Professional Documents
Culture Documents
The Optimisation of Flotation Networks: International Journal of Mineral Processing
The Optimisation of Flotation Networks: International Journal of Mineral Processing
The Optimisation of Flotation Networks: International Journal of Mineral Processing
J.C.A. GREEN*
Department of Chemical Engineering, University of Stellen bosch, Stellenbosch 7600
(R. South Africa)
(Received January 15, 1982; revised and accepted October 25, 1983)
ABSTRACT
Green, J.C.A., 1984. The optimisation of flotation networks. Int. J. Miner. Process., 13:
83--103.
INTRODUCTION
objective function was simple in that only one mineral species recovery was
maximised subject to external, system and mass balance constraints. The
optimisation was performed using different sets of constraints and bounds.
Once this was done, the residence times and circuit flows were computed
using a simulation procedure used to c o m p u t e the residence times in large-
scale circuits (Green, 1981).
The mass balance equations for a flotation network form an integral part
of the constraints. A mass balance for an arbitrary n-cell flotation network
results in the matrix equation (King, 1973; Woodburn et al., 1976):
Gkmk =--uk (1)
where k refers to some mineral species belonging to a set of species Ps. m k is
the vector of tailings mass flow rates from the various cells or banks (a bank
of cells may be treated as a single entity -- hence also a "cell"). The elements
of m k are m k j where k refers to the mineral species and j refers to the cell in
the circuit, uk is the vector of fresh feed mass flow rates to the circuit. There
may be feeds to various points in the circuit -- hence uk will have elements
ukj where cell j will be a feed point. Gk is the connection matrix for the cir-
cuit containing both structural (connection) parameters and the enhance-
ment factors. Gk is an (n × n) matrix with non-linear elements o f the form
a k. = tij + c i j g k j for all i ¢ j and a i i = - ( 1 + g k i ) for all i.
The parameters tiy and ciy are the structural parameters, tiy is the mass
fraction of tailings fed from cell j to i. cij is the mass fraction o f concentrate
fed from cell j to i. gky is the enhancement factor for species k at allj. It is
assumed that no recycle exists around individual cells, hence:
c i i = t i i = 0, f o r all i
Each cell may be a recovery or loss point in the circuit. The overall recovery
is defined by:
n
where
n
~cj = l - - ~ cij
i=l
n
~k = Z fJwjmkj (4)
j=l
where
n
~Tj= I - - Z tij (5)
i=l
gklmk~ gklrnkl
i
Assume t h a t t h e r e are t w o classes o f material e.g. copper-rich and nickel-
rich material. Assume t h a t the fresh feed rates t o cell 1 is 100 u n i t s / m i n u t e
f o r each mineral.
F o r the circuit above t12 = 0, t21 = 1, c12 = 1, c n = 0:
•". 13c = (1, 0) and f3T = (0, 1)
if gcu,l = gcu,2 = 0.5 and gNi, l = gNi,2 = 1.
T h e mass balance e q u a t i o n s are Gkmh = --uh, w h e r e k refers t o c o p p e r
and t h e n nickel:
• k: o.1cut:_i:
1 -1. cu,j
-2
and
1 -2
Solving these t w o e l e m e n t a r y m a t r i x e q u a t i o n s gives:
mcu,1 = 5 7 . 1 4 u n i t s / m i n u t e
mcu,2 = 85.71 u n i t s / m i n u t e
mNi,l = 66.6 u n i t s / m i n u t e
msi,2 = 33.3 u n i t s / m i n u t e
87
The difficult part of any plant optimisation is the setting of realistic goals
or objectives.
The objective in this paper is to primarily investigate the effect that
structural parameters and enhancement factors have on the optimum. The
question that is posed is whether a unique set of interconnections and en-
hancement factors exist which will maximise the recovery of a given set of
valuable mineral species given a set of criteria which will constrain the sys-
tem. L
An objective function of the form J = Z w k P k will be considered subject
k=l
to three types of constraints: (a) external constraints; (b) system constraints;
and (c) mass balance constraints.
E x ternal constraints
These constraints are imposed upon the flotation plant externally and are
demands placed on the plant from outside, e.g. grade requirements, produc-
tion rate requirements, mass flow rate requirements to other sections of the
plant etc.
An upper and lower bound may be placed on the grade for each species
k, assuming L different species:
S y s t e m constraints
The ability of each cell to split the incoming mineral into a stream in the
concentrate and the railings depends upon a large number of process vari-
ables which will define an enhancement factor for each mineral as discussed
in the introduction. These enhancement factors will be bounded above and
below depending on the range of operating variables available at each cell.
This implies an upper and lower bound for the enhancement factors.
The construction or choice of such bounds can be achieved in two ways:
l 1
where d is solid density, d ~ o is water density, V/is cell volume and ri is cell
retention time. An upper bound on cell volume and a lower bound on r] will
ensure an upper bound on mkj. For physical reasons, a lower bound must
exist on mkj. This may be arbitrarily chosen to be a very small number.
Hence:
m~j<~ m k j ~ m~j f o r k E P s , j E ns (10)
If loss streams from a circuit are to be processed, bounds on mass flow
rates, enhancement factors and vent fractions flwj and ~ci ensure the existence
of upper and lower bounds in production rates Pk and losses ~h.
and
/2
Z c i j Y k j + fJcjYkj = Y k j (13)
i=1
(9) Y ij = x k i
j=l
n k
(10) Z mii + ~kj = m k i ; k E Ps, j E n s
i=1
91
n
(11) Y~ ~ . + c~kj = Ykj; k ~ Ps, J E ns
i=l
i~j
(12) ~ k . m r j = K~rimki; k, r ~ Ps, i, j E /2 s
(13) YijYrj
-k -r
= Yiffrj, . k, r E Ps, i, j E ns
The last two constraints are essential from a physical viewpoint. This is
shown in Appendix 1. As the problem stands it may be solved by standard
non-linear programming methods (Himmelblau, 1976). The problem may
however be readily converted to a linear programming problem (Green,
1983). For the optimisation of one mineral species k ~ Ps only, however,
constraints 12 and 13 become redundant and the optimisation becomes a
simple matter using conventional Linear Programme methods.
EXAMPLE
Subject to:
a
(1) Pk >= 0.0172 i.e. ~ ~kj = 0.0172
j=l
n
(8) ~ r-nkk j = -U k i
j=l
92
n
-k
(9) Z Y i j = x k i
j=l
n _k
(I0) 2~ mij+~kj=rnkj; j=l,2and3
i=l
1
Fig. 1. O p t i m u m circuit.
feed stream. At each bound for ~L, three different bounds m3~ L
were con-
sidered viz. 5, 30 and 60% of the inlet nickel feed stream.
The resulting optimum circuits are shown below. The o p t i m u m values are
given as a % of inlet nickel feed.
Circuit 1
Circuit 2
I
- -
I
,/
~1.noa!D
~'6
95
Circuit 6
Circuit 7
--L
P2 = 20%; mLj = 60%; P2 = 80%
Circuit 8
P2 = 4 0 % ; m =30%; ~2 = 6 0 %
96
Circuit 9
-1
Circuit 1
C =
o
0 ; T=
L 95
o o;
0 1
0.08 1 0
Circuit 2
o o
C = 0 ;T = 53 0
0.07 L0_.46 +1
/~c = (1; 0.93; 1); fit = (0; 0; 0.03); g3 = (2.33; 0.5; 0.5)
Circuit 3
0
C = 0 ;T = 0 0.98
Ki °
0.03 °
1 0
1
~c = ( 1 ; 0 . 9 7 ; 1); ~T = (0; 0; 0.02); g3 = (0.67; 0.5; 0.5)
97
Circuit 4
C= 0 + .1 ;T= .1
o o]
0 +1
+1 +1 0
Circuit 5
°
C =
Li ° +0.6
0
oJ
+1 ;T = 0
+1
+ .
Circuit 6
0 0 0
C = 0 ;T = 0 + .
+0.67 +1
Circuit 7
C =
0
0
o
0 0 ;T =
0
+0.06
0
0
0
+1
+0.04
~c = ( 0 . 9 6 ; 1; 1);
0
~T = (0.94; 0; 0);
0
Circuit 8
C =
io +0.25
o
0 ;T =
o ;
0 +
+0.25 0 +1
Circuit 9
0 0 0 0
0 +1 ; T = 0 +~.
0 0 +1
TABLE I
Bank Gangue Cu Ni
The programme computes the residence times r and then the concen-
trate flow rates, tailing f l o w rates, t o t a l p r o d u c t i o n and t o t a l losses given
t h e m a t r i c e s a n d v e c t o r s C, T, u, t h e c e l l v o l u m e v e c t o r V, p u l p d e n s i t i e s
and parameters a and b for each species. One vector of enhancement factors,
g3 is g i v e n ; t h e r e s t is b e i n g c o m p u t e d .
T h e c o m p u t e d c o n c e n t r a t e s a n d t a i l i n g s f l o w r a t e s ar e g i v e n in T a b l e s
II a n d III. T h e m a t r i x o f e n h a n c e m e n t f a c t o r s is g i v e n in T a b l e I V .
TABLE II
Bank Gangue Cu Ni
TABLE III
Bank Gangue Cu Ni
TABLE IV
Enhancement factors
Bank Gangue Cu Ni
TABLE V
F l o t a t i o n variables
SUMMARY
CONCLUSIONS
RECOMMENDATIONS
(2) Effective ways need to be sought for generating bounds for enhance-
ment factors. This may possibly be achieved by a study o f existing flotation
models or b y experimental means using either batch flotation cells or a single
continuously operating cell (possibly within a pilot plant or commercial
plant).
APPENDIX 1
At the optimum:
tijrnkj = m~. and tijmr] = ~rj
tij is the mass fraction of material recycled from cell j to i and must be the
-k, -r ,
same in m 6 s definition as mij s definition for physical consistency.
t~.k. -'r
• . tij = z.___L= mij.
mkj mrj
• ~-tk.rrtrj : m k j m rj
NOMENCLATURE
ti] + c i j g k j
cii Mass fraction of concentrate fed from cell j to cell i
gkj Enhancement factor; Ykj/mhy
gk Enhancement factor vector (gkj)je ns
g Enhancement factor matrix (gkj)kePs j~ns
Lower bound to gkj
Upper b o u n d to gki
k Element of species set Ps
L Number of classes of material, i.e. elements of Ps
mkj Tailings mass flow for species k from cell j
mk Vector of tailings mass flow r a t e s ( m k j ) j ~ ns
Matrix of tailings mass flow rates (mkj)keps;jen~
tijmkj
Number of cells in a circuit
ns The set of cell numbers
n' Number of concentrate vent points
n It
Number of tailings vent points
I
ns {i: ~ci/> 0}
{i: /3zi~>0}
t6 Mass fraction of tailings fed from cell j to cell i
Ukj A m o u n t of species k feed fed to cellj
Uk Fresh feed mass flow rate vector (Ukj)j e ns
U Fresh feed mass flow rate matrix (U~cj)keps;j e ns
102
REFERENCES
Arbiter, N. and Harris, C.C., 1962. Flotation Kinetics. In: D.W. Fuerstenau (Editor), Froth
Flotation, 50th Anniv. Vol. Am. Inst. Min. Metall. Pet. Eng., New York, N.Y., pp.
215--246.
Cramer, L.A., 1975. Industrial applications of flotation models. Ph.D. Thesis, Dept.
Chemical Eng., University of Natal, Durban.
Green, J.C.A., 1981. The mathematical structure associated with flotation networks.
Ph.D. Thesis, Dept. Chemical Eng., University of Natal, Durban.
Green, J.C.A., Meij, J.T., Du Plooy, A.T. and Van Heerden, P., 1983. The use of in-
equalities in the design and optimisation of complex chemical and metallurgical plants.
Comput. Chem. Eng., in press.
Himmelblau, P.M., 1976. Optimal design via structural parameters and non-linear pro-
gramming. Eng. Optimisation, 2: 17--27.
Inoue, T. and Imaizuni, T., 1965. Some kinetic considerations of froth flotation. 6th Int.
Miner. Process. Conf., Cannes, pp. 581--583.
Ichikawa, A. and Fan, L.T., 1973. Optimal synthesis of process systems -- necessary con-
ditions for optimal systems and its use in synthesis of systems. Chem. Eng. Sci., 28:
257--273.
King, R.P., 1973. A cemputer programme for the simulation of the performance of a
flotation plant. S.A. Nat. Inst. Metall., Rep. 1436.
Levin, J. and Engelbrecht, J.A., 1975. Full scale flotation plant data for modelling pur-
poses. NIM Report, 1753.
Loveday, B.K., 1966. An analysis of froth flotation kinetics. Trans. Inst. Mining Metall.,
75: C219--225.
Mehrotra, S.P. and Kapur, P.C., 1974. Optimal-suboptional Synthesis and Design of
Flotation Circuits. Sep. Sci., 9.
Nagiev, M.F., 1957. Material balance in complex and multistage recycle chemical pro-
cesses. Chem. Eng. Progr., 53(6): 297--303.
Sutherland, D.N., 1981. A study on the optimisation of the arrangement of flotation cir-
cuits. Int. J. Miner. Process., 7: 319--341.
Umeda, T . Hiriai, A. and Ichikawa, A., 1972. Synthesis of an optimal processing system
by an integrated approach. Chem. Eng. Sci., 27(IV): 795--804.
Woodburn, E.T. and Loveday, B.K., 1965. The effect of variable residence time on the
performance of a flotation system. J. S.A. Inst. Min. Metall., 65. 612--628.
Woodburn, E.T., Kropholler, H.W., Green, J.C.A. and Cramer, L.A., 1976. The utility and
limitations of mathematical modelling in the prediction of the properties of flotation
networks. In: Flotation, A.M. Gaudin Memorial Volume, Vol. 2. Am. Inst. Min.,
Metall. Pet. Eng., New York, N.Y., Chapter 24.