Professional Documents
Culture Documents
7 AWTFGeotechnicalwork Proformaof SCH Ato F
7 AWTFGeotechnicalwork Proformaof SCH Ato F
7 AWTFGeotechnicalwork Proformaof SCH Ato F
SCHEDULE ‘A’
Schedule of materials to be issued to the contractor : Uploaded separately
Sl.No. Description of item Quantity Rates in figures & Place of
words at which the issue
material will be
charged to the
contractor
1 2 3 4 5
SCHEDULE ‘B’
Schedule of quantities : Uploaded separately
SCHEDULE ‘C’: Not Applicable
Tools and plants to be hired to the contractor
SCHEDULE ‘E’
Reference to General Conditions of contract
Name of work : Geotechnical investigation at proposed Site of Alpha Solid waste
treatment Plant buildings in AWTF-PP complex, BARC, Trombay
LOCATION AND SCOPE OF THE WORK
Location:- AWTF, PP Complex, NRG, BARC, Mumbai.
Scope of work:“Geo technical investigations, cross bore hole test, pressure meter test,
SPT, submission of reports based on geo tech investigations etc ”.
Clause 1
Time allowed for submission of Performance : 15 days / Handing over of siteof the
Guarantee from the date of issue of letter of work, whichever is later
acceptance
Clause 2
Authority for fixing compensation under Clause 2 : Chief Engineer , Associate Director/
Director NRG
Clause 2A
Whether Clause 2A shall be applicable : No
Clause 5
Number of days from the date of issue of letter of : 15 days
acceptance for reckoning date of start after the
date of issue of work order or handing over of site
of work whichever is later
Table of Mile Stone(s)
Authority to decide:
Clause 7
Gross work to be done together : ` 10% of W.O. Value
with net payment / adjustment
of advancesfor material collected,
if any, since the last such
payment for being eligible to
interim payment
Clause 10A
List of testing equipment to be provided by the contractor at site lab.
1. 2. 3.
4. 5. 6.
Clause 10B(ii)
Whether Clause 10B(ii) shall be applicable : No
Clause 10C
Component of labour expressed as percent of value of work = 25 %
Clause 10CA
Materials covered under Nearest Materialsfor which All Base Price of all the
this clause (10 CA) IndiaWholesale Price Index to be Materials covered under
followed clause 10CA*
1. Cement Grey Cement ` 7,300.00/MT
2. Structural Steel Rolled sections and plates ` 40,000.00/MT
Clause 10CC
Clause 10CC to be applicable in contracts with stipulated period of : 12 months
completion exceeding the period shown in next column
Schedule of component of other Materials, Labour, P.O.L. etc. for price escalation.
12.2 & Deviation Limit beyond which clauses12.2 : 30% for superstructure items &
12.3 & 12.3 shall apply for building work 50% for maintenance works
12.5 Deviation Limit beyond which clauses12.2 : 100% for sub-structure items
& 12.3 shall apply for foundation work
Clause 16
Competent Authority for deciding reduced rates : Chief Engineer
Clause 18
List of mandatory machinery, tools & plants to be deployed by the contractor at site :
1. 2. 3.
4. 5. 6.
Clause 25: Authority for levy of compensation and Arbitration : Chief Engineer /
Associate Director, NRG
Clause 36(i)
Assistant Engineers retired from Government services that are holding Diploma will be treated
at par with Graduate Engineers
Clause 42
(I) (a) Schedule / statement for determining theoretical quantity of cement & bitumen on
the basis of BARC Schedule of Rates 2015 printed by BARC
(II) Variations permissible on theoretical quantities
Cement
(a)
For works with estimated cost putto tender : 3% plus / minus
not more than Rs.5 Lakhs
Sl. Description of Item Rates in figures and words at which recovery shall be made
from the contractor
No.
Excess beyond permissible Less use beyond the
variation permissible variation
1. Cement NA
2. Steel reinforcement NA
3. Structural Section NA
4. Bitumen issued free
5. Bitumen issued at
stipulated fixed price
Statement of Wages: The minimum rate of daily wages payable to an employee employed on
daily wages shall be as under: