Cost Comparison of Hollow block & Clay Bricks

Hollow Blocks(HB) & Clay Bricks(CB), Consider each quantity 100 sft
ITEM/ WORKS QTY RATE AMOUNT
SL UNIT
Materials cost HB CB HB CB
1 Cement (i/c Plaster Work) Bag 3.64 4.66 385 1401.4 1794.1
2 Local Sand Cft 18.58 30.26 16 297.28 484.16
3 Sylhet sand Cft 3.13 0 55 172.15 0
4 Pie chips(1/4") Cft 2.89 0.7 62 179.18 43.4
5 110 mm H/Block Pcs 111 0 42 4662 0
6 100 mm Solid Block Pcs 7 0 52 364 0
st
7 1 Class Bricks Pcs 0 500 11.5 0 5750
8 M.S Rod 10 mm dia Kg 5.4 0 49 264.6 0
9 Expended metal Sft 15 19 3.7 55.5 70.3
10 Royal Plug Doz 2.5 0 4 10 0
11 screw (1") Doz 2.5 0 12 30 0
12 nail (1") gram 0 250 0.07 0 17.5
7436.11 8159.46
Total Materials cost of HB= 7436.11 Total Materials cost of CB= 8159.46
Labor cost
13 Brick Soacking Pcs 0 500 0.5 0 250
14 Labour Rate of Block Work Sft 100 0 14.5 1450 0
15 Labour Rate of Brick Work Sft 0 100 10.5 0 1050
16 Drilling Work Nos 6 0 9 54 0
17 Expended Metal Fitting Charge Sft 15 19 11 165 209
18 C.C Casting of block work Rft 37 10 9 333 90
19 Groove cutting rft 0 30 8 0 240
2002.00 1839
Total Labor cost of HB= 2002.00 Total Labor cost of CB= 1839.00

Hollow Blocks Clay Bricks


Total cost.(Materials+labor)= 9438.11 Total cost.(Materials+labor)= 9998.46 Difference
Total Area (Sft) = 100 Total Area (Sft) = 100
Cost Per Sft = 94.381 Cost Per Sft = 99.985 -5.603