Pmi Ca0 001

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 198

s@lm@n

PMI
Exam CA0-001
Certified Associate in Project Management (CAPM) Certification
Version: 6.11

[ Total Questions: 525 ]


PMI CA0-001 : Valid Questions
Topic break down

Topic No. of Questions


Topic 1: Volume A 325
Topic 2: Volume B 100
Topic 3: Volume C 100

100% Valid Questions - Guaranteed Success 2


PMI CA0-001 : Valid Questions
Topic 1, Volume A

Question No : 1 - (Topic 1)

Decomposition is a tool and technique used in which of the following?

A. Define Scope and Define Activities


B. Collect Requirements and Estimate Activity Resources
C. Create WBS and Define Activities
D. Create WBS and Estimate Activity Duration

Answer: C

Question No : 2 - (Topic 1)

Which process involves identifying and documenting the logical relationships among
schedule activities?

A. Schedule development
B. Activity sequencing
C. Create WBS
D. Applying leads and lags

Answer: B

Question No : 3 - (Topic 1)

Which is a tool or technique used in scope definition?

A. Templates, forms and standards


B. Change requests
C. Stakeholder analysis
D. Project assumptions

Answer: C

Question No : 4 - (Topic 1)
100% Valid Questions - Guaranteed Success 3
PMI CA0-001 : Valid Questions
Which of the following are outputs of the Monitor and Control Project Work process?

A. Requested changes, forecasts, recommended corrective actions


B. Forecasts, resources plan, bottom up estimating
C. Recommended corrective actions, cost baseline, forecasts
D. Requested changes, recommended corrective actions, project constraints

Answer: A

Question No : 5 - (Topic 1)

What component of the project scope definition defines project exclusions?

A. Project boundaries
B. Project constraints
C. Project assumptions
D. Project objectives

Answer: A

Question No : 6 - (Topic 1)

What does a SPI value greater than 1.0 indicate?

A. More work was completed than planned


B. Less work was completed than planned
C. Cost overrun for completed work has occurred
D. Cost underrun for completed work has occurred

Answer: A

Question No : 7 - (Topic 1)

Which of the following is an input to the Qualitative Risk Analysis process?

A. Risk register
B. Risk data quality assessment

100% Valid Questions - Guaranteed Success 4


PMI CA0-001 : Valid Questions
C. Risk categorization
D. Risk urgency

Answer: A

Question No : 8 - (Topic 1)

Regardless of style, what information is shown in a process flowchart?

A. Actions, decision points, and process drivers


B. Activities, decision points, and the order of processing
C. Activities, process drivers, and the order of processing
D. Actions, decision points, and activities

Answer: B

Question No : 9 - (Topic 1)

The approval of which of the following indicates formal initiation of the project?

A. Procurement management plan


B. Project management plan
C. Project scope document
D. Project charter

Answer: D

Question No : 10 - (Topic 1)

Which of the following strategies is used to deal with risks that may have a negative impact
on project objectives?

A. Exploit
B. Share
C. Enhance
D. Transfer

100% Valid Questions - Guaranteed Success 5


PMI CA0-001 : Valid Questions
Answer: D

Question No : 11 - (Topic 1)

Draw the precedence diagram for the dependencies and activity times below to answer the
question. Use AON or another technique to derive the answer using F-S relationships.

What is the critical path duration for the given schedule network?

A. 22
B. 23
C. 24
D. 25

Answer: D

Question No : 12 - (Topic 1)

Which process includes facilitated workshops as a tool and technique?

A. Collect Requirements
B. Plan Communications
C. Develop Project Team
D. Report Performance

Answer: A

Question No : 13 - (Topic 1)

Which of the following is a strategy to deal with positive risks or opportunities?

A. Mitigate
B. Transfer
C. Exploit
D. Avoid

100% Valid Questions - Guaranteed Success 6


PMI CA0-001 : Valid Questions
Answer: C

Question No : 14 - (Topic 1)

Which of the following is contained within the communications management plan?

A. An organizational chart
B. Glossary of common terminology
C. Organizational process assets
D. Enterprise environmental factors

Answer: B

Question No : 15 - (Topic 1)

Which contract type is typically used whenever the seller's performance period spans a
considerable period of years?

A. Fixed-Price-Incentive-Fee contracts (FPIF)


B. Fixed Price with Economic Price Adjustment contracts (FP-EPA)
C. Cost-Plus-Fixed-Fee contracts (CPFF)
D. Time and Material contracts (T&M)

Answer: B

Question No : 16 - (Topic 1)

What is one of the objectives of project risk management?

A. Decrease the probability and impact of event on project objectives.


B. Distinguish between a project risk and a project issue so that a risk mitigation plan can
be put in place.
C. Increase the probability and impact of positive events.
D. Removal of project risk.

Answer: C

100% Valid Questions - Guaranteed Success 7


PMI CA0-001 : Valid Questions
Question No : 17 - (Topic 1)

The PV is $1000, EV is $2000 and AC is $1500. What is CPI?

A. 1.33
B. 2.00
C. 0.75
D. 0.5

Answer: A

Question No : 18 - (Topic 1)

In what type of contract is the seller reimbursed for all allowable costs for performing the
contract work and receives a predetermined fee based upon achieving certain performance
objectives as set forth in the contract?

A. Cost-plus-fixed-fee
B. Cost-plus-incentive-fee
C. Firm-fixed-price
D. Fixed-price-incentive-fee

Answer: B

Question No : 19 - (Topic 1)

An Ishikawa or fishbone diagram is used for which of the following?

A. Identifying causes of risks


B. Identifying frequency of occurrence of risks
C. Developing a resource plan
D. Developing schedule

Answer: A

Question No : 20 - (Topic 1)

100% Valid Questions - Guaranteed Success 8


PMI CA0-001 : Valid Questions
The Define Scope process is in which of the following process groups?

A. Initiating
B. Planning
C. Monitoring & Controlling
D. Executing

Answer: B

Question No : 21 - (Topic 1)

What is the name of a graphic display of project team members and their reporting
relationships?

A. Role dependencies chart


B. Reporting flow diagram
C. Project organization chart
D. Project team structure diagram

Answer: C

Question No : 22 - (Topic 1)

When does risk monitoring and control occur?

A. At project initiation
B. During work performance analysis
C. Throughout the life of the project
D. At project milestones

Answer: C

Question No : 23 - (Topic 1)

What is a hierarchically organized depiction of the identified project risks arranged by risk
category?

100% Valid Questions - Guaranteed Success 9


PMI CA0-001 : Valid Questions
A. Risk register
B. Risk breakdown structure (RBS)
C. Risk management plan
D. Risk category

Answer: B

Question No : 24 - (Topic 1)

Who authorizes a project?

A. Sponsor
B. Project manager
C. Project team
D. Buyer

Answer: A

Question No : 25 - (Topic 1)

What defines the portion of work included in a contract for items being purchased or
acquired?

A. Procurement management plan


B. Evaluation criteria
C. Work Breakdown Structure (WBS)
D. Contract Statement of Work (SOW)

Answer: D

Question No : 26 - (Topic 1)

The project manager calculated a schedule performance index of 0.8 and a cost
performance index of 1.1 for the project. What is the actual status of this project?

A. Behind schedule and over budget


B. Behind schedule and under budget

100% Valid Questions - Guaranteed Success 10


PMI CA0-001 : Valid Questions
C. Ahead of schedule and under budget
D. Ahead of schedule and over budget

Answer: B

Question No : 27 - (Topic 1)

What is the number of stakeholders, if the project has 28 potential communication


channels?

A. 7
B. 8
C. 14
D. 16

Answer: B

Question No : 28 - (Topic 1)

What tool and technique includes all costs incurred over the life of a product by investment
in preventing nonconformance to requirements?

A. Cost of quality
B. Measure of design
C. Statistical control
D. Systematic analysis

Answer: A

Question No : 29 - (Topic 1)

Stakeholder analysis identifies what information and relates it to the purpose of the project?

A. Requirements, influence, and functional department


B. Interest, requirements, and functional role
C. Requirements, expectations, and influence
D. Interest, expectations, and influence

100% Valid Questions - Guaranteed Success 11


PMI CA0-001 : Valid Questions
Answer: D

Question No : 30 - (Topic 1)

What are the identified risks for doing excessive decomposition in a WBS?

A. Insufficient project funding and disqualification of sellers


B. Insufficient project funding and ineffective use of resources
C. Disqualification of sellers and non-productive management efforts
D. Non-productive management effort and inefficient use of resources

Answer: D

Question No : 31 - (Topic 1)

Which stakeholder is responsible for managing related projects in a coordinated way?

A. Sponsor
B. Portfolio manager
C. Program manager
D. Project manager

Answer: C

Question No : 32 - (Topic 1)

Which of the following documents allows the project manager to assess risks that may
require near term action?

A. Probability and impact matrix


B. Contingency analysis report
C. Risk urgency assessment
D. Rolling wave plan

Answer: C

100% Valid Questions - Guaranteed Success 12


PMI CA0-001 : Valid Questions

Question No : 33 - (Topic 1)

Which of the following can be used to track the requirements throughout the project life
cycle?

A. Requirements traceability matrix


B. Scope management plan
C. Project charter
D. Work breakdown structure

Answer: A

Question No : 34 - (Topic 1)

Reviewing, tracking, and regulating the process to meet performance objectives defined in
the project management plan are part of which process?

A. Monitor and Control Project Work


B. Direct and Manage Project Execution
C. Monitor and Control Risk
D. Perform Integrated Change Control

Answer: A

Question No : 35 - (Topic 1)

Which of the following is an example of a technique used in quantitative risk analysis?

A. Sensitivity analysis
B. Probability and impact matrix
C. Risk data quality assessment
D. Risk categorization

Answer: A

Question No : 36 - (Topic 1)
100% Valid Questions - Guaranteed Success 13
PMI CA0-001 : Valid Questions
Which of the following is involved in the initiation process group?

A. Develop Project Management Plan


B. Identify Stakeholders
C. Plan Communications
D. Collect Requirements

Answer: B

Question No : 37 - (Topic 1)

What is Project Portfolio Management?

A. Management of a project by dividing the project into more manageable sub-projects.


B. Management of a project by utilizing a portfolio of general management skills, such as
planning, organizing, staffing, executing and controlling.
C. Management of all projects undertaken by a company.
D. Management of a collection of projects that are grouped together to facilitate effective
management and meet strategic business objectives.

Answer: D

Question No : 38 - (Topic 1)

Which of the following events would result in a baseline update?

A. Your project is behind schedule and you want your baseline to reflect estimated actual
completion.
B. Your customer has approved a change request broadening the project scope and
increasing the budget.
C. One of the risks identified in the Risk Management Plan occurs resulting in a schedule
delay.
D. One of your key project team resources has left your team and no replacement is
available.

Answer: B

Question No : 39 - (Topic 1)
100% Valid Questions - Guaranteed Success 14
PMI CA0-001 : Valid Questions
Which of the following lists contain processes that are included within Project Procurement
Management?

A. Plan purchases and acquisitions, plan contracting, request seller responses, select
sellers
B. Plan purchases and acquisitions, request seller responses, select sellers, schedule
control
C. Plan purchases and acquisitions, acquire project team, request seller responses, select
sellers
D. Plan purchases and acquisitions, acquire project team, contract approval, select sellers

Answer: A

Question No : 40 - (Topic 1)

Which is the total float for the activity G?

A. 0
B. 3
C. 5
D. 10

Answer: C

Question No : 41 - (Topic 1)

Which is a true statement regarding project governance?

A. Project governance approach must be described in the project management plan.


B. Project governance is independent of the organization or program sponsoring it.
C. Once a project has begun, it is not necessary to formally initiate each project phase.
D. Review of project performance and key deliverables is not required for each project
phase.

Answer: A

Question No : 42 - (Topic 1)

100% Valid Questions - Guaranteed Success 15


PMI CA0-001 : Valid Questions
What document should be reviewed by a project manager before finalizing the project
closure?

A. Customer acceptance
B. Statement of work
C. Product report
D. User manual

Answer: A

Question No : 43 - (Topic 1)

Many organizations categorize requirements into which of the following two categories?

A. Project and Product


B. Staffing and Budget
C. Stakeholder and Customer
D. Business and Technical

Answer: A

Question No : 44 - (Topic 1)

Which of the following is an input to direct and manage project execution?

A. Requested changes
B. Approved preventive action
C. Work performance information
D. Implemented defect repair

Answer: B

Question No : 45 - (Topic 1)

Company A bought a well-defined project deliverable from Company B. Company A will


pay a fixed total price plus a percentage premium for the schedule target achieved.

100% Valid Questions - Guaranteed Success 16


PMI CA0-001 : Valid Questions
For which type of contract have they subscribed?

A. Fixed-price-incentive-fee contracts (FPIF)


B. Firm-fixed-price-contracts (FFP)
C. Fixed price with Economic Price Adjustment Contracts (FP-EPA)
D. Time and material contracts (T&M)

Answer: A

Question No : 46 - (Topic 1)

Which of the following provides a standardized, effective, and efficient way to centrally
manage approved changes and baselines within a project?

A. Project management information system


B. Configuration management system
C. Change control board
D. Project management plan

Answer: B

Question No : 47 - (Topic 1)

Which schedule development technique modifies the project schedule to account for limited
resources?

A. Human resource planning


B. Fast tracking
C. Critical chain method
D. Rolling wave planning

Answer: C

Question No : 48 - (Topic 1)

What is the lowest level in the WBS at which the cost and activity durations for the work
can be reliably estimated and managed?

100% Valid Questions - Guaranteed Success 17


PMI CA0-001 : Valid Questions
A. Work product
B. Work package
C. Project deliverable
D. Scope baseline

Answer: B

Question No : 49 - (Topic 1)

While implementing an approved change, a critical defect was introduced. Removing the
defect will delay the product delivery. What is the MOST appropriate approach to managing
this situation?

A. Utilize the change control process.


B. Crash the schedule to fix the defect.
C. Leave the defect in and work around it.
D. Fast-track the remaining development.

Answer: A

Question No : 50 - (Topic 1)

Which project management process ensures the seller's performance meets procurement
requirements and that the buyer performs according to the terms of the legal contract?

A. Plan Procurements
B. Perform Quality Assurance
C. Administer Procurements
D. Conduct Procurements

Answer: C

Question No : 51 - (Topic 1)

Define Activities and Estimate Activity Resources are processes in which project
management knowledge area?

100% Valid Questions - Guaranteed Success 18


PMI CA0-001 : Valid Questions
A. Time management
B. Cost management
C. Scope management
D. Human resources management

Answer: A

Question No : 52 - (Topic 1)

What type of project structure is a hierarchically organized depiction of the resources by


type?

A. Organizational Breakdown Structure (OBS)


B. Resource Breakdown Structure (RBS)
C. Work Breakdown Structure (WBS)
D. Project Breakdown Structure (PBS)

Answer: B

Question No : 53 - (Topic 1)

When can pre-assignment of project team members occur?

A. When the project uses capital expenditures.


B. When the required staff can be acquired from outside sources.
C. When the project would be ignored due to travel expenses.
D. When the project is the result of specific people being promised as part of a competitive
proposal.

Answer: D

Question No : 54 - (Topic 1)

The scope management plan is a subsidiary of which project document?

A. Schedule management plan


B. Project management plan

100% Valid Questions - Guaranteed Success 19


PMI CA0-001 : Valid Questions
C. Quality management plan
D. Resource management plan

Answer: B

Question No : 55 - (Topic 1)

When communicating with large audiences, which communication method works most
effectively?

A. Push
B. Interactive
C. Parallel
D. Pull

Answer: D

Question No : 56 - (Topic 1)

Which of the following involves making information available to project stakeholders in a


timely manner?

A. Contract management
B. Performance reporting
C. Project status reports
D. Information distribution

Answer: D
Explanation: The project management term or phrase that is used for the purposes of
representing the project management process that focuses on taking the facts and
happenings in regards to a particular project and disseminating this information to all of the
relevant parties, with a particular focus on providing information to those who have a
financial stake in the ultimate outcomes of the project. These methods of information
dissemination can come in means including regularly scheduled conferences and or
meetings, regularly scheduled conference calls in which some or all members of the project
team participate, informal written communications such as periodic updates via email and
of other short form, less formal means of communications, as well as formal reports that
may or may not have been requisite to the completion of the project. Information
distribution is essential to assuring that the financial stakeholders are fully aware of the

100% Valid Questions - Guaranteed Success 20


PMI CA0-001 : Valid Questions
progress throughout as it helps to assure no surprises arise at the time that deliverables
are expected to be final.
This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Question No : 57 - (Topic 1)

Which of the following consists of the detailed project scope statement and its associated
WBS and WBS dictionary?

A. Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline

Answer: D

Question No : 58 - (Topic 1)

Which of the following equations is used to calculate schedule variance?

A. EV/PV
B. PV/EV
C. EV-PV
D. PV-EV

Answer: C

Question No : 59 - (Topic 1)

Reserve analysis is a tool and technique used in which of the following processes?

A. Monitor and Control Risks


B. Qualitative Risk Analysis
C. Quantitative Risk Analysis

100% Valid Questions - Guaranteed Success 21


PMI CA0-001 : Valid Questions
D. Plan Risk Responses

Answer: A

Question No : 60 - (Topic 1)

Which of the following is the definition of a project?

A. Temporary endeavor undertaken to create a temporary business process or product


B. Temporary endeavor undertaken to create a unique product, service, or result
C. Permanent endeavor that produces repetitive outputs
D. Temporary endeavor that produces repetitive outputs

Answer: B

Question No : 61 - (Topic 1)

Given the following values, what is the calculated expected activity cost (CE) when using
PERT?

CO = $7,000

CM = $10,500

CP = $11,000

A. $ 4,750
B. $ 9,500
C. $10,000
D. $11,500

Answer: C

Question No : 62 - (Topic 1)

Which of the following must be taken into account for every process, even if they are not
explicitly listed as inputs in the process specifications?

100% Valid Questions - Guaranteed Success 22


PMI CA0-001 : Valid Questions
A. Organizational processes and procedures and enterprise environmental factors
B. Organizational processes and procedures and corporate knowledge base
C. Organizational process assets and enterprise environmental factors
D. Corporate knowledge base and enterprise environmental factors

Answer: C

Question No : 63 - (Topic 1)

Cost baseline is an output of which of the following processes?

A. Cost Control
B. Cost Budgeting
C. Cost Estimating
D. Cost Planning

Answer: B

Question No : 64 - (Topic 1)

The initial development of a Project Scope Management plan uses which technique?

A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis

Answer: C

Question No : 65 - (Topic 1)

Which of the following processes includes prioritizing risks for subsequent further analysis
or action by assessing and combining their probability of occurrence and impact?

A. Qualitative risk analysis


B. Quantitative risk analysis
C. Risk management planning

100% Valid Questions - Guaranteed Success 23


PMI CA0-001 : Valid Questions
D. Risk response planning

Answer: A

Question No : 66 - (Topic 1)

Which one of the following is true regarding the change control board?

A. Describes how changes are managed.


B. Approves or rejects change requests.
C. Needs updated project management plans to approve or reject a change.
D. Describes how changes are documented.

Answer: B

Question No : 67 - (Topic 1)

Which of the following is an example of the simplest fixed-price contract?

A. Purchase requisition
B. Purchase order
C. Verbal agreement
D. Request for quote

Answer: B

Question No : 68 - (Topic 1)

What is the definition of project plan execution?

A. Integrating all planned activities.


B. Performing the activities included in the plan.
C. Developing and maintaining the plan.
D. Execution of deliverables.

Answer: B

100% Valid Questions - Guaranteed Success 24


PMI CA0-001 : Valid Questions
Question No : 69 - (Topic 1)

Which of the following is an input to the Direct and Manage Project Execution Process?

A. Approved corrective actions


B. Approved contract documentation
C. Work performance information
D. Rejected change requests

Answer: A

Question No : 70 - (Topic 1)

Project contracts generally fall into which of the following three broad categories?

A. Fixed-price, cost reimbursable, time and materials


B. Make-or-buy, margin analysis, fixed-price
C. Time and materials, fixed-price, margin analysis
D. Make-or-buy, lump-sum, cost-plus-incentive

Answer: A

Question No : 71 - (Topic 1)

What is the term assigned to products or services having the same functional use but
different technical characteristics?

A. Scope
B. Quality
C. Specification
D. Grade

Answer: D

Question No : 72 - (Topic 1)

Which document is a narrative description of products or services to be delivered by the

100% Valid Questions - Guaranteed Success 25


PMI CA0-001 : Valid Questions
project?

A. Project charter
B. Contract
C. Business case
D. Project statement of work

Answer: D

Question No : 73 - (Topic 1)

What causes replanning of the project scope?

A. Requested changes
B. Project scope statement changes
C. Variance analysis
D. Approved change requests

Answer: D

Question No : 74 - (Topic 1)

Which analysis helps to determine the risks that have the most potential for impacting the
project?

A. Expected monetary value analysis


B. Sensitivity analysis
C. Modeling and simulation
D. Expert judgment

Answer: B

Question No : 75 - (Topic 1)

In the three-point estimating technique, if the most likely estimate for an activity to complete
is 100 days, the optimistic estimate is 60 days, and the pessimistic estimate is 200 days,
what is the expected duration in which the activity will be completed?

100% Valid Questions - Guaranteed Success 26


PMI CA0-001 : Valid Questions
A. 90 days
B. 100 days
C. 110 days
D. 660 days

Answer: C

Question No : 76 - (Topic 1)

Which of the following tools or techniques is used for Estimate Activity Duration?

A. Critical path
B. Rolling Wave
C. PDM
D. Parametric

Answer: D

Question No : 77 - (Topic 1)

A purchase order for a specified item to be delivered by a specified date for a specified
price is the simplest form of what type of contract?

A. Cost-reimbursable
B. Time and material
C. Fixed price or lump-sum
D. Cost-plus-fixed-fee

Answer: C

Question No : 78 - (Topic 1)

Which of the following is a project constraint?

A. Twenty-five percent staff turnover is expected.


B. The technology to be used is cutting-edge.
C. Project leadership may change due to volatile political environment.

100% Valid Questions - Guaranteed Success 27


PMI CA0-001 : Valid Questions
D. The product is needed in 250 days.

Answer: D

Question No : 79 - (Topic 1)

A project manager convenes a meeting to determine why the time to produce one product
according to specifications has increased from one day to three days over the past month.
Which tool or technique is used in this case?

A. Expert judgment
B. Quality assurance
C. Quality control
D. Variance analysis

Answer: D

Question No : 80 - (Topic 1)

What name(s) is (are) associated with the Plan-Do-Check-Act cycle?

A. Pareto
B. Ishikawa
C. Shewart-Deming
D. Delphi

Answer: C

Question No : 81 - (Topic 1)

What cost control technique is used to compare actual project performance to planned or
expected performance?

A. Cost aggregation
B. Trend analysis
C. Forecasting
D. Variance analysis

100% Valid Questions - Guaranteed Success 28


PMI CA0-001 : Valid Questions
Answer: D

Question No : 82 - (Topic 1)

Which of the following is a tool and technique for activity duration estimating?

A. Parametric estimating
B. Monte Carlo analysis
C. Top-down estimating
D. Bottom-up estimating

Answer: C

Question No : 83 - (Topic 1)

If the earned value (EV) is $1000, actual cost (AC) is $800, and planned value (PV) is
$1500, what would be the cost performance index (CPI)?

A. 0.66
B. 0.8
C. 1.25
D. 1.5

Answer: C

Question No : 84 - (Topic 1)

Who decides buyer and seller roles in a teaming agreement?

A. Executive management
B. Project members
C. Project manager
D. Contract administrator

Answer: A

100% Valid Questions - Guaranteed Success 29


PMI CA0-001 : Valid Questions

Question No : 85 - (Topic 1)

Which process occurs within the Monitoring and Controlling Process Group?

A. Cost Control
B. Quality Planning
C. Quantitative Risk Analysis
D. Cost Budgeting

Answer: A

Question No : 86 - (Topic 1)

Which of the following is a strategy for positive risks?

A. Avoid
B. Transfer
C. Accept
D. Mitigate

Answer: C

Question No : 87 - (Topic 1)

Project scope statement and resource calendars are inputs to what Project Time
Management process?

A. Activity Sequencing
B. Activity Resource Estimating
C. Schedule Development
D. Schedule Control

Answer: C

Question No : 88 - (Topic 1)

100% Valid Questions - Guaranteed Success 30


PMI CA0-001 : Valid Questions
Which of the following is an input to Develop Human Resource Plan?

A. Team performance assessment


B. Roles and responsibilities
C. Staffing management plan
D. Enterprise environmental factors

Answer: D

Question No : 89 - (Topic 1)

ABC project is at risk for failing to achieve a major project objective due to unresolved
stakeholder issues. Team member morale is low.

Who is primarily responsible for the project being at risk?

A. Team members who have low morale


B. Sponsor who is not actively supporting the project
C. Project manager who is responsible for managing stakeholder expectations
D. Stakeholders who have unrealistic expectations

Answer: C

Question No : 90 - (Topic 1)

What do composite organizations involve?

A. Functional and project managers


B. Functional managers only
C. Project managers only
D. Technical managers and project managers

Answer: A

Question No : 91 - (Topic 1)

What is an objective of the Developing Project Team Process?

100% Valid Questions - Guaranteed Success 31


PMI CA0-001 : Valid Questions
A. Feelings of trust and improved cohesiveness
B. Ground rules for interaction
C. Enhanced resource availability
D. Functional managers become more involved.

Answer: A

Question No : 92 - (Topic 1)

What quality control tool graphically represents how various elements of a system
interrelate?

A. Control chart
B. Flowchart
C. Run chart
D. Pareto chart

Answer: B

Question No : 93 - (Topic 1)

Which type of analysis is used as a general management technique within the Plan
Procurements Process?

A. Risk assessment analysis


B. Make or buy analysis
C. Contract value analysis
D. Cost impact analysis

Answer: B

Question No : 94 - (Topic 1)

Draw the precedence diagram for the dependencies and activity times below to answer the
question. Use AON or another technique to derive the answer using F-S relationships.

100% Valid Questions - Guaranteed Success 32


PMI CA0-001 : Valid Questions

What is the total float on path BEG?

A. 0
B. 1
C. 2
D. 3

Answer: C

Question No : 95 - (Topic 1)

To which process is work performance information an input?

A. Contract administration
B. Direction and management of project execution
C. Create WBS
D. Qualitative risk analysis

Answer: A

Question No : 96 - (Topic 1)

The use of group creativity techniques as a tool and technique is done in which of the
following processes?

A. Plan Quality

100% Valid Questions - Guaranteed Success 33


PMI CA0-001 : Valid Questions
B. Collect Requirements
C. Define Scope
D. Perform Quality Control

Answer: B

Question No : 97 - (Topic 1)

Which knowledge area is concerned with the processes required to ensure timely and
appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of
project information?

A. Project Integration Management


B. Project Communications Management
C. Project Information Management System (PIMS)
D. Project Scope Management

Answer: B

Question No : 98 - (Topic 1)

Monitor and control project work is a process of which of the following knowledge areas?

A. Project risk management


B. Project scope management
C. Project time management
D. Project integration management

Answer: D

Question No : 99 - (Topic 1)

Which document contains initial requirements that satisfy stakeholders' needs and
expectations?

A. Project charter
B. Project management plan

100% Valid Questions - Guaranteed Success 34


PMI CA0-001 : Valid Questions
C. Project statement of work
D. Project scope statement

Answer: A

Question No : 100 - (Topic 1)

Which is an input to the Scope Verification Process?

A. Performance report
B. Work breakdown structure
C. Requested changes
D. Project scope statement

Answer: D

Question No : 101 - (Topic 1)

On what is project baseline development established?

A. Approved product requirements


B. Estimated project cost and schedule
C. Actual project cost and schedule
D. Revised project cost and schedule

Answer: B

Question No : 102 - (Topic 1)

Which process group defines the course of action required to attain the objectives that the
project was undertaken to achieve?

A. Initiating
B. Executing
C. Planning
D. Monitoring and Controlling

100% Valid Questions - Guaranteed Success 35


PMI CA0-001 : Valid Questions
Answer: C

Question No : 103 - (Topic 1)

Which of the following inputs is required for the WBS creation?

A. Project Quality Plan


B. Project Schedule Network
C. Project Management Software
D. Project Scope Management Plan

Answer: D

Question No : 104 - (Topic 1)

Information distribution involves making needed information available to project


stakeholders in a timely manner. What is an output from information distribution?

A. Earned value analysis


B. Trend analysis
C. Project records
D. Performance reviews

Answer: C

Question No : 105 - (Topic 1)

Which of the following processes is necessary to ensure that the project employs all
processes needed to meet its requirements?

A. Perform Quality Control


B. Quality Policy
C. Perform Quality Assurance
D. Quality Planning

Answer: C

100% Valid Questions - Guaranteed Success 36


PMI CA0-001 : Valid Questions
Question No : 106 - (Topic 1)

The decision to approve or reject a particular change request is made in which of the
following processes?

A. Perform Integrated Change Control


B. Monitor and Control Project Work
C. Develop Project Management Plan
D. Direct and Manage Project Execution

Answer: A

Question No : 107 - (Topic 1)

Analogous Cost Estimating relies on which of the following techniques?

A. Expert Judgment
B. Project Management Software
C. Vendor Bid Analysis
D. Reserve Analysis

Answer: A

Question No : 108 - (Topic 1)

What is the expected activity cost for a project having a most likely cost of $140, a best
case scenario of $115, and a worst case scenario of $165?

A. $115
B. $138
C. $140
D. $165

Answer: C

Question No : 109 - (Topic 1)

100% Valid Questions - Guaranteed Success 37


PMI CA0-001 : Valid Questions
What happens to a stakeholder's project influence over time?

A. Increases
B. Decreases
C. Stays the same.
D. Has no bearing.

Answer: B

Question No : 110 - (Topic 1)

Expected Monetary Value (EMV) analysis is commonly used in:

A. probability distribution.
B. decision tree diagram.
C. sensitivity analysis.
D. modeling and simulation.

Answer: B

Question No : 111 - (Topic 1)

What information does the stakeholder register contain?

A. Communication model
B. Identification information
C. Communication method
D. Identification plan

Answer: B

Question No : 112 - (Topic 1)

As part of a mid-project evaluation, your project sponsor has asked you to provide a
forecast of total project cost. You should calculate the forecast using which of the following
methods?

100% Valid Questions - Guaranteed Success 38


PMI CA0-001 : Valid Questions
A. BAC
B. EAC
C. ETC
D. WBS

Answer: B

Question No : 113 - (Topic 1)

What are the components of the "triple constraint"?

A. Scope, time, requirements


B. Resources, time, cost
C. Scope, management, cost
D. Scope, time, cost

Answer: D
Explanation: The Project Management Triangle (called also Triple Constraint) is a model
of the constraints of project management. It is often used to illustrate that project
management success is measured by the project team's ability to manage the project, so
that the expected results are produced while managing time and cost.
Like any human undertaking, projects need to be performed and delivered under certain
constraints. Traditionally, these constraints have been listed as "scope," "time," and "cost".
These are also referred to as the "Project Management Triangle," (also known as the "Iron
Triangle") where each side represents a constraint. One side of the triangle cannot be
changed without affecting the others. A further refinement of the constraints separates
product "quality" or "performance" from scope, and turns quality into a fourth constraint.

Question No : 114 - (Topic 1)

How is the process of collecting requirements defined?

A. Defining and documenting project sponsors' needs to meet the project objectives
B. Defining and documenting stakeholders' needs to meet the project objectives
C. Defining and documenting the project teams' needs to meet the project objectives
D. Defining and documenting the project needs to meet the project objectives

100% Valid Questions - Guaranteed Success 39


PMI CA0-001 : Valid Questions
Answer: B

Question No : 115 - (Topic 1)

What are the formal and informal policies, procedures, and guidelines that could impact
how the project's scope is managed?

A. Organizational process assets


B. Enterprise environmental factors
C. Project management processes
D. Project scope management plan

Answer: A

Question No : 116 - (Topic 1)

Which of the following is an output of the Information Distribution Process?

A. Project calendar
B. Communication management plan
C. Requested changes
D. Communication requirement plan

Answer: C

Question No : 117 - (Topic 1)

Which is the document that presents a hierarchical project organization?

A. WBS
B. CPI
C. OBS
D. BOM

Answer: C

100% Valid Questions - Guaranteed Success 40


PMI CA0-001 : Valid Questions

Question No : 118 - (Topic 1)

What tool or technique of Estimate Activity Durations uses parameters such as duration,
budget, size, weight, and complexity from a previous, similar project as the basis for
estimating the same parameter or measure for a future project?

A. Bottom-up estimating
B. Analogous estimating
C. Parametric estimating
D. Three-point estimates

Answer: B

Question No : 119 - (Topic 1)

Who selects the appropriate processes for a project?

A. Project stakeholders
B. Project sponsor and project stakeholder
C. Project manager and project team
D. Project manager and project sponsor

Answer: C

Question No : 120 - (Topic 1)

The Monitoring and Controlling process group contains which of the following processes?

A. Plan Quality
B. Perform Quality Assurance
C. Perform Quality Control
D. Identify Stakeholders

Answer: C

Question No : 121 - (Topic 1)


100% Valid Questions - Guaranteed Success 41
PMI CA0-001 : Valid Questions
EAC (estimate at complete) is typically based on actual cost (AC) for work completed plus
an ETC (estimate to complete) the remaining work. Which of the following is a valid formula
for calculating EAC?

A. EAC = AC + [(BAC-EV) / (Cumulative CPI * Cumulative SPI)]


B. EAC = BAC - AC
C. EAC = 1 - CPI
D. EAC = EV + [1 - (Cumulative CPI * Cumulative SPI) / BAC]

Answer: A

Question No : 122 - (Topic 1)

Which schedule compression technique has phases or activities done in parallel that would
normally have been done sequentially?

A. Crashing
B. Fast tracking
C. Leads and lags adjustment
D. Parallel task development

Answer: B

Question No : 123 - (Topic 1)

Which of the following is a tool or technique for distribute information?

A. Project management plan


B. Report performance
C. Communications requirements analysis
D. Communication methods

Answer: D

Question No : 124 - (Topic 1)

The project management information system is used as tools and techniques in which of

100% Valid Questions - Guaranteed Success 42


PMI CA0-001 : Valid Questions
the following processes?

A. Develop Project Charter


B. Develop Project Management Plan
C. Direct and Manage Project Execution
D. Monitor and Control Project Work

Answer: C

Question No : 125 - (Topic 1)

Which is the duration of the project?

A. 63
B. 65
C. 66
D. 70

100% Valid Questions - Guaranteed Success 43


PMI CA0-001 : Valid Questions
Answer: D

Question No : 126 - (Topic 1)

The risk register contains which of the following?

A. Identified risks and potential responses


B. Identified risks and updates to scope baseline
C. Risk management plan
D. Risk related contract decisions

Answer: A
Explanation: A Risk Register is a Risk Management tool commonly used in Project
Management and organizational risk assessments. It acts as a central repository for all
risks identified by the project or organization and, for each risk, includes information such
as risk probability, impact, counter-measures, risk owner and so on. It can sometimes be
referred to as a Risk Log

Question No : 127 - (Topic 1)

When would resource leveling be applied to a schedule model?

A. Before constraints have been identified


B. Before it has been analyzed by the critical path method
C. After it has been analyzed by the critical path method
D. After critical activities have been removed from the critical path

Answer: C

Question No : 128 - (Topic 1)

In the precedence diagramming method, which of the following is a logical relationship for
the activities?

100% Valid Questions - Guaranteed Success 44


PMI CA0-001 : Valid Questions
A. Finish-to-start
B. Applying leads and lags
C. Activity-on-node
D. Dependency determination

Answer: A

Question No : 129 - (Topic 1)

Providing forecasts to update current cost and schedule information is a part of which
process?

A. Perform Integrated Change Control


B. Direct and Manage Project Execution
C. Monitor and Control Risks
D. Monitor and Control Project Work

Answer: D

Question No : 130 - (Topic 1)

Which Activity Duration Estimating technique incorporates additional timing for contingency
purposes?

A. Analogous Estimating
B. Expert Judgment
C. Optimistic Estimates
D. Reserve Analysis

Answer: D

Question No : 131 - (Topic 1)

What tool and technique is used to determine whether work and deliverables meet
requirements and product acceptance criteria?

A. Decomposition

100% Valid Questions - Guaranteed Success 45


PMI CA0-001 : Valid Questions
B. Benchmarking
C. Inspection
D. Checklist analysis

Answer: C

Question No : 132 - (Topic 1)

A project manager is responsible for managing which of the following at the project level?

A. Methodology
B. Standards
C. Constraints
D. Interdependencies

Answer: C

Question No : 133 - (Topic 1)

The Project Integration Management knowledge area includes which of the following set of
processes?

A. Develop Project Charter, Direct and Manage Project Execution, Perform Integrated
Change Control
B. Define Project Scope, Create WBS, Close Project or Phase
C. Develop Project Charter, Develop Human Resource Plan, Estimate Costs
D. Identify Stakeholders, Plan Communications, Develop Project Management Plan

Answer: A

Question No : 134 - (Topic 1)

Fast tracking is a schedule compression technique used to shorten the project schedule
without changing project scope. Which of the following can result from fast tracking?

A. The risk of achieving the shortened project time is increased.


B. The critical path will have positive total float.

100% Valid Questions - Guaranteed Success 46


PMI CA0-001 : Valid Questions
C. Contingency reserves are released for redeployment by the project manager.
D. Duration buffers are added to maintain a focus on planned activity durations.

Answer: A

Question No : 135 - (Topic 1)

Using the following data, what is the Schedule Performance Index (SPI)?

EV = $500

PV= $750

AC= $1000

BAC= $1200

A. 0.67
B. 1.50
C. 0.75
D. 0.50

Answer: A

Question No : 136 - (Topic 1)

Where are product requirements and characteristics documented?

A. Product scope description


B. Project charter
C. Preliminary project scope statement
D. Communications management plan

Answer: A

Question No : 137 - (Topic 1)

Who MUST know when a risk event occurs so that a response can be implemented?

100% Valid Questions - Guaranteed Success 47


PMI CA0-001 : Valid Questions
A. Customers
B. Project sponsors
C. Project management team
D. Insurance claims department

Answer: C

Question No : 138 - (Topic 1)

Which schedule format usually shows both the project network logic and the project's
critical path schedule activities with activity date information?

A. Schedule table
B. Schedule network diagram
C. Bar chart
D. Milestone chart

Answer: B

Question No : 139 - (Topic 1)

Which type of control tool identifies whether or not a process has a predictable
performance?

A. Cause and effect diagram


B. Control Charts
C. Pareto Chart
D. Histogram

Answer: B

Question No : 140 - (Topic 1)

What characteristic do project and operational work share in common?

A. Performed by systems
B. Constrained by limited resources

100% Valid Questions - Guaranteed Success 48


PMI CA0-001 : Valid Questions
C. Repetitiveness
D. Uniqueness

Answer: B

Question No : 141 - (Topic 1)

Control Charts, Flowcharting, Histograms, Pareto Charts, Scatter Diagrams are tools and
techniques of what process?

A. Perform Quality Control


B. Perform Quality Assurance
C. Quality Planning
D. Performance Reporting

Answer: A

Question No : 142 - (Topic 1)

Inspection is a tool and technique for which of the following processes?

A. Create WBS
B. Define Scope
C. Control Scope
D. Verify Scope

Answer: D

Question No : 143 - (Topic 1)

Which of the following schedule network analysis techniques is applied when a critical path
method calculation has been completed and resources availability is critical?

A. Applying calendars
B. Resource Leveling
C. Resource Planning
D. Resource Conflict Management

100% Valid Questions - Guaranteed Success 49


PMI CA0-001 : Valid Questions
Answer: B

Question No : 144 - (Topic 1)

Which quality assurance tool and technique confirms the implementation of approved
change requests, corrective actions, defect repairs, and preventive actions?

A. Quality checklists
B. Quality metrics
C. Quality audits
D. Process analysis

Answer: C

Question No : 145 - (Topic 1)

What are assigned risk ratings based upon?

A. Root cause analysis


B. Assessed probability and impact
C. Expert judgment
D. Risk Identification

Answer: B

Question No : 146 - (Topic 1)

During which process would you obtain stakeholders' formal acceptance of the completed
project scope?

A. Quality control
B. Scope verification
C. Scope control
D. Close project

Answer: B

100% Valid Questions - Guaranteed Success 50


PMI CA0-001 : Valid Questions
Question No : 147 - (Topic 1)

Which of the following is an output of Define Scope?

A. Project document updates


B. Project management plan
C. Scope baseline
D. Product analysis

Answer: A

Question No : 148 - (Topic 1)

Which technique is utilized in the Schedule Control process?

A. Performance Measure
B. Baseline Schedule
C. Schedule Comparison
D. Variance Analysis

Answer: D

Question No : 149 - (Topic 1)

Which is an input to the Collect Requirements process?

A. Requirement documentation
B. Organizational process assets
C. Requirements management plan
D. Stakeholder register

Answer: D

Question No : 150 - (Topic 1)

Which activity is an input to the select sellers process?

100% Valid Questions - Guaranteed Success 51


PMI CA0-001 : Valid Questions
A. Organizational process assets
B. Resource availability
C. Change control process
D. Team performance assessment

Answer: A

Question No : 151 - (Topic 1)

The Project Management Body of Knowledge (PMBOK Guide) should be considered as a:

A. guide to project management processes, tools and techniques.


B. methodology for managing projects.
C. guide for project, portfolio and program management.
D. standard for project, portfolio and program management.

Answer: A

Question No : 152 - (Topic 1)

Which of the following is the correct network diagram for the table?

A. Begin - A - C - D - E - End - B - D
B. Begin - A - B - C - D - E - End
C. Begin - A - B - D - E - End A - C - D
D. Begin - A - C - D - E - End - B - C

Answer: A

100% Valid Questions - Guaranteed Success 52


PMI CA0-001 : Valid Questions

Question No : 153 - (Topic 1)

What is one of the MAJOR outputs of activity sequencing?

A. Responsibility assignment matrix


B. Work breakdown structure update
C. Project network diagram
D. Mandatory dependencies list

Answer: C

Question No : 154 - (Topic 1)

An input required to develop a preliminary project scope statement is:

A. Organizational Structure
B. Organizational Process Assets
C. Organizational Matrix
D. Organizational Breakdown Structures

Answer: B

Question No : 155 - (Topic 1)

What process determines which risks might affect the project?

A. Qualitative risk analysis


B. Identify Risks
C. Plan Risk Management
D. Quantitative risk analysis

Answer: B

Question No : 156 - (Topic 1)

100% Valid Questions - Guaranteed Success 53


PMI CA0-001 : Valid Questions
Which of the following equations is used to calculate cost variance?

A. EV-AC
B. AC-EV
C. AC+EV
D. AC/EV

Answer: A

Question No : 157 - (Topic 1)

Which of the following outputs from the Schedule Control process aids in the
communication of SV, SPI or any performance status to stakeholders?

A. Performance organizations
B. Schedule baselines
C. Performance measurements
D. Change requests

Answer: C

Question No : 158 - (Topic 1)

In which of the following team development stages does the team begin to work together,
develop trust, and adjust to the work habits and behavior?

A. Norming
B. Forming
C. Storming
D. Performing

Answer: A

Question No : 159 - (Topic 1)

Within a matrix organization, dual reporting of team members is a risk for project success.
Who is responsible for managing this dual reporting relationship factor?

100% Valid Questions - Guaranteed Success 54


PMI CA0-001 : Valid Questions
A. Functional manager
B. Project manager
C. Functional manager supported by the project manager
D. Project management office

Answer: B

Question No : 160 - (Topic 1)

Which of the following risk response strategies involves allocating ownership of a positive
risk to a third party?

A. Mitigate
B. Transfer
C. Share
D. Avoid

Answer: C

Question No : 161 - (Topic 1)

Based on the following metrics: EV=$20,000, AC=$22,000 and PV=$28,000, what is the
project CV?

A. -$8,000
B. -$2,000
C. $2,000
D. $8,000

Answer: B

Question No : 162 - (Topic 1)

Which technique is commonly used for the Quantitative Risk Analysis activity?

A. Brainstorming
B. Strategies for Opportunities

100% Valid Questions - Guaranteed Success 55


PMI CA0-001 : Valid Questions
C. Decision Tree Analysis
D. Risk Data Quality Assessment

Answer: C

Question No : 163 - (Topic 1)

The project manager decides to conduct a meeting with the team and management after a
new risk has been identified. After the meeting, the decision is to allow the risk to occur.

This is an example of which type of risk response strategy?

A. Mitigate
B. Accept
C. Avoid
D. Transfer

Answer: B

Question No : 164 - (Topic 1)

Projects can be divided into phases to provide better management control. Collectively,
what are these phases known as?

A. Complete project phase


B. Project life
C. The project life cycle
D. Project cycle

Answer: C

Question No : 165 - (Topic 1)

Which enterprise environmental factors are considered during cost estimating?

A. Marketplace conditions and commercial databases


B. Marketplace conditions and company structure

100% Valid Questions - Guaranteed Success 56


PMI CA0-001 : Valid Questions
C. Commercial databases and company structure
D. Existing human resources and market place conditions

Answer: A

Question No : 166 - (Topic 1)

The decomposition technique is used to do which of the following?

A. Subdivide the estimated costs of individual activities


B. Subdivide project deliverables and project work into smaller, more manageable
components
C. Relate the work packages to the performing organizational units
D. Shorten the project schedule duration and the amount of resources needed

Answer: B

Question No : 167 - (Topic 1)

Which of the following will be required to perform simula-tion for schedule risk analysis?

A. Activity list and activity attributes


B. Schedule network diagram and duration estimates
C. Schedule data and activity resource requirements
D. Milestone list and resource breakdown structure

Answer: B

Question No : 168 - (Topic 1)

The project team reviews identified risks and the risk response strategy. For one of the
risks, the team realizes that the implementation of the risk response would generate
another risk.

This new risk is which of the following types of risk?

A. Secondary

100% Valid Questions - Guaranteed Success 57


PMI CA0-001 : Valid Questions
B. Primary
C. Residual
D. Tertiary

Answer: A

Question No : 169 - (Topic 1)

A project manager arranges for project specific training for the new team members. Under
which category does this cost fall?

A. Appraisal
B. Internal failure
C. External failure
D. Prevention

Answer: D

Question No : 170 - (Topic 1)

Which of the following is a tool and technique to the Manage Stakeholder Expectations
process?

A. Issue log
B. Change register
C. Stakeholder register
D. Interpersonal skills

Answer: D

Question No : 171 - (Topic 1)

In which of the following organizational structures does the project manager have full
authority on a project?

A. Functional
B. Strong matrix

100% Valid Questions - Guaranteed Success 58


PMI CA0-001 : Valid Questions
C. Balanced matrix
D. Projectized

Answer: D

Question No : 172 - (Topic 1)

Which of the following is one of the key components of the basic communications model?

A. Push
B. Decode
C. Pull
D. Duration

Answer: B

Question No : 173 - (Topic 1)

Total funding requirements and periodic funding requirements are derived from:

A. funding limit reconciliation


B. scope baseline
C. activity cost estimates.
D. cost baseline.

Answer: D

Question No : 174 - (Topic 1)

Quality and credibility of the qualitative risk analysis process requires that different levels of
the risk's probabilities and impacts be defined is the definition of what?

A. Risk breakdown structure (RBS)


B. Risk probability and impact
C. Qualitative risk analysis
D. Risk response planning

100% Valid Questions - Guaranteed Success 59


PMI CA0-001 : Valid Questions
Answer: B

Question No : 175 - (Topic 1)

Verification of project deliverables occurs during which process?

A. Develop preliminary project scope statement.


B. Close Project or Phase.
C. Develop project charter.
D. Create WBS.

Answer: B

Question No : 176 - (Topic 1)

If the Schedule Variance (SV) =$55, and the Planned Value (PV) =$11, what is the Earned
Value (EV)?

A. $0.2
B. $5
C. $44
D. $66

Answer: D

Question No : 177 - (Topic 1)

Perform quality assurance belongs to which of the following process groups?

A. Planning
B. Executing
C. Monitoring and Control
D. Closing

Answer: B

100% Valid Questions - Guaranteed Success 60


PMI CA0-001 : Valid Questions

Question No : 178 - (Topic 1)

The project management processes presented in the PMBOK Guide should:

A. Always be applied uniformly


B. Be selected as appropriate by the sponsor
C. Be selected as appropriate by the project team
D. Be applied based on ISO guidelines.

Answer: C

Question No : 179 - (Topic 1)

Company A is delivering a product in three parts. The contract allows for the parts to be
delivered either one after the other or at the same time.

Which type of project phasing will allow for the most flexibility in delivering the full product
when product requirements are subject to rapid change?

A. Sequencing the delivery phases one after the other


B. Overlapping the delivery phases
C. Delivering the products iteratively
D. Delivering all of the product at the same time

Answer: C

Question No : 180 - (Topic 1)

Which statement is true about the project management body of knowledge?

A. Recognized by every project manager


B. Constantly evolving
C. The sum of all knowledge related to project management
D. A sum of knowledge that should be applied on every project

Answer: B

100% Valid Questions - Guaranteed Success 61


PMI CA0-001 : Valid Questions

Question No : 181 - (Topic 1)

What type of planning is used where the work to be accomplished in the near term is
planned in detail, while work in the future is planned at a higher level?

A. Finish-to-start planning
B. Rolling wave planning
C. Short term planning
D. Dependency determination

Answer: B

Question No : 182 - (Topic 1)

A weighting system is a tool for which area of procurement?

A. Plan contracting
B. Request seller responses
C. Select sellers
D. Plan purchase and acquisition

Answer: C

Question No : 183 - (Topic 1)

What are three basic types of project phase-to-phase relationships?

A. Sequential, Overlapping, Non-overlapping


B. Sequential, Iterative, Overlapping
C. Sequential, Non-overlapping, Iterative
D. Iterative, Overlapping, Non-overlapping

Answer: B

100% Valid Questions - Guaranteed Success 62


PMI CA0-001 : Valid Questions
Question No : 184 - (Topic 1)

Which of the following is a schedule network analysis technique that takes limited
resources into account?

A. Network reserve analysis


B. Critical chain method
C. Lead and lag adjustment
D. Critical path method

Answer: B

Question No : 185 - (Topic 1)

Identifying major deliverables, deciding if adequate cost estimates can be developed, and
identifying tangible components of each deliverable are all part of which of the following?

A. Work breakdown structure


B. Organizational breakdown structure
C. Resource breakdown structure
D. Bill of materials

Answer: A

Question No : 186 - (Topic 1)

What is a deliverable-oriented hierarchical decomposition of the work to be executed to


accomplish the project objectives and create the required deliverables?

A. Organizational Breakdown Structure (OBS)


B. Work Performance Information
C. Work Package
D. Work Breakdown Structure (WBS)

Answer: D

Question No : 187 - (Topic 1)

100% Valid Questions - Guaranteed Success 63


PMI CA0-001 : Valid Questions
Which tool is used to develop technical details within the project management plan?

A. Expert Judgment
B. Project Management Methodology
C. Project Management Information
D. Project Selection Methods

Answer: A

Question No : 188 - (Topic 1)

Which analysis uses beta and triangular distributions as a tool and technique?

A. Quantitative risk analysis


B. Qualitative risk analysis
C. Perform quality assurance
D. Perform quality control

Answer: A

Question No : 189 - (Topic 1)

Which tool or technique measures performance of the project as it moves from project
initiation through project closure?

A. Resource leveling
B. Parametric measuring
C. Pareto chart
D. Earned value

Answer: D

Question No : 190 - (Topic 1)

What is the function of a Project Management Office (PMO)?

A. To focus on the coordinated planning, prioritization, and execution of projects and

100% Valid Questions - Guaranteed Success 64


PMI CA0-001 : Valid Questions
subprojects that are tied to the parent organizations' or the client's overall business
objectives.
B. To coordinate and manage the procurement of projects relevant to the parent
organization's business objectives and to administer the project charters accordingly.
C. To administer performance reviews for the project manager and the project team
members and to handle any personnel and payroll issues.
D. To focus on the specified project objectives and to manage the scope, schedule, cost,
and quality of the work packages.

Answer: A

Question No : 191 - (Topic 1)

Which schedule development tool and technique produces a theoretical early start date
and late start date?

A. Critical path method


B. Variance analysis
C. Schedule compression
D. Schedule comparison bar charts

Answer: A

Question No : 192 - (Topic 1)

At the end of the project, what will be the value of SV?

A. Positive
B. Zero
C. Negative
D. Greater than one

Answer: B

Question No : 193 - (Topic 1)

Which of the following statements best describes the influence of stakeholders and the cost
of changes as project time advances?

100% Valid Questions - Guaranteed Success 65


PMI CA0-001 : Valid Questions
A. The influence of the stakeholders increases, the cost of changes increases.
B. The influence of the stakeholders decreases, the cost of changes increases.
C. The influence of the stakeholders increases, the cost of changes decreases.
D. The influence of the stakeholders decreases, the cost of changes decreases.

Answer: B
Explanation: Explanations: Stakeholders and changes versus time in the Project Life
Cycle
There are lots of common features regarding project life cycles:
• Most stages of the project follow one after the other and in many cases could be
described in technical way.
• Expenditures and personnel engaged in the task are quite cheap at the beginning of the
project, rise in the middle phase and fall significantly in the final stage. The Picture below
shows exactly the described model.

• At the beginning of the project - in initial stage the risk of failure and not to meet your
goals is very high. When this crucial period is over the project comes into an intermediate
phase where the situation is more stable and predictable.
• Stakeholders have a big influence for the project's product in many technical aspects,
costs etc. at the beginning of its life cycle. However their impact become lower within
duration of the project and cost of changes and other corrections - which are low in initial
phase rise considerably as the project continues. The Picture below demonstrates clearly
this situation.

100% Valid Questions - Guaranteed Success 66


PMI CA0-001 : Valid Questions

In our opinion lots of project life cycles have many similar characteristics but few of them
are the same. For example some projects can consist of five stages, others with ten or
more? Depend on complexity and duration of the project. One institution's hardware testing
can have one individual testing stage whereas another organization can have more phases
for this task like: general and detailed testing, error correction, compatibility with different
computers etc. Separate life cycles can also cover these subprojects for instance: one
team of engineers can analysis and look for any defects of the product and the other team
can simultaneously check compatibility with other devices.

In conclusion we recommend you to deal with every project separately and especially at big
and complex enterprises treat every phase as subproject with an individual life cycle.

Question No : 194 - (Topic 1)

In an organization with a projectized organizational structure, who controls the project


budget?

A. Functional manager
B. Project manager

100% Valid Questions - Guaranteed Success 67


PMI CA0-001 : Valid Questions
C. Program manager
D. Project management office

Answer: B

Question No : 195 - (Topic 1)

In a control chart, the consecutive measurements are 11, 13, 09, 07, 08, 09, 09, 09, 08,
and 12. For the entire process, the goal is 10 and the standard deviation is 1.

For this data set, it is correct to say that the process:

A. is under control.
B. is out of control.
C. has an increasing trend.
D. has a decreasing trend.

Answer: B

Question No : 196 - (Topic 1)

Which process documents the business needs of a project and the new product, service or
other result that is intended to satisfy those requirements?

A. Develop project management plan


B. Develop project charter
C. Develop preliminary project scope statement
D. Scope planning

Answer: B

Question No : 197 - (Topic 1)

Taking out insurance in relation to risk management is called what?

A. Transference
B. Avoidance

100% Valid Questions - Guaranteed Success 68


PMI CA0-001 : Valid Questions
C. Exploring
D. Mitigation

Answer: A

Question No : 198 - (Topic 1)

Which tool and technique is used to sequence activities?

A. Decomposition
B. Project management software
C. Applying lead and lags
D. Expert judgment

Answer: C

Question No : 199 - (Topic 1)

Which of the following is an input to Collect Requirements?

A. Stakeholder register
B. Requirements documentation
C. Prototypes
D. Organizational process assets

Answer: A

Question No : 200 - (Topic 1)

When managing a project team, what helps to reduce the amount of conflict?

A. Clear role definition


B. Negotiation
C. Risk response planning
D. Team member replacement

Answer: A

100% Valid Questions - Guaranteed Success 69


PMI CA0-001 : Valid Questions

Question No : 201 - (Topic 1)

Which of the following choices is a contract closure tool or technique?

A. Contract plan
B. Procurement plan
C. Closure process
D. Procurement audits

Answer: D

Question No : 202 - (Topic 1)

Which of the following is TRUE about most project life cycles?

A. Staffing level is highest at the start.


B. The stakeholders' influence is highest at the start.
C. The level of uncertainty is lowest at the start.
D. The cost of changes is highest at the start.

Answer: B

Question No : 203 - (Topic 1)

What is the schedule performance index (SPI) using the following data?

BAC = $100,000

PV = $50,000

AC = $80,000

EV = $40,000

A. 1.00
B. 0.40

100% Valid Questions - Guaranteed Success 70


PMI CA0-001 : Valid Questions
C. 0.50
D. 0.80

Answer: D

Question No : 204 - (Topic 1)

Activity resource requirements and resource breakdown structure are outputs from what
Project Time Management process?

A. Schedule Control
B. Activity Definition
C. Schedule Development
D. Activity Resource Estimating

Answer: D
Explanation:
Activity Resource Estimate Assumptions and Breakdown StructuresIn the Estimate Activity
Resources process, the key output is activity resource requirements. These requirements
describe the types and quantities of resources needed for each project activity.Once you
know what resources you need, you can begin to estimate the time each activity will take to
complete. In this way, the activity resource requirements list generated by the Estimate
Activity Resources process become inputs for the Estimate Activity Durations process.

Activity resource requirements listThe activity resource requirements list identifies, for
tracking purposes, the activity's code in the work breakdown structure, as well as its name.
Vital to generating the project schedule, it details the resources that you've estimated you
need to complete the activity, and addresses.

Resource description – The Resource description column lists each type of resource that is
required for the activity. This includes human resources, materials, and facilities.
Number required – The Number required column identifies the quantity required of each
resource. This value can be specified in any measurement unit, such as hours, days, or
physical number of units required.
Resource assumptions – Resource assumptions are important factors to consider when
devising the project schedule. Any relevant assumptions about the resource can be
included, for example resource availability, skills, or quality.
Resource availability – The Resource availability column specifies when each resource can
be used. This is vital information for putting together the project schedule.
Resource dependencies – The Resource dependencies column identifies factors that may

100% Valid Questions - Guaranteed Success 71


PMI CA0-001 : Valid Questions
affect the availability of resources. It's important to identify dependencies when devising the
project schedule because any change in an activity that has a dependency can affect the
project timeline.The final row of the activity resource requirements list identifies the total
resources needed for the activity. The resource totals are important in project scheduling
as a base from which to calculate the duration of the activity.
Resource Assumptions - It's important to record resource assumptions, as they can help
during different stages of a project. Select each project stage to find out how resource
assumptions can help.
Monitoring – Recorded assumptions can affect performance monitoring. For example, if a
particular task seems to be taking too long, looking at the assumptions can help you
identify the problem.
Controlling – Recorded assumptions can also help you control performance. Having used
the assumptions to identify a problem, you can now make performance adjustments so that
the project can run more efficiently.
Closing – Recorded assumptions can provide insights during post-project assessments at
the closing stage. For example, if you had made incorrect assumptions about staff
capabilities, looking at the assumptions helps you understand what went wrong. This can
then be recorded in the lessons learned file for the project.Failure to record assumptions
can also have an impact during the Monitor and Control Project Work process.
Resource breakdown structuresAlong with the activity resource requirements list, there's
one more main output of the Estimate Activity Resources process – the resource
breakdown structure.The resource breakdown structure provides a hierarchical diagram of
the resources required for a project. This structure is visually simple, showing resource
information at a glance breaks resources into categories and resource types helps you to
organize a project schedule and report on resource utilization information.
Although they look similar, a resource breakdown structure is not the same as a work
breakdown structure.
A work breakdown structure, or WBS, decomposes a project into manageable units of
work. Elements in a WBS include project phases, tasks, sub-tasks, and work packages.
These represent all the activities in a project.
Project document updatesThe Estimate Activity Resources process concludes with project
document updates – the final output of the process. Initially, various project documents are
used as inputs for the process. Now that resource estimation is complete, new information
may have come to light. For this reason, you may need to update documents so they
reflect the latest project information.
In the process of estimating resource requirements and creating the resource breakdown
structure, it's often necessary to add or delete schedule activities that appear in the activity
list.The activity changes have a subsequent effect on activity attributes and resource
calendars. Because project activities have changed, you need to document those changes
by updating the descriptions of activities and the availability of relevant resources.

100% Valid Questions - Guaranteed Success 72


PMI CA0-001 : Valid Questions
The first output of the Estimate Activity Resources process is an activity resource
requirements list. It's important to record any assumptions you've made about resources in
this list, for use in monitoring and controlling project work, and in post-project assessments.
A second output of the process is the resource breakdown structure. This is a hierarchical
diagram that shows the resources required for the project in a visually simple way. It
groups resources by category, and can be used for organizing and reporting on resources.
The final output of the process is updates to relevant project documents, such as the
activity list, activity attributes, and resource calendars.

Question No : 205 - (Topic 1)

In which process might you use risk reassessment as a tool and technique?

A. Qualitative risk analysis


B. Risk monitoring and control
C. Monitor and control project work
D. Risk response planning

Answer: B

Question No : 206 - (Topic 1)

Which of the following is a tool or technique used to verify scope?

A. Product analysis
B. Ishikawa diagram
C. Inspection
D. Requirements traceability matrix

Answer: C

Question No : 207 - (Topic 1)

Which of the following describes the purpose of the quality control process?

100% Valid Questions - Guaranteed Success 73


PMI CA0-001 : Valid Questions
A. To identify quality requirements of the project
B. To identify ineffective processes and eliminate them
C. To assess performance and recommend necessary changes
D. To ensure quality standards are used

Answer: C

Question No : 208 - (Topic 1)

A contract management plan is a subsidiary of what other type of plan?

A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan

Answer: B

Question No : 209 - (Topic 1)

What is a technique used in the performance reporting process?

A. Expert judgment
B. Project management methodology
C. Stakeholder analysis
D. Status review meetings

Answer: D
Explanation: Performance Reporting is the process for "collecting and distributing
performance information" like "status reporting, progress measurement, and forecasting"
(comp. PMBOK3, p. 221): On the base of the collected performance information
concerning scope, schedule, cost and quality this process generates the reports which are
distributed to the stakeholders (comp. PMBOK3, p. 231). Basicly one can determine four
types of reports:

• Forcast reports for describing future trends


• Progess reports for describing trends from past to presence
• Status reports for describing actual status
• Variance reports for describing differences between the planned baseline and the real

100% Valid Questions - Guaranteed Success 74


PMI CA0-001 : Valid Questions
data

Question No : 210 - (Topic 1)

Company A is launching a new communications satellite system. Resource B was


assigned combined projects of design, construction, integration, and launch of the satellite.

Resource B's role is that of a:

A. Project manager
B. Portfolio manager
C. Work breakdown manager
D. Program manager

Answer: D

Question No : 211 - (Topic 1)

Plurality is a type of which of the following?

A. Group creativity techniques


B. Group decision making techniques
C. Facilitated workshops
D. Prototypes

Answer: B

Question No : 212 - (Topic 1)

Which tool or technique uses the 80/20 principle?

A. Pareto chart
B. Cause and effect diagrams
C. Control charts

100% Valid Questions - Guaranteed Success 75


PMI CA0-001 : Valid Questions
D. Flowcharting

Answer: A

Question No : 213 - (Topic 1)

What is a cost of nonconformance?

A. Rework
B. Inspections
C. Training
D. Testing

Answer: A

Question No : 214 - (Topic 1)

A business case is an input to which of the following processes?

A. Collect Requirements
B. Define Scope
C. Develop Project Charter
D. Develop Project Management Plan

Answer: C

Question No : 215 - (Topic 1)

Another name for an Ishikawa diagram is:

A. Cause and effect diagram


B. Control Chart
C. Flowchart
D. Histogram

Answer: A

100% Valid Questions - Guaranteed Success 76


PMI CA0-001 : Valid Questions
Question No : 216 - (Topic 1)

A work package has been scheduled to cost $1,000 to complete, and was to be finished
today. As of today, the actual expenditure is $1,200 and approximately half of the work has
been completed.

What is the cost variance?

A. -$700
B. -$200
C. +$200
D. +$500

Answer: B

Question No : 217 - (Topic 1)

When is a project finished?

A. After verbal acceptance of the customer or sponsor


B. After lessons learned have been documented in contract closure
C. When the project objectives have been met
D. After resources have been released

Answer: C

Question No : 218 - (Topic 1)

Which process group typically consumes the bulk of a project's budget?

A. Monitoring & Controlling


B. Executing
C. Planning
D. Initiating

Answer: B

100% Valid Questions - Guaranteed Success 77


PMI CA0-001 : Valid Questions
Question No : 219 - (Topic 1)

Which quality control technique illustrates the 80/20 Principle?

A. Ishikawa diagram
B. Control Chart
C. Run Chart
D. Pareto Chart

Answer: D

Question No : 220 - (Topic 1)

The procurement document is an input to which of the following processes?

A. Develop Project Management Plan


B. Develop Schedule
C. Identify Stakeholders
D. Determine Budget

Answer: C

Question No : 221 - (Topic 1)

What is the status of the project whose data is shown in the following S-curve?

100% Valid Questions - Guaranteed Success 78


PMI CA0-001 : Valid Questions

A. Under budget and ahead of schedule


B. Over budget and behind schedule
C. Over budget and ahead of schedule
D. Under budget and behind schedule

Answer: B

Question No : 222 - (Topic 1)

Which of the following is an example of a group creativity technique?

A. Delphi technique
B. Unanimity
C. Observation
D. Presentation technique

Answer: A

Question No : 223 - (Topic 1)

A risk may be graded into different priorities by which process?

A. Risk monitoring and controlling

100% Valid Questions - Guaranteed Success 79


PMI CA0-001 : Valid Questions
B. Risk response planning
C. Qualitative risk analysis
D. Quantitative risk analysis

Answer: C

Question No : 224 - (Topic 1)

Which process group can be performed outside the project's scope of control?

A. Planning
B. Monitoring and Control
C. Closing
D. Initiating

Answer: D

Question No : 225 - (Topic 1)

Which of the following is a Process Group?

A. Scoping
B. Budgeting
C. Closing
D. Quality

Answer: C

Question No : 226 - (Topic 1)

Which of the following provides a comprehensive and consistent method of controlling the
project and ensuring its success?

A. Stakeholder management
B. Monitoring and controlling
C. Project governance
D. Project management methodology

100% Valid Questions - Guaranteed Success 80


PMI CA0-001 : Valid Questions
Answer: C

Question No : 227 - (Topic 1)

What scope definition technique is used to generate different approaches to execute and
perform the work of the project?

A. Build vs. buy


B. Expert judgment
C. Alternatives identification
D. Product analysis

Answer: C

Question No : 228 - (Topic 1)

Which of the following methods is a project selection technique?

A. Flowcharting
B. Earned value
C. Cost-benefit analysis
D. Pareto analysis

Answer: C
Explanation: Selection MethodsThere are various project selection methods practiced by
the modern business organizations. These methods have different features and
characteristics. Therefore, each selection method is best for different organizations.
Although there are many differences between these project selection methods, usually the
underlying concepts and principles are the same.
Following is an illustration of two of such methods (Benefit Measurement and Constrained
Optimization methods).

100% Valid Questions - Guaranteed Success 81


PMI CA0-001 : Valid Questions

As the value of one project would need to be compared against the other projects, you
could use the benefit measurement methods. This could include various techniques, of
which the following are the most common.

• You and your team could come up with certain criteria that you want your ideal project
objectives to meet. You could then give each project scores based on how they rate in
each of these criteria, and then choose the project with the highest score.
• When it comes to the Discounted Cash flow method, the future value of a project is
ascertained by considering the present value and the interest earned on the money. The
higher the present value of the project, the better it would be for your organization.
• The rate of return received from the money is what is known as the IRR. Here again, you
need to be looking for a high rate of return from the project.

The mathematical approach is commonly used for larger projects. The constrained
optimization methods require several calculations in order to decide on whether or not a
project should be rejected.

Cost-benefit analysis is used by several organizations to assist them to make their


selections. Going by this method, you would have to consider all the positive aspects of the
project, which is the benefits, and then deduct the negative aspects (or the costs) from the
benefits. Based on the results you receive for different projects, you could choose which
option would be the most viable and financially rewarding.

These benefits and costs need to be carefully considered and quantified in order to arrive
at a proper conclusion. Questions that you may want to consider asking are in the selection

100% Valid Questions - Guaranteed Success 82


PMI CA0-001 : Valid Questions
process are:

1. Would this decision help me to increase organizational value in the long run?
2. How long will the equipment last for?
3. Would I be able to cut down on costs as I go along?

In addition to these methods, you could also consider Choosing based on opportunity cost -
When choosing any project, you would need to keep in mind the profits that you would
make if you do decide to go ahead with the project.
Profit optimization is therefore the ultimate goal. You need to consider the difference
between the profits of the project you are primarily interested in, and the next best
alternative.

Question No : 229 - (Topic 1)

Which of the following is an output of the Estimate Activity Resources process?

A. Alternative analysis
B. Bottom-up estimating
C. Resource breakdown structure
D. Enterprise environmental factors

Answer: C

Question No : 230 - (Topic 1)

The product scope description is used to:

A. Gain stakeholders' support for the project.


B. Document the characteristics of the product.
C. Describe the project in great detail.
D. Formally authorize the project.

Answer: B

100% Valid Questions - Guaranteed Success 83


PMI CA0-001 : Valid Questions
Question No : 231 - (Topic 1)

Which of these are logical dependencies in a precedence diagram method?

A. End-to-end
B. Finish-to-end
C. Start-to-end
D. Start-to-start

Answer: D

Question No : 232 - (Topic 1)

During the initial stages of the project, what do activity attributes include?

A. Activity name, dependencies, assumptions


B. Activity ID, WBS ID, activity name
C. Activity ID, assumptions, constraints
D. Activity name, WBS ID, activity description

Answer: B

Question No : 233 - (Topic 1)

Which tool and technique uses a statistical relationship between historical data and other
variables to calculate estimates?

A. Analogous estimating
B. Three-point estimates
C. Parametric estimating
D. Bottom-up estimating

Answer: C

Question No : 234 - (Topic 1)

When do stakeholders have the greatest influence?

100% Valid Questions - Guaranteed Success 84


PMI CA0-001 : Valid Questions
A. At the start of the project
B. At the end of the project
C. During execution
D. Stakeholders have constant influence

Answer: A

Question No : 235 - (Topic 1)

In which type of organizational structure are staff members grouped by specialty?

A. Functional
B. Projectized
C. Matrix
D. Balanced

Answer: A

Question No : 236 - (Topic 1)

Which of the following is a conflict resolving technique that emphasizes areas of agreement
rather than areas of difference?

A. Withdrawing/Avoiding
B. Forcing
C. Collaborating
D. Smoothing/Accommodating

Answer: D

Question No : 237 - (Topic 1)

Emphasizing areas of agreement rather than areas of difference is part which of the
following conflict management techniques?

A. Smoothing
B. Compromising

100% Valid Questions - Guaranteed Success 85


PMI CA0-001 : Valid Questions
C. Avoiding
D. Forcing

Answer: A

Question No : 238 - (Topic 1)

Which of the following is one of the tools and techniques for the Define Activities process?

A. Rolling wave planning


B. Dependency determination
C. Schedule network template
D. Applying leads and lags

Answer: A

Question No : 239 - (Topic 1)

Rolling wave planning is used as a tool and a technique in which of the following
processes?

A. Estimate Activity Durations


B. Define Activities
C. Develop Schedule
D. Sequence Activities

Answer: B

Question No : 240 - (Topic 1)

Who is responsible for determining which processes from the Process Groups will be
employed and who will be performing them?

A. Project sponsor and project manager


B. Project sponsor and functional manager
C. Project manager and project team
D. Project team and functional manager

100% Valid Questions - Guaranteed Success 86


PMI CA0-001 : Valid Questions
Answer: C
Explanation: The project management processes are presented as discrete elements with
well- defined interfaces. However, in practice they overlap and interact in ways that are not
completely detailed here. Most experienced project management practitioners recognize
there is more than one way to manage a project. The specifics for a project are defined as
objectives that must be accomplished based on complexity, risk, size, time frame, project
team’s experience, access to resources, amount of historical information, the organization’s
project management maturity, and industry and application area. The required Process
Groups and their constituent processes are guides to apply appropriate project
management knowledge and skills during the project. In addition, the application of the
project management processes to a project is iterative and many processes are repeated
and revised during the project. The project manager and the project team are responsible
for determining what processes from the Process Groups will be employed, by whom, and
the degree of rigor that will be applied to the execution of those processes to achieve the
desired project objective.

Question No : 241 - (Topic 1)

What is the status of a project if the Cost Performance Index is 1.25 and the Schedule
Performance Index is 0.75?

A. Under budget and behind schedule


B. Over budget and ahead of schedule
C. Under budget and ahead of schedule
D. Over budget and behind schedule

Answer: A

Question No : 242 - (Topic 1)

Conflict should be best addressed in which manner?

A. Early, in private, using a direct, collaborative approach


B. Early, in public, using an indirect, collaborative approach
C. Early, in private, using an indirect, cooperative approach
D. As late as possible, in public, using a direct, confrontational approach

100% Valid Questions - Guaranteed Success 87


PMI CA0-001 : Valid Questions
Answer: A

Question No : 243 - (Topic 1)

Which is one of the determining factors used to calculate CPI?

A. EV
B. SPI
C. PV
D. ETC

Answer: A

Question No : 244 - (Topic 1)

What provides information regarding the ways people, teams, and organizational units
behave?

A. Organizational chart
B. Organizational theory
C. Organizational structure
D. Organizational behavior

Answer: B

Question No : 245 - (Topic 1)

Scope verification is PRIMARILY concerned with which of the following?

A. Acceptance of the work deliverables.


B. Accuracy of the work deliverables.
C. Approval of the scope statement.
D. Accuracy of the work breakdown structure.

Answer: A

100% Valid Questions - Guaranteed Success 88


PMI CA0-001 : Valid Questions

Question No : 246 - (Topic 1)

Final product transition is an output of which process?

A. Direct and Manage Project Execution


B. Close Project or Phase
C. Perform Integrated Change Control
D. Monitor and Control Project Work

Answer: B

Question No : 247 - (Topic 1)

A contract change control system defines which of the following?

A. Process by which the procurement is being satisfied


B. Process by which the procurement can be modified
C. Process by which the procurement can be obtained
D. Process by which the procurement can be disposed

Answer: B

Question No : 248 - (Topic 1)

What is the first step in preparing the risk register?

A. Qualitative risk analysis


B. Quantitative risk analysis
C. Risk response planning
D. Risk identification

Answer: D

Question No : 249 - (Topic 1)

100% Valid Questions - Guaranteed Success 89


PMI CA0-001 : Valid Questions
The project budget is set at $150,000. The project duration is planned to be one year. At
the completion of Week 16 of the project, the following information is collected:

Actual cost = $50,000

Plan cost = $45,000

Earned value = $40,000

What is the cost performance index?

A. 0.80
B. 0.89
C. 1.13
D. 1.25

Answer: A

Question No : 250 - (Topic 1)

What is risk tolerance?

A. Ability to manage risks


B. Willingness to accept varying degrees of risks
C. Ability to mitigate risks
D. Willingness to develop a risk management plan

Answer: B

Question No : 251 - (Topic 1)

Which of the following correctly explains the term "progressive elaboration"?

A. Changing project specifications continuously


B. Elaborate tracking of the project progress
C. Elaborate tracking of the project specifications with a change control system
D. Project specifications becoming more explicit and detailed as the project progresses

Answer: D

100% Valid Questions - Guaranteed Success 90


PMI CA0-001 : Valid Questions

Question No : 252 - (Topic 1)

A project becomes officially authorized when which of the following occurs?

A. Project manager is appointed


B. Stakeholders approve the project
C. Project charter is approved
D. Project sponsor approves the project

Answer: C

Question No : 253 - (Topic 1)

Which of the following is an example of contract administration?

A. Negotiating the contract


B. Authorizing contractor work
C. Developing the statement of work
D. Establishing evaluation criteria

Answer: B

Question No : 254 - (Topic 1)

The degree of risk shared between the buyer and seller is determined by the:

A. contract type.
B. sponsors.
C. project manager.
D. stakeholders.

Answer: A

Question No : 255 - (Topic 1)

100% Valid Questions - Guaranteed Success 91


PMI CA0-001 : Valid Questions
In which of the following contract types is a price ceiling set and any additional costs above
the price ceiling becomes the responsibility of the performing organization?

A. Firm-Fixed-Price Contracts (FFP)


B. Fixed-Price-Incentive-Fee Contracts (FPIF)
C. Cost-Reimbursable Contracts
D. Time and Materials Contracts (T&M)

Answer: B

Question No : 256 - (Topic 1)

Placing many or all of the most active project team members in the same physical location
to enhance their ability to perform as a team is called which of the following?

A. Team training
B. Co-location
C. Team location
D. Organization training

Answer: B

Question No : 257 - (Topic 1)

Which tools or techniques will the project manager use for developing the project team?

A. Negotiation
B. Roles and responsibilities
C. Recognition and rewards
D. Prizing and promoting

Answer: C

Question No : 258 - (Topic 1)

Manage Project Team belongs to which knowledge area?

100% Valid Questions - Guaranteed Success 92


PMI CA0-001 : Valid Questions
A. Project Integration Management
B. Project Time Management
C. Project Procurement Management
D. Project Human Resource Management

Answer: D

Question No : 259 - (Topic 1)

What is the primary benefit of meeting quality requirements?

A. Quality metrics
B. Less rework
C. Quality control measurements
D. Benchmarking

Answer: B

Question No : 260 - (Topic 1)

Your project has an EV of 100 work-days, an AC of 120 work-days, and a PV of 80 work-


days. What should be your concern?

A. There is a cost under run.


B. There is a cost overrun.
C. May not meet deadline.
D. The project is 20 days behind schedule.

Answer: B

Question No : 261 - (Topic 1)

The resource calendars document is an output of which process?

A. Estimate Activity Resources


B. Acquire Project Team
C. Develop Schedule

100% Valid Questions - Guaranteed Success 93


PMI CA0-001 : Valid Questions
D. Develop Project Team

Answer: B

Question No : 262 - (Topic 1)

Which of the following is defined by a project's life cycle and varies by application area?

A. Product
B. Product-oriented processes
C. Project management process groups
D. Project-oriented processes

Answer: B

Question No : 263 - (Topic 1)

During what process is the quality policy determined?

A. Initiating
B. Executing
C. Planning
D. Controlling

Answer: C

Question No : 264 - (Topic 1)

Which is a tool used in monitoring and controlling project work?

A. Work performance information


B. Project management information system (PMIS)
C. Activity duration estimates
D. Scheduled network analysis

Answer: D

100% Valid Questions - Guaranteed Success 94


PMI CA0-001 : Valid Questions
Question No : 265 - (Topic 1)

What is the total float of the critical path?

A. Can be any number


B. Zero or positive
C. Zero or negative
D. Depends on the calendar

Answer: C

Question No : 266 - (Topic 1)

What risk technique is used to quantify the probability and impact of risks on project
objectives?

A. Expert judgment
B. Risk registry
C. Risk response planning
D. Interviewing

Answer: D

Question No : 267 - (Topic 1)

Which of the following is a tool and technique to develop the schedule?

A. What-if scenario analysis


B. Benchmarking
C. Variance analysis
D. SWOT analysis

Answer: A

Question No : 268 - (Topic 1)

What is a tool to improve team performance?

100% Valid Questions - Guaranteed Success 95


PMI CA0-001 : Valid Questions
A. Staffing plan
B. External feedback
C. Performance reports
D. Co-Location

Answer: D

Question No : 269 - (Topic 1)

What does a CPI value greater than 1.0 indicate?

A. Cost right at the estimated value


B. Cost under the estimated value
C. Cost right at the actual value
D. Cost over the estimated value

Answer: B

Question No : 270 - (Topic 1)

Which process uses occurrence probability and impact on project objectives to assess the
priority of identified risks?

A. Risk identification
B. Qualitative risk analysis
C. Risk management planning
D. Quantitative risk analysis

Answer: B

Question No : 271 - (Topic 1)

When using the Delphi technique for gathering information, what forecasting method is
being used?

A. Time series method


B. Casual method

100% Valid Questions - Guaranteed Success 96


PMI CA0-001 : Valid Questions
C. Econometric method
D. Judgmental method

Answer: D

Question No : 272 - (Topic 1)

What should be covered in an implementation when the change is approved?

A. Functional requirement
B. Status report
C. Customer need
D. Defect repair

Answer: D

Question No : 273 - (Topic 1)

A Project Management Office (PMO) manages a number of aspects, including what?

A. Project scope, schedule, cost, and quality of the products of the work packages
B. Central coordinator of communication management across projects, and for the delivery
of specific project objectives, organization opportunity assessment
C. Assigns project resources to best meet project objectives
D. Overall risk, overall opportunity and interdependencies among projects

Answer: D

Question No : 274 - (Topic 1)

A project team is in which of the following processes when they finalize all activities across
all of the management process groups to formally complete the project?

A. Closing
B. Executing
C. Monitoring and Controlling
D. Planning

100% Valid Questions - Guaranteed Success 97


PMI CA0-001 : Valid Questions
Answer: A

Question No : 275 - (Topic 1)

Which of the following terms indicates a deliverable-oriented hierarchical decomposition of


the project work?

A. WBS directory
B. Activity list
C. WBS
D. Project schedule

Answer: C

Question No : 276 - (Topic 1)

Which of the following risk management processes uses brainstorming as a technique?

A. Identify Risks
B. Monitor and Control Risks
C. Plan Risk Management
D. Plan Risk Responses

Answer: A

Question No : 277 - (Topic 1)

Which of the following techniques uses historical information to estimate the activity
duration?

A. Three-point estimating
B. Organizational process asset
C. Analogous estimating
D. Reserve analysis

Answer: C

100% Valid Questions - Guaranteed Success 98


PMI CA0-001 : Valid Questions
Question No : 278 - (Topic 1)

In which tool and technique is it possible to find a correlation between dependent and
independent variables?

A. Fishbone diagram
B. Control chart
C. Run chart
D. Scatter diagram

Answer: D

Question No : 279 - (Topic 1)

Which of the following is a technique for resolving conflict?

A. Collaborating
B. Issue log
C. Leadership
D. Motivation

Answer: A

Question No : 280 - (Topic 1)

In which of the following team development stages does the team meet and learn about the
project and their formal roles and responsibilities?

A. Forming
B. Storming
C. Norming
D. Performing

Answer: A

Question No : 281 - (Topic 1)

100% Valid Questions - Guaranteed Success 99


PMI CA0-001 : Valid Questions
What is the minimum a project schedule must include?

A. Variance analysis
B. A planned start date and a planned finish date for each schedule activity
C. A critical path diagram
D. Critical chain analysis

Answer: B

Question No : 282 - (Topic 1)

Project team members begin to address the project work and technical decisions. The
project team is in which of the following stages of team development?

A. Storming
B. Forming
C. Norming
D. Performing

Answer: A

Question No : 283 - (Topic 1)

What is the name of the statistical method that helps identify which factors may influence
specific variables of a product or process under development or in production?

A. Failure modes and effects analysis


B. Design of experiments
C. Quality checklist
D. Risk analysis

Answer: B

Question No : 284 - (Topic 1)

Which knowledge area employs the processes required to ensure timely and appropriate
generation, collection, distribution, storage, retrieval, and ultimate disposition of project

100% Valid Questions - Guaranteed Success 100


PMI CA0-001 : Valid Questions
information?

A. Project Risk Management


B. Project Integration Management
C. Project Communications Management
D. Project Quality Management

Answer: C

Question No : 285 - (Topic 1)

Who must accept the end product for a project to be considered closed?

A. Project team
B. Project manager
C. Project management office
D. Customer or sponsor

Answer: D

Question No : 286 - (Topic 1)

Which of the following is an input to identify risk?

A. Organizational process assets


B. Scope management plan
C. Communication management plan
D. Expert judgment

Answer: A

Question No : 287 - (Topic 1)

How many process groups are there according to the PMBOK Guide?

A. 5
B. 9

100% Valid Questions - Guaranteed Success 101


PMI CA0-001 : Valid Questions
C. 10
D. 12

Answer: A

Question No : 288 - (Topic 1)

Which of the following is a tool or technique of the Collect Requirements process?

A. Group decision making techniques


B. Project management information system
C. Alternative identification
D. Communication requirement analysis

Answer: A

Question No : 289 - (Topic 1)

Forecasts, requested changes, recommended corrective actions, and organizational


process asset updates are all outputs of which process?

A. Risk response planning


B. Risk monitoring and control
C. Performance reporting
D. Manage stakeholders

Answer: C

Question No : 290 - (Topic 1)

How many knowledge areas are there according to PMBOK Guide?

A. 5
B. 8
C. 9
D. 12

100% Valid Questions - Guaranteed Success 102


PMI CA0-001 : Valid Questions
Answer: C

Question No : 291 - (Topic 1)

What is included in a control chart?

A. Baseline
B. Planned value
C. Upper specification limit
D. Expenditure

Answer: C

Question No : 292 - (Topic 1)

A project manager needs the project team to make a group decision. Which of the following
is a method that can be used to reach a group decision?

A. Expert judgment
B. Majority
C. SWOT analysis
D. Brainstorming

Answer: B

Question No : 293 - (Topic 1)

Which of the following are inputs to Activity Definition?

A. Project Scope Statement and Work Breakdown Structure


B. Activity list and Arrow Diagram
C. Change Requests Lists and Organizational Process Assets
D. Project Management Plan and Resource Availability

Answer: A
Explanation:
Activity definition refers to the process of parsing a project into a number of individual tasks

100% Valid Questions - Guaranteed Success 103


PMI CA0-001 : Valid Questions
which must be completed before the deliverables can be considered completed. Activity
definitions rely on a number of specific input processes. These include enterprise
environmental factors, organizational process assets, the project scope statement, the
work breakdown structure, the WBS dictionary, the project management plan (which
consists of the project scope management plan and the schedule management plan).
Through use of these inputs, the activities that will need to ultimately be completed in order
to compete all of the project objectives can be readily defined, and the activity definition
can be further accomplished through the utilization of a number of tools and techniques
including decomposition, templates, rolling wave planning, expert judgment, and planning
components. The four ultimate outputs of the activity definition process are the activity list,
the resulting activity attributes, all requested changes, and any milestones.
This term is defined in the 3rd edition of the PMBOK but not in the 4th.

Question No : 294 - (Topic 1)

Which of the following is an example of a risk symptom?

A. Failure to meet intermediate milestones


B. Force of nature, such as a flood
C. Risk threshold target
D. Crashing front loading or fast tracking

Answer: A

Question No : 295 - (Topic 1)

Which illustrates the connection between work that needs to be done and its project team
members?

A. Work breakdown structure


B. Network diagrams
C. Staffing management plan
D. Responsibility matrix

Answer: D

100% Valid Questions - Guaranteed Success 104


PMI CA0-001 : Valid Questions
Question No : 296 - (Topic 1)

Which process involves aggregating the estimated costs of the individual schedule
activities or work packages?

A. Cost baseline
B. Cost forecasting
C. Cost variance
D. Cost budgeting

Answer: D

Question No : 297 - (Topic 1)

Which estimating technique uses the actual costs of previous similar projects as a basis for
estimating the costs of the current project?

A. Analogous
B. Parametric
C. Bottom-up
D. Top-down

Answer: A

Question No : 298 - (Topic 1)

What should a project manager do with low-priority risks?

A. Ignore low-priority risks


B. Monitor periodically with other low-priority risks
C. Create a mitigation plan for the low-priority risks
D. Increase the contingency reserve

Answer: B

Question No : 299 - (Topic 1)

100% Valid Questions - Guaranteed Success 105


PMI CA0-001 : Valid Questions
A project manager has limited authority in which type of organizational structure?

A. Weak matrix
B. Functional
C. Balanced matrix
D. Projectized

Answer: A

Question No : 300 - (Topic 1)

Which type of analysis is used to examine project results through time to determine if
performance is improving or deteriorating?

A. Control chart
B. Earned value
C. Variance
D. Trend

Answer: D

Question No : 301 - (Topic 1)

Which tool and technique identifies inefficient and ineffective policies, processes and
procedures?

A. Scope audits
B. Scope reviews
C. Quality audits
D. Control chart

Answer: C

Question No : 302 - (Topic 1)

Which type of tool would be used for the quality planning activity?

100% Valid Questions - Guaranteed Success 106


PMI CA0-001 : Valid Questions
A. Schedule Analysis
B. Checklist Analysis
C. Assumption Analysis
D. Cost-Benefit Analysis

Answer: D

Question No : 303 - (Topic 1)

Which type of analysis is used to develop the communications management plan?

A. Product
B. Cost benefit
C. Stakeholder
D. Research

Answer: C

Question No : 304 - (Topic 1)

What is an output of Control Scope?

A. Accepted deliverables
B. Work performance measurements
C. Requirements documentation
D. Work performance information

Answer: B

Question No : 305 - (Topic 1)

There are seven members on the project team not counting the project manager and the
sponsor. How many communication channels are there?

A. 21
B. 28
C. 36

100% Valid Questions - Guaranteed Success 107


PMI CA0-001 : Valid Questions
D. 42

Answer: C

Question No : 306 - (Topic 1)

Which process group establishes the total scope of a project?

A. Initiating
B. Planning
C. Monitoring and Controlling
D. Executing

Answer: B

Question No : 307 - (Topic 1)

In which of the team development stages are the teams interdependent and work through
issues smoothly and effectively?

A. Norming
B. Forming
C. Storming
D. Performing

Answer: D

Question No : 308 - (Topic 1)

Which of the following defines a characteristic of a project?

A. Repetitive
B. Unique
C. No outcome
D. Permanent

Answer: B

100% Valid Questions - Guaranteed Success 108


PMI CA0-001 : Valid Questions

Question No : 309 - (Topic 1)

In which domain of project management would a Pareto chart provide useful information?

A. Scope Management
B. Time Management
C. Communications Management
D. Quality Management

Answer: D

Question No : 310 - (Topic 1)

Which tool and technique of quality planning involves comparing actual or planned
practices to those of other projects to generate ideas for improvement and provide a basis
by which to measure performance?

A. Histogram
B. Quality audits
C. Benchmarking
D. Performance measurement analysis

Answer: C

Question No : 311 - (Topic 1)

How is quality control performed?

A. By identifying quality standards that are relevant to the project and determining how to
satisfy them.
B. By monitoring specific project results in compliance with relevant quality standards and
determining corrective actions as needed.
C. By ensuring that the entire project team has been adequately trained in quality
assurance processes.
D. By applying Monte Carlo, sampling, Pareto analysis and benchmarking techniques to
ensure conformance to quality standards.

100% Valid Questions - Guaranteed Success 109


PMI CA0-001 : Valid Questions
Answer: B

Question No : 312 - (Topic 1)

In which type of organization does a project manager have a moderate-to-high resource


availability?

A. Functional
B. Weak
C. Balanced
D. Strong

Answer: D

Question No : 313 - (Topic 1)

What is the tool and technique used to request seller responses?

A. Procurement documents
B. Expert judgment
C. Bidder conferences
D. Contract types

Answer: C

Question No : 314 - (Topic 1)

Which of the following provides a basis for assessing project performance?

A. Profitability and impact matrix


B. Expert judgment
C. Benchmarking
D. Risk categorization

Answer: C

100% Valid Questions - Guaranteed Success 110


PMI CA0-001 : Valid Questions

Question No : 315 - (Topic 1)

Initiating, Planning, Executing, Monitoring and Controlling and Closing are called:

A. process groups.
B. phase gates.
C. knowledge areas.
D. project phases.

Answer: A

Question No : 316 - (Topic 1)

Information collected on the status of project activities being performed to accomplish the
project work is known as what?

A. Project management information system


B. Work performance information
C. Work breakdown structure
D. Variance analysis

Answer: B
Explanation:
Work Performance Information
Part of the executed project management plan includes the routine collection of work
performance information. The information gathered is important, and is useful as input data
for quality control measures and programs. It is also useful when audits, quality reviews,
and process analyses are conducted. This is especially true of work performance
information collected which includes technical performance measures, project deliverables
status, required corrective actions, and performance reports. Pertinent work performance
Information is essential to the project management plan and includes, but is not limited to:

• Status information on schedule progress.


• Whether deliverables have been completed, or not.
• Start and finish status of schedule activities.
• Quality standards expectation results.
• Authorized costs vs. costs incurred to date.
• Estimated completion time for scheduled activities in progress.

100% Valid Questions - Guaranteed Success 111


PMI CA0-001 : Valid Questions
• Percentage of physical completion of in-progress schedule activities.
• Experience based knowledge acquired, documented, and posted to knowledge base.
• Details of resource utilization.

Gathering and analysis of work performance information is essential to the project


management plan and should be considered a priority. Work performance information
contributes to the efficient use of resources, identifies potential trouble spots and problems,
and serves as an effective project management tool. This term is defined in the 3rd and the
4th edition of the PMBOK.

Question No : 317 - (Topic 1)

What is a specific advantage of analogous estimating in comparison with other cost


estimate techniques?

A. Uses contingency reserves


B. Less costly and time consuming
C. Can be applied to segments of work
D. More accurate

Answer: B

Question No : 318 - (Topic 1)

At which point of the project is the uncertainty the highest and the risk of failing the greatest

A. Final phase of the project


B. Start of the project
C. End of the project
D. Midpoint of the project

Answer: B

Question No : 319 - (Topic 1)

100% Valid Questions - Guaranteed Success 112


PMI CA0-001 : Valid Questions
Approved change requests, approved corrective actions, and updates to organizational
process assets are all outputs of which project management process?

A. Risk response planning


B. Manage stakeholders
C. Scope definition
D. Performance reporting

Answer: B

Question No : 320 - (Topic 1)

You are assigned to implement the project control plan. What should you do to ensure the
plan is effective and current?

A. Perform periodic project performance reviews.


B. Identify quality project standards.
C. Follow ISO 9000 quality standards
D. Complete the quality control checklist.

Answer: A
Explanation: The document control plan is an outline or guide on how physical or virtual
documents will be managed throughout the life of the project. It provides a road map for
tracking documents and for adding, archiving, and removing new documentation from the
process.

Question No : 321 - (Topic 1)

How is scheduled variance calculated using the earned value technique?

A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV

Answer: C

100% Valid Questions - Guaranteed Success 113


PMI CA0-001 : Valid Questions
Question No : 322 - (Topic 1)

Which of the following is a technique for Identify Risks?

A. Risk categorization
B. SWOT analysis
C. Risk register categorization
D. Risk probability and impact assessment

Answer: B

Question No : 323 - (Topic 1)

Which of the following techniques is used during Control Scope?

A. Cost-Benefit Analysis
B. Variance Analysis
C. Reserve Analysis
D. Stakeholder Analysis

Answer: B

Question No : 324 - (Topic 1)

When are deliverables accepted or not accepted?

A. When the project is initiated.


B. As an output of the scope verification process.
C. When the project is closing.
D. In the contract closure process.

Answer: B

Question No : 325 - (Topic 1)

Negotiated Settlements are an example of a technique used in which Project Procurement


Management Process?

100% Valid Questions - Guaranteed Success 114


PMI CA0-001 : Valid Questions
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements

Answer: D

Topic 2, Volume B

Question No : 326 - (Topic 2)

A Risk Register is a part of the ________.

A. Project Scope Statement


B. Project Management plan
C. Project Scheduling plan
D. Project Charter

Answer: B
Explanation:

The Risk Register is detailed part of the project management plan.

Question No : 327 - (Topic 2)

During the planning phase of your project, your project team members have discovered
another way to complete a portion of the project scope. This method is safer for the project
team, but may cost more for the customer. This is an example of _______.

A. Alternative identification
B. "'s^ assessment
C. Alternative selection
D. Product analysis

Answer: A
Explanation:

Alternative identification is a planning process to find alternatives to completing the project

100% Valid Questions - Guaranteed Success 115


PMI CA0-001 : Valid Questions
scope.

Question No : 328 - (Topic 2)

Which one of the following is not an output of contract closure?

A. close contracts
B. Lessons learned documentation
C. Deliverable acceptance
D. Scope statement

Answer: D
Explanation:

All are output of contract closure: Close contracts,Contract file,Lessons learned


documentation and Deliverable acceptance.

Question No : 329 - (Topic 2)

Which of the following is an output of Verify Scope?

A. Formal acceptance
B. WBS template
C. sow acceptance
D. Rework

Answer: A
Explanation:

Output of Verify Scope is formal acceptance.

Question No : 330 - (Topic 2)

Which of the following subsidiary plan contains the quality objectives for the project?

100% Valid Questions - Guaranteed Success 116


PMI CA0-001 : Valid Questions
A. Quality baseline
B. Quality management plan
C. Process improvement plan
D. QA checklist

Answer: A
Explanation:

The quality baseline documents the quality objectives for the project.

Question No : 331 - (Topic 2)

_________ is always the lowest risk for the buyer if the scope of work is not well defined.

A. Cost plus incentive fee


B. F'xed P|ice
C. Time and material
D. "'s^ 's nc* 'elated to price

Answer: A
Explanation:

Cost plus incentive fee is always the lowest risk for the buyer if the scope of work is not
well defined. Fixed price and purchase order are the best choice for buyer when the item is
well defined

Question No : 332 - (Topic 2)

PMI discusses procurement focusing on the ______ relationship.

A. Buyer or seller
B. Vendor or seller
C. Purchasing
D. Sellino-

Answer: A
Explanation:

100% Valid Questions - Guaranteed Success 117


PMI CA0-001 : Valid Questions

PMI discusses procurement focusing on the buyer or seller relationship

Question No : 333 - (Topic 2)

Which of the following provides the least accurate in estimating?

A. Rough order of magnitude


B. Budget estimate
C. WBS estimate
D. Definitive estimate

Answer: A
Explanation:

The rough order of magnitude is the least accurate approach, as it may vary from -25
percent to +75 percent.

Question No : 334 - (Topic 2)

___________ is a group of processes required to purchase or acquire the products,


services, or results needed from outside the project team to perform the work.

A. Procurement Management
B. Planning Management
C. Scope Management
D. Control Management

Answer: A
Explanation:

Procurement Management is groups of processes required to purchase or acquire the


products, services, or results needed from outside the project team to perform the work.

100% Valid Questions - Guaranteed Success 118


PMI CA0-001 : Valid Questions
Question No : 335 - (Topic 2)

In PMBOK, the seller is ________ to the project team.

A. Internal
B. External
C. Outside
D. Assigned

Answer: B
Explanation:

In PMBOK, the seller is External to the project team.

Question No : 336 - (Topic 2)

Function of the __________ is to make sure that changes to anything in the project are
recorded and agreed to by the stakeholders.

A. Project Manager
B. Sponsor
C. Team Lead
D. Management

Answer: A
Explanation:

Function of the project manager is to make sure that changes to anything in the project are
recorded and agreed to by the stakeholders.

Question No : 337 - (Topic 2)

Who has the responsibility for informing the final deliverable to all stakeholders?

A. Project Manager
B. Sponsor

100% Valid Questions - Guaranteed Success 119


PMI CA0-001 : Valid Questions
C. Team Lead
D. Management

Answer: A
Explanation:

Project Manager has the responsibility for informing the final deliverable to all stakeholders.

Question No : 338 - (Topic 2)

Create Procurement document is done in _______.

A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements

Answer: A
Explanation:

Create Procurement document is done in Plan Procurements process.

Question No : 339 - (Topic 2)

Which risk response is most likely to involve contingency reserves?

A. Acceptance
B. shaie
C. Mitigate
D. Transfer

Answer: A
Explanation:

Acceptance is when no change to the project is made for a risk. A contingency can be set
aside to offset the impact of the risk.

100% Valid Questions - Guaranteed Success 120


PMI CA0-001 : Valid Questions

Question No : 340 - (Topic 2)

From whom do you need to gain the formal acceptance at project closure?

A. The customer
B. The qualify director
C. Project management office
D. Project manager

Answer: A
Explanation:

need to gain this formal acceptance at project closure from the customer and sponsor.

Question No : 341 - (Topic 2)

Which of the following does not provided by scope statement?

A. Project justification
B. Project product
C. Project manager authority
D. Project objective

Answer: C
Explanation:

The project charter provides the project manager with authority.

Question No : 342 - (Topic 2)

Project success can be achieved only if:

100% Valid Questions - Guaranteed Success 121


PMI CA0-001 : Valid Questions
A. There is a clear link between the project deliverables and the business strategy.
B. The project sponsor leads the initiatives.
C. The project manager is an expert in managing resources.
D. Team members like project manager.

Answer: A
Explanation:

There is no project for the sake of spending money. There is a clear link between the
project deliverables and the business strategy.

Question No : 343 - (Topic 2)

The main purpose of project initiation is to ________.

A. Assign the project manager to the project


B. Formally describe the project
C. Produce the project charter
D. Formally authorize the project

Answer: D
Explanation:

Output of project initiation is formally authorizing the project. Output of project scope
initiation is: Project charter PM assigned Constraints and Assumptions.

Question No : 344 - (Topic 2)

Which of the following is the most important task of the project manager during the
Execution and Control phase?

A. Information management
B. Maintain scope statement
C. Maintain Charter
D. Maintain Closing document

Answer: A

100% Valid Questions - Guaranteed Success 122


PMI CA0-001 : Valid Questions
Explanation:

One of the most important tasks of the project manager during the Execution and Control
phases of the project is the management of information.

Question No : 345 - (Topic 2)

Which of the following activities is not part of Plan Risk Management?

A. Updating risk register


B. Determining risk roles and responsibilities
C. Identifying risk categories
D. Developing a risk management plan

Answer: A
Explanation:

Updating the risk register first happens in Identify Risks phase. Determining risk roles and
responsibilities, Identifying risk categories and developing a risk management plan are part
of Plan Risk Management.

Question No : 346 - (Topic 2)

What is the lowest level in a work breakdown structure?

A. Project task
B. w°rl< package
C. sow
D. None

Answer: B
Explanation:

A work package is the lowest level of a work breakdown structure.

100% Valid Questions - Guaranteed Success 123


PMI CA0-001 : Valid Questions
Question No : 347 - (Topic 2)

Which of the following are input of close project process?

A. Project management plan


B. Contract documentation
C. Deliverables
D. All of the above

Answer: D
Explanation:

All are inputs of close project process.

Question No : 348 - (Topic 2)

In which phase project manager is assigned to a project?

A. During the initiation stage


B. During the planning stage
C. After approval of budget
D. After the project is proven feasible

Answer: A
Explanation:

output of Initiation process : Project charter PM assigned Constraints Assumptions Project


manager is assigned to a project During the initiation stage.

Question No : 349 - (Topic 2)

Which of the following statement is true about project charter?

A. Provides a high level definition of the effort and its stakeholders


B. Announces who is the project engineer
C. Tells the newspapers and media when the project will end

100% Valid Questions - Guaranteed Success 124


PMI CA0-001 : Valid Questions
D. Announces who is the project sponsor

Answer: A
Explanation:

project charter: The project charter formally authorizes the project, assigns the project
manager, and gives a high-level definition of the projects and its deliverables.

Question No : 350 - (Topic 2)

You are project manager of a project, which of the following is not your responsibility?

A. Quality in the organization


B. Acquiring HR resources for the project team
C. Overall responsibility for risk on the project
D. Al1 of the above

Answer: A
Explanation:

Senior management is responsible for quality in the organization

Question No : 351 - (Topic 2)

If a project with a SPI of 1.8, what you tell?

A. The project is running ahead of the schedule


B. The project is running behind of the schedule
C. Resources assigned to the project cost 1.8 units
D. None

Answer: A
Explanation:

The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule
performance index of 1 or greater suggests that the project is ahead of schedule.

100% Valid Questions - Guaranteed Success 125


PMI CA0-001 : Valid Questions

Question No : 352 - (Topic 2)

Assumptions are factors that, for planning purposes, are considered to be ______.

A. True, real, or certain


B. True, real, or uncertain
C. Real
D. Verbal

Answer: A
Explanation:

PMBOK describes assumptions as "factors that, for planning purposes, are considered to
be true, real, or certain."

Question No : 353 - (Topic 2)

The project baseline is _______.

A. Original plans plus the approved changes


B. Important in the project initiation phase
C. Initial estimates for tasks and resource utilization
D. Original plans and the approved major changes

Answer: A
Explanation:

The project baseline: original plans plus the approved changes.

Question No : 354 - (Topic 2)

Which statement is true about Bottom-up estimating?

100% Valid Questions - Guaranteed Success 126


PMI CA0-001 : Valid Questions
A. Estimating the cost of individual work items and then rolling up the costs to arrive at a
project total.
B. Uses the actual cost of a previous similar project as the basis for estimating the cost of
the current project.
C. Using project characteristics (or parameters) in a mathematical model to predict costs.
D. Cost of quality can also be used to prepare the schedule activity cost estimate.

Answer: A
Explanation:

Bottom-up estimating: Estimating the cost of individual work items and then rolling up the
costs to arrive at a project total. It is more accurate.

Question No : 355 - (Topic 2)

You are managing a project that will implement a new Insurance software package. Two
project team members have difficulty working together. They come to you, for help
resolving the issues. You immediately set up a meeting that includes the functional
manager. After the meeting you and the functional manager discuss the issues and agree
on a solution. What type of organizational structure you are working in?

A. Functional
B. Balanced matrix
C. Piojectized
D. Strong Matrix

Answer: B
Explanation:

Balanced matrix: Power is shared between both Functional and Project Manager. In this
case you include the functional manager in the meeting therefore it is Balanced matrix
organization.

Question No : 356 - (Topic 2)

If a project with a CPI of 1.2, what you tell?

100% Valid Questions - Guaranteed Success 127


PMI CA0-001 : Valid Questions
A. The project is consuming fewer resources than anticipated
B. The project is using fewer resources than anticipated.
C. The project is falling behind.
D. The project is running ahead of schedule.

Answer: A
Explanation:

If your cost performance index is above 1.0, it indicates that you have costs that are less
then estimated; so doing good. Option A is BEST fit for this CPI = EV/AC (Earned value/
Actual cost

Question No : 357 - (Topic 2)

Who gives project acceptance?

A. Sponsor
B. Customer
C. Project Manager
D. Team Lead

Answer: B
Explanation:

Customer gives project acceptance. Customer may be person or organization.

Question No : 358 - (Topic 2)

If a project with a CPI of 0.8, what you tell?

A. The project is consuming more resources than anticipated.


B. The project is using fewer resources than anticipated.
C. The project is falling behind.
D. The project is running ahead of schedule.

Answer: A
Explanation:

100% Valid Questions - Guaranteed Success 128


PMI CA0-001 : Valid Questions

If your cost performance index is above 1.0, it indicates that you have costs that are less
then estimated. CPI = EV/AC (Earned value/ Actual cost)

Question No : 359 - (Topic 2)

Which is not part of Project Plan?

A. Project Scope Management Plan


B. Schedule Management Plan
C. Cost Management Plan
D. Project Charter

Answer: D
Explanation:

All are part of Project Plan except project charter.

Question No : 360 - (Topic 2)

Which document is best suited for tracking the assignment of all resources to specific tasks
in a project?

A. RACI mAl,x
B. sow
C. Staffing management plan D)0 CPI

Answer: A
Explanation:

The RACI matrix lists responsibilities of all resources. The staffing management plan only
lists types of resources and timing.

100% Valid Questions - Guaranteed Success 129


PMI CA0-001 : Valid Questions
Question No : 361 - (Topic 2)

Which type of network diagram is also referred to activity-on-arrow (AOA) diagrams?

A. Precedence Diagramming Method (PDM)


B. Gant Cnart Diagram (GCD)
C. Dependency Diagramming Method (DDM)
D. Arrow Diagramming Method (ADM)

Answer: D
Explanation:

The arrow diagramming method (ADM) is also referred to as activity-on-arrow (AOA)


diagramming method. Precedence diagramming method (PDM) is also referred to as
activity-on-node (AON) diagramming method

Question No : 362 - (Topic 2)

Administrative closure is the process that ________.

A. Closes all activities pertaining to a specific project


B. Collects user acceptance of the project product or service
C. Includes all the activities needed to validate the project products and services
D. Al1 of the above

Answer: A
Explanation:

Administrative closure: Closes all activities pertaining to a specific project

Question No : 363 - (Topic 2)

Who has the responsibility for Plan Quality?

A. Project manager
B. QA manager

100% Valid Questions - Guaranteed Success 130


PMI CA0-001 : Valid Questions
C. Project planner
D. Team lead

Answer: A
Explanation:

Project manager has the responsibility for Plan Quality.

Question No : 364 - (Topic 2)

The product description of a project can help to create procurement details. Which one of
the following best describes product description?

A. The product description defines the contracted work, based on the requirements of the
project customer
B. The product description defines the contracted work
C. The product description defines the requirements for the contract work
D. Al1 of the above

Answer: A
Explanation:

The product description defines the contracted work, based on the requirements of the
project customer

Question No : 365 - (Topic 2)

Which of the following are the inputs of Define Scope?

A. Requirements document created in collect requirements process


B. Project files from previous projects
C. Project Charter
D. Al1 of the above

Answer: D
Explanation:

100% Valid Questions - Guaranteed Success 131


PMI CA0-001 : Valid Questions
Define Scope - Inputs Requirements document created in collect requirements process,
Project Charter and Organizational Process Assets (Project files from previous projects,
lesson learned)

Question No : 366 - (Topic 2)

Delivery dates and availability of resources can be found in the details of the __________.

A. Work Breakdown Structure


B. sow
C. Project Charter
D. Project Scope Statement

Answer: A
Explanation:

Delivery dates and availability of resources can be found in the details of the WBS.

Question No : 367 - (Topic 2)

You are managing a project that will implement a new MARKETING software package. You
have assigned the resources and want to keep the IT manager in the loop by informing him
or her of your decisions. Which type of organizational structure are you working in?

A. Pi'ojectized
B. Strong Matrix
C. Weak Matrix
D. Functional

Answer: B
Explanation:

Projectized Organization: Any organizational structure in which the project manager has full
authority to assign priorities and to direct the work of individuals assigned to the project.
Strong Matrix: The project manager is assigned full time and has a full time support staff.
Project manager has the preeminent position of authority. Weak Matrix: Power reset with

100% Valid Questions - Guaranteed Success 132


PMI CA0-001 : Valid Questions
Functional Manager. Functional: In this organization Project Manager has least power and
all management is taken care by functional manager like marketing engineer, sales
engineer.

Question No : 368 - (Topic 2)

Collect Requirements process starts in Project Planning Phase and uses the outputs of the
__________.

A. Initiation Process
B. Project closer Process
C. Estimation Process
D. Closing process

Answer: A
Explanation:

Collect Requirements process starts in "Project Planning Phase" and uses the outputs of
the Initiation Process.

Question No : 369 - (Topic 2)

Project scope is _____________.

A. The features and functions that are to be included in a product or service


B. The work that must NOT be done in order to deliver a product with the specified features
and functions
C. Part °ftne project charter
D. Part of sow

Answer: A
Explanation:

Project scope : The features and functions that are to be included in a product or service.
The work that must be done in order to deliver a product with the specified features and
functions.

100% Valid Questions - Guaranteed Success 133


PMI CA0-001 : Valid Questions

Question No : 370 - (Topic 2)

Which of the following is conflict resolution technique?

A. Compromise
B. Smoothing
C. Foimal
D. Coercive

Answer: B
Explanation:

smoothing is a conflict resolution technique, the rest are forms of leadership power.

Question No : 371 - (Topic 2)

Make-or-buy decisions measure the costs of both options. What are the two options?

A. Direct ar|d Indirect


B. Tactical and Strategic
C. Management and Project
D. 0n|y Tactical

Answer: A
Explanation:

Make-or-buy decisions measure the costs of both options. When doing this analysis, it
should include both direct and indirect costs so that the final decision is based on
comparisons that are equal.

Question No : 372 - (Topic 2)

100% Valid Questions - Guaranteed Success 134


PMI CA0-001 : Valid Questions
Which of the following technique to identify the underlying cause of a problem and take
steps to prevent further occurrence?

A. Root cause analysis


B. Quality audits
C. Project audits
D. Risk audits

Answer: A
Explanation:

Root cause analysis: A technique to identify the underlying cause of a problem and take
steps to prevent further occurrence.

Question No : 373 - (Topic 2)

The work breakdown structure is ________.

A. Used to break down the project into manageable pieces


B. Set and does not change throughout the project
C. Needed as part of the project charter
D. [Needed as part of the project scope statement

Answer: A
Explanation:

Work Breakdown Structure (WBS): A deliverable-oriented grouping of project elements


which organizes and defines the total scope of the project. It sub divide the major tasks to
minor details.

Question No : 374 - (Topic 2)

You are the project manager of a project that just went into extinction mode. This means
that your project __________.

100% Valid Questions - Guaranteed Success 135


PMI CA0-001 : Valid Questions
A. Has ended before its stated objective
B. 's st'" cunning but missing resources
C. Will be closed due to lack of resources
D. None of the above

Answer: A
Explanation:

A project that ends in extinction mode is a project that has ended before meeting its stated
objectives.

Question No : 375 - (Topic 2)

You are the project manager of the MKTG Project. The project has a budget of $200,000
and is expected to last 2 years. The project is now 20 percent complete and is on schedule.
What is the BAC?

A. $-00,000
B. $200,00
C. $50,000
D. None of the above

Answer: B
Explanation:

The BAC is the budget at completion (Total budgeted cost), which is $200,000.

Question No : 376 - (Topic 2)

Who is responsible for issuing the project charter?

A. The project manager


B. The project sponsor
C. The Team lead
D. The nianagement

Answer: B

100% Valid Questions - Guaranteed Success 136


PMI CA0-001 : Valid Questions
Explanation:

The project sponsor creates and issues the project charter.

Question No : 377 - (Topic 2)

You have a piece of equipment that was purchased for your project recently for $5,000 and
is expected to last 5 years in production. At the end of the five years the expected worth of
the equipment is $2,000. Using straight-line deprecation, what is the amount that can be
written off each year?

A. $600
B. $1200
C. $3000
D. Zero

Answer: A
Explanation:

The straight-line depreciation takes the purchase value of the item, minus the salvage price
of the item, divided by the number of time periods. Calculation is (5000-2000)/5 = $600

Question No : 378 - (Topic 2)

Which of the following is NOT an input of close project process?

A. Project management plan


B. Contract documentation
C. Deliverables
D. WBS

Answer: D
Explanation:

WBS is NOT inputs of close project process.

100% Valid Questions - Guaranteed Success 137


PMI CA0-001 : Valid Questions

Question No : 379 - (Topic 2)

ISO Stands for __________.

A. International Organization for Standardization


B. International Standardized Organization
C. 'n Standardized Organization
D. Indiana Standardized Organization

Answer: A
Explanation:

ISO Stands for International Organization for Standardization.

Question No : 380 - (Topic 2)

Acceptance of the product should be ________.

A. Formal
B. Consistent
C. Personal
D. Verbal

Answer: A
Explanation:

The acceptance should be formal.

Question No : 381 - (Topic 2)

Which time estimating tools estimate the basis for activity durations can be quantitatively
determined by multiplying the quantity of work to be performed by the productivity rate?

100% Valid Questions - Guaranteed Success 138


PMI CA0-001 : Valid Questions
A. Parametric estimating
B. Funding limit reconciliation
C. Reserves analysis
D. None of the above

Answer: A
Explanation:

Parametric Estimating: Estimating the basis for activity durations can be quantitatively
determined by multiplying the quantity of work to be performed by the productivity rate.

Question No : 382 - (Topic 2)

Based on the PMBOK, who is ultimately responsible for the project quality?

A. Project team
B. Project manager
C. QA manager
D. Validation engineer

Answer: B
Explanation:

Project manager is ultimately responsible for the project quality.

Question No : 383 - (Topic 2)

Which of the following is not a form a leadership power?

A. Compromise
B. Smoothing
C. Foimal
D. Coercive

Answer: B
Explanation:

100% Valid Questions - Guaranteed Success 139


PMI CA0-001 : Valid Questions
smoothing is a conflict resolution technique, the rest are forms of leadership power.

Question No : 384 - (Topic 2)

Which one of the following comes first in the project plan?

A. Scope Statement
B. Quality Plan
C. WBS
D. Development Plan

Answer: A
Explanation:

Scope statement comes first in the project plan. Scope statement is the written statement
of project. It contains: Project objectives, Project justification, Project deliverables

Question No : 385 - (Topic 2)

You are creating your WBS and keep decomposing tasks into smaller units. How can you
tell when you are done?

A. Keep decomposing tasks until you reach an amount of work that is small enough to
reliably estimate required resources and duration.
B. Keep decomposing work until you reach a predetermined number of hierarchy levels to
keep the WBS balanced.
C. Keep decomposing tasks until you reach an amount of work that can be accomplished in
one DAY.
D. Keep decomposing tasks until you reach an amount of work that can be accomplished in
one WEEK.

Answer: A
Explanation:

Keep decomposing tasks until you reach an amount of work that is small enough to reliably
estimate required resources and duration.

100% Valid Questions - Guaranteed Success 140


PMI CA0-001 : Valid Questions

Question No : 386 - (Topic 2)

The Ishikawa diagram, Pareto chart, control charts, and statistical sampling are examples
of ________.

A. Quality assurance
B. Quality control
C. Quality rules
D. CMM

Answer: B
Explanation:

The Ishikawa diagram, the control charts, Pareto chart, and statistical sampling are
examples of basic tools of quality control.

Question No : 387 - (Topic 2)

You have been with the organization; you constantly hear rumours about a certain CAPM
failing to live up to the CAPM Code. What you should do?

A. You can gather as much information as you can before proceeding


B. Confront the person immediately
C. Ignore the rumours
D. ^ass the rumours along

Answer: A
Explanation:

You can gather as much information as you can before proceeding.

Question No : 388 - (Topic 2)

100% Valid Questions - Guaranteed Success 141


PMI CA0-001 : Valid Questions
Who applies project selection methods to decide whether to accept or reject a project?

A. Project sponsor
B. Project team
C. Project manager
D. Senior Management

Answer: A
Explanation:

The project sponsor must have the authority to select and fund the project.

Question No : 389 - (Topic 2)

Administrative Closure should occur ___________.

A. At the end of each phase of the project


B. At the end of the whole project
C. At the end of 50% of the project
D. At the end of 100% of the project

Answer: A
Explanation:

Administrative Closure should occur at the end of each phase, not only at the end of the
overall project

Question No : 390 - (Topic 2)

A complete set of indexed project records is called __________.

A. Project archives
B. Index
C. sow
D. Project History

100% Valid Questions - Guaranteed Success 142


PMI CA0-001 : Valid Questions
Answer: A
Explanation:

A complete set of indexed project records for archiving by the appropriate parties.

Question No : 391 - (Topic 2)

What is the communication channel delta if the members in the communication plan are
increased from 5 to 10?

A. 35
B. 5
C. 15
D. 75

Answer: A
Explanation:

Delta = n*(n-1)/2 - n1*(n1-1)/2 where n = individuals and n1 = new individuals 10-45 = 35


No of communication channels: n*(n-1)/2 where n = individual

Question No : 392 - (Topic 2)

Which of the following project document is best suited for tracking costs of resources?

A. Work breakdown structure


B. P'sk breakdown structure
C. Organizational breakdown structure
D. Resource breakdown structure

Answer: A
Explanation:

The resource breakdown structure organizes all resources in a hierarchical structure,


allowing for cost tracking also.

100% Valid Questions - Guaranteed Success 143


PMI CA0-001 : Valid Questions

Question No : 393 - (Topic 2)

The main purpose of project initiation is to ________.

A. Assign the project manager to the project


B. Formally describe the project
C. Produce the project charter
D. Formally authorize the project

Answer: D
Explanation:

Output of project initiation is formally authorizing the project. Output of project scope
initiation is: Project charter PM assigned Constraints and Assumptions.

Question No : 394 - (Topic 2)

How many communication channels will be required in a project in which 5 individual are
participating?

A. 10
B. 12
C. 4
D. 5

Answer: A
Explanation:

No of communication channels: n*(n-1)/2 where n = individual. In this case 5*(5-1)/2 = 10

Question No : 395 - (Topic 2)

100% Valid Questions - Guaranteed Success 144


PMI CA0-001 : Valid Questions
Who is responsibility for making sure that a message in the project team is understood

A. Project Manager
B. Sender
C. Project coordinator
D. Sponsor

Answer: B
Explanation:

The sender has to make sure that the receiver acknowledges the receipt and message is
understood, and the receiver needs to ensure that the sender received the
acknowledgement.

Question No : 396 - (Topic 2)

You are project manager of a project and as part of the team acquisition process; you hire
a new employee and assigns him to your project team. According to Maslow's hierarchy of
needs, what needs level he most likely is at?

A. Social need
B. Physical need
C. Safety and security
D. Security

Answer: A
Explanation:

as new to project he is most likely looking for acceptance and friendship. This comes under
Social need.

Question No : 397 - (Topic 2)

How many communication channels will be required in a project in which 5 individual are
participating?

100% Valid Questions - Guaranteed Success 145


PMI CA0-001 : Valid Questions
A. 10
B. 12
C. 4
D. 5

Answer: A
Explanation:

No of communication channels: n*(n-1)/2 where n = individual. In this case 5*(5-1)/2 = 10

Question No : 398 - (Topic 2)

Assumptions in the project plan should be _________.

A. Written down
B. Understandable
C. Not understandable
D. No need to write

Answer: A
Explanation:

Assumptions that are not written down are the most dangerous.

Question No : 399 - (Topic 2)

A Risk Register is a part of the ________.

A. Project Scope Statement


B. Project Management plan
C. Project Scheduling plan
D. Project Charter

Answer: B
Explanation:

The Risk Register is detailed part of the project management plan.

100% Valid Questions - Guaranteed Success 146


PMI CA0-001 : Valid Questions

Question No : 400 - (Topic 2)

Which document formally authorizes a project?

A. The project charter


B. Project scope statement
C. The P'oject contract
D. Project closing document

Answer: A
Explanation:

The project charter is the formal document for authorizes a project.

Question No : 401 - (Topic 2)

You are the project manager of a project. If there are approved changes to the original
scope, what you do with the old original scope?

A. Save the old versions


B. No need to save old version
C. Scrap the old version
D. Old version is not required

Answer: A
Explanation:

All the version you should keep in version control system.

Question No : 402 - (Topic 2)

_________ is the international organization that controls the standards for quality.

100% Valid Questions - Guaranteed Success 147


PMI CA0-001 : Valid Questions
A. ISO
B. CAPM
C. PMI
D. iscn

Answer: A
Explanation:

ISO is the international organization that controls the standards for quality.

Question No : 403 - (Topic 2)

What are the inputs for Initiation process?

A. Product description and Strategic plan


B. Selection criteria
C. Historical information
D. Al1 of the above

Answer: D
Explanation:

Inputs for Initiation process : Product description Strategic plan Selection criteria Historical
information

Question No : 404 - (Topic 2)

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are
examples of ____________.

A. Enterprise benefits measurement methods when selecting a project


B. Integral parts of the SOW
C. Ways to ensure stakeholder commitment
D. Project selection methods

Answer: A
Explanation:

100% Valid Questions - Guaranteed Success 148


PMI CA0-001 : Valid Questions

Projects are seeded from the recognition of a regulatory or business need. Cost benefit
analysis, scorecard modelling, payback periods, and internal rate of return are examples of
benefits measurement methods when selecting a project. Best Option is A.

Question No : 405 - (Topic 2)

Most change requests are a result of _______.

A. Value added change (enhancements)


B. Schedule constraints
C. Regulatory constraints
D. Improvement to the project scope

Answer: A
Explanation:

Most change requests (CRs) are a result of Value added change (enhancements).

Question No : 406 - (Topic 2)

Who is responsible for the creation of the final project plan?

A. Project Manager
B. Team Leader
C. Sponsor
D. Project Team

Answer: A
Explanation:

Project Manager is responsible for the creation of the final project plan.

Question No : 407 - (Topic 2)


100% Valid Questions - Guaranteed Success 149
PMI CA0-001 : Valid Questions
The end of the project comes after which of the following?

A. Project charter
B. Final deliverable
C. Schedule
D. QA activities are done

Answer: B
Explanation:

Project will close after final deliverable.

Question No : 408 - (Topic 2)

You are project manager and now in middle of creating RFP (Request for proposal). RFP
(Request for proposal) is done in _______.

A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements

Answer: A
Explanation:

RFP (Request for proposal) is done in Plan Procurements process.

Question No : 409 - (Topic 2)

You are the project manager of a project and budgeted money to provide cash awards to
team members that exceed expectations. A project team member that is motivated by the
chance to earn cash reward can most accurately be explained by which theory

A. Hierarchy of needs
B. Expectancy theory
C. Achievement theory

100% Valid Questions - Guaranteed Success 150


PMI CA0-001 : Valid Questions
D. Al1 of the above

Answer: B
Explanation:

The team member is working hard because he expects to be rewarded so it is Expectancy


theory

Question No : 410 - (Topic 2)

If a project with a SPI of 0.8, what you tell?

A. The project is running ahead of the schedule


B. The project is running behind of the schedule
C. Resources assigned to the project cost 1.8 units
D. None

Answer: B
Explanation:

The SPI equals the earned value divided by the planned value. SPI = EV/PV A schedule
performance index of 1 or greater suggests that the project is ahead of schedule.

Question No : 411 - (Topic 2)

A requirement document is an input of __________ process?

A. Collect Requirements
B. Define Scope
C. Integrated Change Control
D. Monitor and Control Project Work

Answer: B
Explanation:

A requirement document request is an input to Define Scope

100% Valid Questions - Guaranteed Success 151


PMI CA0-001 : Valid Questions

Question No : 412 - (Topic 2)

Project Quality Management includes:

A. Customer satisfaction
B. Prevention over inspection
C. Continuous improvement
D. Al1 of the above

Answer: D
Explanation:

Project Quality Management includes : Customer satisfaction, Prevention over inspection,


Continuous improvement, Management responsibility

Question No : 413 - (Topic 2)

__________ is providing detailed plans for tasks that are about to start in the near future
using the most current information and revisiting future activities when they near their
starting dates.

A. Rolling wave planning


B. Progressive elaboration
C. Milestone detail planning
D. Expert judgment

Answer: A
Explanation:

Rolling wave planning is providing detailed plans for tasks that are about to start in the near
future using the most current information and revisiting future activities when they near their
starting dates.

100% Valid Questions - Guaranteed Success 152


PMI CA0-001 : Valid Questions
Question No : 414 - (Topic 2)

When you are developing the estimates for project, you choose to add the individual
estimates for the activities that comprise each phase. What type of estimation method are
you using?

A. Parametric estimating
B. Bottom-up estimating
C. Top-down estimating
D. Analogous estimating

Answer: B
Explanation:

Bottom-up estimating: Estimating the cost of individual work items and then rolling up the
costs to arrive at a project total: It is more accurate. Analogous estimating: Analogous
estimating is also called top-down estimating and uses the actual cost of a previous, similar
project as the basis for estimating the cost of the current project. Parametric estimating:
Using project characteristics (or parameters) in a mathematical model to predict costs (e.g.,
price per square meter).

Question No : 415 - (Topic 2)

A contract cannot contain _____________.

A. Illegal activities
B. deadline for the completion of the work
C. Penalties and fines for disclosure of intellectual rights
D. Al1 of the above

Answer: A
Explanation:

A contract cannot contain illegal activities. A contract can contain other options available.

Question No : 416 - (Topic 2)

100% Valid Questions - Guaranteed Success 153


PMI CA0-001 : Valid Questions
______________ provides details about how the project scope may be changed.

A. Control Scope system


B. VeiirV Scope
C. Scope Charter
D. Scope Management plan

Answer: D
Explanation:

The scope management plan provides details about how the project scope may be
changed.

Question No : 417 - (Topic 2)

Which monitoring or controlling activities would not result in preventive action being
applied?

A. Control Scope
B. Manage project team
C. Quality control
D. Manage Scope statement

Answer: A
Explanation:

Scope, schedule, and Control Costs can all result in corrective action, but not preventive
action.

Question No : 418 - (Topic 2)

The intent of the risk management process group is to ________.

A. Increase the probability of positive outcomes in the project


B. Announce project risks
C. Not consider risks affecting the company

100% Valid Questions - Guaranteed Success 154


PMI CA0-001 : Valid Questions
D. Announce project deliverables

Answer: A
Explanation:

The risk management process group serves as the road map used to reduce its impact on
the project.

Question No : 419 - (Topic 2)

_______ is the road map for the execution of the project.

A. Project plan
B. sow
C. WBS
D. Strategic planning

Answer: A
Explanation:

Project plan is the road map for the execution of the project.

Question No : 420 - (Topic 2)

Which of the following statement is true about Strategic planning?

A. Strategic planning determines which projects will be choosing in order to achieve the
organizational goals
B. Strategic planning determines which projects will be sponsor in order to achieve the
organizational goals
C. Strategic planning determines these are the projects that get chosen and funded
D. Al1 of the above

Answer: D
Explanation:

100% Valid Questions - Guaranteed Success 155


PMI CA0-001 : Valid Questions
Strategic planning determines which projects will be choose or sponsor in order to achieve
the organizational goals. Strategic planning determines these are the projects that get
chosen and funded.

Question No : 421 - (Topic 2)

Which of the following are parts of project scope management?

A. Verify Scope
B. Collect Requirements
C. Control Scope
D. Al1 of the above

Answer: D
Explanation:

There are following processes which are part of Project Scope Management. Collect
Requirements Define Scope Create WBS Verify Scope Control Scope

Question No : 422 - (Topic 2)

You are project manager of a project. During the process of selecting the sellers, you reject
one vendor because it doesn't have the manufacturing capability. This is an example of
which selection tool?

A. Weighting system
B. Screening system
C. Seller rating system
D. Expert judgment

Answer: B
Explanation:

A screening system rejects sellers that does not meet minimum requirements for the
project.

100% Valid Questions - Guaranteed Success 156


PMI CA0-001 : Valid Questions

Question No : 423 - (Topic 2)

What is a corrective action?

A. An action that brings future project events Into alignment with the project plan
B. An action to correct something in the project
C. An action to prevent something in the project
D. Corrective action is not related to project

Answer: A
Explanation:

Corrective action: An action that brings future project events into alignment with the project
plan

Question No : 424 - (Topic 2)

Project just went into inclusion mode. This means that project __________.

A. Has become part of the business processes


B. Has been accepted by the sponsor and the client
C. Will be closed due to lack of resources
D. None of the above

Answer: A
Explanation:

inclusion mode: Has become part of the business processes. A contract cannot contain
_____________.

Question No : 425 - (Topic 2)

100% Valid Questions - Guaranteed Success 157


PMI CA0-001 : Valid Questions
At what point in a project do you have the highest probability that it will fail?

A. The beginning of the project


B. ^ust before the end of the project
C. QA Phase
D. Execution phase

Answer: A
Explanation:

Risk and uncertainty are the highest at the beginning or a project.

Topic 3, Volume C

Question No : 426 - (Topic 3)

You are the project manager of a project .You have just completed the Define Activities,
activity resources estimating, and Estimate Activity Durations processes. Which process
have you left out?

A. Control Schedule
B. Create WBS
C. Sequence Activities
D. Operations

Answer: C
Explanation:

The PMBOK places Sequence Activities between Define Activities and Estimate Activity
Resources.

Question No : 427 - (Topic 3)

To calculate the late start and late finish dates for a set of tasks , you must do :

A. An analysis of the critical path

100% Valid Questions - Guaranteed Success 158


PMI CA0-001 : Valid Questions
B. A forwards pass
C. A backwards pass
D. a and g

Answer: C

Question No : 428 - (Topic 3)

When should a project manager be assigned to a project?

A. As early in the project as feasible.


B. Preferably before much project planning has been done.
C. At least prior to the start of project plan execution.
D. All of the above.

Answer: D

Question No : 429 - (Topic 3)

Which of the following is not a tool or technique for a Source Selection?

A. Contract negotiation
B. Weighting system
C. Payment system
D. Screening system

Answer: C
Explanation:

Payment system is not a tool or technique for Source Selection. Other options are .

Question No : 430 - (Topic 3)

Which process group is for detailed resource assignments and responsibilities?

A. Human resources management plan

100% Valid Questions - Guaranteed Success 159


PMI CA0-001 : Valid Questions
B. Project charter
C. Aplan
D. Project management plan

Answer: A
Explanation:

Develop Human Resource Plan: Planning, identifying, documenting, and assigning project
roles, responsibilities, and reporting relationships to individuals or groups.

Question No : 431 - (Topic 3)

In which phase you define the final deliverable?

A. Closing
B. Execution
C. Planning
D. Initiation

Answer: A
Explanation:

Project will close after final deliverable. Final deliverables are defined in the closing phase.

Question No : 432 - (Topic 3)

Market conditions are a part of ________.

A. Enterprise environmental factors


B. Project management concerns
C. Organizational process assets
D. Cost factor

Answer: A
Explanation:

100% Valid Questions - Guaranteed Success 160


PMI CA0-001 : Valid Questions
Market conditions will influence all factors of procurement.

Question No : 433 - (Topic 3)

The planning processes are:

A. Define Scope, Resource planning, Estimate Costs, Schedule development. Define


Activities
B. Inputs, Control, Status reports, Risk management
C. Planning, Resource planning, Quality assurance, Risk control
D. Define Scope, Team development, Control Schedule, Budget control, Contract
administration

Answer: A

Question No : 434 - (Topic 3)

Define Scope involves subdividing the major project deliverables into smaller, more
manageable components to __________.

A. Improve the accuracy of cost, time and resource estimates


B. Define a baseline for performance measurement and control
C. Facilitate clear responsibility assignments
D. Al1 of the above

Answer: D
Explanation:

Define Scope involves subdividing the major project deliverables into smaller, more
manageable components to: Improve the accuracy of cost, time and resource estimates.
Define a baseline for performance measurement and control. Facilitate clear responsibility
assignments.

Question No : 435 - (Topic 3)

100% Valid Questions - Guaranteed Success 161


PMI CA0-001 : Valid Questions
A major assumption of all network scheduling methods is that the activity duration must be
_____.

A. Statistically dependent
B. Variance distributed
C. Statistically independent
D. Deterministic

Answer: C
Explanation:

Statistically independent

Question No : 436 - (Topic 3)

Which of the following is NOT input of Identify Risks?

A. Project Charter
B. Stakeholder Register
C. Pis'* Management Plan
D. Activity Cost Estimates

Answer: A
Explanation:

Project Charter is NOT input of Identify Risks.

Question No : 437 - (Topic 3)

Which of the following is an output of Define Scope?

A. PBS
B. Project Scope statement
C. WBS Template
D. Constraints

100% Valid Questions - Guaranteed Success 162


PMI CA0-001 : Valid Questions
Answer: B
Explanation:

Output of Define Scope is Project Scope statement.

Question No : 438 - (Topic 3)

At which stage, stakeholders have the maximum influence on a project?

A. Initial stage
B. Closing stage
C. Execution stage
D. None of the above

Answer: A
Explanation:

It is easy to make changes to project goals and approach at the initial stage. Stake holders
have maximum influence at Initial stage.

Question No : 439 - (Topic 3)

Which is the most risky phase of a project?

A. Planning
B. Closing
C. Execution
D. Control

Answer: C
Explanation:

The Planning phase is the phase with the least risk attached. The Execution phase of the
project is when you are using your resources at their highest level .

100% Valid Questions - Guaranteed Success 163


PMI CA0-001 : Valid Questions
Question No : 440 - (Topic 3)

Which document formally authorizes a project?

A. The project charter


B. Project scope statement
C. The P'oject contract
D. Project closing document

Answer: A
Explanation:

The project charter is the formal document for authorizes a project.

Question No : 441 - (Topic 3)

Which of the following best describes project scope?

A. The work that must be done in order to deliver a product with the specified features and
functions
B. The description of the project deliverables
C. The authorizing document that allows the project manager to move forward with the
project and to assign resources to the tasks
D. The process of planning and executing all of the required work to deliver the project

Answer: A
Explanation:

project scope: The work that must be done in order to deliver a product with the specified
features and functions.

Question No : 442 - (Topic 3)

You are project manager of a project and you are offering an estimate that you know will be
changed after the contract is signed is ___________.

100% Valid Questions - Guaranteed Success 164


PMI CA0-001 : Valid Questions
A. Bad practice
B. Unprofessional practice
C. Bacl f°r both tne buyer and seller
D. Al1 of the above

Answer: D
Explanation:

It is both bad and unprofessional to knowingly offer an estimate that is incorrect

Question No : 443 - (Topic 3)

A process that is not part of a Project Risk Management is:

A. Identification
B. Solicitation
C. Quantification
D. Response Development

Answer: B

Question No : 444 - (Topic 3)

Given the following estimates: Optimistic 3 days, Pessimistic 9 days, and most likely 6
days, what is the PERT weighted average?

A. 6
B. 4
C. 6.3
D. 6.1

Answer: A

Question No : 445 - (Topic 3)

Which is not the tools and techniques used in Contract Administration:

100% Valid Questions - Guaranteed Success 165


PMI CA0-001 : Valid Questions
A. Contract change control system
B. Contract negotiation
C. Payment system
D. Performance rating

Answer: B
Explanation:

Contract negotiation is not the tools and techniques used in Contract Administration.

Question No : 446 - (Topic 3)

Which describes how cost variances will be managed?

A. Cost management plan


B. Cost baseline
C. Cost estimate
D. Chart of accounts

Answer: A
Explanation:

Cost management plan describes how cost variances will be managed.

Question No : 447 - (Topic 3)

In which type of organization, a project manager is in complete control of the project?

A. Projectized organization
B. Balanced Matrix organization
C. Strong Matrix
D. Weak Matrix organization

Answer: A

100% Valid Questions - Guaranteed Success 166


PMI CA0-001 : Valid Questions
Question No : 448 - (Topic 3)

Identification of Mandatory Dependencies is done during which of the following process:

A. Sequence Activities
B. Develop Schedule
C. Define Activities
D. Estimate Activity Durations

Answer: A

Question No : 449 - (Topic 3)

You are the project manager for a Project. Project is a global project. Some peoples are
working from US and some are from India. Client says budget should not cost more than
$12 million. Because of the global concerns, the final budget must be in U.S. dollars. This
is an example of which of the following?

A. Internationalization
B. Budget constraint
C. Management constraint
D. Quality constraint

Answer: B
Explanation:

This is an example of a budget constraint. The budget must not exceed $12 million.

Question No : 450 - (Topic 3)

_________ is the best choice for buyer when the item is well defined.

A. Cost plus incentive fee


B. F'xed P|ice
C. Time and material
D. None

Answer: B

100% Valid Questions - Guaranteed Success 167


PMI CA0-001 : Valid Questions
Explanation:

Cost plus incentive fee is always the lowest risk for the buyer if the scope of work is not
well defined. Fixed price and purchase order are the best choice for buyer when the item is
well defined.

Question No : 451 - (Topic 3)

You are working with an organization and you found that one stakeholder not disclosing all
of the costs involved with an upcoming project. Rather, this CAPM is constructing a WBS
that does not include all the tasks necessary to get the project done. What you should do?

A. Talk to the CAPM about the WBS to see if you can rework it to reflect actual costs of the
project
B. Confront the other project manager immediately
C. Mail t0 PMI headquarters
D. Ignore it

Answer: A
Explanation:

You can talk to the CAPM about the WBS changes. If he or she refuses to change the
WBS, you have a responsibility to go to stakeholders and voice your concerns.

Question No : 452 - (Topic 3)

A Reserve Analysis is a technique for:

A. Estimate Activity Durations


B. Estimate Activity Resources
C. Sequence Activities
D. Define Activities

Answer: A

100% Valid Questions - Guaranteed Success 168


PMI CA0-001 : Valid Questions
Question No : 453 - (Topic 3)

__________ involves using project characteristics in a mathematical model

A. Analogous estimating
B. Life-cycle costing
C. Parametric modelling
D. Bottom up estimating

Answer: C
Explanation:

Parametric modeling : Using project characteristics (or parameters) in a mathematical


model to predict costs (e.g., price per square foot).

Question No : 454 - (Topic 3)

The buyer and seller are bound by the ________.

A. Contract
B. Responsibilities
C. WBS
D. Identification

Answer: A
Explanation:

The buyer and seller are bound by the contract.

Question No : 455 - (Topic 3)

When you are developing the estimates for project, you choose in a mathematical model to
predict estimate. What type of estimation method are you using?

100% Valid Questions - Guaranteed Success 169


PMI CA0-001 : Valid Questions
A. Parametric estimating
B. Bottom-up estimating
C. Top-down estimating
D. Analogous estimating

Answer: A
Explanation:

Bottom-up estimating: Estimating the cost of individual work items and then rolling up the
costs to arrive at a project total: It is more accurate. Analogous estimating: Analogous
estimating is also called top-down estimating and uses the actual cost of a previous, similar
project as the basis for estimating the cost of the current project. Parametric estimating:
Using project characteristics (or parameters) in a mathematical model to predict costs (e.g.,
price per square meter).

Question No : 456 - (Topic 3)

What are the outputs of Initiation process?

A. Project charter and PM assigned


B. Constraints
C. Assumptions
D. Al1 of the above

Answer: D
Explanation:

output of Initiation process : Project charter PM assigned Constraints Assumptions

Question No : 457 - (Topic 3)

Your company create software products, and introducing a new product. To determine the
characteristics and features of the new product line, you will have to perform ________.

A. Progressive elaboration
B. Stake holder's review

100% Valid Questions - Guaranteed Success 170


PMI CA0-001 : Valid Questions
C. p'an project life cycle
D. Fast backing

Answer: A
Explanation:

The process of determining the characteristics and features of the product of the project is
called Progressive elaboration. Progressive elaboration is carried out via steps in detailed
fashion.

Question No : 458 - (Topic 3)

An example of a project is:

A. Billing customers
B. Managing an organization
C. Constructing a building
D. Providing technical support

Answer: C

Question No : 459 - (Topic 3)

Which of the following must be measured regularly to identify variances from the plan.

A. Stakeholder requirements
B. Project performance
C. Control Schedule
D. Project controls

Answer: B

Question No : 460 - (Topic 3)

A project plan is:

100% Valid Questions - Guaranteed Success 171


PMI CA0-001 : Valid Questions
A. A formal, approved document used to guide both project execution and project control.
B. A document issued by senior management that provides the project manager with the
authority to apply organizational resources to project activities.
C. A narrative description of products or services to be supplie
D. A document describing the organizational breakdown structure of the company.

Answer: A

Question No : 461 - (Topic 3)

If a project with a CPI of 1.6, what you tell?

A. The project is consuming fewer resources than anticipated


B. The project is using fewer resources than anticipated.
C. The project is falling behind.
D. The project is running ahead of schedule.

Answer: A
Explanation:

A cost performance index of 1 or greater suggests that project in delivering more with less
money; so doing well. Option A is BEST fit for this. CPI = EV/AC (Earned value/ Actual
cost)

Question No : 462 - (Topic 3)

Which of the following plans is not done during the writing of a project plan?

A. Executive Communication
B. Risk Management
C. Quality Management
D. Scope Statement

Answer: A
Explanation:

Executive Communication may be a part of your communication process but not in project
plan.

100% Valid Questions - Guaranteed Success 172


PMI CA0-001 : Valid Questions

Question No : 463 - (Topic 3)

What involves determining what quantities are to be used to perform project activities.

A. Resource planning
B. Estimate Costs
C. Determine Budget
D. Control Costs

Answer: A
Explanation:

Resource planning :Planning, identifying, documenting, and assigning project roles,


responsibilities, and reporting relationships to individuals or groups.

Question No : 464 - (Topic 3)

Which is not included in Performance improvements :

A. Improvements in amount of overtime worked


B. Improvements in individual skills
C. Improvements in team behaviours
D. Improvements in team capabilities

Answer: A

Question No : 465 - (Topic 3)

Which of the following is an output of a Verify Scope process?

A. Formal acceptance
B. WBStemplate
C. SOW acceptance

100% Valid Questions - Guaranteed Success 173


PMI CA0-001 : Valid Questions
D. Rework

Answer: A
Explanation:

Output of Verify Scope is formal acceptance.

Question No : 466 - (Topic 3)

Your project team is composed of team members in three countries plus a contractor team
in a fourth country. What tool would optimize communication?

A. Extranet-based electronic document repository


B. Manual filing system
C. War loom
D. Verbal

Answer: A
Explanation:

An electronic document repository allows all team members access to the documents,
regardless of location.

Question No : 467 - (Topic 3)

Another term for top down estimating is:.

A. Analogous estimating
B. Life-cycle costing
C. Parametric modeling
D. Bottom up estimating

Answer: A

Question No : 468 - (Topic 3)

100% Valid Questions - Guaranteed Success 174


PMI CA0-001 : Valid Questions
You are the project manager of a project. Project is installing AC to hotel rooms. You have
done project cost and time estimates, told the customer that the estimates provided will be
accurate if the rooms meet the requirements like (wooden coated). This is an example of
which of the following?

A. Risk
B. Assumption
C. Constraint
D. Budget

Answer: B
Explanation:

This is an example of an assumption because estimates provided will be accurate if the


rooms meet the requirements like (wooden coated). A and C are incorrect because the
scenario did not describe a risk or constraint.

Question No : 469 - (Topic 3)

Customer formally accepts the deliverables of each project phase. This process is known
as ________.

A. Verify Scope
B. Quality Assurance
C. Quality Control
D. Quality Measurement

Answer: A
Explanation:

Verify Scope is the process of formally accepting the deliverable of a project or phase. A is
incorrect because EVM measures project performance. C is incorrect because quality
control is concerned with the correctness of the work, not the acceptance of the work. QA
is incorrect because this described the quality program for the organization as a whole.

Question No : 470 - (Topic 3)

100% Valid Questions - Guaranteed Success 175


PMI CA0-001 : Valid Questions
The scope management provides:

A. A basis for future decisions about the project.


B. A baseline to accomplish verification measures.
C. A baseline to evaluate potential scope changes.
D. All of the above.

Answer: D

Question No : 471 - (Topic 3)

You are the project manager of a project .You have just completed the Collect
Requirements and Define Scope. What should you do next?

A. Create WBS
B. Vei*<fy Scope
C. Value analysis
D. Control Scope

Answer: A
Explanation:

Create the WBS is the process that follows Collect Requirements and Define Scope.

Question No : 472 - (Topic 3)

You are the project manager of a project and the project is a month into the executing
phase. There are some cliques forming among the team members. Which leadership style
you follow for best outcome?

A. Supporting
B. Delegating
C. Coaching
D. Directing

Answer: C
Explanation:

100% Valid Questions - Guaranteed Success 176


PMI CA0-001 : Valid Questions
Situational leadership style is coaching. Coaching is best fit for this situation.

Question No : 473 - (Topic 3)

Lessons learned session should be held at what point in a project?

A. At the project conclusion


B. At key milestones
C. When risk events occur
D. When sponsor want

Answer: B
Explanation:

Although lessons learned should be held at project conclusion, they should be held
throughout the project any time.

Question No : 474 - (Topic 3)

If you are project manager for a Project and will need as many inputs to the initiation phase
as possible. Of the following, which is the best source of information for your project?

A. Historical information
B. WBS
C. Business plans
D. RBS

Answer: A
Explanation:

Historical information is the best input of the choices available. B is incorrect since the
WBS has not been created at this point of the project. C is incorrect since business plans
are not a likely input to the initiation process

100% Valid Questions - Guaranteed Success 177


PMI CA0-001 : Valid Questions
Question No : 475 - (Topic 3)

Analogous Estimate Costs is _________.

A. Generally Accurate
B. Generally less accurate
C. Bottom-up estimating
D. None

Answer: B
Explanation:

Analogous Estimate Costs is Generally less accurate . Analogous Estimate Costs Uses
Expert Judgment . It is used when reference projects are similar . It is useful in early
phases of the project.

Question No : 476 - (Topic 3)

You are the project manager of a project .You have just completed the Collect
Requirements and Define Scope. What should you do next?

A. Create WBS
B. Vei*<fy Scope
C. Value analysis
D. Control Scope

Answer: A
Explanation:

Create the WBS is the process that follows Collect Requirements and Define Scope.

Question No : 477 - (Topic 3)

A Change Control Board should be _______?

A. flexible

100% Valid Questions - Guaranteed Success 178


PMI CA0-001 : Valid Questions
B. Include the project manager
C. appropriate authority
D. al1 of the above

Answer: D
Explanation:

CCB should have all the mentioned characteristics.

Question No : 478 - (Topic 3)

Which of the following tools and techniques are commonly used in a Define Scope
Process?

A. Product analysis
B. Expert Judgment
C. Alternative Identification
D. All of the above

Answer: D

Question No : 479 - (Topic 3)

A Project Cost Management plan is created as a part of:

A. Develop Project Management Plan process


B. Control Costs process
C. Determine Budget process
D. Estimate Costs process

Answer: A
Explanation:

There is no separate process in the Project Cost Estimation knowledge area to develop a
cost management plan. It is devloped in Develop Project Management Plan process.

100% Valid Questions - Guaranteed Success 179


PMI CA0-001 : Valid Questions

Question No : 480 - (Topic 3)

Information should be communicated to __________.

A. Everyone in the communication plan


B. Everyone on the team
C. Sponsor
D. Team 'eacl

Answer: A
Explanation:

One of the most important tasks of the project manager during the Execution and Control
phases of the project is the management of information. All Information should be
communicated to everyone in the communication plan.

Question No : 481 - (Topic 3)

How many communication channels exist in a team of 10 members?

A. 45
B. 10
C. 30
D. 20

Answer: A
Explanation:

formula (N)(N - 1)/2 where N = no of people. Therefore calculation is (10*9)/2.

Question No : 482 - (Topic 3)

Cost benefit analysis, scorecard modelling, payback periods, and internal rate of return are
examples of:

100% Valid Questions - Guaranteed Success 180


PMI CA0-001 : Valid Questions
A. Enterprise benefits measurement methods when selecting a project
B. Integral parts of the SOW
C. Ways to ensure stakeholder commitment
D. Project selection methods

Answer: A
Explanation:

Projects are seeded from the recognition of a regulatory or business need.

Question No : 483 - (Topic 3)

Which of the following is not a part of the Earned Value calculations?

A. Unknown Unknowns
B. Project Budget
C. Known Unknowns
D. Amount of work completed

Answer: A
Explanation:

Unknown Unknowns is not part of the Earned Value calculations.

Question No : 484 - (Topic 3)

In which type of organization, a project manager is in complete control of the project?

A. Projectized organization
B. Balanced Matrix organization
C. Strong Matrix
D. Weak Matrix organization

Answer: A

100% Valid Questions - Guaranteed Success 181


PMI CA0-001 : Valid Questions
Question No : 485 - (Topic 3)

A Trend Analysis is best described as:

A. Examining project performance over time


B. Calculating Earned Value
C. Calculating Cost Variance
D. Analyzing performance of similar projects over time

Answer: A

Question No : 486 - (Topic 3)

You have a piece of equipment that was purchased for your project recently for $5,000 and
is expected to last 5 years in production. At the end of the five years, the expected worth of
the equipment is $2,000. Using the straight-line deprecation, what is the amount that can
be written off each year?

A. $600
B. $1200
C. $3000
D. $100

Answer: A
Explanation:

A is the correct answer. The straight-line depreciation takes the purchase value of the item,
minus the salvage price of the item, divided by the number of time periods. Calculation is
(5000-2000)/5 = $600.

Question No : 487 - (Topic 3)

Which of the following activity is not performed as part of the direct and manage project
execution process?

A. Monitor implementation of approved changes


B. Validate deliverables

100% Valid Questions - Guaranteed Success 182


PMI CA0-001 : Valid Questions
C. Staff, train, and manage the project team
D. Manage cisks and implement risk responses

Answer: A
Explanation:

In the direct and manage project execution process, approved changes are implemented
but monitoring of those changes is part of monitoring OR controlling project work.

Question No : 488 - (Topic 3)

Which process must occur after a project manager has been assigned to the project?

A. Collect Requirements
B. Develop the project charter
C. Develop the project statement of work
D. Develop project closing document

Answer: A
Explanation:

The Collect Requirements process occurs during project planning. Other options occur
during project initiation. Option D is associated with project closing. Collect Requirements is
the best option.

Question No : 489 - (Topic 3)

What is the purpose of the WBS?

A. To show which work elements have been assigned to organizational units.


B. To ensure that all work within a project is identified and defined within a common
framework.
C. To show the organizational structure of a program.
D. all of the above

Answer: B

100% Valid Questions - Guaranteed Success 183


PMI CA0-001 : Valid Questions

Question No : 490 - (Topic 3)

Which of the following is ensuring that all features and functions are included in a product
or service

A. Project scope
B. Project verification
C. Project control
D. Product scope

Answer: B
Explanation:

Project verification ensuring all features and functions are included in a product or service

Question No : 491 - (Topic 3)

Conformance to specifications document is one description of _________.

A. Quality
B. Scope
C. Integration
D. Procurement

Answer: A
Explanation:

Quality on a project means that you are conforming to a standard that is set before you
start the project.

Question No : 492 - (Topic 3)

Purchasing insurance is an example of __________.

100% Valid Questions - Guaranteed Success 184


PMI CA0-001 : Valid Questions
A. Transfer
B. Acceptances
C. Mitigation
D. Contingency

Answer: A
Explanation:

Purchasing insurance means transfer the risk to third party.

Question No : 493 - (Topic 3)

An activity that consumes no time or resource and shows only that a dependency exists
between two activities is called:

A. A milestone
B. A hammock
C. A dummy activity
D. a and c

Answer: C

Question No : 494 - (Topic 3)

The primary output of the project closing process ____________.

A. To formalize and distribute all information pertaining to the project closing


B. Lessons learned
C. To get customer and sponsor approval
D. Milestone list

Answer: A
Explanation:

The primary output of the project closing process is to formalize and distribute all the
information pertaining to the closing of the project.

100% Valid Questions - Guaranteed Success 185


PMI CA0-001 : Valid Questions
Question No : 495 - (Topic 3)

Stakeholder influence is greatest at the ______ of the project.

A. Beginning
B. Closing
C. Controlling
D. Executing

Answer: A
Explanation:

Stakeholder influence is greatest at the beginning of the project

Question No : 496 - (Topic 3)

You are the project manager and you have created a contract for your customer. The
contract must have ________.

A. Offer and consideration


B. Start date and acceptance of start date
C. Signatures and the stamp of a notary public
D. Signatures of all stakeholders

Answer: A
Explanation:

A contract must have Offer and consideration. Not all contracts demand signatures and
notary public involvement. Contract may specify a start date, but the Acceptance of the
start date is not needed for all contracts.

Question No : 497 - (Topic 3)

In an optimal organization structure, the project manager is:

A. Functional

100% Valid Questions - Guaranteed Success 186


PMI CA0-001 : Valid Questions
B. Weak matrix
C. Piojectized
D. Dedicated project team

Answer: D
Explanation:

Dedicated project team

Question No : 498 - (Topic 3)

Which of the following is NOT an input of Estimate Costs?

A. Earn Value Analysis


B. Scope Baseline
C. P'sk Register
D. Human Resource Plan

Answer: A
Explanation:

Earned value analysis is used during the execution of the project to determine resource
consumption versus planned

Question No : 499 - (Topic 3)

The activity that is most concerned with the current status of the project schedule is called
___________.

A. Project time management


B. Control Schedule
C. Monitoring and controlling
D. Al1 of the above

Answer: B
Explanation:

100% Valid Questions - Guaranteed Success 187


PMI CA0-001 : Valid Questions
Control Schedule: The activity that is most concerned with the current status of the project
schedule.

Question No : 500 - (Topic 3)

Project risk is defined as the cumulative effect of chances of ________ which will adversely
affect project objectives.

A. Likely events
B. Complex activities
C. Complex schedules
D. Uncertain occurrences

Answer: D
Explanation:

Uncertain occurrences can affect project objective.

Question No : 501 - (Topic 3)

Which type of network diagram allows you to depict four types of dependencies (finish-to-
start, finish-to-finish, start-to-start, and start-to-finish)?

A. Precedence Diagramming Method (PDM)


B. Gant Cnart Diagram (GCD)
C. Dependency Diagramming Method (DDM)
D. Arrow Diagramming Method (ADM)

Answer: A
Explanation:

The precedence diagramming method (PDM) supports finish-to-start, finish-to-finish, start-


to-start, and start-to-finish dependencies.

100% Valid Questions - Guaranteed Success 188


PMI CA0-001 : Valid Questions
Question No : 502 - (Topic 3)

Your project has a budget of $240,000 and is expect to last for 1 year, with the work and
budget spread evenly across all months. The project is now in the fourth month, the work is
on schedule, but you have spent $120,000 of the project budget. What is your COST
Variance percentage in this case?

A. -50%
B. 50%
C. 40%
D. 20%

Answer: A

Question No : 503 - (Topic 3)

With triangular distribution, the low, likely and high values are 20, 30 and 40, respectively.
The mean is _____.

A. 30.0
B. 22.5
C. 25.0
D. 27.5

Answer: A
Explanation:

mean = (20+30+40)/3= 30

Question No : 504 - (Topic 3)

Which of the following is NOT an example of a type of schedule report?

A. Gantt chart
B. Milestone chart
C. fishbone diagram
D. network diagram

100% Valid Questions - Guaranteed Success 189


PMI CA0-001 : Valid Questions
Answer: C

Question No : 505 - (Topic 3)

A scope management plan In which of the following scope management processes is the
scope management plan prepared?

A. Initiation
B. Collect Requirements
C. Define Scope
D. Verify Scope

Answer: A

Question No : 506 - (Topic 3)

You are the project manager of a project. Your project just went into integration mode. This
means that your project __________.

A. Has been accepted by the sponsor and the client


B. Will be closed due to lack of resources
C. Resources are being assigned to other areas of the business
D. None of the above

Answer: C
Explanation:

A project that ends in integration mode is the type of project where its resources are being
assigned to other areas.

Question No : 507 - (Topic 3)

Project scope is:

A. The work that must be done in order to deliver a product with the specified features and

100% Valid Questions - Guaranteed Success 190


PMI CA0-001 : Valid Questions
functions.
B. The features and functions that are to be included in a product or service.
C. A narrative description of work to be performed under contract.
D. a and b

Answer: A

Question No : 508 - (Topic 3)

Which of the following is a common characteristic of most project life cycle descriptions?

A. Cost and staffing are low at the start, higher towards the end. and drop rapidly as the
project nears completion.
B. The probability of successfully completing the project is highest at the start of the
project.
C. Stakeholders have the most influence on the final characteristics of the product at the
end of the project.
D. a and b

Answer: A

Question No : 509 - (Topic 3)

Which of the following is not part of project scope management?

A. Verify Scope
B. Collect Requirements
C. Create WBS
D. None of the above

Answer: D
Explanation:

e are following processes which are part of Project Scope Management. Collect
Requirements Define Scope Create WBS Verify Scope Control Scope

Question No : 510 - (Topic 3)


100% Valid Questions - Guaranteed Success 191
PMI CA0-001 : Valid Questions
Which is the most important element of a Project Management Plan that is useful in the
Develop Human Resource Plan process:

A. Risk Management activities


B. Activity Resource requirements
C. Budget Control activities
D. Quality Assurance activities

Answer: B

Question No : 511 - (Topic 3)

In PMBOK, the buyer is ________ to the project team.

A. Internal
B. External
C. Outside
D. Assigned

Answer: A
Explanation:

In PMBOK, the buyer is Internal to the project team.

Question No : 512 - (Topic 3)

Which type of network diagram is also referred to Activity-on-Node (AON) diagrams?

A. Precedence Diagramming Method (PDM)


B. Gantt Cnart Diagram (GCD)
C. Dependency Diagramming Method (DDM)
D. Arrow Diagramming Method (ADM)

Answer: A
Explanation:

The arrow diagramming method (ADM) is also referred to as activity-on-arrow (AOA)

100% Valid Questions - Guaranteed Success 192


PMI CA0-001 : Valid Questions
diagramming method. Precedence diagramming method (PDM) is also referred to as
activity-on-node (AON) diagramming method

Question No : 513 - (Topic 3)

You are the project manager for the software Project. This project must be completed
within one year. This is an example of which of the following?

A. Schedule
B. Assumption
C. Constraint
D. Planning process

Answer: C
Explanation:

A project that must be completed by a deadline is dealing with time constraints. A is


incorrect since the condition does not offer a schedule. B is incorrect because the condition
is not an assumption. D is also incorrect because this is not a planning process.

Question No : 514 - (Topic 3)

Which of the following is not a part of the project cost baseline but is included in the project
budget?

A. Management Contingency Reserve


B. Management Overheads
C. Project Management Planing
D. Activity Cost Contingency Reserve

Answer: A
Explanation:

The difference between the Cost Baseline and Funding requirement at Project completion
is Management Contingency Reserve. Management Contingency Reserve is not part of
project cost baseline.

100% Valid Questions - Guaranteed Success 193


PMI CA0-001 : Valid Questions

Question No : 515 - (Topic 3)

A Project Scope Management includes :

A. Initiation
B. Project Plan Execution
C. Overall Change Control
D. Report Performance

Answer: A
Explanation:

Project scope management includes: Initiation, Collect Requirements, Define Scope, Verify
Scope and Control Scope

Question No : 516 - (Topic 3)

A Project Manager is at the project kick-off meeting. He confidently states the vision and
mission for the project. This PM is exhibiting the following leadership style:

A. Hierarchal
B. Authoritarian
C. Charismatic
D. Associative

Answer: C

Question No : 517 - (Topic 3)

A Resource Leveling is a technique for:

A. Develop Schedule
B. Estimate Activity Durations

100% Valid Questions - Guaranteed Success 194


PMI CA0-001 : Valid Questions
C. Estimate Activity Resources
D. Sequence Activities

Answer: A

Question No : 518 - (Topic 3)

A change requests can occur due to:

A. An external event such as a change in government regulation.


B. An error or omission in defining the scope of the product.
C. An error or omission in defining the scope of the project.
D. all of the above

Answer: D

Question No : 519 - (Topic 3)

The project management plan:

A. Identifies all the steps and processes that will be used after a project is initiated
B. Steps needed to complete a project task
C. Prepared at the beginning and fixed throughout the execution of the project
D. Includes project charter

Answer: A
Explanation:

Project Management Plan: The project management plan provides the overall plan for
executing, monitoring, and controlling, closing the project.

Question No : 520 - (Topic 3)

When the version control numbers should change?

100% Valid Questions - Guaranteed Success 195


PMI CA0-001 : Valid Questions
A. Any change occurs
B. Major changes are made
C. Any change related to scope only
D. Only if minor changes are made

Answer: A
Explanation: If any change occur, the version control numbers should change.

Question No : 521 - (Topic 3)

Adjusting Leads and Lags is a technique for:

A. Develop Schedule
B. Estimate Activity Durations
C. Estimate Activity Resources
D. Sequence Activities

Answer: A
Explanation:

Adjusting Leads and Lags: Since the improper use of leads or lags can distort the project
schedule, the leads or lags are adjusted during schedule network analysis to develop a
viable project schedule. Tools and Techniques for Develop Schedule are : Mathematical
analysis,Duration compression,Simulation,Resource-leveling ,Project management
software,Adjusting Leads and Lags and Coding structure.

Question No : 522 - (Topic 3)

Which of the following relationship is used in the Arrow Diagramming Method [ADM] :

A. Start-to-Finish
B. Finish-to-Start
C. Start-to-Start
D. Finish-to-Finish

100% Valid Questions - Guaranteed Success 196


PMI CA0-001 : Valid Questions
Answer: B

Question No : 523 - (Topic 3)

A _______ is a series of actions bringing about a result.

A. Project plan
B. Process
C. Schedule
D. Flowchart

Answer: B

Question No : 524 - (Topic 3)

What are common types of cost-reimbursable contracts?

A. CPF
B. CPFF
C. CPIF
D. Al1 of the above

Answer: D
Explanation:

Three common types of cost-reimbursable contracts are CPF, CPFF, and CPIF Cost-Plus-
Fee (CPF), Cost-Plus-Fixed-Fee (CPFF) and Cost-Plus-Incentive-Fee (CPIF).

Question No : 525 - (Topic 3)

How many communication channels will be required in a project in which 10 individual are
participating?

A. 45
B. 12

100% Valid Questions - Guaranteed Success 197


PMI CA0-001 : Valid Questions
C. 10
D. 5

Answer: A
Explanation:

No of communication channels: n*(n-1)/2 where n = individual. In this case 10*(10-1)/2 = 45

100% Valid Questions - Guaranteed Success 198

You might also like