Equipment Flexibility Continuous / Restoration

Operating Area Requested by Contract No Project name Substation ID New Circuit Voltage Level (kV) Start date Start time End Date End time Scope of work Additional Comments
designation Window (days) Daily time (hours)

OUTAGES for STAGE-I in WINTER SEASON


Construction of Unclipping of Conductors at Twrs 76 and 77
380KV OHTL's and Shifting to ERS ( Note: Erection of ERS
COA Al-Haider 4400015437 9011-8523 9011-8523 132KV 1-Feb-22 8:00AM 5-Feb-22 5:00PM continuos 5 days
Associated with before the outage should be completed
Sudair PV BSP# 9036 first)

(1) Dismantling of tower 76 and 77 and


Construction of concudtors bet. This two towers. (2)
380KV OHTL's Erection of new Twr 76 and 77. (3) Erection
COA Al-Haider 4400015437 9011-8501 9011-8501 132KV 7-Feb-22 8:00AM 16-Feb-22 5:00PM continuos 10 days
Associated with of 3 gantries. (4) Stringing from new twrs to
Sudair PV BSP# 9036 gantries. (5) OPGW shifting to new towers
and gantryies.

(1) Shifting of Conductors from ERS to new


Construction of
towers (76 and 77) and to Gantries. (2)
380KV OHTL's
COA Al-Haider 4400015437 9011-8523 9011-8523 132KV 17-Feb-22 8:00AM 21-Feb-22 5:00PM continuos 5 days Stringing from new towers to gantries.
Associated with
(Note: Stringing between gantries should be
Sudair PV BSP# 9036
completed before the outage)

(1) Dismantling of twrs 296 and 297 and


Construction of conductors bet. two towers. (2) Erection of
380KV OHTL's new tower 296 and 297. (3) Erection of 3
COA Al-Haider 4400015437 9011-8839 (A&B) 9011-8839 (A&B) 132KV 23-Feb-22 8:00AM 5-Mar-22 5:00PM continuos 10 days
Associated with gantries. (4) Stringing from new towers to
Sudair PV BSP# 9036 gantries. (5) OPGW shifting to new towers
and gantryies

Construction of (1) Erection of new twrs (1A and 1B).


380KV OHTL's Stringing between twr 1A and 1B for the
COA Al-Haider 4400015437 9011-9064 (A&B) 9011-9064 (A&B) 380KV 7-Mar-22 8:00AM 21-Mar-22 5:00PM continuos 15 days
Associated with temporary connection. (5) OPGW
Sudair PV BSP# 9036 temporary jumper works

Construction of (1) Erection of new twrs (1A and 1B).


380KV OHTL's Stringing between twr 1A and 1B for the
COA Al-Haider 4400015437 9011-9025 (A&B) 9011-9025 (A&B) 380KV 24-Mar-22 8:00AM 7-Apr-22 5:00PM continuos 15 days
Associated with temporary connection. (5) OPGW
Sudair PV BSP# 9036 temporary jumper works

OUTAGES for STAGE-II in SUMER SEASON


The outage will be reduced to
(1) Dismantling of Temporary connection 15 days if the temporary FOC
Construction of link between ss 9011-9036 is
between twr 1A and 1B. (2) Live Line
380KV OHTL's 9011-9036 (A) and Depend on readiness Depend on readiness approved by TE&SAD to start
COA Al-Haider 400015437 9011-9064 (A) 380KV continuos 45 days Stringing between Twr 1A and 2A and
Associated with 9064-9036 (A) of ss 9036 of ss 9036 commissioning of ss9036
between Twr 1B and 2B crossing 132KV Line.
Sudair PV BSP# 9036 before outage.
(3) OPGW modification works