Professional Documents
Culture Documents
Well Engineering Guidlines For Hole Cleaning
Well Engineering Guidlines For Hole Cleaning
Hole cleaning has been shown to be the cause of most Non-Productive Time in drilling operations, with
increasing well complexity increasing the risk. Overlooking hole cleaning during planning and execution of
a well design will negate the benefits of even the most powerful drilling rig. The application of techniques
and best practices developed for the industry leading extended reach wells has been observed to reduce
the incidence hole cleaning related Non-Productive Time when applied to any deviated well.
By describing the physics of cuttings and techniques that can be applied to successfully monitor of the
condition of the well this guideline provides a basis to minimize the risk of Stuck Pipe and hole cleaning
Non Productive Time.
With the majority of hole cleaning related adverse drilling events occurring during tripping this guideline
1.0 Hole Cleaning
1.1 What is Good Hole Cleaning?
Practically a clean borehole is one that is has a cuttings distribution and build up that allows trouble free
current and subsequent operations. Thus, a borehole does not need to be free of cuttings to be defined as
‘clean’ and is relative to the operation being performed. A clean hole for drilling may not be the same as a
clean hole for tripping, casing, cementing, or running wireline.
All high angle wells will have cuttings beds formation, regardless of how efficient hole cleaning practices
are. The distribution of the cutting’s beds will dictate the measures required to move them and prepare the
hole for trouble free operation.
Indicative
Inclination
Description
Range
(degrees)
A relatively uninhibited mud system is used which allows the drilled solids to
dissolve, or disperse, into the mud. Large and frequent mud dilutions are
typically required to maintain acceptable rheologies.
Dispersion
More commonly relevant in large diameter top hole sections (>16”) which
include significant soft clay or shale intervals, though have allowed large
diameter high angle wells to be drilled effectively with poor hole cleaning
parameters where lithology has been appropriate.
1.3.2 Rotation
In vertical holes flow rate is the primary factor in hole cleaning as annular velocity distributed concentrically
around the drill pipe. The effect of high-speed drilling string rotation can encourage cuttings tor take a longer
transport path if significant viscous coupling between the rotating drill pipe and drilling fluid occurs. In an
inclined borehole the drill pipe will be on the low side of the borehole causing the flow velocity profile to
become eccentric, as shown in Figure 1. It is common in high angle wells that the flow velocity on the low
side of the well is zero.
Figure 1: Indicative flow velocity profiles in vertical and high angle wells
To enable the movement of cuttings in the a high angle well high speed drill pipe rotation is critical since
flow rate alone is unlikely to move cuttings unless the drill string is rotated above the threshold required to
initiate cuttings transport. Rotation can aid move cuttings into the highest fluid velocity increasing the rate
of hole cleaning.
Figure 2: The impact of rotation in a high angle borehole (to scale 12-1/4 in. borehole & 5
in. drill pipe)
Equipment including bent housing motors and underreamers may limit maximum rotary speed such that it
is not possible to achieve the rotary threshold required to initiate hole cleaning. However, higher rotary
speeds may be permissible depending on the conditions, for example by collapsing the underreamer cutter
blocks or rotating off bottom. Therefore the following points should be considered with all equipment run
into the well:
• Rotary limitations will vary according to tool, supplier and wellbore geometry.
• The maximum RPM should only be exceeded in agreement with the supplier, with consideration
for the wellbore geometry and drilling conditions.
• Rotary speed should be maximized at all times when circulating off bottom.
• Hole Cleaning is paramount, if a tool cannot clean the well it should not be below the rotary table.
Recommended Minimum
Hole Size Drill String Drill String
Flow Rate Flow Rate
(inches) Rotation Rotation
gpm (lpm) gpm (lpm)
rpm rpm
17-1/2 1200 (4550) >150 900 (3400) 120
12-1/4 1000 (3800) >150 800 (3030) 120
8-1/2 * 500 (1900) >100 350 (1330) 80
6* 250 (950) >100 175 (665) 80
* In holes sizes <8-1/2 in. the effect of rotation on ECD must be considered.
Table 3: Indicative recommended and minimum hole cleaning thresholds for common
hole sizes..
If either parameter drops below the minimum value hole cleaning will be compromised. Any time that
parameters drop below the minimum hole cleaning threshold should not be counted towards hole cleaning
time.
• Large diameter surface holes that are drilling soft dispersive formations will benefit from the use
of non-inhibited WBM to allow the hole to be cleaned with dispersion rather than mechanical
removal of the cuttings.
• When drilling nondispersive formations, OBM will generally improve results relative to WBM,
resulting from improved inhibition and gauge hole. The higher the hole angle the higher OWR will
be likely be required to improve available flow rates, manage ECD and improve annular cleaning.
• Mud that is being carried over from previous wells may be more difficult to keep within specification
due to the buildup of low gravity and colloidal solids. This will impact hydraulics and hole cleaning
efficiency.
• Shear thinning fluids with good low-end rheology (3 and 6 rpm readings) are required to support
cuttings in the low shear environment of the annulus. The 6 rpm reading should target 1.1 – 1.5 x
hole size (in inches).
• Rheology should be optimised to allow maximum flow rates to be used.
• Down-hole rheology should be confirmed using Fann 70 measurements to cover the well design.
• The barite sag qualities of should be sufficient to allow constant mud weight in the hole (ECD and
wellbore stability).
• A well specified, properly maintained and operated solids control system from shakers through to
centrifuges is critical in ensuring drilling fluids are maintained as clean as possible.
• If fluid rheology is not controlled and allowed to increase then fluid channeling shown in figure 1 &
Figure 2 will become more pronounced and reduce the hole cleaning effectiveness (also
increasing pump pressure and ECD)
• If fluid rheology is excessively reduced it will reduce hole cleaning effectiveness by reducing the
viscous coupling between fluid and drill string and allowing cuttings to settle quickly
• Does the BHA equipment selected limit available flow rate or rotational speed?
• Will slide drilling above 30 deg inclination be required? Little, if any, cuttings will be removed from
the hole while sliding, although they may be removed on returning to rotary drilling hole cleaning
will become increasingly difficult to maintain as the hole has been loaded up with cuttings.
• What hole size is required? Larger hole sizes are more difficult to clean, slide drilling and reduced
parameters are more easily tolerated in smaller hole sizes.
• Is a dispersive mud system going to be used with dispersive clays present? Dispersive systems
do not require as stringent hole cleaning practices, hole cleaning may not be an issue as rock
predominately dissolves into the mud.
• Has the BHA been tendency screened? Is the assembly design work with the directional tools to
meet planned trajectory, a significant number of unplanned trips for directional control has been
due to poor BHA tendency design (this will also increase tortuosity and impact drilling
performance).
• Has the Bit & BHA been vibration screened? Effective vibration screening will minimise the risk of
vibration related failure and unplanned tripping. BHA equipment requirements may limit the ability
to make stabilization changes due to tool stabilisers.
o A BHA with vibration characteristics may also drill a rugose and larger than gauge hole
which will create more cuttings and have cause reduced hole cleaning effectiveness.
• Is the BHA trippable?
o Are the stabilisers able to be tripped out of hole? (Stabiliser selection criteria are provided
in Table 4).
o Could stabiliser placement cause a BHA lock if tripping in dirty hole?
o Will BHA equipment allow minimum hole cleaning parameters to be applied if remedial
hole cleaning or backreaming is required?
While evidence suggests that these types of tools are effective in improving hole cleaning efficiency, if wells
are planned and drilled with parameters in excess of recommended hole cleaning thresholds for the hole
size then the justification for running these tools can be difficult. The downsides of running these types of
tools include extra makeup / breakout time, cumulative pressure drop increases impacting pump pressure
and ECD, and rental and redress costs. It should be noted the highest stepout wells drilled globally did not
use such equipment.
The times when hole cleaning tools may be considered useful include:
• Drill at maximum instantaneous ROP’s and then perform remedial hole cleaning operations as
required.
• Drill at a safe ROP at which the hole can be kept clean as it is drilled.
High instantaneous ROP’s and remedial hole cleaning may result in periods when the well unloads cuttings
at a rate that cannot be handled by the containment system. This alone may suggest that limiting the
instantaneous ROP and drilling at a steady rate which can be handled by the cuttings containment system
may be the prudent choice.
There are numerous scenarios that should be considered as part of the risk assessment process. For
example, if a problem occurred that prevented hole cleaning from being performed prior to a trip (such as
a wash-out or top drive failure), could the resulting risks be managed adequately?
2.0 Borehole Monitoring
• This very effective technique requires only information that is readily available and easily
interpreted on the rig floor.
• Rotating string weight, pick-up and slack-off weights, and torque is recorded every connection.
• These values are plotted over modelled curves which are prepared in advance. This is the “Torque
& Drag Roadmap” and is specific to the interval or operation.
• Theoretical modelled values can be updated and calibrated for changes in well execution from
plan.
• Any divergence in trends may indicate hole cleaning issues (drilling), or the presence of cuttings
beds (tripping or casing running).
• Techniques are provided for establishing whether cuttings beds are indeed the issue (default
position), or whether alternative factors may be of more significance (e.g. wellbore geometry).
• All assumptions should be included on the Torque and Drag roadmap to provide quality assurance
of the model.
• Torque and drag modelling has proven to be an excellent tool for monitoring cuttings bed build up,
but there are many actions that may be occurring that will not necessarily show up or may be
misinterpreted.
• Differential sticking, key-seating and wellbore instability effects should not be misinterpreted as
cuttings build up. The symptoms of these problems are different, and their identification underlines
the importance of collecting and interpreting the torque and drag data on an ongoing basis.
• The theoretical predictions must be of good quality. Not only is the software model important but
the input data must be good quality and continually calibrated against the actual measured values.
• Friction factors derived from offset wells will form the basis of the planning.
• Different software models will calculate compatible friction factors.
• Deadline measured hookload will be subject to sheave friction effects, at low angle or low drag this
will result in a reversal of weights. While measuring travelling block weight whilst moving may
provide an indication of affect, the quantified effect is proportional to total weight at time of
measurement.
• Cuttings must be suspended in the fluid column to contribute to hydrostatic pressure, cuttings beds
therefore do not contribute to the back-pressure in the annulus.
• Annular pressures are sensitive to small variations in mud weight and rheology.
• The transmitted pressure data is often not of sufficiently frequent to be of use for detailed analysis
and can be difficult to interpret in real time. Recorded data can reveal significant events which
have been missed by the real-time data but is only available after the event.
• The most significant limitation of PWD information is that it is plays no role when tripping in or out
when the risk of stuck pipe is greatest.
Despite these disadvantages, the information from these tools can be very useful. The PWD tool is an
excellent way to monitor down hole pressures in narrow mud weight window environments and can be used
to monitor changes in the drilling fluid that may impact the well. Similarly to torque and drag ECD roadmaps
can be built to monitor real-time data against modelled values for a range of expected flowrates.