Professional Documents
Culture Documents
Pmi Ca0 001
Pmi Ca0 001
Pmi Ca0 001
PMI
Exam CA0-001
Certified Associate in Project Management (CAPM) Certification
Version: 6.11
Question No : 1 - (Topic 1)
Answer: C
Question No : 2 - (Topic 1)
Which process involves identifying and documenting the logical relationships among
schedule activities?
A. Schedule development
B. Activity sequencing
C. Create WBS
D. Applying leads and lags
Answer: B
Question No : 3 - (Topic 1)
Answer: C
Question No : 4 - (Topic 1)
100% Valid Questions - Guaranteed Success 3
PMI CA0-001 : Valid Questions
Which of the following are outputs of the Monitor and Control Project Work process?
Answer: A
Question No : 5 - (Topic 1)
A. Project boundaries
B. Project constraints
C. Project assumptions
D. Project objectives
Answer: A
Question No : 6 - (Topic 1)
Answer: A
Question No : 7 - (Topic 1)
A. Risk register
B. Risk data quality assessment
Answer: A
Question No : 8 - (Topic 1)
Answer: B
Question No : 9 - (Topic 1)
The approval of which of the following indicates formal initiation of the project?
Answer: D
Question No : 10 - (Topic 1)
Which of the following strategies is used to deal with risks that may have a negative impact
on project objectives?
A. Exploit
B. Share
C. Enhance
D. Transfer
Question No : 11 - (Topic 1)
Draw the precedence diagram for the dependencies and activity times below to answer the
question. Use AON or another technique to derive the answer using F-S relationships.
What is the critical path duration for the given schedule network?
A. 22
B. 23
C. 24
D. 25
Answer: D
Question No : 12 - (Topic 1)
A. Collect Requirements
B. Plan Communications
C. Develop Project Team
D. Report Performance
Answer: A
Question No : 13 - (Topic 1)
A. Mitigate
B. Transfer
C. Exploit
D. Avoid
Question No : 14 - (Topic 1)
A. An organizational chart
B. Glossary of common terminology
C. Organizational process assets
D. Enterprise environmental factors
Answer: B
Question No : 15 - (Topic 1)
Which contract type is typically used whenever the seller's performance period spans a
considerable period of years?
Answer: B
Question No : 16 - (Topic 1)
Answer: C
A. 1.33
B. 2.00
C. 0.75
D. 0.5
Answer: A
Question No : 18 - (Topic 1)
In what type of contract is the seller reimbursed for all allowable costs for performing the
contract work and receives a predetermined fee based upon achieving certain performance
objectives as set forth in the contract?
A. Cost-plus-fixed-fee
B. Cost-plus-incentive-fee
C. Firm-fixed-price
D. Fixed-price-incentive-fee
Answer: B
Question No : 19 - (Topic 1)
Answer: A
Question No : 20 - (Topic 1)
A. Initiating
B. Planning
C. Monitoring & Controlling
D. Executing
Answer: B
Question No : 21 - (Topic 1)
What is the name of a graphic display of project team members and their reporting
relationships?
Answer: C
Question No : 22 - (Topic 1)
A. At project initiation
B. During work performance analysis
C. Throughout the life of the project
D. At project milestones
Answer: C
Question No : 23 - (Topic 1)
What is a hierarchically organized depiction of the identified project risks arranged by risk
category?
Answer: B
Question No : 24 - (Topic 1)
A. Sponsor
B. Project manager
C. Project team
D. Buyer
Answer: A
Question No : 25 - (Topic 1)
What defines the portion of work included in a contract for items being purchased or
acquired?
Answer: D
Question No : 26 - (Topic 1)
The project manager calculated a schedule performance index of 0.8 and a cost
performance index of 1.1 for the project. What is the actual status of this project?
Answer: B
Question No : 27 - (Topic 1)
A. 7
B. 8
C. 14
D. 16
Answer: B
Question No : 28 - (Topic 1)
What tool and technique includes all costs incurred over the life of a product by investment
in preventing nonconformance to requirements?
A. Cost of quality
B. Measure of design
C. Statistical control
D. Systematic analysis
Answer: A
Question No : 29 - (Topic 1)
Stakeholder analysis identifies what information and relates it to the purpose of the project?
Question No : 30 - (Topic 1)
What are the identified risks for doing excessive decomposition in a WBS?
Answer: D
Question No : 31 - (Topic 1)
A. Sponsor
B. Portfolio manager
C. Program manager
D. Project manager
Answer: C
Question No : 32 - (Topic 1)
Which of the following documents allows the project manager to assess risks that may
require near term action?
Answer: C
Question No : 33 - (Topic 1)
Which of the following can be used to track the requirements throughout the project life
cycle?
Answer: A
Question No : 34 - (Topic 1)
Reviewing, tracking, and regulating the process to meet performance objectives defined in
the project management plan are part of which process?
Answer: A
Question No : 35 - (Topic 1)
A. Sensitivity analysis
B. Probability and impact matrix
C. Risk data quality assessment
D. Risk categorization
Answer: A
Question No : 36 - (Topic 1)
100% Valid Questions - Guaranteed Success 13
PMI CA0-001 : Valid Questions
Which of the following is involved in the initiation process group?
Answer: B
Question No : 37 - (Topic 1)
Answer: D
Question No : 38 - (Topic 1)
A. Your project is behind schedule and you want your baseline to reflect estimated actual
completion.
B. Your customer has approved a change request broadening the project scope and
increasing the budget.
C. One of the risks identified in the Risk Management Plan occurs resulting in a schedule
delay.
D. One of your key project team resources has left your team and no replacement is
available.
Answer: B
Question No : 39 - (Topic 1)
100% Valid Questions - Guaranteed Success 14
PMI CA0-001 : Valid Questions
Which of the following lists contain processes that are included within Project Procurement
Management?
A. Plan purchases and acquisitions, plan contracting, request seller responses, select
sellers
B. Plan purchases and acquisitions, request seller responses, select sellers, schedule
control
C. Plan purchases and acquisitions, acquire project team, request seller responses, select
sellers
D. Plan purchases and acquisitions, acquire project team, contract approval, select sellers
Answer: A
Question No : 40 - (Topic 1)
A. 0
B. 3
C. 5
D. 10
Answer: C
Question No : 41 - (Topic 1)
Answer: A
Question No : 42 - (Topic 1)
A. Customer acceptance
B. Statement of work
C. Product report
D. User manual
Answer: A
Question No : 43 - (Topic 1)
Many organizations categorize requirements into which of the following two categories?
Answer: A
Question No : 44 - (Topic 1)
A. Requested changes
B. Approved preventive action
C. Work performance information
D. Implemented defect repair
Answer: B
Question No : 45 - (Topic 1)
Answer: A
Question No : 46 - (Topic 1)
Which of the following provides a standardized, effective, and efficient way to centrally
manage approved changes and baselines within a project?
Answer: B
Question No : 47 - (Topic 1)
Which schedule development technique modifies the project schedule to account for limited
resources?
Answer: C
Question No : 48 - (Topic 1)
What is the lowest level in the WBS at which the cost and activity durations for the work
can be reliably estimated and managed?
Answer: B
Question No : 49 - (Topic 1)
While implementing an approved change, a critical defect was introduced. Removing the
defect will delay the product delivery. What is the MOST appropriate approach to managing
this situation?
Answer: A
Question No : 50 - (Topic 1)
Which project management process ensures the seller's performance meets procurement
requirements and that the buyer performs according to the terms of the legal contract?
A. Plan Procurements
B. Perform Quality Assurance
C. Administer Procurements
D. Conduct Procurements
Answer: C
Question No : 51 - (Topic 1)
Define Activities and Estimate Activity Resources are processes in which project
management knowledge area?
Answer: A
Question No : 52 - (Topic 1)
Answer: B
Question No : 53 - (Topic 1)
Answer: D
Question No : 54 - (Topic 1)
Answer: B
Question No : 55 - (Topic 1)
When communicating with large audiences, which communication method works most
effectively?
A. Push
B. Interactive
C. Parallel
D. Pull
Answer: D
Question No : 56 - (Topic 1)
A. Contract management
B. Performance reporting
C. Project status reports
D. Information distribution
Answer: D
Explanation: The project management term or phrase that is used for the purposes of
representing the project management process that focuses on taking the facts and
happenings in regards to a particular project and disseminating this information to all of the
relevant parties, with a particular focus on providing information to those who have a
financial stake in the ultimate outcomes of the project. These methods of information
dissemination can come in means including regularly scheduled conferences and or
meetings, regularly scheduled conference calls in which some or all members of the project
team participate, informal written communications such as periodic updates via email and
of other short form, less formal means of communications, as well as formal reports that
may or may not have been requisite to the completion of the project. Information
distribution is essential to assuring that the financial stakeholders are fully aware of the
Question No : 57 - (Topic 1)
Which of the following consists of the detailed project scope statement and its associated
WBS and WBS dictionary?
A. Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline
Answer: D
Question No : 58 - (Topic 1)
A. EV/PV
B. PV/EV
C. EV-PV
D. PV-EV
Answer: C
Question No : 59 - (Topic 1)
Reserve analysis is a tool and technique used in which of the following processes?
Answer: A
Question No : 60 - (Topic 1)
Answer: B
Question No : 61 - (Topic 1)
Given the following values, what is the calculated expected activity cost (CE) when using
PERT?
CO = $7,000
CM = $10,500
CP = $11,000
A. $ 4,750
B. $ 9,500
C. $10,000
D. $11,500
Answer: C
Question No : 62 - (Topic 1)
Which of the following must be taken into account for every process, even if they are not
explicitly listed as inputs in the process specifications?
Answer: C
Question No : 63 - (Topic 1)
A. Cost Control
B. Cost Budgeting
C. Cost Estimating
D. Cost Planning
Answer: B
Question No : 64 - (Topic 1)
The initial development of a Project Scope Management plan uses which technique?
A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis
Answer: C
Question No : 65 - (Topic 1)
Which of the following processes includes prioritizing risks for subsequent further analysis
or action by assessing and combining their probability of occurrence and impact?
Answer: A
Question No : 66 - (Topic 1)
Which one of the following is true regarding the change control board?
Answer: B
Question No : 67 - (Topic 1)
A. Purchase requisition
B. Purchase order
C. Verbal agreement
D. Request for quote
Answer: B
Question No : 68 - (Topic 1)
Answer: B
Which of the following is an input to the Direct and Manage Project Execution Process?
Answer: A
Question No : 70 - (Topic 1)
Project contracts generally fall into which of the following three broad categories?
Answer: A
Question No : 71 - (Topic 1)
What is the term assigned to products or services having the same functional use but
different technical characteristics?
A. Scope
B. Quality
C. Specification
D. Grade
Answer: D
Question No : 72 - (Topic 1)
A. Project charter
B. Contract
C. Business case
D. Project statement of work
Answer: D
Question No : 73 - (Topic 1)
A. Requested changes
B. Project scope statement changes
C. Variance analysis
D. Approved change requests
Answer: D
Question No : 74 - (Topic 1)
Which analysis helps to determine the risks that have the most potential for impacting the
project?
Answer: B
Question No : 75 - (Topic 1)
In the three-point estimating technique, if the most likely estimate for an activity to complete
is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days,
what is the expected duration in which the activity will be completed?
Answer: C
Question No : 76 - (Topic 1)
Which of the following tools or techniques is used for Estimate Activity Duration?
A. Critical path
B. Rolling Wave
C. PDM
D. Parametric
Answer: D
Question No : 77 - (Topic 1)
A purchase order for a specified item to be delivered by a specified date for a specified
price is the simplest form of what type of contract?
A. Cost-reimbursable
B. Time and material
C. Fixed price or lump-sum
D. Cost-plus-fixed-fee
Answer: C
Question No : 78 - (Topic 1)
Answer: D
Question No : 79 - (Topic 1)
A project manager convenes a meeting to determine why the time to produce one product
according to specifications has increased from one day to three days over the past month.
Which tool or technique is used in this case?
A. Expert judgment
B. Quality assurance
C. Quality control
D. Variance analysis
Answer: D
Question No : 80 - (Topic 1)
A. Pareto
B. Ishikawa
C. Shewart-Deming
D. Delphi
Answer: C
Question No : 81 - (Topic 1)
What cost control technique is used to compare actual project performance to planned or
expected performance?
A. Cost aggregation
B. Trend analysis
C. Forecasting
D. Variance analysis
Question No : 82 - (Topic 1)
Which of the following is a tool and technique for activity duration estimating?
A. Parametric estimating
B. Monte Carlo analysis
C. Top-down estimating
D. Bottom-up estimating
Answer: C
Question No : 83 - (Topic 1)
If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is
$1500, what would be the cost performance index (CPI)?
A. 0.66
B. 0.8
C. 1.25
D. 1.5
Answer: C
Question No : 84 - (Topic 1)
A. Executive management
B. Project members
C. Project manager
D. Contract administrator
Answer: A
Question No : 85 - (Topic 1)
Which process occurs within the Monitoring and Controlling Process Group?
A. Cost Control
B. Quality Planning
C. Quantitative Risk Analysis
D. Cost Budgeting
Answer: A
Question No : 86 - (Topic 1)
A. Avoid
B. Transfer
C. Accept
D. Mitigate
Answer: C
Question No : 87 - (Topic 1)
Project scope statement and resource calendars are inputs to what Project Time
Management process?
A. Activity Sequencing
B. Activity Resource Estimating
C. Schedule Development
D. Schedule Control
Answer: C
Question No : 88 - (Topic 1)
Answer: D
Question No : 89 - (Topic 1)
ABC project is at risk for failing to achieve a major project objective due to unresolved
stakeholder issues. Team member morale is low.
Answer: C
Question No : 90 - (Topic 1)
Answer: A
Question No : 91 - (Topic 1)
Answer: A
Question No : 92 - (Topic 1)
What quality control tool graphically represents how various elements of a system
interrelate?
A. Control chart
B. Flowchart
C. Run chart
D. Pareto chart
Answer: B
Question No : 93 - (Topic 1)
Which type of analysis is used as a general management technique within the Plan
Procurements Process?
Answer: B
Question No : 94 - (Topic 1)
Draw the precedence diagram for the dependencies and activity times below to answer the
question. Use AON or another technique to derive the answer using F-S relationships.
A. 0
B. 1
C. 2
D. 3
Answer: C
Question No : 95 - (Topic 1)
A. Contract administration
B. Direction and management of project execution
C. Create WBS
D. Qualitative risk analysis
Answer: A
Question No : 96 - (Topic 1)
The use of group creativity techniques as a tool and technique is done in which of the
following processes?
A. Plan Quality
Answer: B
Question No : 97 - (Topic 1)
Which knowledge area is concerned with the processes required to ensure timely and
appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of
project information?
Answer: B
Question No : 98 - (Topic 1)
Monitor and control project work is a process of which of the following knowledge areas?
Answer: D
Question No : 99 - (Topic 1)
Which document contains initial requirements that satisfy stakeholders' needs and
expectations?
A. Project charter
B. Project management plan
Answer: A
A. Performance report
B. Work breakdown structure
C. Requested changes
D. Project scope statement
Answer: D
Answer: B
Which process group defines the course of action required to attain the objectives that the
project was undertaken to achieve?
A. Initiating
B. Executing
C. Planning
D. Monitoring and Controlling
Answer: D
Answer: C
Which of the following processes is necessary to ensure that the project employs all
processes needed to meet its requirements?
Answer: C
The decision to approve or reject a particular change request is made in which of the
following processes?
Answer: A
A. Expert Judgment
B. Project Management Software
C. Vendor Bid Analysis
D. Reserve Analysis
Answer: A
What is the expected activity cost for a project having a most likely cost of $140, a best
case scenario of $115, and a worst case scenario of $165?
A. $115
B. $138
C. $140
D. $165
Answer: C
A. Increases
B. Decreases
C. Stays the same.
D. Has no bearing.
Answer: B
A. probability distribution.
B. decision tree diagram.
C. sensitivity analysis.
D. modeling and simulation.
Answer: B
A. Communication model
B. Identification information
C. Communication method
D. Identification plan
Answer: B
As part of a mid-project evaluation, your project sponsor has asked you to provide a
forecast of total project cost. You should calculate the forecast using which of the following
methods?
Answer: B
Answer: D
Explanation: The Project Management Triangle (called also Triple Constraint) is a model
of the constraints of project management. It is often used to illustrate that project
management success is measured by the project team's ability to manage the project, so
that the expected results are produced while managing time and cost.
Like any human undertaking, projects need to be performed and delivered under certain
constraints. Traditionally, these constraints have been listed as "scope," "time," and "cost".
These are also referred to as the "Project Management Triangle," (also known as the "Iron
Triangle") where each side represents a constraint. One side of the triangle cannot be
changed without affecting the others. A further refinement of the constraints separates
product "quality" or "performance" from scope, and turns quality into a fourth constraint.
A. Defining and documenting project sponsors' needs to meet the project objectives
B. Defining and documenting stakeholders' needs to meet the project objectives
C. Defining and documenting the project teams' needs to meet the project objectives
D. Defining and documenting the project needs to meet the project objectives
What are the formal and informal policies, procedures, and guidelines that could impact
how the project's scope is managed?
Answer: A
A. Project calendar
B. Communication management plan
C. Requested changes
D. Communication requirement plan
Answer: C
A. WBS
B. CPI
C. OBS
D. BOM
Answer: C
What tool or technique of Estimate Activity Durations uses parameters such as duration,
budget, size, weight, and complexity from a previous, similar project as the basis for
estimating the same parameter or measure for a future project?
A. Bottom-up estimating
B. Analogous estimating
C. Parametric estimating
D. Three-point estimates
Answer: B
A. Project stakeholders
B. Project sponsor and project stakeholder
C. Project manager and project team
D. Project manager and project sponsor
Answer: C
The Monitoring and Controlling process group contains which of the following processes?
A. Plan Quality
B. Perform Quality Assurance
C. Perform Quality Control
D. Identify Stakeholders
Answer: C
Answer: A
Which schedule compression technique has phases or activities done in parallel that would
normally have been done sequentially?
A. Crashing
B. Fast tracking
C. Leads and lags adjustment
D. Parallel task development
Answer: B
Answer: D
The project management information system is used as tools and techniques in which of
Answer: C
A. 63
B. 65
C. 66
D. 70
Answer: A
Explanation: A Risk Register is a Risk Management tool commonly used in Project
Management and organizational risk assessments. It acts as a central repository for all
risks identified by the project or organization and, for each risk, includes information such
as risk probability, impact, counter-measures, risk owner and so on. It can sometimes be
referred to as a Risk Log
Answer: C
In the precedence diagramming method, which of the following is a logical relationship for
the activities?
Answer: A
Providing forecasts to update current cost and schedule information is a part of which
process?
Answer: D
Which Activity Duration Estimating technique incorporates additional timing for contingency
purposes?
A. Analogous Estimating
B. Expert Judgment
C. Optimistic Estimates
D. Reserve Analysis
Answer: D
What tool and technique is used to determine whether work and deliverables meet
requirements and product acceptance criteria?
A. Decomposition
Answer: C
A project manager is responsible for managing which of the following at the project level?
A. Methodology
B. Standards
C. Constraints
D. Interdependencies
Answer: C
The Project Integration Management knowledge area includes which of the following set of
processes?
A. Develop Project Charter, Direct and Manage Project Execution, Perform Integrated
Change Control
B. Define Project Scope, Create WBS, Close Project or Phase
C. Develop Project Charter, Develop Human Resource Plan, Estimate Costs
D. Identify Stakeholders, Plan Communications, Develop Project Management Plan
Answer: A
Fast tracking is a schedule compression technique used to shorten the project schedule
without changing project scope. Which of the following can result from fast tracking?
Answer: A
Using the following data, what is the Schedule Performance Index (SPI)?
EV = $500
PV= $750
AC= $1000
BAC= $1200
A. 0.67
B. 1.50
C. 0.75
D. 0.50
Answer: A
Answer: A
Who MUST know when a risk event occurs so that a response can be implemented?
Answer: C
Which schedule format usually shows both the project network logic and the project's
critical path schedule activities with activity date information?
A. Schedule table
B. Schedule network diagram
C. Bar chart
D. Milestone chart
Answer: B
Which type of control tool identifies whether or not a process has a predictable
performance?
Answer: B
A. Performed by systems
B. Constrained by limited resources
Answer: B
Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and
techniques of what process?
Answer: A
A. Create WBS
B. Define Scope
C. Control Scope
D. Verify Scope
Answer: D
Which of the following schedule network analysis techniques is applied when a critical path
method calculation has been completed and resources availability is critical?
A. Applying calendars
B. Resource Leveling
C. Resource Planning
D. Resource Conflict Management
Which quality assurance tool and technique confirms the implementation of approved
change requests, corrective actions, defect repairs, and preventive actions?
A. Quality checklists
B. Quality metrics
C. Quality audits
D. Process analysis
Answer: C
Answer: B
During which process would you obtain stakeholders' formal acceptance of the completed
project scope?
A. Quality control
B. Scope verification
C. Scope control
D. Close project
Answer: B
Answer: A
A. Performance Measure
B. Baseline Schedule
C. Schedule Comparison
D. Variance Analysis
Answer: D
A. Requirement documentation
B. Organizational process assets
C. Requirements management plan
D. Stakeholder register
Answer: D
Answer: A
Answer: A
Which of the following is the correct network diagram for the table?
A. Begin - A - C - D - E - End - B - D
B. Begin - A - B - C - D - E - End
C. Begin - A - B - D - E - End A - C - D
D. Begin - A - C - D - E - End - B - C
Answer: A
Answer: C
A. Organizational Structure
B. Organizational Process Assets
C. Organizational Matrix
D. Organizational Breakdown Structures
Answer: B
Answer: B
A. EV-AC
B. AC-EV
C. AC+EV
D. AC/EV
Answer: A
Which of the following outputs from the Schedule Control process aids in the
communication of SV, SPI or any performance status to stakeholders?
A. Performance organizations
B. Schedule baselines
C. Performance measurements
D. Change requests
Answer: C
In which of the following team development stages does the team begin to work together,
develop trust, and adjust to the work habits and behavior?
A. Norming
B. Forming
C. Storming
D. Performing
Answer: A
Within a matrix organization, dual reporting of team members is a risk for project success.
Who is responsible for managing this dual reporting relationship factor?
Answer: B
Which of the following risk response strategies involves allocating ownership of a positive
risk to a third party?
A. Mitigate
B. Transfer
C. Share
D. Avoid
Answer: C
Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the
project CV?
A. -$8,000
B. -$2,000
C. $2,000
D. $8,000
Answer: B
Which technique is commonly used for the Quantitative Risk Analysis activity?
A. Brainstorming
B. Strategies for Opportunities
Answer: C
The project manager decides to conduct a meeting with the team and management after a
new risk has been identified. After the meeting, the decision is to allow the risk to occur.
A. Mitigate
B. Accept
C. Avoid
D. Transfer
Answer: B
Projects can be divided into phases to provide better management control. Collectively,
what are these phases known as?
Answer: C
Answer: A
Answer: B
Which of the following will be required to perform simula-tion for schedule risk analysis?
Answer: B
The project team reviews identified risks and the risk response strategy. For one of the
risks, the team realizes that the implementation of the risk response would generate
another risk.
A. Secondary
Answer: A
A project manager arranges for project specific training for the new team members. Under
which category does this cost fall?
A. Appraisal
B. Internal failure
C. External failure
D. Prevention
Answer: D
Which of the following is a tool and technique to the Manage Stakeholder Expectations
process?
A. Issue log
B. Change register
C. Stakeholder register
D. Interpersonal skills
Answer: D
In which of the following organizational structures does the project manager have full
authority on a project?
A. Functional
B. Strong matrix
Answer: D
Which of the following is one of the key components of the basic communications model?
A. Push
B. Decode
C. Pull
D. Duration
Answer: B
Total funding requirements and periodic funding requirements are derived from:
Answer: D
Quality and credibility of the qualitative risk analysis process requires that different levels of
the risk's probabilities and impacts be defined is the definition of what?
Answer: B
If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned
Value (EV)?
A. $0.2
B. $5
C. $44
D. $66
Answer: D
A. Planning
B. Executing
C. Monitoring and Control
D. Closing
Answer: B
Answer: C
Company A is delivering a product in three parts. The contract allows for the parts to be
delivered either one after the other or at the same time.
Which type of project phasing will allow for the most flexibility in delivering the full product
when product requirements are subject to rapid change?
Answer: C
Answer: B
What type of planning is used where the work to be accomplished in the near term is
planned in detail, while work in the future is planned at a higher level?
A. Finish-to-start planning
B. Rolling wave planning
C. Short term planning
D. Dependency determination
Answer: B
A. Plan contracting
B. Request seller responses
C. Select sellers
D. Plan purchase and acquisition
Answer: C
Answer: B
Which of the following is a schedule network analysis technique that takes limited
resources into account?
Answer: B
Identifying major deliverables, deciding if adequate cost estimates can be developed, and
identifying tangible components of each deliverable are all part of which of the following?
Answer: A
Answer: D
A. Expert Judgment
B. Project Management Methodology
C. Project Management Information
D. Project Selection Methods
Answer: A
Which analysis uses beta and triangular distributions as a tool and technique?
Answer: A
Which tool or technique measures performance of the project as it moves from project
initiation through project closure?
A. Resource leveling
B. Parametric measuring
C. Pareto chart
D. Earned value
Answer: D
Answer: A
Which schedule development tool and technique produces a theoretical early start date
and late start date?
Answer: A
A. Positive
B. Zero
C. Negative
D. Greater than one
Answer: B
Which of the following statements best describes the influence of stakeholders and the cost
of changes as project time advances?
Answer: B
Explanation: Explanations: Stakeholders and changes versus time in the Project Life
Cycle
There are lots of common features regarding project life cycles:
• Most stages of the project follow one after the other and in many cases could be
described in technical way.
• Expenditures and personnel engaged in the task are quite cheap at the beginning of the
project, rise in the middle phase and fall significantly in the final stage. The Picture below
shows exactly the described model.
• At the beginning of the project - in initial stage the risk of failure and not to meet your
goals is very high. When this crucial period is over the project comes into an intermediate
phase where the situation is more stable and predictable.
• Stakeholders have a big influence for the project's product in many technical aspects,
costs etc. at the beginning of its life cycle. However their impact become lower within
duration of the project and cost of changes and other corrections - which are low in initial
phase rise considerably as the project continues. The Picture below demonstrates clearly
this situation.
In our opinion lots of project life cycles have many similar characteristics but few of them
are the same. For example some projects can consist of five stages, others with ten or
more? Depend on complexity and duration of the project. One institution's hardware testing
can have one individual testing stage whereas another organization can have more phases
for this task like: general and detailed testing, error correction, compatibility with different
computers etc. Separate life cycles can also cover these subprojects for instance: one
team of engineers can analysis and look for any defects of the product and the other team
can simultaneously check compatibility with other devices.
In conclusion we recommend you to deal with every project separately and especially at big
and complex enterprises treat every phase as subproject with an individual life cycle.
A. Functional manager
B. Project manager
Answer: B
In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08,
and 12. For the entire process, the goal is 10 and the standard deviation is 1.
A. is under control.
B. is out of control.
C. has an increasing trend.
D. has a decreasing trend.
Answer: B
Which process documents the business needs of a project and the new product, service or
other result that is intended to satisfy those requirements?
Answer: B
A. Transference
B. Avoidance
Answer: A
A. Decomposition
B. Project management software
C. Applying lead and lags
D. Expert judgment
Answer: C
A. Stakeholder register
B. Requirements documentation
C. Prototypes
D. Organizational process assets
Answer: A
When managing a project team, what helps to reduce the amount of conflict?
Answer: A
A. Contract plan
B. Procurement plan
C. Closure process
D. Procurement audits
Answer: D
Answer: B
What is the schedule performance index (SPI) using the following data?
BAC = $100,000
PV = $50,000
AC = $80,000
EV = $40,000
A. 1.00
B. 0.40
Answer: D
Activity resource requirements and resource breakdown structure are outputs from what
Project Time Management process?
A. Schedule Control
B. Activity Definition
C. Schedule Development
D. Activity Resource Estimating
Answer: D
Explanation:
Activity Resource Estimate Assumptions and Breakdown StructuresIn the Estimate Activity
Resources process, the key output is activity resource requirements. These requirements
describe the types and quantities of resources needed for each project activity.Once you
know what resources you need, you can begin to estimate the time each activity will take to
complete. In this way, the activity resource requirements list generated by the Estimate
Activity Resources process become inputs for the Estimate Activity Durations process.
Activity resource requirements listThe activity resource requirements list identifies, for
tracking purposes, the activity's code in the work breakdown structure, as well as its name.
Vital to generating the project schedule, it details the resources that you've estimated you
need to complete the activity, and addresses.
Resource description – The Resource description column lists each type of resource that is
required for the activity. This includes human resources, materials, and facilities.
Number required – The Number required column identifies the quantity required of each
resource. This value can be specified in any measurement unit, such as hours, days, or
physical number of units required.
Resource assumptions – Resource assumptions are important factors to consider when
devising the project schedule. Any relevant assumptions about the resource can be
included, for example resource availability, skills, or quality.
Resource availability – The Resource availability column specifies when each resource can
be used. This is vital information for putting together the project schedule.
Resource dependencies – The Resource dependencies column identifies factors that may
In which process might you use risk reassessment as a tool and technique?
Answer: B
A. Product analysis
B. Ishikawa diagram
C. Inspection
D. Requirements traceability matrix
Answer: C
Which of the following describes the purpose of the quality control process?
Answer: C
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan
Answer: B
A. Expert judgment
B. Project management methodology
C. Stakeholder analysis
D. Status review meetings
Answer: D
Explanation: Performance Reporting is the process for "collecting and distributing
performance information" like "status reporting, progress measurement, and forecasting"
(comp. PMBOK3, p. 221): On the base of the collected performance information
concerning scope, schedule, cost and quality this process generates the reports which are
distributed to the stakeholders (comp. PMBOK3, p. 231). Basicly one can determine four
types of reports:
A. Project manager
B. Portfolio manager
C. Work breakdown manager
D. Program manager
Answer: D
Answer: B
A. Pareto chart
B. Cause and effect diagrams
C. Control charts
Answer: A
A. Rework
B. Inspections
C. Training
D. Testing
Answer: A
A. Collect Requirements
B. Define Scope
C. Develop Project Charter
D. Develop Project Management Plan
Answer: C
Answer: A
A work package has been scheduled to cost $1,000 to complete, and was to be finished
today. As of today, the actual expenditure is $1,200 and approximately half of the work has
been completed.
A. -$700
B. -$200
C. +$200
D. +$500
Answer: B
Answer: C
Answer: B
A. Ishikawa diagram
B. Control Chart
C. Run Chart
D. Pareto Chart
Answer: D
Answer: C
What is the status of the project whose data is shown in the following S-curve?
Answer: B
A. Delphi technique
B. Unanimity
C. Observation
D. Presentation technique
Answer: A
Answer: C
Which process group can be performed outside the project's scope of control?
A. Planning
B. Monitoring and Control
C. Closing
D. Initiating
Answer: D
A. Scoping
B. Budgeting
C. Closing
D. Quality
Answer: C
Which of the following provides a comprehensive and consistent method of controlling the
project and ensuring its success?
A. Stakeholder management
B. Monitoring and controlling
C. Project governance
D. Project management methodology
What scope definition technique is used to generate different approaches to execute and
perform the work of the project?
Answer: C
A. Flowcharting
B. Earned value
C. Cost-benefit analysis
D. Pareto analysis
Answer: C
Explanation: Selection MethodsThere are various project selection methods practiced by
the modern business organizations. These methods have different features and
characteristics. Therefore, each selection method is best for different organizations.
Although there are many differences between these project selection methods, usually the
underlying concepts and principles are the same.
Following is an illustration of two of such methods (Benefit Measurement and Constrained
Optimization methods).
As the value of one project would need to be compared against the other projects, you
could use the benefit measurement methods. This could include various techniques, of
which the following are the most common.
• You and your team could come up with certain criteria that you want your ideal project
objectives to meet. You could then give each project scores based on how they rate in
each of these criteria, and then choose the project with the highest score.
• When it comes to the Discounted Cash flow method, the future value of a project is
ascertained by considering the present value and the interest earned on the money. The
higher the present value of the project, the better it would be for your organization.
• The rate of return received from the money is what is known as the IRR. Here again, you
need to be looking for a high rate of return from the project.
The mathematical approach is commonly used for larger projects. The constrained
optimization methods require several calculations in order to decide on whether or not a
project should be rejected.
These benefits and costs need to be carefully considered and quantified in order to arrive
at a proper conclusion. Questions that you may want to consider asking are in the selection
1. Would this decision help me to increase organizational value in the long run?
2. How long will the equipment last for?
3. Would I be able to cut down on costs as I go along?
In addition to these methods, you could also consider Choosing based on opportunity cost -
When choosing any project, you would need to keep in mind the profits that you would
make if you do decide to go ahead with the project.
Profit optimization is therefore the ultimate goal. You need to consider the difference
between the profits of the project you are primarily interested in, and the next best
alternative.
A. Alternative analysis
B. Bottom-up estimating
C. Resource breakdown structure
D. Enterprise environmental factors
Answer: C
Answer: B
A. End-to-end
B. Finish-to-end
C. Start-to-end
D. Start-to-start
Answer: D
During the initial stages of the project, what do activity attributes include?
Answer: B
Which tool and technique uses a statistical relationship between historical data and other
variables to calculate estimates?
A. Analogous estimating
B. Three-point estimates
C. Parametric estimating
D. Bottom-up estimating
Answer: C
Answer: A
A. Functional
B. Projectized
C. Matrix
D. Balanced
Answer: A
Which of the following is a conflict resolving technique that emphasizes areas of agreement
rather than areas of difference?
A. Withdrawing/Avoiding
B. Forcing
C. Collaborating
D. Smoothing/Accommodating
Answer: D
Emphasizing areas of agreement rather than areas of difference is part which of the
following conflict management techniques?
A. Smoothing
B. Compromising
Answer: A
Which of the following is one of the tools and techniques for the Define Activities process?
Answer: A
Rolling wave planning is used as a tool and a technique in which of the following
processes?
Answer: B
Who is responsible for determining which processes from the Process Groups will be
employed and who will be performing them?
What is the status of a project if the Cost Performance Index is 1.25 and the Schedule
Performance Index is 0.75?
Answer: A
A. EV
B. SPI
C. PV
D. ETC
Answer: A
What provides information regarding the ways people, teams, and organizational units
behave?
A. Organizational chart
B. Organizational theory
C. Organizational structure
D. Organizational behavior
Answer: B
Answer: A
Answer: B
Answer: B
Answer: D
A. 0.80
B. 0.89
C. 1.13
D. 1.25
Answer: A
Answer: B
Answer: D
Answer: C
Answer: B
The degree of risk shared between the buyer and seller is determined by the:
A. contract type.
B. sponsors.
C. project manager.
D. stakeholders.
Answer: A
Answer: B
Placing many or all of the most active project team members in the same physical location
to enhance their ability to perform as a team is called which of the following?
A. Team training
B. Co-location
C. Team location
D. Organization training
Answer: B
Which tools or techniques will the project manager use for developing the project team?
A. Negotiation
B. Roles and responsibilities
C. Recognition and rewards
D. Prizing and promoting
Answer: C
Answer: D
A. Quality metrics
B. Less rework
C. Quality control measurements
D. Benchmarking
Answer: B
Answer: B
Answer: B
Which of the following is defined by a project's life cycle and varies by application area?
A. Product
B. Product-oriented processes
C. Project management process groups
D. Project-oriented processes
Answer: B
A. Initiating
B. Executing
C. Planning
D. Controlling
Answer: C
Answer: D
Answer: C
What risk technique is used to quantify the probability and impact of risks on project
objectives?
A. Expert judgment
B. Risk registry
C. Risk response planning
D. Interviewing
Answer: D
Answer: A
Answer: D
Answer: B
Which process uses occurrence probability and impact on project objectives to assess the
priority of identified risks?
A. Risk identification
B. Qualitative risk analysis
C. Risk management planning
D. Quantitative risk analysis
Answer: B
When using the Delphi technique for gathering information, what forecasting method is
being used?
Answer: D
A. Functional requirement
B. Status report
C. Customer need
D. Defect repair
Answer: D
A. Project scope, schedule, cost, and quality of the products of the work packages
B. Central coordinator of communication management across projects, and for the delivery
of specific project objectives, organization opportunity assessment
C. Assigns project resources to best meet project objectives
D. Overall risk, overall opportunity and interdependencies among projects
Answer: D
A project team is in which of the following processes when they finalize all activities across
all of the management process groups to formally complete the project?
A. Closing
B. Executing
C. Monitoring and Controlling
D. Planning
A. WBS directory
B. Activity list
C. WBS
D. Project schedule
Answer: C
A. Identify Risks
B. Monitor and Control Risks
C. Plan Risk Management
D. Plan Risk Responses
Answer: A
Which of the following techniques uses historical information to estimate the activity
duration?
A. Three-point estimating
B. Organizational process asset
C. Analogous estimating
D. Reserve analysis
Answer: C
In which tool and technique is it possible to find a correlation between dependent and
independent variables?
A. Fishbone diagram
B. Control chart
C. Run chart
D. Scatter diagram
Answer: D
A. Collaborating
B. Issue log
C. Leadership
D. Motivation
Answer: A
In which of the following team development stages does the team meet and learn about the
project and their formal roles and responsibilities?
A. Forming
B. Storming
C. Norming
D. Performing
Answer: A
A. Variance analysis
B. A planned start date and a planned finish date for each schedule activity
C. A critical path diagram
D. Critical chain analysis
Answer: B
Project team members begin to address the project work and technical decisions. The
project team is in which of the following stages of team development?
A. Storming
B. Forming
C. Norming
D. Performing
Answer: A
What is the name of the statistical method that helps identify which factors may influence
specific variables of a product or process under development or in production?
Answer: B
Which knowledge area employs the processes required to ensure timely and appropriate
generation, collection, distribution, storage, retrieval, and ultimate disposition of project
Answer: C
Who must accept the end product for a project to be considered closed?
A. Project team
B. Project manager
C. Project management office
D. Customer or sponsor
Answer: D
Answer: A
How many process groups are there according to the PMBOK Guide?
A. 5
B. 9
Answer: A
Answer: A
Answer: C
A. 5
B. 8
C. 9
D. 12
A. Baseline
B. Planned value
C. Upper specification limit
D. Expenditure
Answer: C
A project manager needs the project team to make a group decision. Which of the following
is a method that can be used to reach a group decision?
A. Expert judgment
B. Majority
C. SWOT analysis
D. Brainstorming
Answer: B
Answer: A
Explanation:
Activity definition refers to the process of parsing a project into a number of individual tasks
Answer: A
Which illustrates the connection between work that needs to be done and its project team
members?
Answer: D
Which process involves aggregating the estimated costs of the individual schedule
activities or work packages?
A. Cost baseline
B. Cost forecasting
C. Cost variance
D. Cost budgeting
Answer: D
Which estimating technique uses the actual costs of previous similar projects as a basis for
estimating the costs of the current project?
A. Analogous
B. Parametric
C. Bottom-up
D. Top-down
Answer: A
Answer: B
A. Weak matrix
B. Functional
C. Balanced matrix
D. Projectized
Answer: A
Which type of analysis is used to examine project results through time to determine if
performance is improving or deteriorating?
A. Control chart
B. Earned value
C. Variance
D. Trend
Answer: D
Which tool and technique identifies inefficient and ineffective policies, processes and
procedures?
A. Scope audits
B. Scope reviews
C. Quality audits
D. Control chart
Answer: C
Which type of tool would be used for the quality planning activity?
Answer: D
A. Product
B. Cost benefit
C. Stakeholder
D. Research
Answer: C
A. Accepted deliverables
B. Work performance measurements
C. Requirements documentation
D. Work performance information
Answer: B
There are seven members on the project team not counting the project manager and the
sponsor. How many communication channels are there?
A. 21
B. 28
C. 36
Answer: C
A. Initiating
B. Planning
C. Monitoring and Controlling
D. Executing
Answer: B
In which of the team development stages are the teams interdependent and work through
issues smoothly and effectively?
A. Norming
B. Forming
C. Storming
D. Performing
Answer: D
A. Repetitive
B. Unique
C. No outcome
D. Permanent
Answer: B
In which domain of project management would a Pareto chart provide useful information?
A. Scope Management
B. Time Management
C. Communications Management
D. Quality Management
Answer: D
Which tool and technique of quality planning involves comparing actual or planned
practices to those of other projects to generate ideas for improvement and provide a basis
by which to measure performance?
A. Histogram
B. Quality audits
C. Benchmarking
D. Performance measurement analysis
Answer: C
A. By identifying quality standards that are relevant to the project and determining how to
satisfy them.
B. By monitoring specific project results in compliance with relevant quality standards and
determining corrective actions as needed.
C. By ensuring that the entire project team has been adequately trained in quality
assurance processes.
D. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to
ensure conformance to quality standards.
A. Functional
B. Weak
C. Balanced
D. Strong
Answer: D
A. Procurement documents
B. Expert judgment
C. Bidder conferences
D. Contract types
Answer: C
Answer: C
Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:
A. process groups.
B. phase gates.
C. knowledge areas.
D. project phases.
Answer: A
Information collected on the status of project activities being performed to accomplish the
project work is known as what?
Answer: B
Explanation:
Work Performance Information
Part of the executed project management plan includes the routine collection of work
performance information. The information gathered is important, and is useful as input data
for quality control measures and programs. It is also useful when audits, quality reviews,
and process analyses are conducted. This is especially true of work performance
information collected which includes technical performance measures, project deliverables
status, required corrective actions, and performance reports. Pertinent work performance
Information is essential to the project management plan and includes, but is not limited to:
Answer: B
At which point of the project is the uncertainty the highest and the risk of failing the greatest
Answer: B
Answer: B
You are assigned to implement the project control plan. What should you do to ensure the
plan is effective and current?
Answer: A
Explanation: The document control plan is an outline or guide on how physical or virtual
documents will be managed throughout the life of the project. It provides a road map for
tracking documents and for adding, archiving, and removing new documentation from the
process.
A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV
Answer: C
A. Risk categorization
B. SWOT analysis
C. Risk register categorization
D. Risk probability and impact assessment
Answer: B
A. Cost-Benefit Analysis
B. Variance Analysis
C. Reserve Analysis
D. Stakeholder Analysis
Answer: B
Answer: B
Answer: D
Topic 2, Volume B
Answer: B
Explanation:
During the planning phase of your project, your project team members have discovered
another way to complete a portion of the project scope. This method is safer for the project
team, but may cost more for the customer. This is an example of _______.
A. Alternative identification
B. "'s^ assessment
C. Alternative selection
D. Product analysis
Answer: A
Explanation:
A. close contracts
B. Lessons learned documentation
C. Deliverable acceptance
D. Scope statement
Answer: D
Explanation:
A. Formal acceptance
B. WBS template
C. sow acceptance
D. Rework
Answer: A
Explanation:
Which of the following subsidiary plan contains the quality objectives for the project?
Answer: A
Explanation:
The quality baseline documents the quality objectives for the project.
_________ is always the lowest risk for the buyer if the scope of work is not well defined.
Answer: A
Explanation:
Cost plus incentive fee is always the lowest risk for the buyer if the scope of work is not
well defined. Fixed price and purchase order are the best choice for buyer when the item is
well defined
A. Buyer or seller
B. Vendor or seller
C. Purchasing
D. Sellino-
Answer: A
Explanation:
Answer: A
Explanation:
The rough order of magnitude is the least accurate approach, as it may vary from -25
percent to +75 percent.
A. Procurement Management
B. Planning Management
C. Scope Management
D. Control Management
Answer: A
Explanation:
A. Internal
B. External
C. Outside
D. Assigned
Answer: B
Explanation:
Function of the __________ is to make sure that changes to anything in the project are
recorded and agreed to by the stakeholders.
A. Project Manager
B. Sponsor
C. Team Lead
D. Management
Answer: A
Explanation:
Function of the project manager is to make sure that changes to anything in the project are
recorded and agreed to by the stakeholders.
Who has the responsibility for informing the final deliverable to all stakeholders?
A. Project Manager
B. Sponsor
Answer: A
Explanation:
Project Manager has the responsibility for informing the final deliverable to all stakeholders.
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements
Answer: A
Explanation:
A. Acceptance
B. shaie
C. Mitigate
D. Transfer
Answer: A
Explanation:
Acceptance is when no change to the project is made for a risk. A contingency can be set
aside to offset the impact of the risk.
From whom do you need to gain the formal acceptance at project closure?
A. The customer
B. The qualify director
C. Project management office
D. Project manager
Answer: A
Explanation:
need to gain this formal acceptance at project closure from the customer and sponsor.
A. Project justification
B. Project product
C. Project manager authority
D. Project objective
Answer: C
Explanation:
Answer: A
Explanation:
There is no project for the sake of spending money. There is a clear link between the
project deliverables and the business strategy.
Answer: D
Explanation:
Output of project initiation is formally authorizing the project. Output of project scope
initiation is: Project charter PM assigned Constraints and Assumptions.
Which of the following is the most important task of the project manager during the
Execution and Control phase?
A. Information management
B. Maintain scope statement
C. Maintain Charter
D. Maintain Closing document
Answer: A
One of the most important tasks of the project manager during the Execution and Control
phases of the project is the management of information.
Answer: A
Explanation:
Updating the risk register first happens in Identify Risks phase. Determining risk roles and
responsibilities, Identifying risk categories and developing a risk management plan are part
of Plan Risk Management.
A. Project task
B. w°rl< package
C. sow
D. None
Answer: B
Explanation:
Answer: D
Explanation:
Answer: A
Explanation:
Answer: A
Explanation:
project charter: The project charter formally authorizes the project, assigns the project
manager, and gives a high-level definition of the projects and its deliverables.
You are project manager of a project, which of the following is not your responsibility?
Answer: A
Explanation:
Answer: A
Explanation:
The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule
performance index of 1 or greater suggests that the project is ahead of schedule.
Assumptions are factors that, for planning purposes, are considered to be ______.
Answer: A
Explanation:
PMBOK describes assumptions as "factors that, for planning purposes, are considered to
be true, real, or certain."
Answer: A
Explanation:
Answer: A
Explanation:
Bottom-up estimating: Estimating the cost of individual work items and then rolling up the
costs to arrive at a project total. It is more accurate.
You are managing a project that will implement a new Insurance software package. Two
project team members have difficulty working together. They come to you, for help
resolving the issues. You immediately set up a meeting that includes the functional
manager. After the meeting you and the functional manager discuss the issues and agree
on a solution. What type of organizational structure you are working in?
A. Functional
B. Balanced matrix
C. Piojectized
D. Strong Matrix
Answer: B
Explanation:
Balanced matrix: Power is shared between both Functional and Project Manager. In this
case you include the functional manager in the meeting therefore it is Balanced matrix
organization.
Answer: A
Explanation:
If your cost performance index is above 1.0, it indicates that you have costs that are less
then estimated; so doing good. Option A is BEST fit for this CPI = EV/AC (Earned value/
Actual cost
A. Sponsor
B. Customer
C. Project Manager
D. Team Lead
Answer: B
Explanation:
Answer: A
Explanation:
If your cost performance index is above 1.0, it indicates that you have costs that are less
then estimated. CPI = EV/AC (Earned value/ Actual cost)
Answer: D
Explanation:
Which document is best suited for tracking the assignment of all resources to specific tasks
in a project?
A. RACI mAl,x
B. sow
C. Staffing management plan D)0 CPI
Answer: A
Explanation:
The RACI matrix lists responsibilities of all resources. The staffing management plan only
lists types of resources and timing.
Answer: D
Explanation:
Answer: A
Explanation:
A. Project manager
B. QA manager
Answer: A
Explanation:
The product description of a project can help to create procurement details. Which one of
the following best describes product description?
A. The product description defines the contracted work, based on the requirements of the
project customer
B. The product description defines the contracted work
C. The product description defines the requirements for the contract work
D. Al1 of the above
Answer: A
Explanation:
The product description defines the contracted work, based on the requirements of the
project customer
Answer: D
Explanation:
Delivery dates and availability of resources can be found in the details of the __________.
Answer: A
Explanation:
Delivery dates and availability of resources can be found in the details of the WBS.
You are managing a project that will implement a new MARKETING software package. You
have assigned the resources and want to keep the IT manager in the loop by informing him
or her of your decisions. Which type of organizational structure are you working in?
A. Pi'ojectized
B. Strong Matrix
C. Weak Matrix
D. Functional
Answer: B
Explanation:
Projectized Organization: Any organizational structure in which the project manager has full
authority to assign priorities and to direct the work of individuals assigned to the project.
Strong Matrix: The project manager is assigned full time and has a full time support staff.
Project manager has the preeminent position of authority. Weak Matrix: Power reset with
Collect Requirements process starts in Project Planning Phase and uses the outputs of the
__________.
A. Initiation Process
B. Project closer Process
C. Estimation Process
D. Closing process
Answer: A
Explanation:
Collect Requirements process starts in "Project Planning Phase" and uses the outputs of
the Initiation Process.
Answer: A
Explanation:
Project scope : The features and functions that are to be included in a product or service.
The work that must be done in order to deliver a product with the specified features and
functions.
A. Compromise
B. Smoothing
C. Foimal
D. Coercive
Answer: B
Explanation:
smoothing is a conflict resolution technique, the rest are forms of leadership power.
Make-or-buy decisions measure the costs of both options. What are the two options?
Answer: A
Explanation:
Make-or-buy decisions measure the costs of both options. When doing this analysis, it
should include both direct and indirect costs so that the final decision is based on
comparisons that are equal.
Answer: A
Explanation:
Root cause analysis: A technique to identify the underlying cause of a problem and take
steps to prevent further occurrence.
Answer: A
Explanation:
You are the project manager of a project that just went into extinction mode. This means
that your project __________.
Answer: A
Explanation:
A project that ends in extinction mode is a project that has ended before meeting its stated
objectives.
You are the project manager of the MKTG Project. The project has a budget of $200,000
and is expected to last 2 years. The project is now 20 percent complete and is on schedule.
What is the BAC?
A. $-00,000
B. $200,00
C. $50,000
D. None of the above
Answer: B
Explanation:
The BAC is the budget at completion (Total budgeted cost), which is $200,000.
Answer: B
You have a piece of equipment that was purchased for your project recently for $5,000 and
is expected to last 5 years in production. At the end of the five years the expected worth of
the equipment is $2,000. Using straight-line deprecation, what is the amount that can be
written off each year?
A. $600
B. $1200
C. $3000
D. Zero
Answer: A
Explanation:
The straight-line depreciation takes the purchase value of the item, minus the salvage price
of the item, divided by the number of time periods. Calculation is (5000-2000)/5 = $600
Answer: D
Explanation:
Answer: A
Explanation:
A. Formal
B. Consistent
C. Personal
D. Verbal
Answer: A
Explanation:
Which time estimating tools estimate the basis for activity durations can be quantitatively
determined by multiplying the quantity of work to be performed by the productivity rate?
Answer: A
Explanation:
Parametric Estimating: Estimating the basis for activity durations can be quantitatively
determined by multiplying the quantity of work to be performed by the productivity rate.
Based on the PMBOK, who is ultimately responsible for the project quality?
A. Project team
B. Project manager
C. QA manager
D. Validation engineer
Answer: B
Explanation:
A. Compromise
B. Smoothing
C. Foimal
D. Coercive
Answer: B
Explanation:
A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan
Answer: A
Explanation:
Scope statement comes first in the project plan. Scope statement is the written statement
of project. It contains: Project objectives, Project justification, Project deliverables
You are creating your WBS and keep decomposing tasks into smaller units. How can you
tell when you are done?
A. Keep decomposing tasks until you reach an amount of work that is small enough to
reliably estimate required resources and duration.
B. Keep decomposing work until you reach a predetermined number of hierarchy levels to
keep the WBS balanced.
C. Keep decomposing tasks until you reach an amount of work that can be accomplished in
one DAY.
D. Keep decomposing tasks until you reach an amount of work that can be accomplished in
one WEEK.
Answer: A
Explanation:
Keep decomposing tasks until you reach an amount of work that is small enough to reliably
estimate required resources and duration.
The Ishikawa diagram, Pareto chart, control charts, and statistical sampling are examples
of ________.
A. Quality assurance
B. Quality control
C. Quality rules
D. CMM
Answer: B
Explanation:
The Ishikawa diagram, the control charts, Pareto chart, and statistical sampling are
examples of basic tools of quality control.
You have been with the organization; you constantly hear rumours about a certain CAPM
failing to live up to the CAPM Code. What you should do?
Answer: A
Explanation:
A. Project sponsor
B. Project team
C. Project manager
D. Senior Management
Answer: A
Explanation:
The project sponsor must have the authority to select and fund the project.
Answer: A
Explanation:
Administrative Closure should occur at the end of each phase, not only at the end of the
overall project
A. Project archives
B. Index
C. sow
D. Project History
A complete set of indexed project records for archiving by the appropriate parties.
What is the communication channel delta if the members in the communication plan are
increased from 5 to 10?
A. 35
B. 5
C. 15
D. 75
Answer: A
Explanation:
Which of the following project document is best suited for tracking costs of resources?
Answer: A
Explanation:
Answer: D
Explanation:
Output of project initiation is formally authorizing the project. Output of project scope
initiation is: Project charter PM assigned Constraints and Assumptions.
How many communication channels will be required in a project in which 5 individual are
participating?
A. 10
B. 12
C. 4
D. 5
Answer: A
Explanation:
A. Project Manager
B. Sender
C. Project coordinator
D. Sponsor
Answer: B
Explanation:
The sender has to make sure that the receiver acknowledges the receipt and message is
understood, and the receiver needs to ensure that the sender received the
acknowledgement.
You are project manager of a project and as part of the team acquisition process; you hire
a new employee and assigns him to your project team. According to Maslow's hierarchy of
needs, what needs level he most likely is at?
A. Social need
B. Physical need
C. Safety and security
D. Security
Answer: A
Explanation:
as new to project he is most likely looking for acceptance and friendship. This comes under
Social need.
How many communication channels will be required in a project in which 5 individual are
participating?
Answer: A
Explanation:
A. Written down
B. Understandable
C. Not understandable
D. No need to write
Answer: A
Explanation:
Assumptions that are not written down are the most dangerous.
Answer: B
Explanation:
Answer: A
Explanation:
You are the project manager of a project. If there are approved changes to the original
scope, what you do with the old original scope?
Answer: A
Explanation:
_________ is the international organization that controls the standards for quality.
Answer: A
Explanation:
ISO is the international organization that controls the standards for quality.
Answer: D
Explanation:
Inputs for Initiation process : Product description Strategic plan Selection criteria Historical
information
Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are
examples of ____________.
Answer: A
Explanation:
Projects are seeded from the recognition of a regulatory or business need. Cost benefit
analysis, scorecard modelling, payback periods, and internal rate of return are examples of
benefits measurement methods when selecting a project. Best Option is A.
Answer: A
Explanation:
Most change requests (CRs) are a result of Value added change (enhancements).
A. Project Manager
B. Team Leader
C. Sponsor
D. Project Team
Answer: A
Explanation:
Project Manager is responsible for the creation of the final project plan.
A. Project charter
B. Final deliverable
C. Schedule
D. QA activities are done
Answer: B
Explanation:
You are project manager and now in middle of creating RFP (Request for proposal). RFP
(Request for proposal) is done in _______.
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements
Answer: A
Explanation:
You are the project manager of a project and budgeted money to provide cash awards to
team members that exceed expectations. A project team member that is motivated by the
chance to earn cash reward can most accurately be explained by which theory
A. Hierarchy of needs
B. Expectancy theory
C. Achievement theory
Answer: B
Explanation:
Answer: B
Explanation:
The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule
performance index of 1 or greater suggests that the project is ahead of schedule.
A. Collect Requirements
B. Define Scope
C. Integrated Change Control
D. Monitor and Control Project Work
Answer: B
Explanation:
A. Customer satisfaction
B. Prevention over inspection
C. Continuous improvement
D. Al1 of the above
Answer: D
Explanation:
__________ is providing detailed plans for tasks that are about to start in the near future
using the most current information and revisiting future activities when they near their
starting dates.
Answer: A
Explanation:
Rolling wave planning is providing detailed plans for tasks that are about to start in the near
future using the most current information and revisiting future activities when they near their
starting dates.
When you are developing the estimates for project, you choose to add the individual
estimates for the activities that comprise each phase. What type of estimation method are
you using?
A. Parametric estimating
B. Bottom-up estimating
C. Top-down estimating
D. Analogous estimating
Answer: B
Explanation:
Bottom-up estimating: Estimating the cost of individual work items and then rolling up the
costs to arrive at a project total: It is more accurate. Analogous estimating: Analogous
estimating is also called top-down estimating and uses the actual cost of a previous, similar
project as the basis for estimating the cost of the current project. Parametric estimating:
Using project characteristics (or parameters) in a mathematical model to predict costs (e.g.,
price per square meter).
A. Illegal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above
Answer: A
Explanation:
A contract cannot contain illegal activities. A contract can contain other options available.
Answer: D
Explanation:
The scope management plan provides details about how the project scope may be
changed.
Which monitoring or controlling activities would not result in preventive action being
applied?
A. Control Scope
B. Manage project team
C. Quality control
D. Manage Scope statement
Answer: A
Explanation:
Scope, schedule, and Control Costs can all result in corrective action, but not preventive
action.
Answer: A
Explanation:
The risk management process group serves as the road map used to reduce its impact on
the project.
A. Project plan
B. sow
C. WBS
D. Strategic planning
Answer: A
Explanation:
Project plan is the road map for the execution of the project.
A. Strategic planning determines which projects will be choosing in order to achieve the
organizational goals
B. Strategic planning determines which projects will be sponsor in order to achieve the
organizational goals
C. Strategic planning determines these are the projects that get chosen and funded
D. Al1 of the above
Answer: D
Explanation:
A. Verify Scope
B. Collect Requirements
C. Control Scope
D. Al1 of the above
Answer: D
Explanation:
There are following processes which are part of Project Scope Management. Collect
Requirements Define Scope Create WBS Verify Scope Control Scope
You are project manager of a project. During the process of selecting the sellers, you reject
one vendor because it doesn't have the manufacturing capability. This is an example of
which selection tool?
A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment
Answer: B
Explanation:
A screening system rejects sellers that does not meet minimum requirements for the
project.
A. An action that brings future project events Into alignment with the project plan
B. An action to correct something in the project
C. An action to prevent something in the project
D. Corrective action is not related to project
Answer: A
Explanation:
Corrective action: An action that brings future project events into alignment with the project
plan
Project just went into inclusion mode. This means that project __________.
Answer: A
Explanation:
inclusion mode: Has become part of the business processes. A contract cannot contain
_____________.
Answer: A
Explanation:
Topic 3, Volume C
You are the project manager of a project .You have just completed the Define Activities,
activity resources estimating, and Estimate Activity Durations processes. Which process
have you left out?
A. Control Schedule
B. Create WBS
C. Sequence Activities
D. Operations
Answer: C
Explanation:
The PMBOK places Sequence Activities between Define Activities and Estimate Activity
Resources.
To calculate the late start and late finish dates for a set of tasks , you must do :
Answer: C
Answer: D
A. Contract negotiation
B. Weighting system
C. Payment system
D. Screening system
Answer: C
Explanation:
Payment system is not a tool or technique for Source Selection. Other options are .
Answer: A
Explanation:
Develop Human Resource Plan: Planning, identifying, documenting, and assigning project
roles, responsibilities, and reporting relationships to individuals or groups.
A. Closing
B. Execution
C. Planning
D. Initiation
Answer: A
Explanation:
Project will close after final deliverable. Final deliverables are defined in the closing phase.
Answer: A
Explanation:
Answer: A
Define Scope involves subdividing the major project deliverables into smaller, more
manageable components to __________.
Answer: D
Explanation:
Define Scope involves subdividing the major project deliverables into smaller, more
manageable components to: Improve the accuracy of cost, time and resource estimates.
Define a baseline for performance measurement and control. Facilitate clear responsibility
assignments.
A. Statistically dependent
B. Variance distributed
C. Statistically independent
D. Deterministic
Answer: C
Explanation:
Statistically independent
A. Project Charter
B. Stakeholder Register
C. Pis'* Management Plan
D. Activity Cost Estimates
Answer: A
Explanation:
A. PBS
B. Project Scope statement
C. WBS Template
D. Constraints
A. Initial stage
B. Closing stage
C. Execution stage
D. None of the above
Answer: A
Explanation:
It is easy to make changes to project goals and approach at the initial stage. Stake holders
have maximum influence at Initial stage.
A. Planning
B. Closing
C. Execution
D. Control
Answer: C
Explanation:
The Planning phase is the phase with the least risk attached. The Execution phase of the
project is when you are using your resources at their highest level .
Answer: A
Explanation:
A. The work that must be done in order to deliver a product with the specified features and
functions
B. The description of the project deliverables
C. The authorizing document that allows the project manager to move forward with the
project and to assign resources to the tasks
D. The process of planning and executing all of the required work to deliver the project
Answer: A
Explanation:
project scope: The work that must be done in order to deliver a product with the specified
features and functions.
You are project manager of a project and you are offering an estimate that you know will be
changed after the contract is signed is ___________.
Answer: D
Explanation:
A. Identification
B. Solicitation
C. Quantification
D. Response Development
Answer: B
Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6
days, what is the PERT weighted average?
A. 6
B. 4
C. 6.3
D. 6.1
Answer: A
Answer: B
Explanation:
Contract negotiation is not the tools and techniques used in Contract Administration.
Answer: A
Explanation:
A. Projectized organization
B. Balanced Matrix organization
C. Strong Matrix
D. Weak Matrix organization
Answer: A
A. Sequence Activities
B. Develop Schedule
C. Define Activities
D. Estimate Activity Durations
Answer: A
You are the project manager for a Project. Project is a global project. Some peoples are
working from US and some are from India. Client says budget should not cost more than
$12 million. Because of the global concerns, the final budget must be in U.S. dollars. This
is an example of which of the following?
A. Internationalization
B. Budget constraint
C. Management constraint
D. Quality constraint
Answer: B
Explanation:
This is an example of a budget constraint. The budget must not exceed $12 million.
_________ is the best choice for buyer when the item is well defined.
Answer: B
Cost plus incentive fee is always the lowest risk for the buyer if the scope of work is not
well defined. Fixed price and purchase order are the best choice for buyer when the item is
well defined.
You are working with an organization and you found that one stakeholder not disclosing all
of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS
that does not include all the tasks necessary to get the project done. What you should do?
A. Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the
project
B. Confront the other project manager immediately
C. Mail t0 PMI headquarters
D. Ignore it
Answer: A
Explanation:
You can talk to the CAPM about the WBS changes. If he or she refuses to change the
WBS, you have a responsibility to go to stakeholders and voice your concerns.
Answer: A
A. Analogous estimating
B. Life-cycle costing
C. Parametric modelling
D. Bottom up estimating
Answer: C
Explanation:
A. Contract
B. Responsibilities
C. WBS
D. Identification
Answer: A
Explanation:
When you are developing the estimates for project, you choose in a mathematical model to
predict estimate. What type of estimation method are you using?
Answer: A
Explanation:
Bottom-up estimating: Estimating the cost of individual work items and then rolling up the
costs to arrive at a project total: It is more accurate. Analogous estimating: Analogous
estimating is also called top-down estimating and uses the actual cost of a previous, similar
project as the basis for estimating the cost of the current project. Parametric estimating:
Using project characteristics (or parameters) in a mathematical model to predict costs (e.g.,
price per square meter).
Answer: D
Explanation:
Your company create software products, and introducing a new product. To determine the
characteristics and features of the new product line, you will have to perform ________.
A. Progressive elaboration
B. Stake holder's review
Answer: A
Explanation:
The process of determining the characteristics and features of the product of the project is
called Progressive elaboration. Progressive elaboration is carried out via steps in detailed
fashion.
A. Billing customers
B. Managing an organization
C. Constructing a building
D. Providing technical support
Answer: C
Which of the following must be measured regularly to identify variances from the plan.
A. Stakeholder requirements
B. Project performance
C. Control Schedule
D. Project controls
Answer: B
Answer: A
Answer: A
Explanation:
A cost performance index of 1 or greater suggests that project in delivering more with less
money; so doing well. Option A is BEST fit for this. CPI = EV/AC (Earned value/ Actual
cost)
Which of the following plans is not done during the writing of a project plan?
A. Executive Communication
B. Risk Management
C. Quality Management
D. Scope Statement
Answer: A
Explanation:
Executive Communication may be a part of your communication process but not in project
plan.
What involves determining what quantities are to be used to perform project activities.
A. Resource planning
B. Estimate Costs
C. Determine Budget
D. Control Costs
Answer: A
Explanation:
Answer: A
A. Formal acceptance
B. WBStemplate
C. SOW acceptance
Answer: A
Explanation:
Your project team is composed of team members in three countries plus a contractor team
in a fourth country. What tool would optimize communication?
Answer: A
Explanation:
An electronic document repository allows all team members access to the documents,
regardless of location.
A. Analogous estimating
B. Life-cycle costing
C. Parametric modeling
D. Bottom up estimating
Answer: A
A. Risk
B. Assumption
C. Constraint
D. Budget
Answer: B
Explanation:
Customer formally accepts the deliverables of each project phase. This process is known
as ________.
A. Verify Scope
B. Quality Assurance
C. Quality Control
D. Quality Measurement
Answer: A
Explanation:
Verify Scope is the process of formally accepting the deliverable of a project or phase. A is
incorrect because EVM measures project performance. C is incorrect because quality
control is concerned with the correctness of the work, not the acceptance of the work. QA
is incorrect because this described the quality program for the organization as a whole.
Answer: D
You are the project manager of a project .You have just completed the Collect
Requirements and Define Scope. What should you do next?
A. Create WBS
B. Vei*<fy Scope
C. Value analysis
D. Control Scope
Answer: A
Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.
You are the project manager of a project and the project is a month into the executing
phase. There are some cliques forming among the team members. Which leadership style
you follow for best outcome?
A. Supporting
B. Delegating
C. Coaching
D. Directing
Answer: C
Explanation:
Answer: B
Explanation:
Although lessons learned should be held at project conclusion, they should be held
throughout the project any time.
If you are project manager for a Project and will need as many inputs to the initiation phase
as possible. Of the following, which is the best source of information for your project?
A. Historical information
B. WBS
C. Business plans
D. RBS
Answer: A
Explanation:
Historical information is the best input of the choices available. B is incorrect since the
WBS has not been created at this point of the project. C is incorrect since business plans
are not a likely input to the initiation process
A. Generally Accurate
B. Generally less accurate
C. Bottom-up estimating
D. None
Answer: B
Explanation:
Analogous Estimate Costs is Generally less accurate . Analogous Estimate Costs Uses
Expert Judgment . It is used when reference projects are similar . It is useful in early
phases of the project.
You are the project manager of a project .You have just completed the Collect
Requirements and Define Scope. What should you do next?
A. Create WBS
B. Vei*<fy Scope
C. Value analysis
D. Control Scope
Answer: A
Explanation:
Create the WBS is the process that follows Collect Requirements and Define Scope.
A. flexible
Answer: D
Explanation:
Which of the following tools and techniques are commonly used in a Define Scope
Process?
A. Product analysis
B. Expert Judgment
C. Alternative Identification
D. All of the above
Answer: D
Answer: A
Explanation:
There is no separate process in the Project Cost Estimation knowledge area to develop a
cost management plan. It is devloped in Develop Project Management Plan process.
Answer: A
Explanation:
One of the most important tasks of the project manager during the Execution and Control
phases of the project is the management of information. All Information should be
communicated to everyone in the communication plan.
A. 45
B. 10
C. 30
D. 20
Answer: A
Explanation:
Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are
examples of:
Answer: A
Explanation:
A. Unknown Unknowns
B. Project Budget
C. Known Unknowns
D. Amount of work completed
Answer: A
Explanation:
A. Projectized organization
B. Balanced Matrix organization
C. Strong Matrix
D. Weak Matrix organization
Answer: A
Answer: A
You have a piece of equipment that was purchased for your project recently for $5,000 and
is expected to last 5 years in production. At the end of the five years, the expected worth of
the equipment is $2,000. Using the straight-line deprecation, what is the amount that can
be written off each year?
A. $600
B. $1200
C. $3000
D. $100
Answer: A
Explanation:
A is the correct answer. The straight-line depreciation takes the purchase value of the item,
minus the salvage price of the item, divided by the number of time periods. Calculation is
(5000-2000)/5 = $600.
Which of the following activity is not performed as part of the direct and manage project
execution process?
Answer: A
Explanation:
In the direct and manage project execution process, approved changes are implemented
but monitoring of those changes is part of monitoring OR controlling project work.
Which process must occur after a project manager has been assigned to the project?
A. Collect Requirements
B. Develop the project charter
C. Develop the project statement of work
D. Develop project closing document
Answer: A
Explanation:
The Collect Requirements process occurs during project planning. Other options occur
during project initiation. Option D is associated with project closing. Collect Requirements is
the best option.
Answer: B
Which of the following is ensuring that all features and functions are included in a product
or service
A. Project scope
B. Project verification
C. Project control
D. Product scope
Answer: B
Explanation:
Project verification ensuring all features and functions are included in a product or service
A. Quality
B. Scope
C. Integration
D. Procurement
Answer: A
Explanation:
Quality on a project means that you are conforming to a standard that is set before you
start the project.
Answer: A
Explanation:
An activity that consumes no time or resource and shows only that a dependency exists
between two activities is called:
A. A milestone
B. A hammock
C. A dummy activity
D. a and c
Answer: C
Answer: A
Explanation:
The primary output of the project closing process is to formalize and distribute all the
information pertaining to the closing of the project.
A. Beginning
B. Closing
C. Controlling
D. Executing
Answer: A
Explanation:
You are the project manager and you have created a contract for your customer. The
contract must have ________.
Answer: A
Explanation:
A contract must have Offer and consideration. Not all contracts demand signatures and
notary public involvement. Contract may specify a start date, but the Acceptance of the
start date is not needed for all contracts.
A. Functional
Answer: D
Explanation:
Answer: A
Explanation:
Earned value analysis is used during the execution of the project to determine resource
consumption versus planned
The activity that is most concerned with the current status of the project schedule is called
___________.
Answer: B
Explanation:
Project risk is defined as the cumulative effect of chances of ________ which will adversely
affect project objectives.
A. Likely events
B. Complex activities
C. Complex schedules
D. Uncertain occurrences
Answer: D
Explanation:
Which type of network diagram allows you to depict four types of dependencies (finish-to-
start, finish-to-finish, start-to-start, and start-to-finish)?
Answer: A
Explanation:
Your project has a budget of $240,000 and is expect to last for 1 year, with the work and
budget spread evenly across all months. The project is now in the fourth month, the work is
on schedule, but you have spent $120,000 of the project budget. What is your COST
Variance percentage in this case?
A. -50%
B. 50%
C. 40%
D. 20%
Answer: A
With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively.
The mean is _____.
A. 30.0
B. 22.5
C. 25.0
D. 27.5
Answer: A
Explanation:
mean = (20+30+40)/3= 30
A. Gantt chart
B. Milestone chart
C. fishbone diagram
D. network diagram
A scope management plan In which of the following scope management processes is the
scope management plan prepared?
A. Initiation
B. Collect Requirements
C. Define Scope
D. Verify Scope
Answer: A
You are the project manager of a project. Your project just went into integration mode. This
means that your project __________.
Answer: C
Explanation:
A project that ends in integration mode is the type of project where its resources are being
assigned to other areas.
A. The work that must be done in order to deliver a product with the specified features and
Answer: A
Which of the following is a common characteristic of most project life cycle descriptions?
A. Cost and staffing are low at the start, higher towards the end. and drop rapidly as the
project nears completion.
B. The probability of successfully completing the project is highest at the start of the
project.
C. Stakeholders have the most influence on the final characteristics of the product at the
end of the project.
D. a and b
Answer: A
A. Verify Scope
B. Collect Requirements
C. Create WBS
D. None of the above
Answer: D
Explanation:
e are following processes which are part of Project Scope Management. Collect
Requirements Define Scope Create WBS Verify Scope Control Scope
Answer: B
A. Internal
B. External
C. Outside
D. Assigned
Answer: A
Explanation:
Answer: A
Explanation:
You are the project manager for the software Project. This project must be completed
within one year. This is an example of which of the following?
A. Schedule
B. Assumption
C. Constraint
D. Planning process
Answer: C
Explanation:
Which of the following is not a part of the project cost baseline but is included in the project
budget?
Answer: A
Explanation:
The difference between the Cost Baseline and Funding requirement at Project completion
is Management Contingency Reserve. Management Contingency Reserve is not part of
project cost baseline.
A. Initiation
B. Project Plan Execution
C. Overall Change Control
D. Report Performance
Answer: A
Explanation:
Project scope management includes: Initiation, Collect Requirements, Define Scope, Verify
Scope and Control Scope
A Project Manager is at the project kick-off meeting. He confidently states the vision and
mission for the project. This PM is exhibiting the following leadership style:
A. Hierarchal
B. Authoritarian
C. Charismatic
D. Associative
Answer: C
A. Develop Schedule
B. Estimate Activity Durations
Answer: A
Answer: D
A. Identifies all the steps and processes that will be used after a project is initiated
B. Steps needed to complete a project task
C. Prepared at the beginning and fixed throughout the execution of the project
D. Includes project charter
Answer: A
Explanation:
Project Management Plan: The project management plan provides the overall plan for
executing, monitoring, and controlling, closing the project.
Answer: A
Explanation: If any change occur, the version control numbers should change.
A. Develop Schedule
B. Estimate Activity Durations
C. Estimate Activity Resources
D. Sequence Activities
Answer: A
Explanation:
Adjusting Leads and Lags: Since the improper use of leads or lags can distort the project
schedule, the leads or lags are adjusted during schedule network analysis to develop a
viable project schedule. Tools and Techniques for Develop Schedule are : Mathematical
analysis,Duration compression,Simulation,Resource-leveling ,Project management
software,Adjusting Leads and Lags and Coding structure.
Which of the following relationship is used in the Arrow Diagramming Method [ADM] :
A. Start-to-Finish
B. Finish-to-Start
C. Start-to-Start
D. Finish-to-Finish
A. Project plan
B. Process
C. Schedule
D. Flowchart
Answer: B
A. CPF
B. CPFF
C. CPIF
D. Al1 of the above
Answer: D
Explanation:
Three common types of cost-reimbursable contracts are CPF, CPFF, and CPIF Cost-Plus-
Fee (CPF), Cost-Plus-Fixed-Fee (CPFF) and Cost-Plus-Incentive-Fee (CPIF).
How many communication channels will be required in a project in which 10 individual are
participating?
A. 45
B. 12
Answer: A
Explanation: