Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

Lakhisarai Shekhpura Path Se Shishma Gramin Path

Quantities & Cost Estimate for R.C.C. Slab Culvert - No. x 2.00 m Span x 2.00 m Vent Height

1.266

3.000 2.000 3.000


0.600

0.447 0.12 0.150 0.020 mm Expansion Joint


0.400 0.300 40 mm Cover
0.240
0.200
0.150 M PCC M-15 0.700
1:3

0.100 M L/S Filling


1.800

0.100 0.100
1.3
0.150 1.500
0.100
1.400

0.064
0.064
0.107
0.600
0.100 2.100 0.100

0.200 PCC M-15 200mm Thick


0.600 0.700
1.300
1.500
2.100
2.300

Sectional Elevation
3.750

HALF PLAN

0.400
0.150
1 :3

2.090

0.100 0.697 0.100


1.400

0.100 0.600
0.200 0.200 m PCC M-15
1.097
1.297
1.897
2.097

Section of Return Wall


Quantities & Cost Estimate for R.C.C. Slab Culvert - No. x 2.00 m Span x 2.00 m Vent Height

Sl
SOR No. Description of Items Total Qty Unit Rate ( ) Amount ( )
No
1 2 3 4 5 6 7
1 11.1 Earthwork in excavation for structures as per drawing and technical
specifications Clause 305.1 including setting out, construction of shoring and
bracing, removal of stumps and other deleterious material and disposal upto a
lead of 50 m, dressing of sides and bottom and backfilling in trenches with
excavated suitable material.
Abutment 2 x 9.100 x 2.300 x 1.600 = 66.976
Return Wall 4 x 1.600 x 2.097 x 1.600 = 21.473
Floor Under Deck Slab 1 x 7.700 x 0.400 x 0.250 = 0.770
10% Qty Extra for Slope = 8.922
Total 98.14 cum 314.41 30,856.00

2 11.2 Sand Filling in Foundation Trenches as per drawing and technical specification
Clause 1108.
Floor Under Deck Slab 1 x 7.700 x 1.629 x 0.100 = 1.254
Total 1.25 cum 531.02 664.00

3 11.4 Providing PCC M 15 (1:2.5:5) concrete for plain concrete in open foundations
(II) complete as per drawings and technical specifications Clause 802, 803, 1202 &
1203
Abutment 2 x 9.100 x 2.300 x 0.200 = 8.372
Return Wall 4 x 1.600 x 2.097 x 0.200 = 2.684
Floor Under Deck Slab 1 x 7.700 x 1.736 x 0.150 = 2.005
Total 13.06 cum 5,354.59 69,931.00

4 11.4 Providing PCC M 15 (1:2.5:5) concrete for plain concrete in open


(II) foundations complete as per drawings and technical specifications Clause
802, 803, 1202 & 1203
Qty below GL :
Abutment 2 x 8.300 x 1.800 x 1.400 = 41.832
Return Wall 4 x 1.600 x 1.597 x 1.400 = 14.309
Total 56.14 cum 5,354.59 3,00,607.00

5 12.5 II Plain/Reinforced cement concrete (PCCM-20) in substructure complete as per


drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202 ans
1204
Qty above GL :
Abutment 2 x 7.500 x 1.000 x 1.800 = 27
Return Wall 4 x 1.900 x 0.749 x 2.090 = 11.889
Total 38.89 cum 6,227.83 2,42,200.00

6 12.5 II Plain/Reinforced cement concrete (PCCM-20) in substructure complete as


per drawings and technical specification Clauses 802, 804, 805, 806, 807, 1202
ans 1204
Abutment Cap 2 x 7.500 x 0.700 x 0.200 = 2.100
Dirt Wall 2 x 7.500 x 0.400 x 0.240 = 1.440
Return Wall Coping 4 x 2.200 x 0.400 x 0.150 = 0.528
Total 4.07 cum 6,227.83 25,347.00

7 5.2 Providing Bitumen painting over top surface of Abutment cap & inner vertical
surface of Dirt Wall including Heating the bitumen & cost of painting brush etc.
all complete.
Abutment Cap 2 x 7.500 x 0.700 = 10.500
Dirt Wall 2 x 7.500 x 0.240 = 3.600
Total 14.10 sqm 20.23 285.00
Sl
SOR No. Description of Items Total Qty Unit Rate ( ) Amount ( )
No

8 13.1 RCC M25 in Deck Slab :-- Providing and laying reinforced cement concrete in
superstructure (Deck slab M25) as per drawing and technical specifications
Clauses 800, 1205.4, 1205.5
1 x 7.500 x 2.560 x 0.240 = 4.608
Total 4.61 cum 6,855.14 31,602.00

9 13.2 Supplying, fitting and placing HYSD bar reinforcement in super-structure


complete as per drawing and technical specifications
Abutment Cap & Dirt Wall @ 75 Kg per Cum qty of
Concrete 3.540 x 75.00 = 265.500
Deck Slab @ 105 Kg per Cum qty of Concrete 4.61 x 105.00 = 484.050
Sub Total 749.550
Add 2% for Laps & Wastage = 14.991
Total in Kg = 764.54 Kg
Total in MT 764.54 ÷ 1000 = 0.760 MT 76,689.25 58,284.00

10 13.16 Providing and filling joint sealing compound as per drawings and technical
specifications with coarse sand and 6 per cent bitumen by weight
2 x 7.500 = 15.000
Total 15.000 RM 44.59 669.00

11 12.5 II Plain/Reinforced cement concrete (PCCM-20) in substructure complete as


per drawings and technical specification Clauses 802, 804, 805, 806, 807,
1202 ans 1204
PARAPET 2 x 8.000 x 0.400 x 0.600 = 3.840
Total 3.84 cum 6,227.83 23,915.00

12 10.45 Painting two coats including primer coat after filling the surface with synthetic
enamel paint in all shades on new, plastered / concrete surfaces as per drawing
and Technical Specification Clause 1701
Parrapet Wall (Sides) 4 x 8.000 x 0.600 = 19.200
Parrapet Wall (Top) 2 x 8.000 x 0.400 = 6.400
Parrapet Wall (Ends) 4 x 0.400 x 0.600 = 0.960
Total Punning Area 26.56 sqm 110.69 2,940.00

13 12.9 Providing Weepholes in brick masonary , Plain / Reinforced concrete


abutement , wing wall , return wall with 100 mm dia AC pipe extending through
the full width of the structure with slope of 1V: 20H towards drawing
2 x 12 + 4 x 4 = 40 Nos. 89.08 3,563.00

Total 7,90,863.00

Cost of 1 No SLAB CULVERT Size ( 2 m x 2 m) . = 7,90,863.00

You might also like