Professional Documents
Culture Documents
205 EOT Crane
205 EOT Crane
Woorrkk IInnssttrruuccttiioonn
Offshore and Industrial Services
Branch Office Abu Dhabi
Signature: Signature:
No part of this document shall be reproduced in any form, in an electronic retrieval system or otherwise, without the prior written permission from
Germanischer Lloyd Abu Dhabi Office
Work Instruction
Inspection and Testing an E.O.T Crane
Doc. No. 0940-LE-205 Rev.0 Offshore and Industrial Services
TABLE OF CONTENT
1.1. A test is carried out to prove an Overhead Crane of its capacity to handle the Safe Working Load
to which it is designed for and hence it should be borne in mind that the crane might not
withstand the loading applied in all the cases. Due importance must be given also to the gantry
structure on which the crane is installed. It is therefore necessary to ensure that all safety
requirements are carefully followed.
1.2. All necessary safety precautions must be taken to ensure the safety of both the inspector and any
other persons who are involved in the activity or likely to enter the testing area.
1.3. The inspector can proceed with the examination and test of a crane only after ensuring that all the
necessary steps have been taken with regards to the safety of personals involved, other equipment
underneath the subject crane and the crane under test itself.
C) Weather Conditions:
In the case of Out-door duty cranes and especially Gantry (Goliath) Cranes, prior to the load
test, careful attention must be given to the prevailing weather conditions.
Certain weather conditions will affect the cranes safe operation. These include conditions such as:
i) Strong Winds.
ii) Heavy Rain.
iii) Blowing Sand.
iv) Thick Fog.
v) And other adverse weather conditions, particularly, ice and snow in colder climates.
The limitations on wind speed for testing a crane may be lower than the limitations for normal
operation and this must be established.
The crane must not be operated in wind speeds that are in excess of those specified in the
operating instructions for the crane.
Gusting wings conditions may have an additional adverse effect on the safe handling of the load
and the safety of the crane and must be taken into account when load testing.
Tests must never be undertaken when the crane or load cannot be easily seen because of fog or
blowing sand.
d) Test Weights.
In order for a load test to proceed in is important to use the correct weight of load, therefore, the
inspector must be sure that the test weights are of a known weight and he must ascertain that the
weights are correct.
Only test weights with a proven accuracy to within +/- 1% should be used.
Weights proven on a weigh-bridge should only be used if the weigh-bridge has been calibrated
within the last 12 months.
Weights such as water bags or concrete blocks can be suspended from a calibrated weighing
device (i.e. Load Cell or Dynamometer,) provided that the device has a certificate of calibration
dated within the last 12 months.
Work Instruction
Inspection and Testing an E.O.T Crane
Doc. No. 0940-LE-205 Rev.0 Offshore and Industrial Services
2.4. Responsibilities
The Overload tests shall be carried out in accordance with these procedures and
under the direction and responsibility of Inspector. The Inspector shall have to be able to detect
the defects or weakness, that is the purpose of the examination and test and to assess their
importance in relation to the safety of the equipment at the time of inspection and for the
continued use.
Work Instruction
Inspection and Testing an E.O.T Crane
Doc. No. 0940-LE-205 Rev.0 Offshore and Industrial Services
The Inspector shall decide the appropriate Test load under reference to the crane manufacturer's
data and statutory regulations and shall normally but not necessarily be 1.25 x SWL.
The test load shall include the test weights, the slings and tackles used for securing the load. In
certain cases the weight of the bottom hook block may also be included, if and only if it is
recommended by the manufacturer.
During these no-load test operations, all motions must be checked for its correctness and perfection for
the full length of both Crab and Bridge travel. In addition to this, all limit switches for the following
motions must be tested on no-load and ensured of its proper functioning.
Besides this, in case micro movements are provided for any of the motions, same also must be
checked as described.
On conclusion of test and examination with satisfactory results, the inspector shall issue a
Certificate of Test and Thorough Examination’ of E O T Crane in the format attached.