Professional Documents
Culture Documents
Pune Metro Report
Pune Metro Report
Pune Metro Report
1 INTRODUCTION 1
1.1 General 1
1.2 Mission 1
1.3 Vision 1
1.4 Logo 2
1.5 Why Pune Metro? 3
1.6 About the Project 6
1.7 Project Breakdown 8
1.8 Execution of Construction 9
2 FOUNDATION
2.1 General 12
2.2 Objectives 12
2.3 Types of foundation 12
2.4 Open foundation 13
2.4.1 Materials 13
2.4.2 Construction Sequence 13
2.5 Pile foundation 18
2.5.1 Materials 18
2.5.2 Construction Sequence 18
2.5.3 Pile testing 22
2.6 Micro-pile 22
2.7 Critical case of open foundation 23
3 SUPERSTRUCTURE
3.1 General 25
3.2 Materials 25
3.3 Construction Sequence 26
3.4 Pedestal and Seismic Arrestor Block 31
4 CASTING YARD
4.1 General 33
4.2 Kasarwadi Casting Yard 33
4.2.1 Site location and site layout 33
4.2.2 Various parts of casting yard 34
4.2.3 Types of girders 35
4.2.4 Number of segments according to span 35
4.2.5 Concrete Details 35
4.2.6 Batching Plant 36
4.2.7 Casting of segments 36
4.2.8 Match Casting 37
4.2.9 Procedure for casting of segments 37
4.2.10 Components of mould 38
4.2.11 Types of beds 38
4.2.12 Duct profiling 38
4.2.13 Shuttering and De-shuttering 39
4.3 Kiwale Casting Yard 40
4.3.1 Site location and site layout 40
4.3.2 Types of girders 40
4.3.3 Construction Materials 40
4.3.4 Work Procedure 41
5 LAUNCHING GIRDER
5.1 General 49
5.2 Machinery and Equipment 49
5.3 Components of Launching Gantry 50
5.4 Procedure 51
5.5 Sequence of Segment Launching 52
5.6 Bearing 55
6 SAFETY MEASURES
6.1 General 56
6.2 Safety Measures 56
6.3 Safety Rules 58
6.4 Passenger Safety Features 58
6.5 Safety Rules in Maintenance Depots 60
7 QUALITY
7.1 General 62
7.2 Lab Testing 62
9 REFERENCES 73
Table 1 Internship Schedule
SUBJECT
DAY DATE
SHIFT 1 SHIFT 2
1 01/06/2019 Office Office
2 02/06/2019 Holiday
3 03/06/2019 Office Office
4 04/06/2019 Office Office
5 05/06/2019 Holiday
6 06/06/2019 Safety Induction Nashik Phata
7 07/06/2019 Office Range Hills
8 08/06/2019 Safety Induction Harris Bridge
9 09/06/2019 Holiday
10 10/06/2019 Nashik Phata Harris Bridge
Seminar on Traffic
11 11/06/2019 Casting Yard (Kasarwadi
Management and BBS
12 12/06/2019 Office Office
13 13/06/2019 Office Nashik Phata
14 14/06/2019 Office Casting Yard
15 15/06/2019 Office
16 16/06/2019 Holiday
17 17/06/2019 Nashik Phata Range Hills
18 18/06/2019 Launching Gantry Office
19 19/06/2019 Nashik Phata Launching Gantry
20 20/06/2019 Nashik Phata Launching Gantry
21 21/06/2019 Nashik Phata Launching Gantry
22 22/06/2019 Seminar on Quality Lab visit
23 23/06/2019 Holiday
24 24/06/2019 Casting Yard (Kiwale)
25 25/06/2019 Office Pre-tensioning
26 26/06/2019 Palkhi seva
27 27/06/2019 Casting Yard (Kasarwadi)
28 28/06/2019 Office Office
29 29/06/2019 Office Office
30 30/06/2019 Holiday
CHAPTER 1
INTRODUCTION
1.1 General
MMRCL-Maharashtra Metro Rail Corporation Limited (MAHA-METRO)
MAHA-METRO a Special Purpose Vehicle (SPV), 50:50 jointly owned company of
Government of India and Government of Maharashtra. The existing Nagpur Metro Rail
Corporation Limited (NMRCL) which would be reconstituted into Maharashtra Metro Rail
Corporation Limited (MAHA-METRO) for implementation of all metro projects including Pune
Metro Rail Project Phase-1 in the State of Maharashtra outside Mumbai Metropolitan Region for
the smooth implementation, execution and operations.
Project will be covered under the legal framework of the Metro Railways (Construction of
Works) Act, 1978; the Metro Railways (Operation and Maintenance) Act, 2002; and the Railways
Act, 1989, as amended from time to time.
1.2 Mission
To provide a safe, reliable, efficient, affordable, commuter friendly and environmentally
sustainable rapid public transport system for the Nagpur Metro Region.
1.3 Vision
To create an energy efficient Metro Rail System of International standard which will
enhance the quality of life of the citizens of Nagpur and be instrumental in the overall development
of the city by making it more vibrant & attractive and utilize the full potential of ‘Green Energy’ in
the form of Solar, Wind, etc.
1
1.4 Logo
The logo of any organization is the symbolic representation of the philosophy of the
organization and the values and goals for which the organization works to achieve. Pune Metro
Rail Project is under the entity Maharashtra Metro Rail Corporation Limited. The logo is the
identity of Maharashtra Metro and hence Pune Metro Rail have carried that logo and painted it
with the city's grandeur.
• The circle is a representation of Safety and ensures us that the commuters are in safe hands.
• The two bars at the bottom depicts elevated & underground rail tracks to be used for the Pune
Metro train travel.
• The words on top "महा मेट्रो" pumps up the excitement as it means a "Great Metro" and will add
a uniformity to all the metro rail projects in the state of Maharashtra dedicated to all the
citizens, senior citizens, visitors, tourists, children, students, etc.
Each colour in Pune Metro logo has it significance personifying the city.
• Orange symbolizes culture, warmth and happy nature of Pune
• Blue expresses the fluidity of water that surrounds the City and easy going life that Pune gives
us.
• Green represents the greenery and forest covering Pune. It also signifies the wellbeing and
hope of Punekars.
• While Purple symbolises a positive vision that inspires to move further.
Thus, the elegant and simple Logo of Pune Metro is a true representation of the service that
it is going to provide to the city and its residents.
2
1.5 Why Pune Metro
Pune, the cultural and historical capital of the state of Maharashtra, known as the ‘Queen of
Deccan’ due to its scenic beauty and rich natural resources.The birth place of holy Saint Tukaram,
Capital of the greatest warrior king of all time Chhatrapati Shivaji Maharaj who established
"Hindavi Swarajya", Social reformers Mahatma Jyotiba Phule, Savitribai Phule, Maharshi Karve,
home of great freedom fighters like Bal Gangadhar Tilak, Agarkar and Gopal Krishna Gokhale.
In last decades, the city witnessed a rise in population and people migrating from a
different part of the country for job opportunities. However, the sustainable infrastructure to
facilitate easy commute to the citizens was missing. Average travel time for citizens using public
transport in Pune is over ~100 mins a day.
Here in, Pune Metro, will help tackle all these issues, provide comfortable and convenient
commute in the city by significantly reducing the travel time by 75%. It will facilitate many
youths, students, professionals, etc. traveling to their destination. Metro rail will act as the back
bone to the public transport system of the Smart City Project and strengthen on various parameters:
Table 1.1
3
Travel Time Is excessive due to traffic Will reduce the travel time by around 50%.
congestions and traffic signals.
Cost Is high due to high fuel Will be much less as compared to cost of running
consumption & high fuel cost individual vehicles.
& more running time due to
traffic congestion.
4
Fig 1.3 Traffic Issue
Thus there is a need for a safe, reliable, efficient, affordable, commuter friendly and
environmentally sustainable rapid public transport system for the Pune Metro Region.
5
1.6 About the Project
Pune Metro project has been undertaken by MAHA Metro, a SPV (Special Purpose
Vehicle) of Government of India and Government of Maharashtra. The project intends to develop
world class metro stations and surrounding areas featuring the rich cultural heritage. Modern, Safe,
Secured, Comfortable and an integrated public transport system for the city of Pune and Pimpri -
Chinchwad will enhance the lifestyle of the citizens.
Table 1.2
No. of Stations
Alignment Corridor Rail Length
UG ELE
6
• The Fig. shoes the alignment map of Pune Metro Rail Line which includes Line 1 & Line 2
PARTICULARS DESCRIPTION
Integration facilities at Metro stations include approach roads to the stations, circulation
facilities, pedestrian ways and circulation areas for various modes likely to come to important
stations, including feeder buses.
7
1.7 PROJECT BREAKDOWN
8
1.8 EXECUTION OF CONSTRUCTION
Methodology adopted for the construction are given in the Table 1.4
Table 1.4 Methodology adopted for Construction
Sr No. Element Type Construction Grade of
Methodology Concrete Used
Adapted
1 Foundation Open foundation- used Mechanical M35
in piers Excavation
9
Concreting by
Normal pier: when Boom placer
footing cl and From transit
Mixer.
Rail cl is same
Cantilever pier: when
footing cl
and rail cl is different
Remaining height: a
mixture of
Crushed sand (zone-ii)
and GSB
(granular sub base)
10
6 Bearings Type: elastomeric bearings
As all the spans are less than 45 m (as per the technical
Specifications in tender. Pot PTFE bearings used for higher
Loading Conditions (more than 45m span)
11
CHAPTER 2
FOUNDATION
2.1 General
The lowermost part of any structure is known as Foundation. The main objective of
foundation is to transfer the load coming from superstructure to the soil.
2.2 Objectives
The main objectives of the foundation are as follows
Distributetheweightofthestructureoverlargeareatoavoidoverloadingofthe soil beneath
Load the sub- stratum evenly and thus prevent unequal settlement.
To provide a level surface for building operations.
Take the structure deep into the ground and thus increase its stability, and prevent
overturning.
FOUNDATION
SHALLOW DEEP
FOUNDATION FOUNDATION
12
2.4 Open Foundation
When the hard strata is found at shallow depth it is recommended to lay down the
open foundation below the structure.
2.4.1Materials
The materials used for construction of open foundation are given in Table 2.1
CONCRETING
DE-SHUTTERING
CURING
13
2.4.2.1 Setting Out of Open Foundation
Survey is conducted out using the total station and the pier points are marked on the site
using iron pegs.
The co-ordinates of selected points are recorded and are submitted to the GC before the
start of the activity
Dimensions of excavation are suitably increased for placing and removal of shutters and
for shoring arrangements.
14
Fig 2.4 Laying of PCC
For provision of proper cover, cover blocks are placed at sides and bottom.
In the process of tying reinforcement for foundation, pier reinforcement is also tied in its
position.
A working tower using scaffolding pipes with working platform are made to support the
pier reinforcement vertical.
If the reinforcement of pier is very high, the reinforcement is cut to a workable length and
the balance reinforcement is tied with alternate laps after casing of the footing.
15
Fig 2.5 Open foundation Reinforcement
16
After the final setting time, curing is started.
Curingisdonebyusingpoundingmethodorhessianclothandsprinklingwateratregular
intervals.
Sometimes, curing compound can be used.
Concrete is placed by below of temperature 35Celsius.
Slump is maintained 125mm (+ or -25mm).
2.4.2.7 De-Shuttering
After 24 hours, the de-shuttering is started.
De-shutteringisdonecarefullytoavoidanydamagestotheedgesoftheopenFoundation
Concrete.
All the shuttering materials are lifted and stacked properly above ground level.
After removal of shutters from the excavation pit, the earth excavated earlier is used for
backfilling of the foundation area.
2.4.2.8 Curing
Open Foundation top & 4 sides are cured for 21days.
Cement mortar bunds to be provided on open foundation.
The sides are covered with hessian cloth & continuous water sprinkling to be maintained
till back filling started.
Further curing is to be ensured by keeping the backfilling moist with water.
17
2.5 Pile Foundation
Pile foundations are deep foundations used when the site has weak shallow bearing
strata making it necessary to transfer load to deeper strata either by friction or end bearing
principle.
2.5.1 Materials
The materials used for construction of pile foundation are given in Table 2.2
Sr No Description Specification
1 Cement OPC 53 Grade- IS 8112/IS12269
2 Reinforcement Steel Fe500D-IS 1786
3 Coarse Aggregate IS 383
4 Fine Aggregate IS 383
5 Water IS 456
6 Concrete Mix M35
7 Binding Wire IS 280
BORING OF PILE
LOWERING OF CAGE
CONCRETING
18
2.5.2.1 Setting Up for Each Pile Point
Survey is conducted out using the total station and the pier points are marked on the site
using iron pegs.
The co-ordinates of selected points are recorded and are submitted to the GC before the
start of the activity.
19
Fig 2.7 Auger used for boring
20
Tremie fixing & removing records are recorded in the checklist.
2.5.2.6 Concreting
The pile requires more strength hence, the mix for pile containing 400 kg/m3 cement
content and 20 mm maximum size of aggregate is prepared.
The cubes are made of this mix and is tested for consistency.
The hopper is attached and tremie pipes are wetted with water before commencing the
concrete works.
Concrete is poured in the stopper plate fitted above the hopper at the neck of the hopper.
The stopper plate is removed and then concrete is released into the tremie pipe.
Tremie pipes are removed in stages during pouring of concrete ensuring that tremie bottom
always penetrate the previously placed concrete.
The top of concrete in a pile are brought to 1.0 meter above the cut-off-level to remove
weak concrete and to ensure good concrete at cut off level.
The casting height of concrete above the cut off level is decided by GC after the
inspection.
After completing the pile concrete, the hopper and the tremie pipes are removed and
cleaned properly.
After completion of pile concrete, casing is removed by using a crane without disturbing
the bank.
When a casing is being extracted sufficient quantity of concrete is maintained within the
bore to avoid necking of the pile.
Bored muck is placed temporarily adjacent to the pile under construction and subsequently
21
disposed off in an environment friendly manner.
Concrete slump is 150 to 180 mm.
Pile is tested after it is placed. Two tests should be performed on the pile viz., Pile
Integrity test and Cross Sonic Echo Logging Test.
3.5.3.1 Pile Integrity Test
Pile integrity testing using low strain tests such as the TDR (Transient Dynamic
Response) method, is a rapid way of assessing the continuity and integrity of concrete
piled foundations.
The test measures: Pile length, or depth to anomalies Pile head stiffness Pile shaft
mobility – which is dependent on pile section and concrete properties. The software also
produces computer simulations and impedance profiles of the test result, to analyse in
detail any intermediate pile shaft responses.
The test is based on wave propagation theory.
This procedure is performed with a handheld hammer to generate an impact, an
accelerometerorgeophoneplacedontopofthepiletobetestedtomeasuretheresponse to the
hammer impact, and a data acquisition and interpretation electronic instrument.
ThismethodiscoveredunderASTMD5882-16-Standard Test Method for Low Strain
Integrity Testing of Piles.
3.6.1 Details
Piles are of 0.3 m diameter
Micro piles are provided to give support to existing structure.
I Shaped Beams (ISMB-Indian Standard Medium Beams) are inserted inside the bored
pile.
Steel plates are attached to I beam from both sides to give it more strength.
7 Group*40 piles = 280 micro piles are provided between NP20 to NP27.
22
C/C distance between micro piles is 375 mm.
Boring is done by Auger Boring Machine.
23
Fig 2.9 Micro Piles
24
CHAPTER 3
SUPERSTRUCTURE
3.1 General
A Pier and Pier Cap is termed as superstructure for a bridge like structure or Metro. A
pier is a member that resists the lateral force mainly by a shear mechanism. The simplest
cross section of the pier is square, or rectangular, but other shapes are also common. Pier
support the spans of the bridge and transfer the loads from superstructure to the foundation.
Piers should be strong enough to take the both vertical and horizontal load. They are subjected
to huge axial loads and bi-axial moments and shear forces in transverse and longitudinal
direction. Pier are usually compression elements of a bridge.
Pier Cap / Headstock is the component which transfers loads from the superstructure
to the piers. Pier cap provide sufficient seating for the Bridge girders and disperse the loads
from the bearings to the Piers. The upper or bearing part of a bridge pier; usually made of
concrete or hard stone; designed to distribute concentrated loads evenly over the area of the
pier.
3.2 Materials
The materials used for the construction of the pier and pier cap are shown in Table 3.1
Table 3.1 Materials for pier and pier cap
Sr No Description Specification
OPC 53 grade
Cement
1 IS 8112/ IS 12269
2 Reinforcement steel Fe 500 - IS 1786
3 Coarse aggregate IS 383-1970
4 Fine aggregate IS 383-1970
5 Water IS 456-2000
6 Concrete mix M60
25
3.3 Construction Sequence
The construction sequence of the pier is shown in Fig 3.1
STARTER CONCRETING
CURING
26
beveled on four sides are embedded.
• The wooden pieces are loosened and removed before next pour without damaging the
concrete.
• The top surface is finished rough using wire brush.
• The shutters are removed after 24hrs from the time of placing of concrete.
• Hessian cloth are spread over the starter concrete and curing is started by sprinkling water
over it
27
• Alternate laps are provided in the main reinforcement.
• G.I. Binding wires are used for tying of reinforcement.
• Once all the reinforcements have been tied then the staging formed using heavy duty
towers are removed for placing the pier shutters.
28
Shuttering Oil.
• All the joints are suitably bolted and tightened.
• All the joints are flushed and no projections are allowed.
• After the vertical placing of shutter, the co-ordinates of pier and pier cap are checked using
total station.
• Working platform are made at the top of the pier Cap to facilitate the concreting work of the
pier and Pier Cap.
• Top level of the pier and Pier Cap shutter is checked using the auto level instrument and
are marked in the shutter.
29
3.3.4 Concreting of Pier and Pier Cap
• M60 Concrete mix is required for the pier and it is prepared at batching plant in the
casting yard.
• The concrete is then transported to the respective site using transit mixers.
• Tremie pipes are lowered inside the pier mould and a concrete hopper are fixed at the top.
• Concrete is placed with the help of Boom placers/concrete pumps in layers.
• The concrete is checked for consistency & cubes are casted.
• The height of free fall of concrete is restricted to 1.5m and the layer thickness is not more
than 300mm.
• After pouring of each layer the same is vibrated with the help of mould vibrators and
needle vibrators.
• The frequency of the compaction is at each layer of concrete pour.
• The vibration process should not be carried out for long time since it can lead to the
segregation of concrete.
• Top level is levelled and finished smoothly.
• Maximum height of concrete pouring is 15m.
• After completion of concreting, curing is done in the exposed areas after the final setting
of concrete.
• Concrete slump value is 125mm (+ or - 25mm).
• The temperature should be maintained below 35 Celsius.
30
Fig 3.5 De-shuttering of Pier
3.3.6 Curing
• Curing is done for 21 days by tying hessian cloths all over the pier and Pier Cap by
continuous sprinkling of water over it for a period of not less than 21 days.
• Curing is done with application of curing compound.
• Red Coloured curing compound has been used on site for curing of pier and pier cap.
31
• It is placed centrally on the pier cap and prevents the movement of the segments.
• RCC pedestal and seismic arrestor block are provided above the pier cap
32
CHAPTER 4
CASTING YARD
4.1 General
Casting Yard is a confined place where all the concrete structures like segments,
parapets, I-girder, T-girder etc. are manufactured, shifted to their stack, cured for a specific
period and then shifted to their stack, cured for a specific period and then shifted to the site after
they gain the required strength.
33
Fig 4.2 Casting yard layout
34
4.2.3 Types of Girders
• Box girder
• U girder
• I girder
Out of above types, box girders are used in Pune metro project.
SPAN(m) 22 25 28 31 34
NO. OF SEGMENTS 8 9 10 11 12
35
Also, to avoid shrinkage cracks, Bajaj Polyfibre is used, but only in segments subjected to
temperature variation. The quantity of Bajaj Polyfibre used is 227g/m3 of concrete.
In long-line casting, all segments are cast on a soffit the full length of the cantilever (or half length
if the cantilever is symmetrical). All geometric control is accomplished while constructing the
36
soffit, greatly simplifying control during segment production. A full soffit constructed for the long-
line method, however, requires a large area, and the soffit might only be used once because it is
difficult to accommodate variation s for different bridge spans. With this method, the first segment
is cast between bulkheads and successive segments are cast between a movable bulkhead on one
end and the previously cast segment on the other.
37
3. Duct profiling
4. Concreting
5. Initial settlement
6. De-shuttering
7. Curing
38
4.2.13 Shuttering and De-shuttering
MIVAN shutters are used. The bed is prepared/aligned according to design. The end
segments are cast differently on short beds, while the intermediate ones are cast later on long bed.
Hence, side shutters are fixed first, and then a bulkhead is placed on one end, while on other end,
end segment supporti is already present. Shuttering process takes 30-45 minutes, while inner
shutter takes 15-30 minutes for placing, and 2 labourers do alternate shuttering. Inner shutter is
fixed using a track arrangement and jacking rods attached to the shutter.
De-shuttering is done after 20 MPa strength is attained by concrete, according to IRC-SP 65.
It is generally attained between 30-36 hours. The strength is tested using cubes of concrete cast
during segment casting.
39
4.3 Kiwale Casting Yard
4.3.1 Site location and site layout
Girders
Reinforced
Pre-stressed
cement
concrete
concrete
40
• Fabricated formwork
• Concrete
• Shuttering release agent
• Anti-corrosive treatment chemical
41
• Then again dipping it into the sealant solution to arrest the coat on the bar. After it gets
touch dry, the reinforcement steel is shifted to the desired location on the
casting yard.
C. Shifting of cut and bend pieces of reinforcements to casting location.
• The cut and bend pieces of reinforcements shall be worked out as per the approved
BBS provided by site engineer.
• The cut and bend pieces shall be matched as per BBS before shifting to casting location
and due care being taken to avoid the reinforcement from sticking of mud and coating of
other unwanted materials.
D. Fabrication and assembling of rebar cage:
• Number of Rebar cage shall be made as per Requirement in order to meet the
Schedule submitted above.(Typical Cycle time)
• Rebar Cage shall be shifted with the help of Lifting Beam as per requirement and
length of girder.
• Fabrication of rebar cage for PSC girder shall be done at a designated platform away
from the casting platform. Fabrication of platform for rebar cage shall be done as per
approved GFC drawing.
• All reinforcements of PSC girder shall be tied as per GFC drawing.
• Minimum lap length shall be provided in staggered manner for rebar as per approved
42
GFC drawing
• Temporary supports (if any) shall be provided in between the cage at suitable
locations to support the reinforcements so that the whole assembly shall be made
fixed.
• The fixing of rebar cage shall be done on soffit of girder.
• Approved make of Cover block with required dimension & shape shall be placed at
adequate intervals so that the uniform cover shall be available at all locations.
• Cover block shall be same grade as concrete of PSC girder.
E. Formwork Fixing
• The formwork shall provide a smooth finish of uniform texture and appearance
• Ensuring necessary care will be taken, the form work in true to line levels, plumbed,
rigid, adequately braced both horizontally and vertically. Form joints shall be
minimized as much shall be tight and shall not permit any leakage of slurry from
concrete.
• Required formwork shall be made out of steel shutters to suit the site.
43
• The formwork shall be so removed as not to cause any damage to the concrete.
• Formwork shall be gradually and uniformly lowered so as the concrete to take
stresses due to its self-weight to avoid any jerk or vibration.
• Before re-use all components of formwork shall be examined for damage and
damages shall be rectified. Also, they should be cleaned of deposits of soils
concrete or others unwanted materials. Threaded parts shall be oiled after cleaning.
F. Pre-tensioning Work procedure
The entire work procedure for casting of girders is sub-divided into following activities:
I. Cutting of HT Strands
Coils should be kept on elevated stand. Strands shall be cut to the required length by using
abrasive cutting tool. Strands should be cut on the platform with proper safety arrangements so
as to avoid contact with any foreign material such as dust, water etc.
II. Threading of strands
15.2 mm dia. H. T. Strands shall be inserted one by one from dead end bulkhead to jacking end
bulkhead through end shuttering and reinforcement cage. De bonding tubes (20 mm ID 24mm
OD) of specific dimensions are to be placed in position for strands as per drawing.
III. Tensioning & De-tensioning of Strands
1. Barrels & wedges are fixed to H. T. Strands on both the sides. i.e live end (LE) and Dead
End (DE).
2. Slackness in the strands is removed one-by-one by applying a pressure of 20-30 kg/cm2
(approx.) with single pull jack from Live end (LE)
3. All H. T. Strands are stressed one by one to the desired value from the side of Live end (LE)
with the help of Monojack or Single Strand Jack.
4. Stressing operation shall be carried out as under:
44
Fig 4.10 Setup for pre-tensioning
• Initial pressure of 50 kg/cm2 shall be applied at the Live end (LE) to remove the slack of
the H. T. Strand.
• Mark the position of Piston at Live end (LE) and Elongation of the strands shall
be measured by reading the distance moved by the piston of the jack with
respect to initial reading recorded from the piston.
• The pressure shall be increased at regular intervals as per the rate of stress
specified in approved drawing and the extent of elongations is noted down from
the datum marks on the jack piston. Net elongations are calculated accordingly.
• After reaching the desired pressure / elongation, anchorages shall be locked.
• Jacks shall be released thereafter and shall be mounted on the next strands.
• Slips, if any shall be measured accurately and subtracted from the elongation
to arrive at net elongation.
5. Debonding tube shall be repositioned and sealed the end by epoxy or PVC tape after stressing
all the strands.
45
• Concrete of specified grade shall be prepared & mixed as per the approved mix design
at batching plant using materials from approved sources.
• Workability & temperature shall be checked & maintained as established as per
approved mix design Refer-IS:7861 Part I & II.
• Concrete shall be transported to casting location in transit mixer & conveyed to the
pouring location with the boom placer / static pump concrete bucket as per site
condition with uniform rate of pour.
• Concrete shall be poured in individual layers of maximum 300mm thick & shall be
compacted uniformly with high frequency electrical needle vibrator of 60mm /40mm
size or shutter vibrators.
• Concrete shall be poured from working platforms which are installed over the outer
shutters for uniform pouring throughout section.
• While inserting the vibrator, care shall be taken that it does not damage the inserts
• Concrete shall be placed into the form gently and shall not drop from height more than
1.5m.
• Special care shall be taken to fill the concrete at corner and joint locations.
• The concrete at top surface of the soffit portion & web portion shall be finished
properly with required level
• The excess concrete shall be removed from the steel shutter immediately after finishing
the pour.
• Protection measure for green concrete to done like as covering with tarpaulins.
Sprinkling of water till initial setting of concrete.
46
• Immediately after initial setting of concrete exposed surface of concrete shall be cover
with wet hessian cloth.
• After final setting of concrete removal of formwork, curing shall be done by continuously
wetting the surface with water soaked hessian cloth and ponding of water on flat surface
if required.
• Girder shall be water cured for a minimum period of 21 days from its date of Casting.
• Sufficient pumps and piping arrangements shall be provided for curing the curing shall be
done initially on casting bed till the structure element achieve required strength for lifting
and stacking. Further curing shall be continued in stacking bed.
9. If required compressive strength of concrete is obtained as mentioned in GFC, de-
shuttering of end shutter and de-stressing can be done.
IV. De-Stressing:
The de-stressing operation shall be carried out sequentially in the following steps:
• The de-Stressing jacks which are placed at 2 specific locations on the concrete anchor
block depending upon the CG of the entire system, as per approved on GFC drawing.
• The 88% ram of the jack is kept upon which means if the total stroke length of the jack is
250mm then the ram shall be protruded out by approx. 220mm.
• When in stressed condition, the locking key shall bear the load, however the jack ram in
protruded condition will be touching the horizontal beam.
• After the concrete achieves required strength, the jack shall be activated and roughly 5 to
10 mm ram length shall be extended further. Thus the locking key will get free /unlocked
and shall be removed with the help of gantry/Suitable crane.
• Now the load will be completely on the jacks and slowly the load is released thereby the
ram gets retrieved into the jack. The cables relaxing takes place and de-stressing
operation gets completed
• Once the strands are free (un-tensioned) then these strands are cut at the end as well as in
between the girder positions by sharp girders as per specifications.
• The sequence of cutting the strands should be symmetrical or as per specification and
approved in GFC drawing.
47
10. Excess lengths of H.T. Strands are cut at the ends of all the girder ends and formwork
is removed as Per IS 456 and the T-girder is lifted to stacking yard.
48
CHAPTER 5
LAUNCHING OF GIRDER
5.1 General
Segmental construction is precast segmental superstructure, constructed by span-by span
method of construction. Precast segmental superstructure can be further classified as simply
supported or continuous, internally prestressed or externally prestressed, epoxy jointed or dry
jointed.
A launching gantry is an item of bridge construction equipment, also known as beam
launcher or bridge girder launcher is used to install precast girders.
Sr No Description
1 Launching Girder
2 Mobile crane
3 Man Lift
4 Hydraulic Jack
5 Stressing Jack
6 Stressing Pump
7 Grout Mixer and Pump
8 Strand Pushing Machine
9 Air Compressor
10 Grout Mixer
49
5.3 Components of launching gantry
Components of launching gantry are as follows
5.3.1 Front support
1. Front support assembly includes upper cross beam, bottom cross beam, a pair of vertical
telescopic legs operated by two hydraulic cylinders, base and hydraulic pump station.
2. The truss is connected to the top beam.
3. All the components are connected by bolts and pins of 100 mm dia.
4. The entire front leg assembly weighs 13 MT.
4. There are 8 motors for the motion of middle support during support shifting before commencing
auto launching.
50
3. The entire rear leg assembly weighs 6 MT.
4. There are 4 motors for the motion of rear bracket during support shifting before commencing
auto launching.
5.3.5 Winch
1. The lifting capacity of winch is 60 T. Lifting height is 28 m. Wire rope dia is 26 mm. drum dia-
500 mm.
5.4 Procedure
1. The span to be launched, one rear and one front span are barricaded. The whole space
is levelled for placement of LG (launching Gantry) boxes and crane.
2. The trailers are brought to the site and loaded and unloaded using suitable capacity
cranes.
3. The front support, middle support and temporary trestle on the already erected span.
4. First S1 box is erected on the front support and the trestle and it is joined with the front
support.
5. Place the trestle on the span and erect the S2 box on trestle and join S1 and S2 with the
splice plate. Same procedure for S3.
6. Then erect and fix the rear support. Place the temporary trestle and erect S4 box over it
and join S3 and S4 with splice plate.
7. The rear and middle supports are activated and trestle is removed from below S1 S2 S3
S4.
8. Place the trestle and erect the S5 box and join S4 and S5 by splice plate. Follow same
procedure for S6.
51
9. Place the rail in position to place the rear trolley and erect and place the rear trolley in
position. Erect the S7 box and join S6 and S7 by splice plate.
10. Erect the counterweight one by one on the S7 box.
11. Release the front support and start auto launching till the front support reaches the next
pier.
3. Lifting of segments
52
The segment to be lifted is arrived in a trailer from casting yard and is aligned below the
LG box. It is then inserted with lifting beam and macaulay's bar at 4 corner in the deck of the
EJ segment. A force is applied at the bars to create a stress by hydraulic jack. The segment is
then lifted with help of LG.
4. Dry Matching
All the segments after lifting and vertical stressing are dry matched and made ready for the
gluing.
53
5. Gluing of Segments
1. The Epoxy compound is applied to the face of the segments and then stressed using jack
for strong bond.
2. The epoxy gluing is applied by hands using safety hand gloves.
3. The epoxy coating while applying is in semi-solid state and it takes two hours to set the
coating.
8. Lowering of span
While segment lifting, segment S10 is placed on 300 mm stool on pedestal bearing and after
gluing and temporary stressing segment S1 is placed on 600 mm stool on pedestal bearing. We
need to lower down the span to bearing pedestal top + 200 mm level on both the sides.
9. Grouting
1. After 24 hours of stressing grouting is done.
2. The extra strands are cut and grout cap is fixed.
3. For the preparation of grout, the water is first fed into the mixer, followed by the admixture
and at last 53 grade OPC.
4. Then the water is flushed through the cable ducts.
5. The grout mix is pumped using a grouting pump.
54
6. The grout is pumped from one end and the consistency of grout is checked using
hydrometer at the other end.
7. Admixture used is 0.225 kg/50 kg cement (CEBEX 100).
5.6 Bearing
• A bridge bearing is a component of a bridge which typically provides a resting surface
between bridge piers and the bridge deck.
• The purpose of a bearing is to allow controlled movement and thereby reduce the stresses
involved.
• An elastomeric bearing is provided.
55
CHAPTER 6
SAFETY MEASURES
6.1 General
Currently, metro rail transit projects are growing rapidly in India. Almost every state
have a metro project or very soon to start. When we think about safety, its new field and have
unique challenges where lots of safety research, analysis and risk management to be
established.
Throughout the metro construction process, the highest priority on the safety of workers and
the community are the main challenges. A Project Construction Safety Compliance Program
shall be developed to take a proactive approach in promoting safe behaviours near
construction sites and increasing construction safety awareness for workers, public and
stakeholders in the areas along the alignment.
6.2.1Protective Equipment
Employers on construction sites need specific Personal Protective Equipment (PPE) to
ensure their safety and health.
6.2.1.1Safety helmet
56
6.2.1.2 Footwear
Protective footwear should be provided to workers who are
exposed to the risk of injury of materials being dropped on their feet or
nail or other sharp objects penetrating their sole.
Where it is likely that employees will be working in water or wet
concrete, appropriate boots should be provided
Protective gloves and suitable protective clothing to protect hands or the whole body
as required when exposed to heat radiation or while handling hot, hazardous or other
substances which might cause injury to the skin should be provided by the employer
57
6.3 Safety Rules
Metro construction zones are very dangerous, so remember to always stay safe when
you’re around them. Here are ten simple safety rules to help you stay safe:
• Restrict yourself from going near the construction zone, whenever possible. Debris
and heavy machines can be hazardous.
• Avoid playing, running, riding or walking near the construction zone or around
construction equipment’s, dirt piles and work areas.
• Always prefer walking on the designated walkways or sidewalks. Keep your eyes for
sidewalk closure signs and remain alert to posted notices on the temporary walkways.
• Using cell phones, other hand held devices, video games and headphones in
construction zones can be really dangerous. Avoid distraction, stay alert to your
surroundings, this reduces the likelihood of an incident.
• Stay alert, stop, look and listen carefully for construction vehicles like dump trucks,
bulldozers etc. as dust can impede your vision. Always be prepared for sudden wide
turns and stops.
• Be careful, make an eye contact with drivers and construction vehicles while crossing
and cross only at intersections.
• Lower your speed, follow sign boards that tell you where to walk.
• Be aware of falling objects in construction area, even if they are not directly overhead,
wind can blow them towards you.
• Respect the construction signs and any instructions provided by people working on
the project.
• Stay outside construction fences, chain link fences and orange cones.
• Looking at the volume, intricacies, variety of EHS issues and hazards; safety training
becomes an important aspect which cannot be ignored. Meticulous planning; brisk
execution, supervision and control; strict compliance of EHS measures satisfying the
legal and regulatory requirements; adoption of preventative and proactive measures of
world class levels; inculcation and sustenance of positive and progressive work
culture are the main requirements for HSE compliance by the metro projects.
58
6.4.1 ATP/ATO
The rolling stock is provided with Continuous Automatic Train Protection and Automatic
Train Operation in future) to ensure absolute safety in the train operation. It is an accepted
fact that the 60-70% of accidents take place on account of human error. Adoption of this
system ensures freedom from human error. The on board computerized ATC system compare
and verify the continuous data like speed etc for safest train control
6.4.2 Fire
The rolling stock is provided with fire retardant materials having low fire laad low heat
release rate, low smoke and toxicity inside the cars The electric cables used are also normally
low smoke zero halogen type which ensures passenger safety in case of fire
6.4.5 Ganways
Broad gangway are provided in between the cars to ensure free passenger movement between
cars in case of any emergency
59
Fig 6.1 PPE for Safety
60
ensure maintenance staff are enabled to climb on the roof inspection platform only
after the OHE is isolated
• Control Centre, PPIO & store depot must be close to Workshop
• Width of the doors of the sections wherein repairs of equipments are done should be
at least 2 meters wide to allow free passage of equipment through them
• Provision of water hydrants should be done in workshops stains yards also
• Compressed air points along with water taps should be available in interior of
for cleaning
61
CHAPTER 7
QUALITY ANALYSIS
7.1 General
Quality analysis is divided mainly in these two categories: Quality Assurance and Quality
Control. Quality Assurance (QA) is a way of preventing mistakes and defects in manufactured products
and avoiding problems when delivering products or services to customers, whereas Quality Control
(QC) is a process by which entities review the quality of all factors involved in production. ISO 9001
defines quality control as a part of quality management focused on fulfilling quality requirements.
62
2. COMPRESSIVE STRENGTH TESTS
• Compressive strength is the ability of material or structure to carry the loads on its surface
without any crack or deflection. A material under compression tends to reduce the size,
while in tension, size elongates.
• Formula = Load / Cross-sectional Area
• Compression testing machine is used for this test.
• Concrete is poured in the mould and tempered properly so as not to have any voids.
• After 24 hours these moulds are removed and test specimens are put in water for curing.
• These specimens are tested by compression testing machine after 7 days, 14 days and 28
days curing.
• The temperature of water must be at 27±2oC.
• Load should be applied gradually at the rate of 140 kg/cm2 per minute till the Specimens
fails.
• Load at the failure divided by area of specimen gives the compressive strength of concrete.
63
7.3 Compressive Testing Machine
64
CHAPTER 8
CONCLUSION AND LEARNINGS
As an undergraduate student study of bridge structure like a metro is of great help for our
future. The knowledge gained here in Pune Metro by this internship is very useful. This was a
great experience and opportunity for us to work with a semi-government body.
This internship has given us an introduction of professional skills which we are going to
need in our near future. The Training has given us the knowledge and access to all the
instruments which we use in the construction process of Metro.
As Metro is the future, we were always keen to pursue our training at a Metro Project.
The internship at metro has given us the chance of experiencing and applying the theory
knowledge we have gained in the classrooms. The guidance from senior engineers and
employees from time to time gave us a broader imagination of work and their execution in the
infrastructure projects.
We will always be thankful to MAHA-Metro for giving us the permission to learn and
experience the metro project.
65
LEARNINGS
Mayur R. Patil
1. In Casting Yard, I have learned about the Short Line Method and Long Line Method.
2. I have understood the purpose of the downstands.
3. The process of Pre-tensioning is learned. In Kiwale Casting Yard I have seen the reaction
beam.
4. Lifting of Segments is seen.
5. Size of one segment is big and very carefully they are handling them by the Gantry
having 75 Tonnes of the capacity of lifting.
6. I have learned about the machines like Hydra crane, Rig Machine for pile boring.
7. I have understood how to read the drawings.
8. PPE is taken very seriously over here. Helmets, safety shoes and jackets are must wear
before you enter in the working area.
Ajinkya Y. Surwade
1. I have understood how actually the progress of construction goes with respect to the
targeted task given to the contractor.
2. How Pune Metro achieved the solution in constructing the foundation near harris bridge.
3. I got an idea regarding how construction firm functions.
4. I learned different types of contracts and got to know about various contracts proceed in
the pune metro.
5. I got an idea about how traffic operations operated during the construction processes.
6. I have seen how pre-tensioned members construct and handled in kiwale casting yard.
7. I have learned the temporary stressing process in lifting of girders,
8. I got an idea regarding how the shoring process work to support the adjacent structure.
66
Pratik B. Trale
Ashwini V. Bhondve
1. From the method statements provided to us before going to sites, I learned the
steps/procedure to be followed for carrying out the various construction activities.
2. I saw various tests carried out before excavation like utility trenching to check for any
utilities etc.
3. I learned to read GAD (General arrangement details) and bar bending schedule for open
foundation and pier
4. Type of foundation i.e. open or pile foundation is provided according to type of soil
strata. I understood the detailed procedure for construction of both types of foundation.
5. Types of contracts and brief about tendering process.
6. We visited Kasarwadi casting yard where the segments for box girder are casted. Long
line method of casting is used for casting of segments. We witnessed the batching process
of concrete from the batching plant at the same casting yard.
7. We also visited Kiwale casting yard where girders for stations are casted. We learned the
procedure of constructing pre-stressed(pre-tensioned) concrete segments.
8. We witnessed the launching process of segments and how the segments are glued.
Temporary stressing is done by using Macaulay bars.
67
9. We learned the post-tensioning method which is used in the span(made up of several no
of segments) between two piers.
10. Harris Bridge was one of the critical cases where there were too many space constraints.
I-Shaped stepped footing and eccentric pier is provided at the location.
Gayatri V. Shinde
1. Types of contracts:
Traditional
68
9. The casting yard at Kasarwadi has 2 batching plants, of capacity 30 cu. m and 60 cu. m.
Segments are casted here by long bed(intermediate segments) and short bed method(end
segments). Concreting work is done only at night for maintaining the temperature
conditions. Post tensioning method of pre-stressing is used for holding all the segments of
a span together. The casting yard at Kiwale is used for casting of girders. RCC T girder,
RCC rectangular and pre-stressed T and L girder are casted here. Pre tensioning method
of pre-stressing is used for construction of girders. Gantry crane is used for lifting
segments as well as girders at the casting yard.
10. Launching Gantry is used for launching of segments for erection of each span. 4 LGs are
used in this project.
11. Bar Bending Schedule is used for calculating the total quantity of steel required for each
structure and also to calculate the amount to be spent for the same.
12. Types of piers used are normal pier, cantilever pier and portals. At Harris Bridge,
eccentric pier has been used.
Siddhant M. Tajane
1. I have learned about different types of foundation used in metro rail project (open type
and pile type).
2. Learned about what type of safety is taken on site, and how it changes from site to site.
3. Learned about checking of the machinery in casting yard and about its safety.
4. Learned about how the precast structure is constructed and why there is a need of precast
structure.
5. Learned about the different types of the contracts.
6. Learned about different types of hindrances that occurred in the project.
7. Importance of micropiles (used for the protection of the foundation of old structure.)
8. Learned about the critical case of Harris bridge (eccentric pier, H- type of foundation,
different types of shutters used)
9. Learned about shoring, pre stressing, future stressing, types of LG, boring, different types
of lab tests.
69
Mohd Junej Iqbal Ansari
1. I learned about the different types of foundation and how it is actually done on the field.
(Open Foundation- Range Hills, Pile Foundation- NashikPhata). I saw how the casing of
pile is cut by Acetlyn Gas, where and why Shore Piles are provided.
2. I learned about the unusual case of Harris Bridge where the Metro is to pass between two
bridges (3 layer foundation is provided with intermediate pier cap and an eccentric pier).
3. I learned about the different lab tests that are done at the casting yard. The tests
performed are: Sieve Analysis, Impact Value Test, Abrasion Test, Flakiness Test,
Compressive Test by CTM, Permeability Test.
4. I came to know about the methods used in Casting Yard for casting of segments. The
methods are: Long line method and Short Line method. Short Line method is used to cast
end segments. Match casting is done for casting of segments.
5. I saw the process of launching of segments by Launching Gantry. The 2 types of LG’s
used are Box type and Double Truss type.
6. I learned about the concept and process of temporary and permanent stressing done in the
span.
7. I learned about Quality Analysis: Quality Assurance and Quality Control.
8. I learned the basics of Bar Bending Schedule.
70
SUGGESTIONS
1. Hygiene should be maintained in the casting yard. The gutters which carry sewage water
and curing water should be covered to avoid mosquito breeding.
2. As per the schedule of the activities, work must be completed on higher priority by all
workers and staff.
3. The construction and demolition waste should be disposed off properly so that it doesn’t
cause any harm to the environment.
4. Untimely transportation of materials to site leads to delay in work. Hence, engineers
should ensure that materials are procured on time.
5. Housekeeping on the site must be followed by the engineers for smooth operations and
safety of the workers.
71