks and breaks.
3
IS 7500:2000
STEEL TAPE
Ii
tml’
Ql!F
w
00
TAPE EYE
10 mm YOKE
A
1
—35mm d 1:
READING
-3EL-. “
%
w I
Dfie,Tin.&-
FuallluN 0 ! ~_-PAWL S
1 s
PAWLS 1
LOT Iii
4
—
AfMlrSTVERNIERSCALE
F~ ZERO ATTHIS POINT
(LEvEL POINT)
\
BRASSSTRIP
#-
F-
r 64 mm STANO
PIP E
19mm 51AN0AR0
[ COUPLING \
‘oRpEoO\
r -.
F 40mm * STANDARD
PIPES INSERT
u ENLARGED L)
AOAPTGR FOR SOmm PtPE
$
sOmm * STANDARD
PIPE -
I
[
e
HEXAGONAL NUT
WELOEO
u
\ THUM8 SCREW
z
NOTES
1 Recommend a 15-kg spring scale. grapple hook. tape clamp handle and a 10-kg tension on tape wheit taking settlement readings.
2 Use device as shown during construction. Thereafter cut device to I I 20 mm length and thread bottom end of 50-mm pipe to tit top of installation. ..
N
o
FIG. 4 READING SCALE wtrri ADAWOR 0
0
. ... . I I
1s 7500:2000
6
IS 7500:2000
6.3.2 Procedure forlnstallation in Rocky Soils cover leaving a depression around the pipe cover. A
50 mm thick sand pad should be placed and then the
6.3.2.1 Since boring of holes for aligning the cross
cross arm device should be placed and aligned (after
arm device is not possible in rocky soils, a practicable
removing the top cover of the upper spacer pipe).
method is mounding around the 40 mm pipe of the
cross armdevice. TEIS method should be adopted in 6.3.2.5 The sequence of operations involved in
previous zones of zoned embankments. installing cross arms in rocky soils is given in Fig. 6.
6.3.2.2 The cross arm device should be placed and 6.4 Correction for Alignment
then aligned and backfilled with previous (rocky)
material .up to 250 mm above the cross arm. The lower After installing the 2500 mm length of spacer pipe in
1 250.mm section of 50 mm spacer pipe should then the bored hole and again after the cross arm assembly
be placed and aligned. has been installed, the protective pipe cover should
be removed and the vertical alignment of the system
6.3.2.3 The pipe cover should be placed and rocky checked by lowering a plumb bob from the straddle
materials mounded to lower end of pipe cover. The hub strings. If it is impracticable to correct the error.
embankment should be raised 1 200 mm above cross succeeding pipe sections should be placed vertically
arm. The upper 1250 mm section of50 mm spacer and the offsetfrom the true vertical alignment recorded.
pipe with coupling should be connected to the lower If a deviation from vertical alignment is found, an
section of the spacer pipe and pipe cover should be attempt should be made immediately to correct the
put on the top of the upper section of the spa~~r error.
pipe.
6.5 Rotation of Cross Arms
6.3.2.4 Rocky material should be mounded around
the upper section of spacer pipe. Embankment placing Each cross arm section should be placed in a
should be continued to 150 mm above top of pipe manner that will distribute the weight of the channel
COVE
.An&xz&;
i$ll --OAKUM ( B)
ti-
—1
f-.
7s
Pm Cevm
#A-
1 1-
8
40 mm 6 PIPE
PHASE 1 PHASE 2
Operations Operations
1.Locate centre of installation 1. Locate centre of installation
a, ---- ,r-.r.—— J: ----- _
2. Excavate trench remove soil above soil pipe cover
J:------- ------ -l-_-,—_
L. LtwtrI vu wrr ukd area aujaceru w cenwe 12rrxmng
3. Bore 100 mm minimum dia hole; clean hole 3. Remove pipe cover from foundation extension
4. Place and align foundation extension in hole 4. Place and align cross arm
5. Place sand-cement grout around pipe preferably with 5. Place pipe cover at top of 40 mm pipe, warp with oakum
a tremie burlap of(A) and (B)
6. Place removable pipe coveC tamp fine soil around cover 6. Backfill hole and trench to level of oakum ( B)
to foundation line 7, Obtain original elevation of cross arm measuring point
7. Compact embankment above installation 8. Complete backfilling
9. Continue embankent placing
PE
I 4’
I ;~..y
—200mm 6 BORED
PHASE 3 PHASE 4
Operations Operations
1. Locate centre of installation 1. At outer slope of rock-free zone locate centre of
installation
2. Excavate trench
2. Level a working area, bore hole
3. Bore hole, remove pipe cover
3. Assemble, place and align 50 mm standard pipe
4. Place 50 mm spacer pipe, align pipe extension to outer surtace of embankment
5. Backfill hole to 400 mm below bottom of trench 4. Backfillhole
6. Continue with operation 4 through 9 of phase 2 5. Mould rocky soils around pipe to outer embankment
7. Repeat operation for each cross arm unit slope
6. Place concrete
6.6 Compaction of Soil Around Installation 6.8.1 I.engths of 50 .mm spacer pipe should be
Soil around the installation should be compacted assembled to extend the installation progressively
to the equivalent unit dry weight of the surrounding to the surface of the completed embankment.
material and recorded samples of the soiI at the location
6.8.2 As construction progresses pipe cover should
of each cross arm should be taken.
be removed, assembled 50mm spacer pipe extension
6.7 Protection of Telescopic Joints should t-seinstalled and the soil (rock-free or rocky)
To prevent the ingress of soils all the telescopic joints backfilled or mounded around the pipe as the case
should be protected with hemp packing or oakum may be, to outer embankment slope.
held in place by hessian wired on the pipes, taking
care that the telescopic movement of the pipes is not 6.8.3 Concrete should be-placed near the top of the
prevented. slope as shown in Fig. 1.
8
IS 7500:2000
C OF INSTALLATION
/- ●IPE Gov&R
1 <
mu
EMT
PIPE,
PHASE 1 PHASE 2
Operations Operations
1. Locate centre of installation 1. Raise embankment 100 m above cross arm
2. Level 75 cmarea adjacent to centre of installation 2. Place and align upper section of spacer pipe
3. Bore 100 mm dia hole; clean hole 3. Place pipe cover and mound around pipe
4. Place and align foundation extension in hole 4. Continue embankment placing to 150 mm above top of
pipe cover, leaving a depression around pipe
5. With a tremie, place sand-cement grout around
extension pipe
6. Placeand align cross arm unit
7. Place oakum and wrap with burlap at ( A ), backfill
to 225 mm above centre line of cross arm
8. Obtain originalelevation of cross arm measuring point
9. Place and align lower section of spacer pipe
10. Place oakum and wrap with burlap at ( B ), seat pipe
cover
11.Mound soil around pipe to lower end of pipe cover
All dimensions in millimetres.
FIG. 6 TYPiCAL VERTiCAL MOVEMENT DEVICE — INSTALLATION IN ROCKYSOILS( Confinued )
9
Is 7500:2000
— PIPE COVSR
T HRE40EB ENo
so m m $ SP4CER
PIPS LOWER
-J=. SEC,,ON
12s0
4%, +> OAKSJM(B)
I /GO1 F i x ~Omm # PIPS
v
.
OIL
2
T
‘ llR
2000
SURRtSD
SO mm #
SPACER ●IPES
~ OP IMSTALLAT ION
J+&
BURRICO CROSS ARM
c:?!*’’ocR”sA
c * CROSS.ARM
=-.
PAO
PHASE 3 PHASE 4
Operations Operations
1. Check centre of installation 1. When embankment is raised to 300 mm below top of
2. If necessary, realign column lower spacer pipe, remove cover, place and align pipe
extension assembly
3. Place and pad
2. Place mound around pipe as embankment is raisecf
4. Place and align cross arm
3. Place concrate cap
5. Repeat operations 7.through 11 of Phase 1
be determined by Ievelling methods with reference The torpedo should then be withdrawn from the pipe
to an established-benchma~k located away from the column.
dam. The original elevationshould be recorded when
a cross arm is installed. These original elevations NOTE — If the pawls on the torpedo fai I to latch when
the device reaches the bottom of the pipe column, a
should be recorded when backfill around a cross arm
section of 10 mm pipe 60 mm long may be slipped over
is placedto within approximately 500 mm of the top
the tape cable and lowered by means of a wire. into the
of the 40 mm pipe. At that time, the pipe cover should installation until it rests on top of the torpedo. This
be removed, the reading scale attached and the added weight should latch the torpedo.
elevation of the zero or reference point on the scale
determined to the nearest 2 mm. Then the torpedo 7.3 Current elevations of cross artn measuring points
(which is attached to an Engineer’s tape or calibrated should then.be determined by using the established
aircraft cable) should be lowered into the pipe and elevation of the top of the reading scale and the measured
the initial distance to the measuring point of the top vertical distance. Then by subtracting the current
cross arm unit read and recorded. The distance should elevations of originally established ( see 7.2 ) vertical
be read and the elevations of all cross arm measuring movements of cross arms should be obtained, Elevation
points below the cross arm unit just placed determined. of the top of the reading scale should be obtained
After determining the elevation of the bottom ctoss for each set of periodic readings with reference to a
arm in the system, the torpedo should be dropped permanent benchmark but this elevation is temporary
to the latching place to latch the pawls ( see Note ). and is not a fixed point on the structure.
10
Is 7500:2000
7.3.1 Water depth in the pipe system should be I‘ecord tests mentioned in 8. In addition, other relevant
determined by using the water level indicator, every ~ata, such as the corresponding lake levels, pore
time the set of observations by torpedo is taken. 1)ressure in the vicinity of the cross arm installation
I‘ainfall on the day of observation and the exact stage
7.4 A complete set of readings should be made on
>f construction should also be reported.
the entire existing installation, each time an additional
cross arm unit is installed during construction of the 10 GENERAL GUIDANCE
embankment. When construction is suspended the
system should be so adopted so that readings can
10.1 All steel parts of the installation should be coated
with 2 coats of red oxide or any similar anti-corrosive
be made at monthly (30 days ) intervals or earlier in
special cases, if required. The first set of periodic Ipaint to prevent corrosion.
reading should be made immediately after installation, 10.2 The edges of the 40 mm pipe should be machine
thereafter readings should be taken every three months cut or filed flat so that the accuracy of the readings
for the first three years and every six months thereafter. k maintained.
A proforma for the record of observations is given in
Annex A. 10.3 It is necessary to see that the 40 mm steel pipe
is securely bolted to the channel to prevent slippage.
8 RECORD OF TESTS Alternatively it could be welded.
8.1 Record tests of embankment and foundation 11 MAINTENANCE
-materials at the instrument installation are necessary
to obtain data on the soils adjacent to the instruments. 11.1 It is essential to ensure plumbness of the
These should include tests for grain size analysis, installation by preventing movement of heavy
consistency limits and consolidation characteristics equipment, particularly during construction.
for the soil placed at every C}OSSarm level. 11.2 Ciipping of the installation during all.d after
8.2 In addition, at-each unit of the internal vertical installation should be ensured to prevent any foreign
movement apparatus in earthfill material, two field debris, etc, being introduced into the installation by
density tests should be made; one test sample should unauthorized personnel.
be obtained from the soil at the bottom of the trench 11.3 Each time the measuring torpedo is used, it
excavated for the cross arm unit; the other should be should be properly cleaned and lubricated for free
obtained in the tamped backfi II of the trench after it movement of the spring loaded pawls. The steel tape
has been brought up to grade. of the stainless steel cable should also be inspected
for any kinks or damage and cleaned and oiled. if
8.3 When all or a part of the dam is founded on
required.
highly compressible materials representative
undisturbed samples should be obtained from the 11.4 To prevent unnecessary misuse and possible
foundation at the location of the vertical movement loss of the measuring torpedo, use of a dummy torpedo
installations, unless suitable samples have been of equal length and 33 mm dia with soft wire or strong
obtained previously from these locations. nylon cord or string should be used to determine if
there is any inclination and/or obstruction in the
8.4 No tests are required when the internal movement
installation. Thereafter the measuring torpedo should
device is placed on rock foundation unless specially
be used.
requested.
12 ADVANTAGES AND LIMITATIONS
8.5 Tests at the internal movement units should be
designated ‘record rolled’, ‘record tamped’ or 12.1 Advantages
‘undisturbed’ depending on the material being tested.
The installation is relatively simple and cheap which
9 PROGRESS REPORTS provides accurate determination of consolidation at
different levels during and after construction, thereby
9.1 The report should show the current elevation
controlling the progress of fill material .This data
of the embankment at the installation, the number of
provides a warning of any instability in the foundation
cross arms, the compression of the embankment and
and/or embankment due to uneven settlement which
the settlement of the foundation. The narrative portion
may call for remedial measures.
of the progress report should discuss variations from
the instructions and installation procedures. 12.2 Limitations
Photographs, drawings and charts pertinent to
Since drill hole installations are not possible in this
the installation should be included.
case the device has to be placed during construction
9.2 The report should also contain results of of embankments. This”will obstruct the movement of
11
—
1s 7500:2000
construction equipment causing delay and possible similar to the mechanical type (Section I ) except for
damage to device. the following:
Maintaining the vertical alignment of the whole a) Plastic pipes are used instead of steel pipes.
installation is very essential for the measurement of
the settlement with torpedo. Since construction of b) Aluminium channel sections are used for the
high dams take comparatively longer period, there cross arms instead of steel channels.
exists greater possibility of horizontal movements in c) The aluminium channels are not fastened to
embankment and plumbness of the installation is the vertical pipes.
affected. Hence cross arms may be installed w ith greater
confidence in medium dams of 30 to 40 metres height. d) An electrical probe attached to graduated cable
is used for measuring depths of cross arm of
SECTION 2 ELECTRICAL TYPE ——
torpedo.
13 EQUIPMENT
13.1. I A typical installation enabling measurements
13;1 The electrical type OTcross arm installation is at 1 500 mm interval is illustrated in Fig. 7.
Ii??
ID
Alldimensionsin millimetres.
FIG. 7 TYPICALCOMPLETEDCROSSARM INSTALLATION
ELECTRICALTYPE FOR I 500 mm SPACING OF CROSS ARMS
12
1S 7500:2000
7
1150
and 54 mm outside diameter and of variable length
extending the column of pipes to the surface of the 400
13
1s 7500:2000
-i501- ———
I
—
T
3-1
SECTION XX
0
Mq!31
1-o.
—.— .._.
1OOO--I
I
IL I
~PIPE COVER i
+ 450mm#lN BACKFILL
I 1,~ OVER PIPEI COYER
I I
j!
I
750 750 -—;
LA .-— J
II ALUMINIUM CHANNEL
I II
1~:1
/’+’TRENCH.MIN DIMENSIONS \ AUGER HOLE, 150mm -+ x
1500 X750 X1050rnm DEEP, 950 mm DEEP
MAX DEPTH 1200 mm
cover should be placed over the extending 40 mm to keep dirt from entering the pipe system when the
pipe and covered with a450 mm minimum of compacted pipe cover is removedfrom the existing installation.
embankment material. The pipe cover should be removed and replaced as
required with a twisting motion in order not to disturb
16.3 Placing Cross Arm Units “ the packing between the lengths of telescoping pipe.
The vertical movement apparatus ( see Fig. 7 ) can 16.”3.1.2 A practical method for boring the required
be installed either in ‘rock-free’ soil or in ‘rocky’ soils, holes below the excavated trench for a cross arm
or in a combination of soils as foundin a zoned type unit is by the use of a power auger. After the cross
of earth and rockfill embankment. A ‘rock-free’ soil arm unit is installed, the angular space surrounding
is defined as a soil that can be penetrated by; 250 mm the pipe in the bore should be backfilled with selected
diameter power auger. Installation of the apparatus fine material and the soil compact day hand rodding
in ‘rock-free’ soils is given in 6.3.1 and in ‘rocky’ around the telescoping ~ipe section.
soils in 6.3.2.
16.3.1.3 When the embankment co”ntains a
16.3.1 Procedure for Installation in Rock-Free Soils considerable amount of rock, the augering of holes
for installation of cross arm units can be expedited if
16.3.1.1 In ‘rock-free’ soils the embankment should the backfill over the pipe cover is of selected fine
reach an elevation of approximately 4500 mm above material. This fine material can be placed and compacted
the measuring points of a cross arm unit previously inside a cylinder of metal pipe,or tubing having an
placed before excavating the trench and boring the internal diameter of approximately 250.mm. The pipe
hole for the cross arm. After excavating the trench may be progressively jacked to a higher elevation.
and boring the hole of a cross arm unit, a section of When the holeis augered for succeeding cross arm
light-weight pipe or tubing maybe placed in the hole unit, most of the fine material is removed.
14
1s 7500:2000
1-6.3.1.4 Backjllling tr.enchesfor cross armunil of each cross arm should be taken.
Whenthe trench has been backfilled with typical 16.7 Protection of Telescoping Joints
embankment materials to within approximately
300 mm of the top of the 25 mm pipe (bottom of To prevent the.ingress of soil, all the telescopic joints
pipe cover) the initial elevation of the cross arm shall be protected with rubber ‘O’ ring seals as
measuring point should be recorded as described described in”Fig. 8.
in 17.2. Thereafter, a minimum of 500 mm of typical
embankment material should be compacted over the 16.8 Completion of an Installation
pipe cover before embankment placing operations
are resumed at the place of installation. As the installation nears the outer surface of the
dam embankment, the operations given in 16.8.3
16.3.2 Procedure for Installation in Rocky Soils should be carried out.
16.3.2.1 Since boring of holes for aligning the cross 16.8.1 Lengths of 40 mm spacer pipe should be
arm device is not possible in rocky soils, a practicable assembled to extend the installation progressively
method is mounding around the 25 mm pipe of the to the surface of the completed embankment.
cross arm device. This method should be adopted in
perviously zoned embankrnemts. 16.8.2 As construction progresses pipe cover should
be removed, assembled, 40 mm spacer pipe extension
16.3.2.2 The cross arm @vi,c~l should be placed and should be installed and the soil ( rock-free or rocky )
then aligned and backfilled with pervious ( rocky ) backfilled or mounded around the pipe as the case
material up to 175 mm above the crd~s arm. TAe may be, to outer embankment slope.
40 mm spacer pipe should than be placed and aligned.
16.8.3 Concrete should be placed about the top of
16.3.2.3 Rocky material should be mounded around the slope as shown in Fig. 7.
the upper section of spacer.pipe. Embankment placing
should be continued to 75 mm above the top of pipe 17 OBSERVATIONS
cover leaving a depression around it, A 50 mm thick
sand pad should be placed and then the cross arm 17.1 The equipment required for obtaining settle-
device should be pIacedand aligned (after removing ment readings are an Electrical Probe, Marked Cable
the top cover of the upper spacer pipe). and an Indicator. The elevation of the cross arm units
are determined by lowering the probe through the
16.4 C-orrection for Alignment reading scale ( see Fig. 10) and into the pipe system
by means of the calibrated cable. The cable is passed
After installing the 1150 mm length of spacer pipe in over the pulley and the probe is lowered into the
the bored hole and also the cross arm assembly, the 25 mm pipe ( measuring points on each cross arm
protective pipe cover should be removed and the unit ). On reading the location of each cross arm, the
vertical alignment of the system checked by lowering indicator gives an audio signal upon which the reading
a p“lumb bob from the straddle hub strings. It is is taken with the help of the marking on the cable
impracticable to correct the error, succeeding pipe and on the scale. When readings are made, the reading
sections should be placed vertically and the offset scale is attached to the top section of the pipe projecting
from the true vertical alignment recorded. If a deviation from the -existing installation. The elevation of the
from vertical alignment is found, an attempt should levelling plate on top of the reading scale should be
be made immediately to ccmrect the error. established from the top of the reading scale to the
respective cross arm measuring points are obtained
16.5 Rotation of Cross Arms by using, the probe and attached cable.
is attached to a calibrated electrical cable) should be cross arm unit is installed during construction of the
Iow-ered into the pipe and the initial distance to the embankment. When construction is suspended, the
location of the top cross arm unit read and recorded. system should be adopted so that readings can be
This distance should be read and the elevations of taken at monthly ( 3b days ) intervals or earlier in
all cross arm measuring points below the cross arm special cases, if required. The first set of periodic
unit just placed determined. After determining the readings should be taken immediately after installation,
elevation of the bottom cross arm in the system, the thereafter readings should be taken every three months
probe should be withdrawn from the pipe column. for the first three years and every six months thereafter.
A profc)rma for the record of observations is given
17.3 See 7.3.
in Annex A.
17.3.1 See 7.3.1.
18 RECORD.OF TESTS ( See 8 )
17.4 A complete set of readings should be made on
the entire existing installation each time an additional 19 PROGRESS REPORTS ( See 9 )
aJo&&EoCASTER
ADJUST SCALE
FOR zERO AT THIS
~lNT (LEVELMINT)
\ ( BRASS PLATE
STRAP IRON
SUPPORT
MARKEO
SRASS STRIP CADLE
1[
Iv
t
\
% PROBE
o
w \
* M mm L.fh
STANOARD PVC
. PIPE NSERT,
THREADED TO
SUIT TOP OF
I
‘
I
hJSTALLATION
II
[ COmm L-
ll\~ TNREAO~D
BOSS GLUCD J
1 THUMB SCREW
NOTE — Use device as shown during construction. Thereafter cut device to I I 20 mm Iengtts to fit top of installittion,
16
ANNEX A
( Clauses 7.4 and 17.4)
PROFORMA FOR RECORD OBSERVATION OF VERTICAL CROSSARM INSTALLATION
Project ............................................ Dam .......................................................
Location ......................................... Topofdm ...........................................
Date ................................................ Reservoir water level R. L ...................
Observed by ................................... Water level in the installation .............
Cross arm Top Level Tape Correction Corrected Original Present settlement Original Present Consolidation Remarks
No. of Reading for Scale Elevatibn Elevaticin of Distance Distance Between
Measuring Torpedo Rkading of Cross Arm of Croks Arm Cross Arm Betweeh Between Cross Arms
Scale Length ( See Notes ( See Note I ) Cross Arms Cross Arms
land3) ( See Notes
2and3)
(1) (2) (3) (4) (5) (6) (7) (8) (9) (lo) (11) (12)
NOTES
I The elevation of the cross arms are the elevation df the cross arm measuring points.’
2 Original distance betueen cross arms is tbe difference between e[cva(ions of successive cross arm measuring points the cross arm unit is placed.
3 Once established. [he original elevations of cross arm measuring points and the original distance be[ween points are fixed values and appear as constants in later readings.
.,.. .. . I
p!nm
BIS is a statuto~ institution establishtiunder the BUIWKIUofZnc/ian Stundard.T.4cf, 1986 to promote harmonious
development of the activities of standardization, marking and quality certification of goods and attending to
-connected matters in the country.
Copyright
BIS has the copyright of all its publications. NOpart of these publicationsmay be reproduced in any form without
the prior permission in writing of BIS. This does not preclude the free use, in the course of implementing the
standard, of necessary details, such as symbols and sizes, type or grade designations. Enquiries relating to
copyright be addressed to the Director (Publications), BIS.
This Indian Standard has been developed from Doc : No. WRD 16 (24).
‘t
Amend No. Date of Issue Text Affected