ChevronTexaco Darajat III

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

CHEVRONTEXACO ENERGY INDONESIA, LTD

Darajat III 110 MW Geothermal Project


Plant Optimization, Engineering and Commissioning
Java, Indonesia

PROJECT SPECIFICS PROJECT DESCRIPTION


COMPLETE ENGINEERING DESIGN AND COMMISSIONING FOR THE LARGEST
CLIENT GEOTHERMAL TURBINE-GENERATOR IN THE WORLD
Thiess Construction
Jakarta, Indonesia Home of the world’s most energetic The dream of the driller
geothermal well The new plant, at 110 MW in capacity, will
Kanematsu Corporation In 2004, ChevronTexaco (formerly Amoseas be the largest geothermal turbine-generator
Japan
Indonesia) and PT Pertamina began the unit ever built when it enters service in 2006.
EPC development of the Darajat III The Darajat field is remarkable in another
PROJECT SERVICES
geothermal project, the third and largest way; it is one of only few dry steam
> Technical support for successful EPC
bid to ChevronTexaco (Amoseas) geothermal unit in the Darajat field. The geothermal resources used for commercial
> Gathering/injection system design project is located on the flanks of Mt. power generation, in distinguished company
review Kendang, a young volcano on the island of with two legendary geothermal fields: the
> Plant engineering and complete design Java near the town of Garut, about 100 miles Geysers in California and Lardarello, in Italy.
for 3D model-based construction south of the Indonesian capital of Jakarta.
> Switchyard and substation engineering The Darajat resource is notable for dry
and design ChevronTexaco, doing business as steam and high well deliverabilities, whereby
> Procurement support to Thiess ChevronTexaco Energy Indonesia, awarded wells readily produce steam at high pressure
> Management of commissioning and
the EPC development to a consortium which and high flow rates.
start-up process
includes Kanematsu (a large Japanese
trading company), as the lead EPC entity,
Thiess Corporation of Indonesia as the
construction contractor and POWER
Engineers of the US as the engineer.

The Darajat field is the home of the world’s most


energetic geothermal well, a well completed in
1998 with a capacity of 40 MW.
THIESS CONSTRUCTION

PROJECT DESCRIPTION (continued)

A grand contraption Other noble toil by POWER


POWER is designing the Darajat III power POWER’s scope also includes technical
plant around a single Mitsubishi Power procurement support for the entire BOP
Systems geothermal steam turbine. The supply. POWER is also responsible for direct
turbine is a dual-entry bottom-exhausting procurement expediting for all equipment
turbine with a design inlet pressure of more and materials sourced in the U.S.
than 15 bara.
Finally, POWER will be the responsible
This inlet pressure, notably high in the manager for all completion testing and
geothermal turbine world, is made possible commissioning activity when the Darajat III
by the exceptional quality of the geothermal plant enters service in 2006. „
steam produced by the Darajat field.

The plant will also include a single direct-


The Darajat field is in the highlands of south contact condenser, two sets of hotwell
Java. The plant shown above is Darajat II.
The Darajat III power plant is at an elevation pumps, a large array of wet cooling towers,
of approximately 2,000 m. (Photo: Eka and a three-stage hybrid NCG extraction
Binawana)
system using steam ejectors and a liquid ring
vacuum pump.

Construction on the cooling tower, August 2006

The plant design scope also includes the


plant 150kV substation and the transmission
line interconnection.