Review Test Submission: Constraint Mgt - Assign #3

Review Test Submission: Constraint Mgt - Assign #3

User Neerav Sareen


Course MGTS-352-CC51(1) - 2021 Fall - Operations Management
Test Constraint Mgt - Assign #3
Started 10/29/21 9:43 PM
Submitted 10/29/21 10:38 PM
Due Date 10/29/21 11:00 PM
Status Completed
Attempt Score 2 out of 2 points
 
Time Elapsed 54 minutes out of 1 hour and 30 minutes
Results All Answers, Submitted Answers, Correct Answers, Incorrectly Answered
Displayed Questions

Question 1 1 out of 1 points

If a production manager wanted to maximize the bottleneck to ensure it is never idle, which
step of the theory of constraint is this describing?

Selected Answer: C.
Exploiting the bottleneck

Answers: A.
Identifying the bottleneck

B.
Subordinating the bottleneck

C.
Exploiting the bottleneck

D.
Elevating the bottleneck

Question 2 1 out of 1 points

A business manufactures four products (A, B, C, D), each requiring a number of input
materials for production.  Information on each of the products, including selling price and
profit margin per unit, demand per week, and the number of each input required to produce
one unit of product is provided below.

It has been found that the business does not have enough butterfly clamps to meet the full
demand for all four products, and must thus find the “product mix” that maximizes profit. 
Please find the optimal product mix.  How many units of Product B will the optimal
product mix include?
Selected Answer:
52
Correct Answer:
Evaluation Method Correct Answer Case Sensitivity
Contains 52
Friday, October 29, 2021 10:38:35 PM MDT