Professional Documents
Culture Documents
CP N-05 Vol.2 Sec.6 Ib Ts 100
CP N-05 Vol.2 Sec.6 Ib Ts 100
BIDDING DOCUMENT
for the Procurement of
The Malolos to Clark Railway Project (MCRP)
Package CP N-05
VOLUME 2
Part II – Requirements
Section 6 – The Employers Requirements
Part I – The Specifications
Book 2 – TS 100
Civil Works
Issued on : April 2019
OCB No. :
Employer : The Government of the
Republic of the Philippines
through the Department of
Transportation
Country : Republic of the Philippines
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TABLE OF CONTENTS
TS100 - 1
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 3
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 4
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 7
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 11
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 12
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
LIST OF TABLES
Table 106-1 Grading Requirements....................................................................................................................... 40
Table 107-1 Grading Requirements for Sub-ballast ............................................................................................... 44
Table 108-1 Grading Requirements for Fine Aggregate ......................................................................................... 48
Table 108-2 Grading Requirements for Coarse Aggregate ..................................................................................... 49
Table 120-1 Straw Erosion Control Mat .............................................................................................................. 113
Table 120-2 Straw and Coconute Mat ................................................................................................................. 114
Table 120-3 Coconut Mat ................................................................................................................................... 114
Table 120-4 Synthetic Erosion Control Mat ........................................................................................................ 115
Table 120-5 Synthetic Polypropylene Mesh ........................................................................................................ 115
Table 120-6 Synthetic Polypropylene Erosion Control Mat ................................................................................. 115
Table 125-1 Specifications Covering Welded Wire Reinforcement ...................................................................... 134
Table 125-2 Minimum Requirements of Steel Wires in Welded Wire Reinforcement WELDED PLAIN WIRE
REINFORCEMENT ASTM A1064 .................................................................................................................... 135
Table 125-3 Test of Elongation (total - Elastic & Plastic) for various Wire Sizes ................................................. 135
Table 125-4 Summary of Test Criteria in Table 3(b) (27 Samples Tested) ........................................................... 136
Table 129-1 Reflective Brightness of Traffic Signs Surfaces ............................................................................... 145
Table 130-1 Physical Properties .......................................................................................................................... 150
Table 130-2 Composition Requirements ............................................................................................................. 150
Table 131-1 Raised Profile Pavement Studs: Photometric Properties ................................................................... 153
Table 136-1 Composition Requirements ............................................................................................................. 170
Table 136-2 Qualitative Requirements ................................................................................................................ 170
Table 140-1 Recommended Spacing for Chevron Signs ...................................................................................... 186
Table 140-2 Types of Chevron Signs .................................................................................................................. 187
Table 140-3 Reflective Brightness of Traffic Signs Surfaces ............................................................................... 187
Table 141-1 Physical Propertoes of Coco-net ...................................................................................................... 190
Table 141-2 Physical Properties of Coco-log ....................................................................................................... 191
TS100 - 13
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Term Definition
AASHTO American Association of State Highway and Transportation Officials
ACI American Concrete Institute
AFCS Automatic Fare Collection System
AIDS Acquired Immune Deficiency Syndrome
AISI American Iron & Steel Institute
ANSI American National Standards Institute
Applicable Laws The governing laws and regulations in force in the Philippines.
AREA American Railway Engineering Association
Drawings produced by the Contractor and endorsed by the Engineer
as true records of the construction of the Permanent Works and
As-Built Drawings which have been agreed with the Engineer. If the Employer’s Design
is changed during the course of the Works. The As-Built Drawings
shall be prepared by the Contractor and endorsed by the Engineer.
American Society of Heating, Refrigerating, and Air-Conditioning
ASHRAE
Engineers
ASTM American Society for Testing and Materials
Automatic Train Control – similar to ATP and used as an overall term
ATC
for ATP, ATS and Interlocking.
Automatic Train Protection - subsystem of ATC that, through train
ATP detection, train separation and speed limit enforcement maintains
safe train operation.
The mode of train operation when train speed is controlled manually
ATP Mode (Train
but is supervised by the primary ATP system to ensure safety speed
Operation)
limits are not exceeded.
AWS American Welding Society
BAC Bid & Awards Committee
BDS Bid Data Sheet
BF Bidding Forms
BMS Building Management System
BOQ Bill of Quantities
BPS Bureau of Product Standards, DTI-Philippines
BS British Standards
TS100 - 14
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 15
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 16
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 17
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
EXCAVATION Means the removal of material for the footing and abutments of bridges.
TS100 - 20
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 21
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
2) Grubbing of pits, channel changes and ditches will be required only to the depth
necessitated by the proposed excavation within such areas.
3) In areas covered by cogon, wild grass and other vegetations, top soil shall be
cut to a maximum depth of 150mm below the original ground surface or as
designated by the Engineer, and disposed outside the clearing and grubbing
limits as indicated in the Drawings or directed by the Engineer.
4) In areas to be excavated, stump holes and other holes from which obstructions
are removed shall be backfilled with suitable material and compacted to the
required density.
Holes left after removal of roots shall be filled with suitable material compacted to the
density of the surrounding material. Before commencing the filling work, the
Contractor shall submit in writing to the Engineer for approval his proposal for the
works.
Materials, debris and perishable materials may be disposed of by methods and at
locations approved by the Engineer, on or off the project. The Contractor however, shall
see to it that no burning, burying or dumping of wastes shall be done within the
temporary depositing area, or construction sites and other non-designated areas. Burying
shall be done in layers. Each layer shall be covered or mixed with earth material by the
land-fill method to fill all voids. The top layer of material buried shall be covered with
at least 300mm of earth or other approved material and shall be graded, shaped and
compacted to present a pleasing appearance.
If the disposal location is off the project, the Contractor shall make all necessary
arrangements with property owners in writing for obtaining suitable disposal locations
which are outside the limits of view from the project. The cost involved shall be
included in the unit bid price. A copy of such agreement shall be furnished to the
Engineer. The disposal areas shall be seeded, fertilized and mulched at the Contractor’s
expense.
Woody material may be disposed of by chipping. The wood chips may be used for
mulch, slope erosion control or may be uniformly spread over selected areas as directed
by the Engineer. Wood chips used as mulch for slope erosion control shall have a
maximum thickness of 12mm and faces not exceeding 3900mm2 on any individual
surface area. Wood chips not designated for use under other sections shall be spread
over the designated areas in layers not to exceed 75mm loose thickness. Diseased trees
shall be buried or disposed of as directed by the Engineer.
Low hanging branches and unsound or unsightly branches on trees or shrubs designated
to remain shall be trimmed as directed. All trimming shall be done by skilled workmen
and in accordance with good tree surgery practices.
TS100 - 22
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
The work measured as provided above shall be paid for in accordance with the
applicable unit prices as indicated in the Bill of Quantities which payment shall be for
full compensation for furnishing all labor, materials, tools, equipment, and incidentals
necessary to complete the work and for doing Clearing and Grubbing in the designated
areas, as specified in the Drawings and as directed by the Engineer.
The Payment shall be also inclusive of all work necessary for the removal and proper
disposal of materials.
Payment will be made under:
- END OF SECTION -
TS100 - 23
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
102 EXCAVATION
102.1 The Work
The works in this section shall consist of railway including maintenance road, drainage
and borrow excavation, and the disposal of material in accordance with this
Specification and in conformity with the lines, grades and dimensions shown on the
Drawing or established by the Engineer.
102.1.1 Railway Excavation
Railway excavation will include excavation and grading for railways, parking areas,
intersections, approaches, slope rounding, benching, waterways and ditches; removal
of unsuitable material from the roadbed and beneath embankment areas; and
excavating selected material found in the railway as ordered by the Engineer for
specific use in the improvement. Railway excavation will be classified as “unclassified
excavation”, “rock excavation”, “common excavation”, or “muck excavation” as
indicated in the Bill of Quantities and hereinafter described.
1) Unclassified Excavation.
Unclassified excavation shall consist of the excavation and disposal of all
materials regardless of its nature, not classified and included in the Bill of
Quantities under other pay items.
2) Rock Excavation.
Rock excavation shall consist of excavation of igneous, sedimentary and
metamorphic rocks which cannot be excavated without blasting or the use of
rippers, and all boulders or other detached stones each having a volume of 1 cubic
meter or more as determined by physical measurements or visually by the
Engineer.
3) Common Excavation.
Common excavations shall consist of all excavation not included in the Bill of
Quantities under “rock excavation” or other pay items.
4) Muck Excavation.
Muck excavation shall consist of the removal and disposal of deposits of saturated
or unsaturated mixtures of soils and organic matter not suitable for foundation
materials regardless of moisture content.
102.1.2 Borrow Excavation
Borrow excavation shall consist of the excavation and utilization of approved materials
required for the construction of embankments or for other portions of the work, and
shall be obtained from sources provided by the Contractor and approved by the
Engineer.
102.2 Construction Requirements
102.2.1 General
When there is evidence of discrepancies on the actual elevations and that shown on the
Drawings, a pre-construction survey referred to the datum plane used in the approved
Drawing shall be undertaken by the Contractor under the control of the Engineer to
serve as basis for the computation of the actual volume of the excavated materials.
TS100 - 24
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 25
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
102.2.5 Presplitting
Unless otherwise provided in the Contract, rock excavation which requires drilling and
shooting shall be presplit.
Presplitting to obtain faces in the rock and shale formations shall be performed by:
(1) drilling holes at uniform intervals along the slope lines, (2) loading and stemming
the holes with appropriate explosives and stemming material, and (3) detonating the
holes simultaneously.
Prior to starting drilling operations for presplitting, the Contractor shall furnish the
Engineer a plan outlining the position of all drill holes, depth of drilling, type of
explosives to be used, loading pattern and sequence of firing. The drilling and blasting
plan is for record purposes only and will not absolve the Contractor of his responsibility
for using proper drilling and blasting procedures. Controlled blasting shall begin with a
short test section of a length approved by the Engineer. The test section shall be
presplit, production drilled and blasted and sufficient material excavated whereby the
Engineer can determine if the Contractor’s methods are satisfactory. The Engineer may
order discontinuance of the presplitting when he determines that the materials
encountered have become unsuitable for being presplit.
The holes shall be charged with explosives of the size, kind, strength, and at the spacing
suitable for the formations being presplit, and with stemming material which passes a
9.5mm standard sieve and which has the qualities for proper confinement of the
explosives.
The finished presplit slope shall be reasonably uniform and free of loose rock. Variance
from the true plane of the excavated backslope shall not exceed 300mm; however,
localized irregularities or surface variations that do not constitute a safety hazard or
impairment to drainage courses or facilities will be permitted.
A maximum offset of 600mm will be permitted for a construction working bench at
the bottom of each lift for use in drilling the next lower presplitting pattern.
102.2.6 Excavation of Ditches, Gutters, etc.
All materials excavated from side ditches and gutters, channel changes, irrigation
ditches, inlet and outlet ditches, toe ditches, furrow ditches, and such other ditchesas
may be designated on the Drawings or staked by the Engineer, shall be utilized as
provided in Section 102.2.3.
Ditches shall conform to the slope, grade, and shape of the required cross-section, with
no projections of roots, stumps, rock, or similar matter. The Contractor shall maintain
and keep open and free from leaves, sticks, and other debris all ditches dug by him until
final acceptance of the work.
Furrow ditches shall be formed by plowing a continuous furrow along the line staked
by the Engineer. Methods other than plowing may be used if acceptable to the Engineer.
The ditches shall be cleaned out by hand shovel work, by ditcher, or by some other
suitable method, throwing all loose materials on the downhill side so that the bottom
of the finished ditch shall be approximately 450mm below the crest of the loose
material piled on the downhill side. Hand finish will not be required, but the flow lines
shall be in satisfactory shape to provide drainage without overflow.
TS100 - 26
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
shall be signed by the engineer or his representation, prior to off-site transfer of waste
material.
102.3 Measurement and Payment
102.3.1 Method of Measurement
The cost of excavation of material which is incorporated in the Works or in other areas
of fill shall be deemed to be included in the Items of Work where the material is used.
Measurement of Unsuitable or Surplus Material shall be the net volume in its original
position.
For measurement purposes, surplus suitable material shall be calculated as the
difference between the net volume of suitable material required to be used in
embankment corrected by applying a shrinkage factor or a swell factor in case of rock
excavation, determined by laboratory tests to get its original volume measurement, and
the net volume of suitable material from excavation in the original position. Separate
pay items shall be provided for surplus common, unclassified and rock material.
The Contractor shall be deemed to have included in the contract unit prices all costs of
obtaining land for the disposal of unsuitable or surplus material.
102.3.2 Basis of Payment
The accepted quantities, measured as prescribed in Section 102.3.1 shall be paid for at
the contract unit price for each of the Pay Items listed below that is included in the Bill
of Quantities which price and payment shall be full compensation for the removal and
disposal of excavated materials including all labor, equipment, tools, and incidentals
necessary to complete the work prescribed in this Item.
Payment will be made under:
- END OF SECTION -
TS100 - 28
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
103 EMBANKMENT
103.1 The Work
The works in this section shall consist of the construction of embankment in accordance
with this Specification and in conformity with the lines, grades and dimensions shown
on the Drawings or established by the Engineer.
103.2 Material Requirements
Embankments shall be constructed of suitable materials, in consonance with the
following definitions:
1) Suitable Material – Material which is acceptable in accordance with the
Contract and which can be compacted in the manner specified in this section. It
can be common material or rock.
Selected Borrow, for topping – soil of such gradation that all particles will pass a
sieve with 75mm square openings and not more than 15 mass percent will pass
the 0.075mm (No. 200) sieve, as determined by AASHTO T 11. The material
shall have a plasticity index of not more than 6 as determined by AASHTO T 90
and a liquid limit of not more than 30 as determined by AASHTO T 89.
2) Unsuitable Material – Material other than suitable materials such as:
a) Materials containing detrimental quantities of organic materials, such as
grass, roots and sewerage.
b) Organic soils such as peat and muck.
c) Soils with liquid limit exceeding 80 and/or plasticity index exceeding 55.
d) Soils with a natural water content exceeding 100%.
e) Soils with very low natural density, 800 kg/m3 or lower.
f) Soils that cannot be properly compacted as determined by the Engineer.
103.3 Construction Requirements
103.3.1 General
Prior to construction of embankment, all necessary clearing and grubbing in that area
shall have been performed in conformity with Section 101, Clearing and Grubbing.
Embankment construction shall consist of constructing depot, railway and maintenance
road embankments, including preparation of the areas upon which they are to be placed;
the placing and compacting of approved material within the embankment areas shown
on the Drawings where unsuitable material has been removed; and the placing and
compacting of embankment material in holes, pits, and other depressions within the
embankment area.
Embankments and backfills shall contain no muck, peat, sod, roots or other deleterious
matter. Rocks, broken concrete or other solid, bulky materials shall not be placed in
embankment areas where piling is to be placed or driven.
Where shown on the Drawings or staked by the Engineer, the surface of the existing
ground shall be compacted to a depth of 150mm and to the specified requirements of
this section.
TS100 - 29
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 30
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
than 300mm.
Each layer shall be leveled and smoothed with suitable leveling equipment and by
distribution of spalls and finer fragments of earth. Lifts of material containing more
than 25 mass percent of rock larger than 150mm in greatest dimensions shall not be
constructed above an elevation 300mm below the finished subgrade. The balance of
the embankment shall be composed of suitable material smoothed and placed in layers
not exceeding 200mm in loose thickness and compacted as specified for embankments.
Dumping and rolling areas shall be kept separate, and no lift shall be covered by another
until compaction complies with the requirements of Section 103.3.3 Compaction.
Hauling and leveling equipment shall be so routed and distributed over each layer of
the fill in such a manner as to make use of compaction effort afforded thereby and to
minimize rutting and uneven compaction.
103.3.3 Compaction
1) Compaction Trials
Before commencing the formation of embankments, the Contractor shall submit
in writing to the Engineer for approval his proposals for the compaction of each
type of fill material to be used in the works. The proposals shall include the
relationship between the types of compaction equipment, the number of passes
required and the method of adjusting moisture content. The Contractor shall carry
out full scale compaction trials on areas not less than 10m wide and 50m long as
required by the Engineer and using his proposed procedures or such amendments
thereto as may be found necessary to satisfy the Engineer that all the specified
requirements regarding compaction can be consistently achieved. Compaction
trials with the main types of fill material to be used in the works shall be
completed before work with the corresponding materials will be allowed to
commence.
Throughout the periods when compaction of earthwork is in progress, the
Contractor shall adhere to the compaction procedures found from compaction
trials for each type of material being compacted, each type of compaction
equipment employed and each degree of compaction specified.
The Contractor shall compact the material placed in all embankment layers and
the material scarified to the designated depth below subgrade in cut sections, until
a uniform density of not less than 95 mass percent of the maximum dry density
determined by AASHTO T 99 Method C, is attained, at a moisture content
determined by Engineer to be suitable for such density. Acceptance of
compaction may be based on adherence to an approved roller pattern developed
as set forth in Section 105, Compaction Equipment and Density Control Strips.
The Engineer shall during progress of the Work, make density tests of compacted
material in accordance with AASHTO T 191, T 205, or other approved field density
tests, including the use of properly calibrated nuclear testing devices. A correction
for coarse particles may be made in accordance with AASHTO T 224. If, by such
tests, the Engineer determines that the specified density and moisture conditions
have not been attained, the Contractor shall perform additional work as may be
necessary to attain the specified conditions.
At least one group of three in-situ density tests shall be carried out for each 500m2
TS100 - 31
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
1) Compacted Berm
Compacted berm construction shall consist of moistening or drying and placing
material as necessary in locations shown on the drawings or as established by the
Engineer. Material shall contain no frozen material, roots, sod, or other
deleterious materials. Contractor shall take precaution to prevent material from
escaping over the embankment slope. Shoulder surface beneath berm will be
roughened to provide a bond between the berm and shoulder when complete. The
Contractor shall compact the material placed until at least 90 mass percent of the
maximum density is obtained as determined by AASHTO T 99, Method C. The
cross-section of the finished compacted berm shall reasonably conform to the
typical cross-section as shown on the Drawings.
2) Uncompacted Berm
Uncompacted berm construction shall consist of drying, if necessary and placing
material in locations shown on the Drawings or as established by the Engineer.
Material shall contain no frozen material, roots, sod or other deleterious materials.
The Contractor shall take precautions to prevent material from escaping over the
embankment slope.
103.4 Measurement and Payment
103.4.1 Method of Measurement
The quantity of embankment to be paid for shall be the volume of material compacted
in place, accepted by the Engineer and formed with material obtained from any source.
Material from excavation per Section 102, Excavation which is used in embankment
and accepted by the Engineer will be paid under Embankment and such payment will
be deemed to include the cost of excavating, hauling, stockpiling and all other costs
incidental to the work.
Material for Selected Borrow topping will be measured and paid for under the same
conditions specified in the preceding paragraph.
The plate load bearing tests in accordance with ASTM D1196 shall be paid according
to the number of tests instructed by and accepted by the Engineer.
103.4.2 Basis of Payment
The accepted quantities, measured as prescribed in Section 103.4.1, shall be paid for at
the Contract unit price for each of the Pay Items listed below that is included in the Bill
of Quantities. The payment shall continue full compensation for placing and
compacting all materials including all labor, equipment, tools and incidentals necessary
to complete the work prescribed in this section.
Payment will be made under:
103 (1)c Embankment for At grade section for Depot (Selected Cubic Meter
Borrow Material)
TS100 - 33
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 34
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Permitted variation from design LONGITUDINAL GRADE over 25m length: ± 0.1 %
TS100 - 35
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
After the embankment has been completed, the full width shall be conditioned by
removing any soft or other unstable material that will not compacted properly. The
resulting areas and all other low sections, holes or depressions shall be brought to grade
with suitable material. The entire roadbed shall be shaped and compacted to the
requirements of Section 103.3.3 Compaction. Scarifying, blading, dragging, rolling or
other methods of work shall be performed or used as necessary to provide a thoroughly
compacted roadbed shaped to the cross-sections shown on the Drawings.
104.3.6 Subgrade on Existing Pavement
Where the new pavement is to be constructed immediately over an existing Portland
Cement concrete pavement and if so specified in the Contract, the slab shall be broken
into pieces with greatest dimension of not more than 500mm and the existing pavement
material compacted as specified in Section 103.3.3 Compaction, as directed by the
Engineer. The resulting subgrade level shall, as part of pavement construction be shaped
to conform to the allowable tolerances of Section 104.3.2 by placing and compacting
where necessary a leveling course comprising the material of the pavement course to
be placed immediately above.
Where the new pavement is to be constructed immediately over an existing asphalt
concrete pavement or gravel surface pavement and if so specified in the Contract, the
pavement shall be scarified, thoroughly loosened, reshaped and recompacted in
accordance with Section 103.3.3 Compaction. The resulting subgrade level shall
conform to the allowable tolerances of Section 104.3.2 Subgrade Level Tolerances.
104.3.7 Protection of Completed Work
The Contractor shall be required to protect and maintain at his own expense the entire
work within the limits of his Contract in good condition satisfactory to the Engineer
from the time he first started work until all work shall have been completed.
Maintenance shall include repairing and recompacting ruts, ridges, soft spots and
deteriorated sections of the subgrade caused by the traffic of the Contractor’s
vehicle/equipment or that of the public.
104.3.8 Templates and Straight-edges
The Contractor shall provide for use of the Engineer, approved templates and straight-
edges in sufficient number to check the accuracy of the work, as provided in this
Specification.
104.3.9 Plate Load Bearing Tests
Where required or instructred by the Engineer, the Contractor shall carry out plate load
bearing tests to ASTM D1196 to determine the bearing capacity of the stratum.
104.4 Measurement and Payment
104.4.1 Method of Measurement
Measurement of Items for payment shall be provided only for:
1) The compaction of existing ground below subgrade level in cuts of common
material as specified in Section 104.3.3.
2) The breaking up or scarifying, loosening, reshaping and recompacting of existing
pavement as specified in Section 104.3.6. The quantity to be paid for shall be the
area of the work specified to be carried out and accepted by the Engineer.
TS100 - 36
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Payment for all work for the preparation of the subgrade, including shaping to the
required levels and tolerances, other than as specified above shall be deemed to
be included in the Pay Item for Embankment.
Measurement for payment for plate loading tests to ASTM D1196 shall be the
number of tests instructed by and accepted by the Engineer.
- END OF SECTION -
TS100 - 37
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 38
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Compaction of control strips shall commence immediately after the course has been
placed to the specified thickness, and shall be continuous and uniform over the entire
surface. Compaction of the control strip shall be continued until no discernible increase
in density can be obtained by additional compactive effort.
Upon completion of the compaction, the mean density of the control strip will be
determined by averaging the results of ten in-place density tests taken at randomly
selected sites within the control strip. The mean density of the control strip shall be the
target density for the remainder of the course which it represents.
If the mean density of the control strip is less than 98 percent of the density of
laboratory compacted specimens as determined by testing procedures appropriate for
the material being placed, the Engineer may order the construction of another control
strip.
A new control strip may also be ordered by the Engineer or requested by the Contractor
when:
1) A change in the material or job-mix formula, is made.
2) Ten days of production have been accepted without construction of a new control
strip.
3) There is reason to believe that a control strip density is not representative of the
material being placed.
105.3 Measurement and Payment
105.3.1 Method of Measurement
No measurement for payment will be made for this Item.
105.3.2 Basis of Payment
Unless otherwise provided, the cost of constructing the control strip will be considered
incidental to the cost of the work item for which a control strip is required. Payment
for the work item shall be deemed to include compensation for performing the work
herein specified and the furnishing of all materials, labors, tools, equipment and
incidentals necessary to construct the density control strip. No payment will be made
for any material used in the construction of unacceptable control strip.
- END OF SECTION -
TS100 - 39
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
50 2” 100
25 1” 55 – 85
9.5 3/8” No. 40 – 75
0.075 200 0 - 12
The fraction passing the 0.075mm (No. 200) sieve shall not be greater than 0.66 (two
thirds) of the fraction passing the 0.425mm (No. 40) sieve.
The fraction passing the 0.425mm (No. 40) sieve shall have a liquid limit not greater
than 35 and plasticity index not greater than 12 as determined by AASHTO T 89 and T
90, respectively.
The coarse portion, retained on a 2.00mm (No. 10) sieve, shall have a mass percent of
wear not exceeding 50 by the Los Angeles Abrasion Tests as determined by AASHTO
T 96.
The material shall have a soaked CBR value of not less than 30% as determined by
AASHTO T 193. The CBR value shall be obtained at the maximum dry density and
determined by AASHTO T 180, Method D.
The required frequency of test for aggregation subbase course consumed at site are as
follows:
For every 3000 cu.m. or fraction thereof:
1) Grading Test, 1-Plasticity Test (LL, PL, PI)
For every 1500 cu.m. and fraction thereof:
1) 1-Laboratory Compaction Test
For every 300 cu.m. and fraction thereof:
1) One (1) CBR, California Bearing Ratio Test, One (1) Abrasion Test
TS100 - 40
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 41
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
has been achieved. In-place density determination shall be made in accordance with
AASHTO T 191.
106.3.4 Trial Sections
Before subbase construction is started, the Contractor shall spread and compact trial
sections as directed by the Engineer. The purpose of the trial sections is to check the
suitability of the materials, the efficiency of the equipment and the construction method
which is proposed to be used by the Contractor. Therefore, the Contractor must use the
same material, equipment and procedures that he proposes to use for the main work.
One trial section of about 500m2 shall be made for every type of material and/or
construction equipment/procedure proposed for use.
After final compaction of each trial section, the Contractor shall carry out such field
density tests and other tests required as directed by the Engineer.
If a trial section shows that the proposed materials, equipment or procedures in the
Engineer’s opinion are not suitable for subbase, the material shall be removed at the
Contractor’s expense, and a new trial section shall be constructed.
If the basic conditions regarding the type of material or procedure change during the
execution of the work, new trial sections shall be constructed.
106.3.5 Tolerances
Aggregate subbase shall be spread with equipment that will provide a uniform layer
which when compacted will conform to the designed level and transverse slopes as
shown on the Drawings. The allowable tolerances shall be as specified hereunder:
Permitted variation from design Thickness Of Layer ± 20mm
TS100 - 42
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Item.
Payment will be made under:
106(4) Aggregate Subbase Course for Gil Puyat Avenue Cubic Meter
TS100 - 43
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
107 SUB-BALLAST
107.1 The Work
The works in this section shall consist of furnishing, placing and compacting an
aggregate sub-ballast of all running tracks, loops and sidings of the railway in
accordance with this Specification and the lines, grades and cross-sections shown on
the Drawings, or as directed by the Engineer.
107.2 Material Requirements
The sub-ballast shall be a granular material so graded as to prevent penetration into the
subgrade and penetration of track ballast particles into the sub-ballast zone. Material
for sub-ballast shall consist of hard, durable particles or fragments of crushed stone,
crushed slag, or crushed or natural gravel and filler of natural or crushed sand. The
material shall be free from vegetable matter and lumps or balls of clay, and shall be of
such nature that it can be compacted readily to form a firm, stable sub-ballast.
Material most commonly available for use as sub-ballast are those aggregates
ordinarily specified and used in construction for highway bases and subbases. These
include crushed stone, natural or crushed gravels, natural or manufactured sands,
crushed slag or a homogeneous mixture of these materials.
Applying the filter principle used in drainage to the grading of the subgrade material
will determine the grain size distribution of the sub-ballast. Most state highway
specifications include standard gradations for dense graded aggregate (DGA) and
aggregate base course (ABC). These gradations may meet the requirements for use as
sub-ballast. Other standard gradations may also meet these requirements.
The grading of Sub-ballast material, when tested in accordance with ASTM C 136, shall
conform to Table 107-1, Grading Requirements.
Table 107-1 Grading Requirements for Sub-ballast
Sieve Designation Percentage passing
50 mm (2”) 100 %
25 mm (1”) 90% to 100%
9,5 mm (2/8”) 50 % to 84 %
2 mm (No.10) 26 % to 50 %
0,425 mm (No.40) 12 % to 30 %
0,075 mm (No.200) 0 % to 10 %
Source location of sub-ballast material shall be proposed by the Contractor and
approved by the Engineer. The Contractor shall be responsible for the selecting proper
materials in the pit and shall not use material not approved by the Engineer for sub-
ballast.
Deleterious substance shall not be present in sub-ballast materials in excess of the
following amounts:
Deleterious Substance ASTM Method of Test Amount
Soft and Friable pieces C 235 5 .0 %
Clay Lumps C 142 0.50%
TS100 - 44
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 46
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
If a trial section shows that the proposed materials, equipment or procedures in the
Engineer’s opinion are not suitable for sub-ballast, the material shall be removed at the
Contractor’s expense, and a new trial section shall be carried out.
If the basic conditions regarding the type of material or procedure change during the
execution of the work, new trial section shall be constructed.
107.3.5 Tolerances
The allowable tolerances shall be as specified hereunder:
Permitted variation ± 20mm
from design thickness of sub-ballast
Subgrade -50mm~+30mm
Level Of Surface
Sub-ballast -20mm~+10mm
END OF SECTION -
TS100 - 47
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 48
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
108.2.4 Water
Water used in mixing, curing or other designated application shall be reasonably clean
and free of oil, salt, acid, alkali, grass or other substances injurious to the finished
product. Water will be sampled for every source and it will be tested in accordance
with and shall meet the requirements of Section 206.3.2. Water which is drinkable may
be used without test. Where the source of water is shallow, the intake shall be so
enclosed as to exclude silt, mud, grass or other foreign materials.
108.2.5 Reinforcing Steel
TS100 - 49
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
It shall conform to the requirements of Section 207, Reinforcing Steel. Dowels and tie
bars shall conform to the requirements of AASHTO M 31 or M 42, except that rail
steel shall not be used for tie bars that are to be bent and restraightened during
construction. Tie bars shall be deformed bars. Dowels shall be plain round bars. Before
delivery to the site of work, one-half of the length of each dowel shall be painted with
one coat of approved lead or tar paint.
The sleeves for dowel bars shall be metal of approved design to cover 50mm, plus or
minus 5mm of the dowel, with a closed end, and with a suitable stop to hold the end of
the sleeve at least 25mm from the end of the dowel. Sleeves shall be of such design that
they do not collapse during construction.
108.2.6 Wire Mesh
The diameter of wire for lateral and longitudinal directions shall not be less than 6mm
in diameter. Tie wire shall be No. 16 gauged annealed wire.
108.2.6.1 Fabrication of Wire Mesh
The spacing on the lateral direction is twice wider than that of the longitudinal
direction. The weight of wire mesh shall not be less than 3 kg/m2. It shall be fabricated
by welding or binding at each crossing point and shall meet the requirements of ASTM
A 185.
108.2.6.2 Installation of Wire Mesh
After placement of slip bar placed at every 9.0m maximum interval for weakened plane
joint, wire mesh shall be placed at a depth of 5.0cm to 7.5cm below the surface of the
slab or at 2/3 of thickness from the bottom of the pavement. It shall be supported by
any approved support assemblies or spacers against displacement and shall be tied to
it using tie wires. The sheets of the welded wire mesh shall be flat, and proper care
shall be observed in handling and placing it to ensure its installation in the proper
position.
Welded wire mesh that have become bent or kinked shall be rejected.
108.2.7 Joint Fillers
Poured joint fillers shall be mixed asphalt and mineral or rubber filler conforming to
the applicable requirements of ASTM D 1752, Joint Materials.
Preformed joint filler shall conform to the applicable requirements ASTM D 1752. It
shall be punched to admit the dowels where called for in the Drawings. The filler for
each joint shall be furnished in a single piece for the full depth and width required for
the joint.
108.2.8 Admixtures
Air-entraining admixture shall conform to the requirements of AASHTO M 154.
Chemical admixtures, if specified or permitted, shall conform to the requirements of
AASHTO M 194.
Fly Ash, if specified or permitted as a mineral admixture and not exceeding 20% partial
replacement of Portland Cement in concrete mix shall conform to the requirements of
ASTM C 618.
Admixture/s maybe added to the concrete mix to produce some desired modifications
to the properties of concrete if necessary, but not as partial replacement of cement. If
TS100 - 50
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 51
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 52
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
The Contractor shall perform all sampling, testing and inspection necessary to
assure quality control of the component materials and the concrete.
The Contractor shall be responsible for determining the gradation of fine and
coarse aggregates and for testing the concrete mixture for slump, air content,
water-cement ratio and temperature. He shall conduct his operations so as to
produce a mix conforming to the approved mix design.
5) Documentation
The Contractor shall maintain adequate records of all inspections and tests. The
records shall indicate the nature and number of observations made, the number
and type of deficiencies found, the quantities approved and rejected, and nature
of any corrective action taken.
The Engineer may take independent assurance samples at random location for
acceptance purposes as he deems necessary.
The Contractor also maintain the Certificate(s) of test result in the approved
laboratory and photo of the inspections and tests.
108.3.2 Equipment
Equipment and tools necessary for handling materials and performing all parts of the
work shall be approved by the Engineer as to design, capacity and mechanical
condition. The equipment shall be at the jobsite sufficiently ahead of the start of
construction operations to be examined thoroughly and approved.
1) Batching Plant and Equipment
a) General. The batching shall include bins, weighing hoppers, and scales for
the fine aggregate and for each size of coarse aggregate. If cement is used in
bulk, a bin, a hopper, and separate scale for cement shall be included. The
weighing hopper shall be properly sealed and vented to preclude dusting
operation. The batch plant shall be equipped with a suitable non- resettable
batch counter which will correctly indicate the number of batches
proportioned.
b) Bins and Hoppers. Bins with adequate separate compartments for fine
aggregate and for each size of coarse aggregate shall be provided in the
batching plant.
c) Scales. Scales for weighing aggregates and cement shall be of either the
beam type or the springless-dial type. They shall be accurate within one-
half percent (0.5%) throughout the range of use. Poises shall be designed to
be locked in any position and to prevent unauthorized change.
Scales shall be inspected and sealed as often as the Engineer may deem necessary
to assure their continued accuracy.
d) Automatic Weighing Devices. Unless otherwise allowed on the Contract,
batching plants shall be equipped with automatic weighing devices of an
approved type to proportion aggregates and bulk cement.
2) Mixers
a) General. Concrete may be mixed at the Site of construction or at a central
plant, or wholly or in part in truck mixers. Each mixer shall have a
TS100 - 53
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 54
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
provided with adequate devices for secure setting so that when in place, they will
withstand, without visible spring or settlement, the impact and vibration of the
consolidation and finishing or paving equipment.
108.3.3 Preparation of Grade
After the subgrade of base has been placed and compacted to the required density, the
areas which will support the paving machine and the grade on which the pavement is
to be constructed shall be trimmed to the proper elevation by means of a properly
designed machine extending the prepared work areas compacted at least 60cm beyond
each edge of the proposed concrete pavement. If loss of density results from the
trimming operations, it shall be restored by additional compaction before concrete is
placed. If any traffic is allowed to use the prepared subgrade or base, the surface shall
be checked and corrected immediately ahead of the placing concrete.
The subgrade or base shall be uniformly moist when the concrete is placed.
108.3.4 Setting Forms
1) Base Support.
The foundation under the forms shall be hard and true to grade so that the form
when set will be firmly in contact for its whole length and at the specified grade.
(Any roadbed, which at the form line is found below established grade, shall be
filled with approved granular materials to grade in lifts of three (3) cm or less,
and thoroughly rerolled or tamped.) Imperfections or variations above grade shall
be corrected by tamping or by cutting as necessary.
2) Form Setting
Forms shall be set sufficiently in advance of the point where concrete is being
placed. After the forms have been set to correct grade, the grade shall be
thoroughly tamped, mechanically or by hand, at both the inside and outside edges
of the base of the forms. The forms shall not deviate from true line by more than
one (1) cm at any point.
3) Grade and Alignment
The alignment and grade elevations of the forms shall be checked and corrections
made by the Contractor immediately before placing the concrete. Testing as to
crown and elevation, prior to placing of concrete can be made by means of holding
an approved template in a vertical position and moved backward and forward on
the forms.
When any form has been disturbed or any grade has become unstable, the form
shall be reset and rechecked.
108.3.5 Conditioning of Subgrade or Base Course
When side forms have been securely set to grade, the subgrade or base course shall be
brought to proper cross-section. High areas shall be trimmed to proper elevation. Low
areas shall be filled and compacted to a condition similar to that of surrounding grade.
The finished grade shall be maintained in a smooth and compacted condition until the
pavement is placed.
Unless waterproof subgrade or base course cover material is specified, the subgrade or
base course shall be uniformly moist when the concrete is placed. If it subsequently
becomes too dry, the subgrade or base course shall be sprinkled, but the method of
TS100 - 55
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 56
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
The Contractor shall furnish test data acceptable to the Engineer verifying that the make
and model of the mixer will produce uniform concrete conforming to the provision of
AASHTO M 157 at the reduced number of revolutions shown on the serial plate.
When mixed at the site or in a central mixing plant, the mixing time shall not be less
than fifty (50) seconds nor more than ninety (90) seconds for drum type mixers, unless
mixer performance tests prove adequate mixing of the concrete in shorter time period.
The operation and mixing time for pan, twinshaft and other type of central mixers shall
be based on the mixer manufacturer’s instructions.
Four (4) seconds shall be added to the specified mixing time if timing starts at the
instant the skip reaches its maximum raised positions. Mixing time ends when the
discharge chute opens. Transfer time in multiple drum mixers is included in mixing
time. The contents of an individual mixer drum shall be removed before a succeeding
batch is emptied therein.
The mixer shall be operated at the drum speed as shown on the manufacturer’s name
plate attached on the mixer. Any concrete mixed less than the specified time shall be
discarded and disposed off by the Contractor at his expense. The volume of concrete
mixed per batch shall not exceed the mixer’s nominal capacity in cubic meter, as shown
on the manufacturer’s standard rating plate on the mixer, except that an overload up to
ten (10) percent above the mixer’s nominal capacity may be permitted provided
concrete test data for strength, segregation, and uniform consistency are satisfactory,
and provided no spillage of concrete takes place.
The batches shall be so charged into the drum that a portion of the mixing water shall
be entered in advance of the cement and aggregates. The flow of water shall be uniform
and all water shall be in the drum by the end of the first fifteen (15) seconds of the
mixing period. The throat of the drum shall be kept free of such accumulations as may
restrict the free flow of materials into the drum.
Mixed concrete from the central mixing plant shall be transported in truck mixers, truck
agitators or non-agitating truck specified in Section 108.3.2, Equipment. The time
elapsed from the time water is added to the mix until the concrete is deposited in place
at the Site shall not exceed forty-five (45) minutes when the concrete is hauled in non-
agitating trucks, nor ninety (90) minutes when hauled in truck mixers or truck agitators,
except that in hot weather or under other conditions contributing to quick hardening of
the concrete, the maximum allowable time may be reduced by the Engineer.
In exceptional cases and when volumetric measurements are authorized for small
project requiring less than 75 cu.m. of concrete per day of pouring, the weight
proportions shall be converted to equivalent volumetric proportions. In such cases,
suitable allowance shall be made for variations in the moisture condition of the
aggregates, including the bulking effect in the fine aggregate. Batching and mixing
shall be in accordance with ASTM C 685, Section 6 through 9.
Concrete mixing by chute is allowed provided that a weighing scales for determining
the batch weight will be used.
Retempering concrete by adding water or by other means shall not be permitted, except
that when concrete is delivered in truck mixers, additional water may be added to the
batch materials and additional mixing performed to increase the slump to meet the
specified requirements, if permitted by the Engineer, provided all these operations are
performed within forty-five (45) minutes after the initial mixing operation and the
TS100 - 57
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
water-cement ratio is not exceeded. Concrete that is not within the specified slump
limits at the time of placement shall not be used. Admixtures for increasing the
workability or for accelerating the setting of the concrete will be permitted only when
specifically approved by the Engineer.
108.3.8 Limitation of Mixing
No concrete shall be mixed, placed or finished when natural light is insufficient, unless
an adequate and approved artificial lighting system is operated.
During hot weather, the Engineer shall require that steps be taken to prevent the
temperature of mixed concrete from exceeding a maximum temperature of 30°C.
Concrete not in place within ninety (90) minutes from the time the ingredients were
charged into the mixing drum or that has developed initial set shall not be used.
Retempering of concrete or mortar which has partially hardened, that is remixing with
or without additional cement, aggregate, or water, shall not be permitted.
In order that the concrete may be properly protected against the effects of rain before
the concrete is sufficiently hardened, the Contractor will be required to have available
at all times materials for the protection of the edges and surface of the unhardened
concrete.
108.3.9 Placing Concrete
Concrete shall be deposited in such a manner to require minimal rehandling. Unless
truck mixers or non-agitating hauling equipment are equipped with means to discharge
concrete without segregation of the materials, the concrete shall be unloaded into an
approved spreading device and mechanically spread on the grade in such a manner as
to prevent segregation. Placing shall be continuous between transverse joints without
the use of intermediate bulkheads. Necessary hand spreading shall be done with
shovels, not rakes. Workmen shall not be allowed to walk in the freshly mixed concrete
with boots or shoes coated with earth or foreign substances.
When concrete is to be placed adjoining a previously constructed lane and mechanical
equipment will be operated upon the existing lane, that previously constructed lane
shall have attained the strength for fourteen (14) day concrete. If only finishing
equipment is carried on the existing lane, paving in adjoining lanes may be permitted
after three (3) days.
Concrete shall be thoroughly consolidated against and along the faces of all forms and
along the full length and on both sides of all joint assemblies by means of vibrators
inserted in the concrete. Vibrators shall not be permitted to come in contact with a joint
assembly, the grade, or a side form. In no case shall the vibrator be operated longer than
fifteen (15) seconds in any one location.
Concrete shall be deposited as near as possible to the expansion and contraction joints
without disturbing them, but shall not be dumped from the discharge bucket or hopper
into a joint assembly unless the hopper is well centered on the joint assembly. Should
any concrete material fall on or be worked into the surface of a complete slab, it shall
be removed immediately.
108.3.10 Test Specimens
As work progresses, at least one (1) set consisting of three (3) concrete beam test
specimens, 150mm × 150mm × 525mm shall be taken from each 330m2 of pavement,
TS100 - 58
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
230mm depth, or fraction thereof placed each day. Test specimens shall be made under
the supervision of the Engineer, and the Contractor shall provide all concrete and other
facilities necessary in making the test specimens and shall protect them from damage
by construction operations. Cylinder samples shall not be used as substitute for
determining the adequacy of the strength of concrete.
The beams shall be made, cured, and tested in accordance with AASHTO T 23 and T
97.
108.3.11 Strike-off of Concrete and Placement of Reinforcement
Following the placing of the concrete, it shall be struck off to conform to the cross-
section shown on the Drawings and to an elevation such that when the concrete is
properly consolidated and finished, the surface of the pavement will be at the elevation
shown on the Drawings. When reinforced concrete pavement is placed in two (2) layers,
the bottom layer shall be struck off and consolidated to such length and depth that the
sheet of fabric or bar mat may be laid full length on the concrete in its final position
without further manipulation. The reinforcement shall then be placed directly upon the
concrete, after which the top layer of the concrete shall be placed, struck off and
screeded. Any portion of the bottom layer of concrete which has been placed more than
30 minutes without being covered with the top layer shall be removed and replaced
with freshly mixed concrete at the Contractor’s expense. When reinforced concrete is
placed in one layer, the reinforcement may be firmly positioned in advance of concrete
placement or it may be placed at the depth shown on the Drawings in plastic concrete,
after spreading by mechanical or vibratory means.
Reinforcing steel shall be free from dirt, oil, paint, grease, mill scale and loose or thick
rust which could impair bond of the steel with the concrete.
108.3.12 Joints
Joints shall be constructed of the type and dimensions, and at the locations required by
the Drawings or Special Provisions. All joints shall be protected from the intrusion of
injurious foreign material until sealed.
1) Longitudinal Joint
Deformed steel tie bars of specified length, size, spacing and materials shall be
placed perpendicular to the longitudinal joints, they shall be placed by approved
mechanical equipment or rigidly secured by chair or other approved supports to
prevent displacement. Tie bars shall not be painted or coated with asphalt or other
materials or enclosed in tubes or sleeves. When shown on the Drawings and when
adjacent lanes of pavement are constructed separately, steel side forms shall be
used which will form a keyway along the construction joint. Tie bars, except those
made of rail steel, may be bent at right angles against the form of the first lane
constructed and straightened into final position before the concrete of the adjacent
lane is placed. In lieu of bent tie bars, approved two-piece connectors may be
used.
Longitudinal formed joints shall consist of a groove or cleft, extending downward
from and normal to the surface of the pavement. These joints shall be effected or
formed by an approved mechanically or manually operated device to the
dimensions and line indicated on the Drawings while the concrete is in a plastic
state. The groove or cleft shall be filled with either a premolded strip or poured
material as required.
TS100 - 59
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
regardless of weather conditions. The sawing of any joint shall be omitted if crack
occurs at or near the joint location prior to the time of sawing. Sawing shall be
discounted when a crack develops ahead of the saw. In general, all joints should
be sawed in sequence. If extreme condition exist which make it impractical to
prevent erratic cracking by early sawing, the contraction joint groove shall be
formed prior to initial set of concrete as provided above.
4) Transverse Construction Joint
It shall be constructed when there is an interruption of more than 30 minutes in
the concreting operations. No transverse joint shall be constructed within 1.50m
of an expansion joint, contraction joint, or plane of weakness. If sufficient
concrete has been mixed at the time of interruption to form a slab of at least 1.5m
long, the excess concrete from the last preceding joint shall be removed and
disposed of as directed.
5) Load Transfer Device
Dowel, when used, shall be held in position parallel to the surface and center line
of the slab by a metal device that is left in the pavement.
The portion of each dowel painted with one coat of lead or tar, in conformance
with the requirements of Section 207, Reinforcing Steel, shall be thoroughly
coated with approved bituminous materials, e.g., MC-70, or an approved
lubricant, to prevent the concrete from binding to that portion of the dowel. The
sleeves for dowels shall be metal designed to cover 50mm plus or minus 5mm, of
the dowel, with a watertight closed end and with a suitable stop to hold the end
of the sleeves at least 25mm from the end of the dowel.
In lieu of using dowel assemblies at contraction joints, dowel may be placed in
the full thickness of pavement by a mechanical device approved by the Engineer.
108.3.13 Final Strike-off (Consolidation and Finishing)
1) Sequence
The sequence of operations shall be the strike-off and consolidation, floating,
removal of laitance, straight-edging and final surface finish. Work bridges or
other devices necessary to provide access to the pavement surface for the purpose
of finishing, straight- edging, and make corrections as hereinafter specified, shall
be provided by the Contractor.
In general, the addition of water to the surface of the concrete to assist in finishing
operations will not be permitted. If the application of water to the surface is
permitted, it shall be applied as fog spray by means of an approved spray
equipment.
2) Finishing Joints
The concrete adjacent to joints shall be compacted or firmly placed without voids
or segregation against the joint material assembly, also under and around all load
transfer devices, joint assembly units, and other features designed to extend into
the pavement. Concrete adjacent to joints shall be mechanically vibrated as
required in Section 108.3.9, Placing Concrete.
After the concrete has been placed and vibrated adjacent to the joints as required
in Section 108.3.9, the finishing machine shall be brought forward, operating in
TS100 - 61
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
equipment.
In operation, the screed shall be moved forward on the forms with a combined
longitudinal and transverse shearing motion, moving always in the direction in
which the work is progressing and so manipulated that neither end is raised from
the side forms during the striking off process. If necessary, this shall be repeated
until the surface is of uniform texture, true to grade and cross-section, and free
from porous areas.
5) Floating
After the concrete has been struck off and consolidated, it shall be further
smoothed, trued, and consolidated by means of a longitudinal float, either by hand
or mechanical method.
a) Hand Method. The hand-operated longitudinal float shall be not less than
365cm in length and 15cm in width, properly stiffened to prevent flexibility
and warping. The longitudinal float, operated from foot bridges resting on
the side forms and spanning but not touching the concrete, shall be worked
with a sawing motion while held in a floating position parallel to the road
center line, and moving gradually from one side of the pavement to the
other. Movement ahead along the center line of the pavement shall be in
successive advances of not more than one- half the length of the float. Any
excess water or soupy material shall be wasted over the side forms on each
pass.
b) Mechanical Method. The mechanical longitudinal float shall be of a design
approved by the Engineer, and shall be in good working condition. The
tracks from which the float operates shall be accurately adjusted to the
required crown. The float shall be accurately adjusted and coordinated with
the adjustment of the transverse finishing machine so that a small amount of
mortar is carried ahead of the float at all times. The forward screed shall be
adjusted so that the float will lap the distance specified by the Engineer on
each transverse trip. The float shall pass over each areas of pavement at least
two times, but excessive operation over a given area will not be permitted.
Any excess water or soupy material shall be wasted over the side forms on
each pass.
c) Alternative Mechanical Method. As an alternative, the Contractor may use a
machine composed of a cutting and smoothing float or floats suspended
from and guided by a rigid frame. The frame shall be carried by four or more
visible wheels riding on, and constantly in contact with the side forms. If
necessary, following one of the preceding method of floating, long handled
floats having blades not less than 150cm in length and 15cm in width may
be used to smooth and fill in open-textured areas in the pavement. Long-
handled floats shall not be used to float the entire surface of the pavement in
lieu of, or supplementing, one of the preceding methods of floating. When
strike off and consolidation are done by the hand method and the crown of
the pavement will not permit the use of the longitudinal float, the surface
shall be floated transversely by means of the long- handled float. Care shall
be taken not to work the crown out of the pavement during the operation.
After floating, any excess water and laitance shall be removed from the
surface of the pavement by a 3-m straight-edge or more in length. Successive
TS100 - 63
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 64
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
and reasonably free from grooves over 1.5mm in depth. Drag shall be maintained
clean and free from encrusted mortar. Drags that cannot be cleaned shall be
discarded and new drags be substituted.
Regardless of the method used for final finish, the hardened surface of pavement
shall have a coefficient of friction of 0.25 or more. Completed pavement that is
found to have a coefficient of friction less than 0.25 shall be grounded or scored
by the Contractor at his expense to provide the required coefficient of friction.
8) Edging at Forms and Joints
After the final finish, but before the concrete has taken its initial set, the edges of
the pavement along each side of each slab, and on each side of transverse
expansion joints, formed joints, transverse construction joints, and emergency
construction joints, shall be worked with an approved tool and rounded to the
radius required by the Drawings. A well–defined and continuous radius shall be
produced and a smooth, dense mortar finish obtained. The surface of the slab shall
not be unduly disturbed by tilting the tool during the use.
At all joints, any tool marks appearing on the slab adjacent to the joints shall be
eliminated by brooming the surface. In doing this, the rounding of the corner of
the slab shall not be disturbed. All concrete on top of the joint filler shall be
completely removed. All joints shall be tested with a straight-edge before the
concrete has set and correction made if one edge of the joint is higher than the
other.
108.3.14 Surface Test
As soon as the concrete has hardened sufficiently, the pavement surface shall be tested
with a 3-m straight-edge or other specified device. Areas showing high spots of more
than 3mm but not exceeding 12mm in 3m shall be marked and immediately ground down
with an approved grinding tool to an elevation where the area or spot will not show
surface deviations in excess of 3mm when tested with 3m straight- edge. Where the
departure from correct cross-section exceeds 12mm, the pavement shall be removed and
replaced by and at the expense of the Contractor.
Any area or section so removed shall be not less than 1.5m in length and not less than
the full width of the lane involved. When it is necessary to remove and replace a section
of pavement, any remaining portion of the slab adjacent to the joints that is less than
1.5m in length, shall also be removed and replaced.
108.3.15 Curing
Immediately after the finishing operations have been completed and the concrete has
sufficiently set, the entire surface of the newly placed concrete shall be cured in
accordance with either one of the methods described herein. Failure to provide
sufficient cover material of whatever kind the Contractor may elect to use, or the lack
of water to adequately take care of both curing and other requirements, shall be a cause
for immediate suspension of concreting operations. The concrete shall not be left
exposed for more than ½ hour between stages of curing or during the curing period.
In all congested places, concrete works should be designed so that the designed strength
is attained.
1) Cotton of Burlap Mats
TS100 - 65
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
The surface of the pavement shall be entirely covered with mats. The mats used
shall be of such length (or width) that as laid they will extend at least twice the
thickness of the pavement beyond the edges of the slab. The mat shall be placed
so that the entire surface and the edges of the slab are completely covered. Prior
to being placed, the mats shall be saturated thoroughly with water. The mat shall
be so placed and weighted down so as to cause them to remain in intimate contact
with the covered surface. The mat shall be maintained fully wetted and in position
for 72 hours after the concrete has been placed unless otherwise specified.
2) Waterproof Paper
The top surface and sides of the pavement shall be entirely covered with
waterproof paper, the units shall be lapped at least 45cm. The paper shall be so
placed and weighted down so as to cause it to remain in intimate contact with the
surface covered. The paper shall have such dimension but each unit as laid will
extend beyond the edges of the slab at least twice the thickness of the pavement,
or at pavement width and 60cm strips of paper for the edges.
If laid longitudinally, paper not manufactured in sizes which will provide this
width shall be securely sewed or cemented together, the joints being securely
sealed in such a manner that they do not open up or separate during the curing
period. Unless otherwise specified, the covering shall be maintained in place for
72 hours after the concrete has been placed. The surface of the pavement shall be
thoroughly wetted prior to the placing of the paper.
3) Straw Curing
When this type of curing is used, the pavement shall be cured initially with burlap
or cotton mats, until after final set of the concrete or, in any case, for 12 hours
after placing the concrete. As soon as the mats are removed, the surface and sides
of the pavement shall be thoroughly wetted and covered with at least 20cm of
straw or hay, thickness of which is to be measured after wetting. If the straw or
hay covering becomes displaced during the curing period, it shall be replaced to
the original depth and saturated. It shall be kept thoroughly saturated with water
for 72 hours and thoroughly wetted down during the morning of the fourth day,
and the cover shall remain in place until the concrete has attained the required
strength.
4) Impervious Membrane Method
The entire surface of the pavement shall be sprayed uniformly with white
pigmented curing compound immediately after the finishing of the surface and
before the set of the concrete has taken place, or if the pavement is cured initially
with jute or cotton mats, it may be applied upon removal of the mass. The curing
compound shall not be applied during rain.
Curing compound shall be applied under pressure at the rate 4 L to not more than
14m2 by mechanical sprayers. The spraying equipment shall be equipped with a
wind guard. At the time of use, the compound shall be in a thoroughly mixed
condition with the pigment uniformly dispersed throughout the vehicle. During
application, the compound shall be stirred continuously by effective mechanical
means. Hand spraying of odd widths or shapes and concrete surface exposed by
the removal of forms will be permitted. Curing compound shall not be applied to
the inside faces of joints to be sealed, but approved means shall be used to insure
TS100 - 66
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
proper curing at least 72 hours and to prevent the intrusion of foreign material
into the joint before sealing has been completed. The curing compound shall be of
such character that the film will harden within 30 minutes after application. Should
the film be damaged from any cause within the 72 hour curing period, the
damaged portions shall be repaired immediately with additional compound.
5) White Polyethylene Sheet
The top surface and sides of the pavement shall be entirely covered with
polyethylene sheeting. The units used shall be lapped at least 45cm. The sheeting
shall be so placed and weighted down so as to cause it to remain intimate contact
with the surface covered. The sheeting as prepared for use shall have such
dimension that each unit as laid will extend beyond the edges of the slab at least
twice the thickness of the pavement. Unless otherwise specified, the covering
shall be maintained in place for 72 hours after the concrete has been placed.
108.3.16 Removal of Forms
Forms for concrete shall remain in place undisturbed for not less than twenty-four
(24) hours after concrete pouring. In the removal of forms, crowbars should be used in
pulling out nails and pins. Care should be taken so as not to break the edges of the
pavement. In case portions of the concrete are spalled, they shall be immediately
repaired with fresh mortar mixed in the proportion of one part of Portland Cement and
two parts fine aggregates. Major honeycomb areas will be considered as defective
work, and shall be removed and replaced at the expense of the Contractor. Any area or
section so removed shall not be less than the distance between weakened plane joint
nor less than the full width of the lane involved.
108.3.17 Sealing Joints
Joints shall be sealed with asphalt sealant soon after completion of the curing period and
before the pavement is opened to traffic, including the Contractor’s equipment. Just
prior to sealing, each joint shall be thoroughly cleaned of all foreign materials including
membrane curing compound and the joint faces shall be clean and surface dry when
the seal is applied.
The sealing material shall be applied to each joint opening to conform to the details
shown on the Drawings or as directed by the Engineer. Material for seal applied hot
shall be stirred during heating so that localized overheating does not occur. The pouring
shall be done in such a manner that the material will not be spilled on the exposed
surfaces of the concrete. The use of sand or similar material as a cover for the seal will
not be permitted.
Preformed elastomeric gaskets for sealing joints shall be of the cross- sectional
dimensions shown on the Drawings. Seals shall be installed by suitable tools, without
elongation and secured in placed with an approved lubricant adhesive which shall cover
both sides of the concrete joints. The seals shall be installed in a compressive condition
and shall at time of placement be below the level of the pavement surface by
approximately 6mm.
The seals shall be in one piece for the full width of each transverse joint.
108.3.18 Protection of Pavement
The Contractor shall protect the pavement and its appurtenances against both public
TS100 - 67
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
traffic, and traffic caused by his own employees and agents. This shall include
watchmen to direct traffic, and the erection of and maintenance of warning signs, lights,
pavement bridges or cross-overs, etc. The Drawings or Special Provisions will indicate
the location and type of device or facility required to protect the work and provide
adequately for traffic.
All boreholes after thickness and/or strength determinations of newly constructed
asphalt and concrete pavements shall be immediately filled/restored with the prescribed
concrete/asphalt mix after completion of the drilling works. Any damage to the
pavement, occurring prior to final acceptance, shall be repaired or the pavement be
replaced.
108.3.19 Concrete Pavement – Slip Form Method
If the Contract calls for the construction of pavement without the use of fixed forms, the
following provisions shall apply:
1) Grade
After the grade or base has been placed and compacted to the required density, the
areas which will support the paving machine shall be cut to the proper elevation
by means of a properly designed machine. The grade on which the pavement is
to be constructed shall then be brought to the proper profile by means of properly
designed machine. If the density of the base is disturbed by the grading operation,
it shall be corrected by additional compaction before concrete is placed. The grade
should be constructed sufficiently in advance of the placing of the concrete. If any
traffic is allowed to use the prepared grade, the grade shall be checked and
corrected immediately before the placing of concrete.
2) Placing Concrete
The concrete shall be placed with an approved slip-form paver designed to spread,
consolidate, screed and float-finish the freshly placed concrete in one complete
pass of the machine in such a manner that a minimum of hand finish will be
necessary to provide a dense and homogenous pavement in conformance with the
Drawings and Specifications. The machine shall vibrate the concrete for the full
width and depth of the strip of pavement being placed. Such vibration shall be
accompanied with vibrating tubes or arms working in the concrete or with a
vibrating screed or pan operating on the surface of the concrete. The sliding forms
shall be rigidly held together laterally to prevent spreading of the forms. The
forms shall trail behind the paver for such a distance that no appreciable slumping
of the concrete will occur, and that necessary final finishing can be accomplished
while the concrete is still within the forms. Any edge slump of the pavement,
exclusive of edge rounding, in excess of 6mm shall be corrected before the
concrete has hardened.
The concrete shall be held at a uniform consistency, having a slump of not more
than 40mm. The slip form paver shall be operated with as nearly as possible a
continuous forward movement and that all operations of mixing, delivering and
spreading concrete shall be coordinated so as to provide uniform progress with
stopping and starting of the paver held to a minimum. If, for any reason, it is
necessary to stop the forward movement of the paver the vibratory and tamping
elements shall also be stopped immediately. No tractive force shall be applied to
the machine, except that which is controlled from the machine.
TS100 - 68
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
3) Finishing
The surface smoothness and texture shall meet the requirements of Section
108.3.13 and Section 108.3.14.
4) Curing
Unless otherwise specified, curing shall be done in accordance with one of the
methods included in Section 108.3.15. The curing media shall be applied at the
appropriate time and shall be applied uniformly and completely to all surfaces and
edges of the pavement.
5) Joints
All joints shall be constructed in accordance with Section 108.3.12.
6) Protection Against Rain
In order that the concrete may be properly protected against rain before the
concrete is sufficiently hardened, the Contractor will be required to have available
at all times, materials for the protection of the edges and surface of the unhardened
concrete. Such protective materials shall consist of standard metal forms or wood
planks having a nominal thickness of not less than 50mm and a nominal width of
not less than the thickness of the pavement at its edge for the protection of the
pavement edges, and covering material such as burlap or cotton mats, curing paper
or plastic sheeting materials for the protection of the surface of the pavement.
When rain appears imminent, all paving operations shall stop and all available
personnel shall begin placing forms against the sides of the pavement and
covering the surface of the unhardened concrete with the protective covering.
108.3.20 Acceptance of Concrete
The strength level of the concrete will be considered satisfactory if the averages of all
sets of three (3) consecutive strength test results equal or exceed the specified strength,
fc’ and no individual strength test result is deficient by more than 15% of the specified
strength, fc’. A set shall consist of a minimum of three (3) concrete beam specimens.
Concrete deemed to be not acceptable using the above criteria may be rejected unless
the Contractor can provide evidence, by means of core tests, that the quality of concrete
represented by failed test results is acceptable in place. At least three (3) representative
cores shall be taken from each member or area of concrete in place that is considered
deficient. The location of cores shall be determined by the Engineer so that there will
be at least impairment of strength of the structure. The obtaining and testing of drilled
cores shall be in accordance with AASHTO T 24.
Concrete in the area represented by the cores will be considered adequate if the average
strength of the cores is equal to at least 85% of, and if no single core is less than 75%
of, the specified strength, fc’.
If the strength of control specimens does not meet the requirements of this subsection,
and it is not feasible or not advisable to obtain cores from the structure due to structural
considerations, payment of the concrete will be made at an adjusted price due to
strength deficiency of concrete specimens as specified hereunder:
Deficiency in Strength of Concrete Percent (%) of Contract Price Allowed
Specimens, Percent (%)
TS100 - 69
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 70
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 72
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Joint Mortar – Joint mortar for concrete pipes shall consist of 1 part, by volume of
TS100 - 73
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Portland Cement and two (2) parts of approved sand with water as necessary to obtain
the required consistency.
Portland Cement and sand shall conform to the requirements of Section 206, Concrete
Structures. Mortar shall be used within 30 minutes after its preparation.
or selected sandy soil all of which passes a 9.5mm sieve and not more than 10 percent
of which passes a 0.075mm sieve. The layer of the bedding material shall be shaped to
fit the conduit for at least 15 percent of its total height. Recesses in the trench bottom
shall be shaped to accommodate the bell when bell and spigot type conduit is used.
Class C bedding shall consist of bedding the conduit to a depth of not less than 10
percent of its total height. The foundation surface, completed in accordance with
Section 201 Structure Excavation in TS200 Bridge and Viaduct shall be shaped to fit
the conduit and shall have recesses shaped to receive the bells, if any.
For flexible pipe, the bed shall be roughly shaped and a bedding blanket of sand or fine
granular material as specified above shall be provided as follows:
Pipe Corrugation Depth Minimum Bedding Depth
10mm 25mm
25mm 50mm
50mm 75mm
For large diameter structural plate pipes the shaped bed need not exceed the width of
bottom plate.
109.3.3 Laying Conduit
The conduit laying shall begin at the downstream end of the conduit line. The lower
segment of the conduit shall be in contact with the shaped bedding throughout its full
length. Bell or groove ends of rigid conduits and outside circumferential laps of flexible
conduits shall be placed facing upstream. Flexible conduit shall be placed with
longitudinal laps or seams at the sides.
Paved or partially-lined conduit shall be laid such that the longitudinal center line of
the paved segment coincides with the flow line. Elliptical and elliptically reinforced
conduits shall be placed with the major axis within 5 degrees of a vertical plane through
the longitudinal axis of the conduit.
109.3.4 Jointing Conduit
Rigid conduits may either be of bell and spigot or tongue and groove design unless
another type is specified. The method of joining conduit sections shall be such that the
ends are fully entered and the inner surfaces are reasonably flush and even.
Joints shall be made with (a) Portland Cement mortar, (b) Portland Cement grout, (c)
rubber gaskets, (d) oakum and mortar, (e) oakum and joint compound, (f) plastic
sealing compound, or by a combination of these types, or any other type, as may be
specified. Mortar joints shall be made with an excess of mortar to form a continuous
bead around the outside of the conduit and finished smooth on the inside. For grouted
joints, molds or runners shall be used to retain the poured grout. Rubber ring gaskets
shall be installed so as to form a flexible water-tight seal. Where oakum is used, the
joint shall be called with this material and then sealed with the specified material.
When Portland Cement mixtures are used, the completed joints shall be protected
against rapid drying by any suitable covering material.
Flexible conduits shall be firmly joined by coupling bands.
Concrete for Conduit joint shall be cured at least 7days and conduits shall be inspected
before any backfill is placed. Any pipe found to be out of alignment, unduly settled, or
damaged shall be taken up and re-laid or replaced.
TS100 - 75
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 76
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
side of the conduit for the portion above the top of the trench shall be equal to twice
the diameter of the conduit or 3.5m, whichever is less. The backfill material used in the
trench section and the portion above the top of the trench for a distance on each side of
the conduit equal to the horizontal inside diameter and to 300mm above the top of the
conduit shall conform to the requirements for backfill materials in this section. The
remainder of the backfill shall consist of materials from excavation and borrow that is
suitable for embankment construction.
Compaction to the density specified in Section 103, Embankment, shall be achieved by
use of mechanical tampers or by rolling.
All conduits after being bedded and backfilled as specified in this subsection shall be
protected by one-meter cover of fill before heavy equipment is permitted to cross
during construction of the railway.
109.3.8 Imperfect Trench
Under this method, for rigid conduit, the embankment shall be completed as described
in Section 109.3.7, Backfilling, to a height above the conduit equal to the vertical outside
diameter of the conduit plus 300mm. A trench equal in width to the outside horizontal
diameter of the conduit and to the length shown on the Drawings or as directed by the
Engineer shall then be excavated to within 300mm of the top of the conduit, trench
walls being as nearly vertical as possible. The trench shall be loosely filled with highly
compressible soil. Construction of embankment above shall then proceed in a normal
manner.
109.4 Measurement and Payment
109.4.1 Method of Measurement
Conduit of the different types and sizes, both new and re-laid, will be measured by the
linear meter in place. Conduit with sloped or skewed ends will be measured along the
invert. Branch connection and elbows will be included in the length of measurement
for conduit.
Class B bedding material placed and approved shall be measured by the cubic meter in
place.
When the Bid Schedule contains an estimated quantity for “Furnishing and Placing
Backfill Material, Pipe Culvert”, the quantity to be paid for will be the number of cubic
meter completed in place and accepted, measured in final position between limits as
follows:
1) Measurement shall include backfill material in the trench up to the top of the
original ground line but will not include any material placed outside of vertical
planes 450mm up outside of and parallel to the inside wall of pipe at its widest
horizontal dimension.
2) When the original ground line is less than 300mm above the top of the pipe, the
measurement will also include the placing of all backfill materials, above the
original ground line adjacent to the pipe for a height of 300mm above the top of
pipe and for a distance on each side of the pipe not greater than the widest
horizontal dimension of the pipe.
3) The measurement shall include the placing of backfill material in all trenches of
the imperfect trench method. Materials re-excavated for imperfect trench
TS100 - 77
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 78
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 79
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
110 UNDERDRAINS
110.1 The Works
The works in this section shall consist of constructing underdrains, using pipe and
granular filter materials, underdrain pipe outlets, and blind drains using granular
material in accordance with this Specification and in reasonably close conformity with
the lines and grades shown on the Drawings or as established by the Engineer.
110.2 Material Requirements
Material shall meet the requirements specified in the following specifications:
Zinc coated (galvanized) corrugated iron or steel culverts AASHTO M 36
and underdrains:
Extra strength and standard strength clay pipe and AASHTO M 65
perforated clay pipe:
Perforated concrete pipe: AASHTO M 175
Porous concrete pipe: AASHTO M 176
TS100 - 80
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
specified. Upgrade end sections of all subdrainage pipe installations shall be closed with
suitable plugs to prevent entry of soil materials.
After the pipe installation has been inspected and approved, granular backfill material
shall be placed to a height of 300mm above the top of pipe. Care shall be taken not to
displace the pipe or the covering at open joints. The remainder of the granular backfill
material shall then be placed and compacted in 150mm maximum layers to the required
height. Any remaining portion of trench above the granular backfill shall be filled with
either granular or impervious material, as may be specified, and thoroughly compacted.
110.3.2 Underdrain Outlets
Trenches for underdrain outlets shall be excavated to the width and depth shown on the
Drawings or as otherwise directed. Pipes shall be laid in the trench with all ends firmly
joined by the applicable methods and means. After inspection and approval of the pipe
installation, the trench shall be backfilled in accordance with Section 201, Structure
Excavation.
The end of drain pipe projection into the open tranch shall not be less than 50mm from
the open trench side wall.
110.3.3 Blind Drain
Trenches for blind drains shall be excavated to the width and depth shown on the
Drawings. The trench shall be filled with granular backfill material to the depth
required by the Drawings. Any remaining upper portion of trench shall be filled with
either granular or impervious material in accordance with Section 201102, Structure
Excavation.
110.4 Measurement and Payment
110.4.1 Method of Measurement
Underdrains and outlets shall be measured by the linear meter for pipe of the type and
size specified, including all excavation, backfill and backfill materials required. Blind
drains shall be measured by the linear meter including all excavation and backfill
materials required.
110.4.2 Basis of Payment
The accepted quantities determined as provided in Section 110.4.1, Method of
Measurement, shall be paid for at the contract unit prices.
Payment will be made under:
Pay Item Description Unit of
Number Measurement
110 (1) Under drain, 100mm Diameter Linear Meter
110 (2) Under drain, 150mm Diameter Linear Meter
110 (3) Under drain, 200mm Diameter Linear Meter
110 (4) Under drain, 250mm Diameter Linear Meter
110 (5) Under drain, 300mm Diameter Linear Meter
- END OF SECTION -
TS100 - 81
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Pre-cast Concrete Units – These units shall be cast in substantial permanent steel forms.
Structural concrete used shall attain a minimum 28-day compressive strength of 21
MPa. The pre-cast units shall be cured in accordance with AASHTO M 171. Water
absorption of individual cores taken from such units shall not exceed 7 percent.
TS100 - 82
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 83
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
The number of existing manholes, inlets and catch basins adjusted as directed will be
measured as acceptably completed.
111.4.2 Basis of Payment
The accepted quantities, determined as provided in Section 111.4.1, Method of
Measurement of the Pay Items in the Bill of Quantities will be paid for at the contract
unit prices, which shall constitute full compensation for furnishing and placing all
materials and for all labor, equipment, tools and incidentals necessary to complete the
Item.
Payment will be made under:
Pay Item Description Unit of
Number Measurement
111 (1) Curb Inlet Manhole (Drainage Channel, W1000 × Each
D1000)
MANHOLE/CATCH BASIN RCPC
TS100 - 84
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 85
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 86
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 87
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 88
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 89
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 90
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 91
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 92
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 93
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 94
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 95
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
readily in the same position when installed. Inaccuracy of bearings shall be corrected
by machining, if necessary. The steel grating and its corresponding frame shall
constitute one pair.
When grade adjustment of existing drainage grates is specified, the frames and steel
gratings shall be removed and the walls shall be reconstructed as required. The cleaned
frames shall be reset at the required elevation. Upon completion, each drainage grates
shall be cleaned of any accumulations of silt, debris, or foreign matter of any kind and
shall be kept clear of such accumulation until final acceptance of the work.
Excavation and backfill shall be done in accordance with Section 102, Excavation.
112.6 Acceptance Requirement
A sufficient number of cylinders for concrete construction shall be cast from the
concrete for each unit for compression tests at 7, 14 and 28 days, and to allow for at
least 3 cylinders of each test. If the strength requirement is met at 7 or 14 days, the units
shall be certified for use 14 days from the date of casting. If the strength is not met at
28 days, all units made from that batch or load will be rejected.
The steel grating plants will be inspected periodically for compliance with specified
manufacturing and fabricating methods and bars samples will be obtained for
laboratory testing for compliance with material quality requirements.
All draining grates materials shall be subjected to inspection for acceptance as to
condition at the latest practicable time the Engineer has the opportunity to check for
compliance prior to or during incorporation of materials into the work.
112.7 Measurement and Payment
112.7.1 Method of Measurement
The quantity to be measured and paid for will be the number of pairs of metal frames
and gratings completed and accepted. Concrete and reinforcing steel (AASHTO M 31)
will be measured and paid for under Section 206, Concrete Structures and Section 207,
Reinforcing Steel, respectively.
Excavation and backfill will be measured and paid for as provided in Section 102
Excavation.
112.7.2 Basis of Payment
The accepted quantities, determined as provided in Section 112.7.1, Method of
Measurement of the Pay Items in the Bill of Quantities will be paid for at the contract
unit prices, which shall constitute full compensation for furnishing and placing all
materials and for all labor, equipment, tools and incidentals necessary to complete the
item.
Payment will be made under:
TS100 - 96
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 97
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 98
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
-END OF SECTION-
TS100 - 99
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 101
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
course is an integral part of the wall. The tops of top course of stone shall be pitched to
line, in both vertical and horizontal planes.
115.3.7 Cleaning Exposed Faces
Immediately after being laid, and while the mortar is fresh, all face stones shall be
thoroughly cleaned of mortar stains and shall be kept clean until the work is
completed.
115.3.8 Curing
In hot or dry weather, the masonry shall be satisfactory protected from the sun and
shall be kept wet for a period of at least three days after completion.
115.4 Measurement and Payment
115.4.1 Method of Measurement
Stone masonry shall not be measured and paid for separately, but the cost thereof
shall be considered as included in the contract unit price of Items where called for.
The quantity to be paid for shall be the number of cubic meters of stone masonry
complete in place and accepted. Projections extending beyond the faces of the walls
shall not be included. In computing the quantity for payment, the dimensions used
shall be those shown on the Drawings or as ordered in writing by the Engineer. No
deductions shall be made for weep holes, drain pipes or other openings of less than
one square meter in area.
115.4.2 Basis of Payment
The quantity of masonry, determined as provided in Section 115.4.1, Method of
Measurement, shall be paid for at the contract unit price per cubic meter for Stone
Masonry, which price and payment shall be full compensation for furnishing and
placing all materials, including mortar for masonry, for all necessary excavations, and
for all labor, equipment, tools and incidentals necessary to complete the Item.
- END OF SECTION -
TS100 - 102
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 103
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 104
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 105
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 106
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 107
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Test Method
TS100 - 108
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
The PVC coating shall not show cracks or breaks after the wires are twisted in the
fabrication of the mesh.
4) Style 4 double-twisted mesh shall be manufactured from aluminum- coated steel
wire conforming to Specification ASTM A 809, soft temper.
119.2.3 Lacing Wire and Stiffener
Lacing wire and stiffeners shall be made of wire having the same coating material as
the double-twisted wire mesh conforming to Specification ASTM A 641, A 856/A
856 M or A 809 with a tensile strength in accordance with Section 119.2.7.
1) Fasteners made from zinc-coated steel wire, zinc - 5% aluminum mischmetal
alloy-coated steel wire and aluminum-coated steel wire shall conform to
specification A 764, Type A, B, or C, Table 2 or Table 3.
2) Gabions and mattresses shall be manufactured with all components mechanically
connected at the production facility with the exception of the mattresses lid that
is produced separately from the base. All gabions and mattresses shall be supplied
in collapsed form, either folded and bundled or rolled, for shipping.
119.2.4 Dimensions
The minimum size of the galvanized and PVC coated wire to be used in the
fabrication of the gabion and mattresses shall be as follows:
Diameter, mm
TS100 - 109
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Strength, MPa
Gabions and Mattresses Wires
Gabions Mattresses
TS100 - 110
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
2) When the gabion length exceeds its width, it shall have securely tied diaphragms
connected at all edges to form individual cells of equal length and width.
Gabions shall be fabricated in such a manner that the sides, ends, lids and
diaphragms can be assembled at the construction site into rectangular baskets of
the specified sizes. Gabions shall be of single unit construction, base, lids, ends
and sides shall be either woven into a single unit or one edge of these members
connected to the base section of the gabion in such a manner that the strength and
flexibility at the point of connection is at least equal to that of the mesh.
The gabion shall be equally divided by diaphragms, placed at not more than 1.0m
intervals, and of the same mesh and gauge as the body of the gabions, into cells
the length of which does not exceed the horizontal width. The gabion shall be
furnished with the necessary diaphragms secured in proper position on the base
in such a manner that no additional tying at this junction will be necessary.
3) Four cross-connecting wires shall be provided in each cell having a height of one
half the width or less, and eight cross-connecting wires shall be provided in each
cell having a height greater than one half the width.
All perimeter edge of the mesh forming the gabion shall be securely selvedged so
that the joints, by tying the selvedges, have at least the same strength as the body
of the mesh.
Selvedge wire used through all the edges (perimeter wire) shall not be less than
3.80mm diameter and shall meet the same specifications as the wire mesh.
119.3.2 Assembly and Construction
1) Gabions shall be installed in a workmanlike manner. The gabions shall be placed
on a smooth foundation. The final line and grade shall be approved by the
Engineer.
Each gabion unit shall be assembled by binding together all vertical edges with
wire ties on approximately 152mm spacing or by a continuous piece of connecting
wire stitched around the vertical edges with a coil every 102mm. Empty gabion
units shall be set to line and grade as shown on the Drawings or as described by
the Engineer. Wire ties or connecting wires shall be used to join the units together
in the same manner as described above for assembling. Internal tie wires shall be
uniformly spaced and securely fastened in each cell of the structure.
A standard fence stretcher, chain fall, or iron rod may be used to stretch the wire
baskets and hold alignment.
2) When possible the subgrade of the mattress and gabion shall be properly
compacted to a depth of 150mm. The Contractor shall consider the cost of
subgrade preparation in the unit prices. Filter fabric as beds of gabions and
mattresses forming the structure shall be suitably leveled and shall be securely
connected along the complete length of all contact edges by means of the above
specified tying and connecting wire.
3) Before the filling material is placed, the gabions and mattresses shall be carefully
selected for uniformity of size, and the pieces shall be handplaced to provide a
neat appearance as approved by the Engineer.
The gabions shall be filled with stone carefully placed by hand or machine to
TS100 - 111
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
assure alignment and avoid bulges with minimum voids. Alternate placing of rock
and connection wires shall be performed until the gabion is filled. After a gabion
has been filled, the lid shall be bent over until it meets the sides and edges. The
lid shall then be secured to the sides, ends and diaphragms with the wire ties or
connecting wire in the manner described for assembling.
The vertical joints of gabions and mattress baskets shall be staggered as in running
bond in brickwork.
4) The cells in any row shall be filled in stage so that local deformation may be
avoided. That is at no time shall the cell be filled by stage 1/3rd filling, 2/3rd and
then to full with final level few mm above the top of the gabions and mattreses.
than the adjoining cell.
To ensure no movement of rockfill inside the cells, add laying pattern of the
mattresses on slopes and along the watercourse as construction requirements.
5) Filter fabric shall be placed between earth surface and gabion or mattress
structures. Filter fabric shall be rolled out into a flat non- rutted surface free from
sharp objects, weighing down the edges. Construction equipment shall not be
allowed into unprotected fabric. Jointing is normally affected by overlapping not
less than 300mm, but it is preferable to joint by sewing or industrial stapling. Joint
edges should be facing downwards to avoid protruding through the surface
material.
119.4 Measurement and Payment
119.4.1 Method of Measurement
Gabion shall not be measured and paid for separately, but the cost thereof shall be
considered as included in the contract unit price of Items where called for.
- END OF SECTION -
TS100 - 112
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
approved yarn woven into a plain weave mesh. Straw and coconut mats shall
conform to Table 120-2 as shown below:
Table 120-2 Straw and Coconute Mat
Material Property Specification
TS100 - 114
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 115
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 116
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 117
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 118
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 119
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Backfill the system with topsoil. Hand-compact the topsoil within each cell. Apply
permanent turf establishment.
120.4 Acceptance Requirements
120.4.1 Certification
The manufacturer shall file with the purchaser a certificate stating the name of the
manufacturer, the chemical composition of the filaments or yarns, and other pertinent
information so as to fully describe material (including mats, roving and other cellular
confinement systems) for erosion control, ditch and slope protection, and
stabilization. The manufacturer shall include in the certificate a guarantee stating that
the material that is furnished meets the requirements of the specification. The
certificate shall be attested to by a person having legal authority to bind the company.
Either mismarking or misinterpretation by the manufacturer shall be reason to
discontinue acceptance under these specifications. Notice sent to the manufacturer by
the purchaser regarding the discontinuance of acceptance will be considered to be
notice to all wholesalers, jobbers, distributors, agents and other intermediaries
handling the manufacturer’s product.
The Engineer shall evaluate acceptance for the material for topsoil through visual
inspection comply with the requirements of Section 132, Topsoil.
The Engineer shall evaluate acceptance for turf establishment work through visual
inspection and certification as prescribed in Section 120.4.1, Certification.
120.5 Quality Control
The manufacturer of the material is responsible for establishing and maintaining a
quality control program so as to assure compliance with the requirements of this
specification.
120.6 Shipment and Storage
During periods of shipment and storage, the material shall be protected from direct
sunlight, ultraviolet rays, and temperatures greater than 60ºC, mud, dust, and debris.
To the extent possible, the material shall be maintained wrapped in a heavy-duty
protective covering. Each shipping document shall include a notation certifying that
the material is in accordance with the manufacturer’s certificate and guarantee
previously filed with the purchaser.
120.6.1 Product Marking
Label the material and its container with the manufacturer’s name, material’s type or
trade name, lot number and quantity.
120.7 Measurement and Payment
120.7.1 Method of Measurement
1) Erosion control mats, roving, and cellular confinement systems shall be
measured by the number of square meters excluding overlaps.
2) Topsoil will be measured and paid for as provided in Section 132, Topsoil.
3) Turf establishment will be measured on the following applicable methods:
a) Seeding and mulching will be measured by the number of square meters.
b) Fertilizer, dry method will be measured by the metric ton.
TS100 - 120
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 121
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 122
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
5 35-75
2 20-50
0.425 5-25
0.075 1-7
TS100 - 123
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
outlets of water can be obtained and shall be spaced not more than three (3) meters
center to center as shown on the approved Drawings or as directed by the Engineer.
121.4 Measurement and Payment
121.4.1 Method of Measurement
Wet stone masonry (cobble stone) shall not be measured and paid for separately, but
the cost thereof shall be considered as included in the contract unit price of Items
where called for.
- END OF SECTION -
TS100 - 124
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 125
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 126
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
123 HYDROSEEDING
123.1 The Work
The works in this section shall consist of furnishing grass seeds mixed with an airtrol
geobinder, cellulose fiber mulch, cocopeat and fertilizer to form into a consistent and
homogenous slurry and then sprayed evenly on the ground in accordance with this
specification and in conformity with the lines, grades and dimensions shown on the
Drawings or as established by the Engineer.
123.2 Material Requirements
123.2.1 Grass Seeds
The seeds to be used for vegetative cover shall be the approved seed varieties that is
tested to withstand harsh weather conditions, characteristically aggressive, perennial,
tropical, produce both runners and thizomes, deep-rooted, will rapidly colonize bare
ground and form a dense mat of vegetation ground cover. When established will form
an umbrella surface cover to dissipate rain drops impact. Environmental friendly and
low maintenance.
Permanent Ground Cover Grass Seed Centrosa 50% Calopogonium 50% - 80 to 100kg/ha.
Temporary Grass Nursing Seed White Millet – 30 kg/ha.
Seed Purity 85%
Germination 80 – 90% Average
Adaptability Tropical
123.2.2 Geobinder
Airtrol geobinder is a low cost cementitious binder, when mixed with water and
mulch, sets in a predictable way to form an erosion resistant crust. The application
rate for Geobinder Airtrol should be 1,500 kg/ha.
123.2.3 Cellulose Fiber Mulch
It is manufactured and processed from recycled paper.
Moisture Content 15-20%
Organic Matter 99.5%
Water Holding Capacity 100 grams DW will hold 1,000
grams of water
pH Level 5.5 to 6.0% Dry Weight (DW) of water
Mulching Rate 1850 kg/hectare
123.2.4 Cocopeat
By-product of coco fiber consisting coco fiber and dust sieved in 5mm mesh.
123.2.5 Fertilizer
Chemical/Grade/Organic Fertilizer locally produced and must be both environmental
friendly and non-toxic.
TS100 - 127
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 128
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 129
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
more than 25cm at the base. The precast curb and gutter shall be 1.0m in length and
shall be put side by side consecutively with joint in between.
Joints between consecutive curb and gutter shall be filled with cement mortar to the
full section of the curb and gutter. Expansion joints shall be formed at intervals shown
on the Drawings. Where a curb and gutter is placed next to a concrete pavement,
expansion joints in the curb and gutter shall be located opposite expansion joints in
the pavement.
Minor defects shall be repaired with mortar containing one part of Portland Cement
and two parts of fine aggregates. Plastering shall not be permitted and all rejected
portions shall be removed and replaced at the Contractor’s expense. The exposed
surface shall be finished by rubbing the surfaces with a wetted soft brick or wood
until they are smooth. The surfaces shall be wetted thoroughly, either by dipping the
brick or wood in water, or by throwing water on the surfaces with a brush. After the
concrete has been rubbed smooth using water, it shall then be rubbed with a thin grout
containing one part of Portland Cement and one part of fine aggregate. Rubbing with
grout shall continue until uniform color is produced.
124.3.3.2 Handling Precast Curb and Gutter
In preparation for the handling of precast curb and gutter, all fabricated curb and
gutter of one (1) meter in length shall be provided or inserted with 2(25mm) Ø PVC
pipes for fitting at their required locations. The PVC pipes shall be placed 25mm from
both edge during the plastic state of fresh concrete.
Precast curb and gutter shall be lifted on upright position and not at the points of
support and shall be the same during transporting and storage.
Extreme care shall be exercised in handling and moving precast curb and gutter to
avoid cracking.
No precast curb and gutter shall be used that does not reach its final position in the
forms with the required time stipulated prior to installation.
Precast curb and gutter shall be transferred to the construction site. Fresh curb and
gutter shall not be placed against in-situ concrete which has been in a position for
more than 30 minutes.
124.4 Measurement and Payment
124.4.1 Method of Measurement
The length of curb and gutter to be paid for shall be the number of linear meters of
curb and gutter (cast in place) or the number of pieces of precast curb and gutter of the
required dimensions shown on the Drawings measured along its front face in- place,
completed and accepted. No deductions shall be made for flattening of curbs at
entrances and no additional allowances shall be made for curbs and gutters
constructed on curves.
124.4.2 Basis of Payment
The length of curb and gutter determined in Section 124.4.1, Method of
Measurement, shall be paid for at the contract unit price per linear meter for curb and
gutter, which price and payment shall constitute full compensation for furnishing and
placing all materials for concrete, reinforcing steel, expansion joint materials, forms,
excavation for curb and gutter, backfilling, dumping and disposal of surplus materials,
TS100 - 132
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
and for all labor, equipment, tools and incidentals necessary to complete the Item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
124 (1) Concrete Curb (Cast in place) Linear Meter
124 (2) Concrete Gutter (Cast in place) Linear Meter
124 (3) Concrete Curb (Precast) Linear Meter
124 (4) Concrete Gutter (Precast) Piece
124 (5) Concrete Curb & Gutter (Precast) Piece
- END OF SECTION -
TS100 - 133
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 134
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
required grade for yield strength and corresponding tensile strengths as well as minimum
reduction of area (%) for a given wire size range for both the plain (smooth) and deformed
wire and welded wire reinforcement.
Elongation test criteria on maximum strength (or maximum stretch) is shown in Table
125-3 and Table 125-4. Maximum stretch can be defined as total elongation which is a
test in A370, A4.4.2, measuring both the elastic & plastic extension. The testing done here
and recorded in the Table 125-3 & Table 125-4 correlate with other testing/research done
by some major universities. They have found that high strength welded wire mesh is
capable of developing significant strains and exhibits sufficient ductility to redistribute
the strains to avoid brittle shear failure.
125.2.5.2 Weld Shear Strength
The values shown in Table 125-2, Table 125-3 and Table 125-4 are the ASTM
requirements for weld shear strength which contribute to the bond and anchorage of the
wire reinforcement in concrete.
A maximum size differential of wires being welded together is maintained to assure
adequate weld shear strength. For both plain and deformed wires, the smaller wire must
have an area of 40 percent or more of the steel area of the larger wire.
Larger Wire Size Smaller Wire Size
W20 (MW 129) W8 (MW 52)
W15 (MW 97) W6 (MW 39)
D20 (MD 129) D8 (MD 52)
Table 125-2 Minimum Requirements of Steel Wires in Welded Wire Reinforcement
WELDED PLAIN WIRE REINFORCEMENT ASTM A1064
Wire Size Tensile Strength MPa Yield Strength MPa Weld Shear Strength MPa
W1.2 & over 520 450 240
Under W1.2 480 390 -
TS100 - 135
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Table 125-4 Summary of Test Criteria in Table 3(b) (27 Samples Tested)
% Elongation
fy Range @ 0.35% of Strain ft Range (ult) Total* Permanent
A370, A4.4.2 A370, A4.4.1
6-14% 4-6%
73-88ksi 91-102 ksi
Mean - 8.9% 5%
* Maximum strength or maximum stretch is the full measure of extension before fracture. It is
the true measure of elongation (total). Research background for this testing can be found in the
ACI discussion paper, Disc.88-S60 in ACI Structural Journal, July - August 1992.
125.3 Construction Requirements
The bed material shall be placed in accordance with the Section 106 Aggregate Subbase
Course.
All forms shall be staked securely in position at the correct line and level. Preformed joint
filler shall be set in position shown on the Drawings before placing of the concrete is
started. The top of the joint filler shall be placed 5mm below the top surface of the
finished sidewalk.
The mixing, placing, finishing and curing of concrete shall be as specified in Section 206,
Concrete Structures. The Portland Cement concrete shall be placed to the total depth
shown on the Drawings
The surface shall be cut through to a depth of 10mm with a trowel at intervals of 1m or,
were required, in straight lines perpendicular to the edge of sidewalk. The surface shall
then be brushed. The edges of the sidewalk and the transverse cuts shall be shaped with
a suitable tool so formed as to round the edges to a radius of 15mm.
125.4 Measurement and Payment
125.4.1 Method of Measurement
The area to be paid for shall be the number of square meters of sidewalk measured,
completed in-place and accepted.
125.4.2 Basis of Payment
The quantities determined as provided in Section 125.4.1, Method of Measurement, shall
be paid for at the contract unit price per square meter for sidewalk, which price and
payment shall constitute full compensation for furnishing and placing all materials for
concrete, expansion joint, wire mesh, forms, excavation and compacting foundation bed,
and for all labor, equipment, tools and incidentals necessary to complete the Item.
TS100 - 136
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 137
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 138
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 139
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
127 GUARDRAIL
127.1 The Works
The works in this section shall consist of furnishing and constructing posts and
guardrails of the types called for in the contract and in accordance with this
Specification, at the locations, and in conformity with the lines and grades shown on
Contract Documents, or as required by the Engineer.
127.2 Material Requirements
Materials for the desired type of guardrail shall meet the requirements specified in
the following specifications:
1) Wire rope or wire cable AASHTO M 30
2) Chain link fabric AASHTO M 181
3) Metal beam rail AASHTO M 180
4) Timber rail, unless otherwise indicated in the Drawings or Special Provisions, any
of the following first group of Philippine Timber shall be used: Ipil, Molave,
Tindalo or Yacal. Only one species of timber shall be used in the construction of
any one continuous length of guardrail.
Timber guardrail shall be well-seasoned, straight and free of injurious defects. They
shall be dressed and of sufficient length so that joints shall be on the rail posts.
Guardrail Hardware. Offset brackets of the resilient and non-resilient types shall be
of the type specified, or as shown on the Drawings, and shall meet the strength
requirements specified.
Splices and end connections shall be of the type and design specified or as shown on
the Drawings, and shall be of such strength as to develop the full design strength of the
rail elements.
Unless otherwise specified, all fittings, bolts, washers and other accessories shall be
galvanized in accordance with the requirements of AASHTO M 111 or ASTM A 153,
whichever may apply. All galvanizing shall be done after fabrication.
Guardrail Post. Posts shall be of either wood, steel, or concrete, as may be specified.
Only one kind of post shall be used for any one continuous guardrail.
Wood post shall be fabricated from an approved or specified timber specie and shall
be of the quality, diameter or section and length as specified, or as shown on the
Drawings.
Steel post shall be of the section and length as specified, or as shown on the Drawings.
They shall be of a copper bearing steel when so specified. Steel shall conform to the
requirements of AASHTO M 183 for the grade specified. The posts shall be
galvanized or shop painted as may be specified.
Pre-cast reinforced concrete posts shall be of a section and length as specified or as
shown on the Drawings. Concrete shall conform with the requirements of Section
206, Concrete Structures, for class specified. Reinforcement shall conform with the
requirements of AASHTO M 31 Grade 60. All bars shall be of the deformed type.
Concrete deadmen for end anchorages shall be as specified, or as shown on the
Drawings. Concrete and reinforcement shall conform to the requirements as stated
TS100 - 140
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 142
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
128 FENCING
128.1 The Work
The works in this section shall consist of furnishing and constructing posts and barbed
wire, chain link fences or Concrete block fence in accordance with the details, and at the
locations, shown on Contract Documents, or as required by the Engineer.
128.2 Material Requirements
128.2.1 Barbed Wire
Barbed wire shall conform to the requirements of ASTM A 121, Class I. The barbed
wire shall consist of 2 strands of 12.5 gauge wire, twisted with 2 points, 14 gauge
barbs spaced 100mm apart.
128.2.2 Chain Link Fence Fabric
Chain link fence fabric shall be fabricated from 10 gauge galvanized wire conforming
to AASHTO M 181 and shall be of the type shown on Contract Documents. Before
ordering the chain link fence fabric, the Contractor shall submit a sample of the
material to the Engineer for testing and for approval.
128.2.3 Concrete Hollow Block
Concrete Hollow Block (CHB) shall be of 150 mm (6") CHB unless shown otherwise
on the Drawings.
128.2.4 Concrete Post
Concrete posts shall be made of Class A concrete in accordance with Section 206,
Concrete Structures. The posts shall be cast to a tapered section 3m long, or to the
length shown on the detailed Drawings, and shall have a smooth surface finish.
128.2.5 Steel Post
Steel posts shall be of the sections and length as specified or as shown on Contract
Documents. The posts shall be copper bearing steel and shall conform to the
requirements of AASHTO M 183 for the grade specified.
128.2.6 Steel Reinforcement
Steel reinforcement for concrete posts shall be deformed steel bars conforming to the
provisions of Section 207, Reinforcing Steel.
128.2.7 Hardwares
Nuts, bolts, washers and other associated hardware shall be galvanized after
fabrication as specified in ASTM A 153.
128.3 Construction Requirements
The Contractor shall perform such clearing and grubbing as may be necessary to
construct the fence to the required grade and alignment. Fence shall generally follow
the contour of the ground. Grading shall be performed where necessary to provide a
neat appearance.
128.3.1 Erection Post
The post shall be erected vertically in position inside the formwork of the foundation
block prior to the placing of concrete and shall be adequately supported by bracing to
TS100 - 143
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
prevent movement of the post during the placing and setting of the concrete. The
posts shall be erected to the height and location shown on Drawing, or as ordered by
the Engineer.
128.3.2 Installation of Chain Link Fence fabric
The chain link fence fabric shall be set to line and elevation, and pulled taut between
each post before spot welding or other method of fixing, is carried out. Where splicing
of the fence fabric is necessary, or at joints, the lapping of the chain link fence fabric
shall be for a minimum of 100mm and shall occur only at the post. No horizontal
splicing will be permitted. The fence fabric shall be fixed to the posts as shown on
Contract Documents. Any surface protective layer damaged during welding and/or
construction shall be restored properly.
128.4 Measurement and Payment
128.4.1 Method of Measurement
The quantity to be paid for shall be the number of linear meters measured center to
center of posts of fencing erected in place and accepted.
128.4.2 Basis of Payment
The quantity, as determined in Section 128.4.1, Method of Measurement, shall be
paid for at the contract price per unit of measurement respectively for each of the
particular items listed below and as shown in the Bid Schedule, which price and
payment shall be full compensation for furnishing and placing all materials and for all
labor, equipment, tools and incidentals necessary to complete the Item.
Payment will be made under:
Pay Item Description Unit of
Number Measurement
128 (1) Perimeter Fence for Depot (CHB t=150mm Linear Meter
with Barbed wire)
128 (2) Fencing with 500mm Barbed wire spike (Chain Linear Meter
Link Fence Fabric)
128 (3) Fencing (Barbed wire) Linear Meter
128 (4) Fencing (CHB t=150mm x 2500mm high) Linear Meter
- END OF SECTION -
TS100 - 144
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Backfilling shall be carried out by using suitable material approved by the Engineer
and shall be compacted in layers not exceeding 150mm in depth. Surplus excavated
material shall be disposed of by the Contractor as directed by the Engineer.
129.3.2 Erection of Posts
The posts shall be erected vertically in position inside the formwork of the foundation
block prior to the placing of the concrete and shall be adequately supported by bracing
to prevent movement of the post during the placing and setting of concrete. The posts
shall be located at the positions shown on Contract Documents.
129.3.3 Sign Panel Installation
Sign panels shall be installed in accordance with the details shown on Contract
Documents. Any chipping or bending of the sign panels shall be considered as
sufficient cause to require replacement of the panels at the Contractor’s expense.
The exposed portion of the fastening hardware on the face of the signs shall be painted
with enamels matching the background color.
All newly erected traffic road signs shall be covered until ordered removed by the
Engineer.
129.4 Measurement and Payment
129.4.1 Method of Measurement
The quantities of warning and regulatory road signs shall be the number of such signs
of the size specified, including the necessary posts and supports erected and accepted.
The quantities for standard reflective informatory signs and non-standard reflective
informatory signs shall be the number of such, including the necessary posts and
supports, erected and accepted.
129.4.2 Basis of Payment
The quantities measured as determined in Section 129.4.1, Method of Measurement,
shall be paid for at the contract unit price for the Pay Items shown in the Bid Schedule
which price and payment shall be full compensation for furnishing and installing road
signs, for excavation, backfilling, post installation and construction of foundation
blocks, and all labor, equipment, tools and incidentals necessary to complete the Item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
129 (1)a Warning Signs (450mm x 600mm) , Including Each
Post and Base
129 (1)b Warning Signs, W7-4, Size 1200mm x 800mm, Each
Including Post and Base
129 (2)a Regulatory Signs R1-1 (Octagonal), Including Each
Post and Base
129 (2)b Regulatory Signs R1-2 (Triangular), Including Each
Post and Base,
129(2)c Regulatory Signs R4-1(60) (Circular), Each
Including Post and Base
129(2)d Regulatory Signs R1-3-8 (Circular), Including Each
Post and Base
TS100 - 147
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 148
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 149
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Index of Refraction: The index of refraction of the beads shall be within the range of
1.50 to 1.60 when tested by the liquid immersion method at 29°C.
Appearance: The glass beads shall be transparent, colorless and the sum of particles
that are fused, plane, angular and colored and contains bubble shall not exceed 20
percent.
TS100 - 150
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
- END OF SECTION -
TS100 - 152
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Incidence Angle
0° 3.00 1.20 1.80
20° 0.72 0.75 0.30
2) Each reflector for testing shall be located with the center of the reflecting face at
a diameter of 1.5m from a uniformly bright light source having an effective
diameter of 5mm. The width of the photocell shall be 1.2mm and shall be
shielded from stray light. The distance from the centers of the light source and
photocell shall be 5mm. Failure of more than 4% of the reflective faces shall be
a cause for rejection of the complete batch.
3) The reflectors shall support a vertical load of 10kN when tested in the following
manner. A reflector shall be centered horizontally over the open end of a
vertically positioned hollow metal cylinders, 75mm internal diameter, 25mm
high and wall thickness of 6mm. The load shall be applied to the top of the
TS100 - 153
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
reflector through a 6mm diameter by a 6mm high metal plug centered on top of
the reflector. Failure shall constitute either breakage or significant deformation
of the marker at any load less than 1000 kgf.
131.2.2 Adhesive
When “Raised Profile” type reflectors are specified, an approved two-part epoxy
adhesive shall be used.
131.2.3 Cement Mortar
Cement mortar shall consist of 1 part of Portland Cement to 2 parts of fine aggregate
with water added as necessary to obtain the required consistency.
131.3 Construction Requirements
131.3.1 Flush Surface Type
The stud shall be installed into the pavement in accordance with the manufacturer’s
instructions but shall also comply with the following requirements.
Cavities in the pavement shall be clearly cut to the dimensions of the pavement stud
and shall allow a clearance of 10mm around the stud base. The longitudinal centerline
axis of the cavity shall be the same as that required for the pavement stud when laid to
the correct line and direction. The walls of the cavity shall be splayed back at the angle
of approximately 30° to the vertical to facilitate a “dove-tail” joint after the mortar has
set. The bottom of the cavity shall be levelled with asphalt concrete prior to placing
the stud base which shall be pounded into position with a pounder foot attached to the
pneumatic drill. The depth of the activity shall be such that when the stud base and
reflectors have been installed, the elevation of the floor of the lens socket shall not be
greater than 2.0mm or less than 1.0mm above the pavement surface.
When the studs are installed into a cement concrete pavement, the stud shall be
grouted into position with asphalt concrete containing fine aggregate only or with a
cement mortar as described in Section 131.2.3 above.
131.3.2 Raised Profile Type
The pavement studs shall be installed in accordance with the manufacturer’s
instructions.
131.4 Measurement and Payment
131.4.1 Method of Measurement
The quantity of reflectorized pavement studs to be paid for shall be the number of
reflectorized pavement studs of either the flush surface type or the raised profile type,
whichever is called for in the Contract, installed complete and accepted.
131.4.2 Basis of Payment
The quantities measured as described in Section 131.4.1, Method of Measurement,
shall be paid for at the contract unit price of the Pay Items shown in the Bid Schedule,
which payment shall constitute full compensation for furnishing and placing all
materials, excavating cavities, preparation of surfaces, applying adhesive and mortar
and for all labor, equipment, tools and incidentals necessary to complete the Item.
Payment will be made under:
TS100 - 154
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 155
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
132 TOPSOIL
132.1 The Work
The works in this section shall consist of topsoil furnished, transported and spread, or
topsoil removed from designated areas, hauled and spread, in accordance with this
Specification at the location shown on the Drawings or as required by the Engineer.
132.2 Material Requirements
Topsoil furnished shall consist of fertile friable soil of loamy character without
admixture of undesirable subsoil, refuse or foreign materials. It shall be obtained from
well-drained arable land and shall be reasonably free from roots, hard clay, coarse
gravel, stones larger than 50mm in size, coarse sand, noxious seeds, sticks, brush,
litter and other deleterious substances. Topsoil shall be capable of sustaining healthy
plant life and shall be subject to the approval of the Engineer. Topsoil shall contain
not less than five (5) percent organic matter as determined by loss or ignition of
samples oven-dried to constant weight.
132.3 Construction Requirements
132.3.1 Sources of Material
The Contractor shall notify the Engineer at least five days before he intends to start
topsoil stripping operations. After inspection and approval by the Engineer and prior
to stripping any topsoil, the Contractor shall remove noxious weeds and tall grass,
brush roots and stones larger than 50mm in diameter.
132.3.2 Placing
The topsoil shall be evenly spread on the areas and to the line and level shown on
Contract Documents, and compacted with a light roller to a depth of not less than
100mm. Spreading shall not be done when the ground topsoil is excessively wet, or
otherwise in a condition detrimental to such work. The railway surfaces shall be kept
clean during hauling and spreading operations. After spreading has been completed,
large clods, stones, roots, stumps and other loose-lying materials shall be raked up
and removed. Any erosion, irregularities of grade or other incidental damage to the
surface of the topsoil shall be repaired and/or restored to the Engineer’s satisfaction.
132.4 Measurement and Payment
132.4.1 Method of Measurement
The quantities to be paid for shall be the number of cubic meters of Topsoil removed,
furnished and hauled and completed in place and accepted.
132.4.2 Basis of Payment
The quantities, as determined in Section 132.4.1, Method of Measurement, shall be
paid for at the contract unit price respectively, for each of the particular Pay Items
listed below that is shown on the Bid Schedule, which price and payment shall be
full compensation for furnishing and placing all materials and for all labor,
equipment, tools and incidentals necessary to complete the Item.
TS100 - 156
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 157
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
133 SPRIGGING
133.1 The Work
The works in this section shall consist of planting sprigs of living grass plants in
accordance with this Specification at locations shown on the Drawings or as required
by the Engineer.
133.2 Material Requirements
133.2.1 Sprigs
Sprigs shall be healthy living stems (stolons or rhizomes) with attached roots or
perennial turf-forming grasses of the kinds shown on the Drawings, harvested without
adhering soil and obtained from approved sources in the locality of the work where
the sod is heavy and thickly matted. The presence of objectionable grasses, weeds or
other detrimental material will be a cause for rejection.
133.2.2 Fertilizers
Fertilizers shall be standard commercial fertilizers supplied separately or in mixture
containing the percentages of total nitrogen, available phosphoric acid and water-
soluble potash. They shall be furnished in standard containers with name, weight and
guaranteed analysis of contents clearly marked. The fertilizers may be supplied in the
following form:
1) A dry, free-flowing fertilizer soluble in water, suitable for application by a
common fertilizer spreader.
2) A finely ground fertilizer, soluble in water suitable for application by power
sprayer.
3) A granular or pellet form suitable for application by blower equipment.
133.2.3 Ground Limestone
Ground limestone shall contain not less than 85 percent of calcium and magnesium
carbonates and shall be of such fineness that 100 percent shall pass through a 2.00mm
sieve and not less than 35 percent through a 0.150mm sieve. Granulated slag may be
substituted in lieu of ground limestone subject to the approval of the Engineer of an
adjusted application rate that will provide the equivalent total neutralizing power of
the specified limestone.
133.2.4 Topsoil
Topsoil shall perform to the requirements of Section 132.
133.2.5 Mulch Material
Mulch material shall be hay, straw or other local non-toxic material.
133.3 Construction Requirements
133.3.1 Harvesting Sprigs
The Contractor shall notify the Engineer at least 5 days before sprigs are to be
harvested and the source shall be approved by the Engineer before harvesting begins.
To begin harvesting, grass and woods shall be mowed to a height of 50 to 75mm and
all clippings removed. Sprigs shall then be loosened by cross-disking, shallow
plowing or other acceptable methods. After loosening the sprigs from the soil, they
TS100 - 158
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
shall be gathered in small piles or windrows, watered and kept moist until planted.
Not more than 24 hours shall elapse between harvesting and planting sprigs, except
that when weather or other uncontrollable condition interrupts the work, a time
extension may be granted, provided the sprigs are still moist and viable. Sprigs that
have heated in stockpiles, permitted to dry out or otherwise seriously damaged during
harvesting or delivery shall be rejected and be disposed off as directed.
133.3.2 Advance Preparation and Cleanup
After grading of areas has been completed and before applying fertilizer and ground
limestone, areas to be sprigged shall be raked or otherwise cleared of stone larger than
50mm in diameter, sticks, stumps and other debris which might interfere with
sprigging, growth of grasses or subsequent maintenance of grass-covered areas. If
any damage by erosion or other causes has occurred after grading of areas and before
beginning the application of fertilizer and ground limestone, the Contractor shall
repair such damage. This may include filling gullies, smoothing irregularities and
repairing other incidental damage.
133.3.3 Topsoiling
If topsoiling is shown on the Drawings, it shall be done in accordance with the
requirements of Section 132, Topsoil.
133.3.4 Applying Fertilizer and Ground Limestone
Following advance preparation and cleanup, fertilizer shall be uniformly spread at the
rate indicated on the Drawings. If use of ground limestone is required, it shall be
spread at the rate shown on the Drawings. These materials shall be incorporated into
the soil to a depth of not less than 50mm by disking, raking or other methods
acceptable to the Engineer. Stones larger than 50mm in diameter, large clods, roots
and other litter brought to the surface by this operation shall be removed.
On steep slopes where fertilizer and ground limestone cannot be incorporated
effectively by mechanical equipment, they may be applied with power sprayers,
blower equipment or other approved method and need not be incorporated into the
soil.
133.3.5 Planting Sprigs
Sprigging shall not be done during windy weather or when the ground is dry,
excessively wet or otherwise untillable. Sprigs shall be planted in existing ground or
in formed embankments or on topsoil as shown on the Drawings. If the soil is not
moist when the sprigs are being set, water shall be applied until the soil is moist and in
a workable condition. One or more of the following methods shall be used, whichever
is directed by the Engineer:
1) Broadcast Sprigging – Sprigs shall be broadcast by hand or by suitable
equipment in a uniform layer over the prepared surface with spacing between
sprigs not to exceed 150mm. The sprigs shall then be forced into the soil to a
depth of 50mm to 100mm with a straight spade or similar tool, or with a disk
harrow or other equipment set to cover the sprigs to the required depth.
2) Row Sprigging – Furrows shall be opened along the approximate contour of
slopes at the spacing and depth indicated on the Drawings. Sprigs shall be
placed without delay in continuous row in the open furrow with successive
TS100 - 159
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 160
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
134 SODDING
134.1 The Work
The works in this section shall consist of furnishing and laying of live sod on the
shoulders, slopes, ditches, or other locations as designated, construction of sod ditch
checks or similar appurtenances, as shown on the Drawings or as ordered and laid out
in the field by the Engineer, all in accordance with this Specification.
134.2 Material Requirements
The sod shall consist of healthy, dense, well-rooted growth of permanent and
desirable grasses indigenous to the general locality where it is to be used and shall be
free from weeds or undesirable grasses. At the time the sod is cut, the grass on the
sod shall have a length of approximately 50mm (if longer, the grass shall be cut to
approximately this length) and the sod shall have been raked free from debris.
The sod shall be cut into uniform squares approximately 300mm × 300mm, but not
larger than is convenient for handling and transporting.
The thickness of the sod shall be uniform as possible approximately 40mm or more
depending on the nature of the sod, so that practically all of the dense root system of
the grasses will be retained, but exposed, in the sod strip and that the sod can be
handled without undue tearing or breaking.
In the event the sod to be cut is in a dry condition as to cause scrumbling or breaking
during cutting operations, the Contractor, at his own expense, shall apply water in
sufficient quantities at least 12 hours before cutting to provide a well- moistened
condition of the sod to the depth to which it is to be cut. Sods shall be subject to the
approval of the Engineer.
134.3 Construction Requirements
134.3.1 Preparation of the Earth Bed
The area to be sodded shall be constructed to the required cross-section and contour,
and the tops and bottoms of the slopes shall be rounded as shown in the typical
railway sections.
The areas to be sodded shall be free from stones, roots or other undesirable foreign
materials.
The soil on the area to be sodded shall be loosened and brought to a reasonably fine
texture to a depth of not less than 30mm by means of equipment on hand methods
adapted for the purpose.
134.3.2 Placing the Sod
The earth bed upon which the sod is to be placed shall be moistened to the loosened
depth, if not naturally sufficiently moist, and the sod shall be placed thereon within 24
hours after the same has been cut.
Unless otherwise required, the sod on slopes shall be laid on horizontal strips
beginning at the bottom of the slope and working upwards. When placing sod in
ditches, or in the construction of sod ditch checks or similar appurtenances, the length
of the strips shall be laid at right angles to the direction of the flow of the water.
Sod shall be laid so that the joints caused by abutting ends of sod strip are not
TS100 - 161
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
continuous. Each sod strip shall be so laid as to abut snugly against the strip
previously laid.
As the sod is being laid it shall be lightly tamped with suitable wooden or metal
tampers sufficiently to set or press the sod into the underlying soil.
At points where it is anticipated that water may flow over a sodded area, the upper
edges of the sod strips shall be turned into the soil to be below the adjacent area and
a layer of earth place over this juncture and thoroughly compacted. At the limits of
sodded areas, the end strips shall be turned in and treated similarly.
134.3.3 Staking the Sod
On all slopes steeper than one vertical to four horizontals, sod shall be pegged with
stakes 200-300mm in length, spaced as required by the nature of the soil and
steepness of slope. Stakes shall be driven into the sod at right angles to the slope until
flush with the bottom of the grass blades.
134.3.4 Top Dressing
After staking has been completed, the surface shall be cleared of loose sod, excess
soil or other foreign material, whereupon a thin layer of topsoil shall be scattered over
the sod as a top dressing and the areas shall then be thoroughly moistened by
sprinkling with water.
134.3.5 Watering
The Contractor shall regularly water and maintain sodded areas in a satisfactory
condition for the duration of the Contract and until final acceptance of the work by the
Engineer.
134.4 Measurement and Payment
134.4.1 Method of Measurement
Sodding shall be measured by the square meter and the quantity to be measured for
payment shall be the actual number of square meters of area on which sod has been
placed in accordance with this Specification and within the limits of construction as
designated on the Drawings or as ordered by the Engineer.
134.4.2 Basis of Payment
The quantity as determined in Section 134.4.1, Method of Measurement, shall be paid
for at Contract unit price per square meter for Sodding which price and payment shall
be full compensation for preparing the earth bed, for furnishing, placing, staking, top
dressing and watering the sod, and for all labor, equipment, tools and incidentals
necessary to complete the Item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
- END OF SECTION -
TS100 - 162
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 163
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
removed for planting in a manner appropriate to the conditions and satisfactory to the
Engineer.
Such emergency storage of plant shall be at the entire risk of the Contractor, including
maintenance of same.
135.3.4 Layout of Planting
Before digging pocket holes or beds, the Contractor shall lay out, by suitable staking,
the location of all pocket holes and beds. The layout of planting shall be approved by
the Engineer.
135.3.5 Roots and Top Pruning
The ends of all broken and damaged roots, 6mm diameter or larger, shall be pruned
with a clean cut, removing no more than the injured portion. All plants shall be pruned
to balance the top with the root system keeping the natural shape of the species. All
dead woods shall be removed. All cuts and wounds, 12mm or over in diameter, shall
be painted with tree wound dressing immediately after the pruning.
135.3.6 Pocket Holes
Pocket holes shall be dug at the locations shown on the Drawings or as directed by
Engineer. The holes shall be dug to the depth and cross-section specified and should
be of sufficient size to provide for not less than 150mm of top soil backfill beneath
and around the root system. The holes shall be dug with the sides vertical. Surplus
excavation from the bed and pocket holes shall be disposed off as directed by the
Engineer.
135.3.7 Backfill
The pocket holes shall be backfilled with topsoil as each plant is set. The topsoil shall
be well-tamped by the worker’s feet, rods or other approved tamping devices as it is
shovelled into the holes. The backfill in holes on slopes shall be built- up on the lower
side to catch and hold water. During planting the topsoil surrounding the plant be
slightly depressed to hold water.
135.3.8 Planting
The plants to be planted shall be the specie, variety and size specified. The operation
of the actual planting shall not be performed at any time when the soil is not in a
friable or workable condition. The Engineer shall also approve the location of each
individual plant taking into consideration its size and shape, in order that the best
possible arrangement will result.
One plant shall be planted in the center of each pocket hole and in the arrangement
shown on the Drawings. The plants shall be set on tamped topsoil backfill brought to
the height necessary to plant them at the same depth they grew, carefully spreading
out the roots of barefoot stock in their natural position. Upright plants shall be kept
in a vertical position. After placing the plant in the hole, the backfill shall be carefully
made, tamping with the worker’s feet and with round-end rods or other approved
tamping devices to insure topsoil in and about all the roots. The topsoil shall be settled
in and about the plant roots by application of water but at no time shall tamping or
further topsoil backfill be made while this wet topsoil backfill is of a consistency that
would permit its being compacted or puddled by so doing. All compaction shall be
such that no plant will settle lower than the depth above specified. No air pocket shall
TS100 - 165
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 166
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
hole and the area 150mm outside the periphery of the plant hole. The depth and
application for wood chips shall be a minimum of 150mm. For ground or crushed
corn cobs, sawdust or peat moss the minimum depth shall be 100 mm.
135.3.10 Watering and Maintenance
All plants shall be watered during the planting operations, subject to direction and
approval of the Engineer. From time to time during the life of the Contract, sufficient
water shall be applied so that not only will the topsoil backfill about each plant be kept
moist, but also for moisture to extend into the surrounding soil.
The Contractor shall, during the life of the Contract, properly care for all plants
furnished, planted or stored, performing such watering, weeding, cultivating or other
ordinary maintenance work as shall be necessary to keep the stock in a live and
healthy condition. Plants which have died back into the crown or beyond a normal
pruning line shall be replaced by the Contractor at no additional expense to the
Government.
135.3.11 Bracing
All deciduous and evergreen trees shall be braced immediately after planting.
Deciduous trees from 1.20m to 1.80m in height shall have one vertical support stake.
Deciduous trees from 1.80m to 2.50m in height shall have two vertical support stakes.
Balled and burlapped deciduous or evergreen trees within the above size ranges shall
be supported with the number of stakes specified for the group but instead of being
placed vertically, shall be driven so that the stake does not enter or contact the earth
ball around the plant roots. The stake or stakes shall be so placed that after being driven
in place, the upper foot of the stake is within approximately 1 0 0 m m of the trunk at
one-half of the height of the tree. If two are required, they shall be driven on opposite
sides of the tree with the stake tops on opposite sides for fastening.
All trees, deciduous or evergreen over two and one-half meters shall be braced by the
tripod method as directed by the Engineer.
135.3.12 Dead Trees
Before completion and final acceptance of the project, all trees not healthy or that
have died back into the crown or beyond the normal pruning line shall be replaced by
the Contractor at his own expense with trees of the specified species or variety, size
and quality and meeting the Specification.
135.4 Measurement and Payment
135.4.1 Method of Measurement
The quantity to be paid for shall be the number of trees of each specie or variety called
for in the Drawings furnished, planted and accepted with the necessary mulch,
topsoil, water, fertilizer and other incidentals to complete the Item.
135.4.2 Basis of Payment
The quantities as determined in Section 135.4.1, Method of Measurement, shall be
paid for at the contract unit price each of the trees of each specie or variety furnished,
planted and accepted which price and payment shall constitute full compensation for
furnishing all labor, tools and incidentals necessary to complete the Item.
Payment will be made under:
TS100 - 167
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 168
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 169
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
136.3.2 Qualitative
The material shall conform to the qualitative requirements as specified in Table 136-2.
Table 136-2 Qualitative Requirements
Requirements
Property
White Yellow
Specific Gravity, max. 2.15
Drying Time, minutes, max. 10.00
Bond Strength to Portland Cement concrete after heating for four 1.24
(4) hours
±5 min. @ 218°C, MPa, max.
Cracking Resistance @ low temp. after heating for four (4) hours No cracks
±5 min. @ 218±2°C.
Impact Resistance after heating for four (4) hours 115.0
±5 min. @ 218 ±2°C and forming test specimens, mm/kg, min.
Softening Point after heating for four (4) hours ±5 min. 102.5 ± 9.5°C
@ 218 ±2°C.
Daylight reflectant @ 45 Degrees – 0 degrees, % min. 75.00 45.00
136.5 Sampling
A minimum weight of 10 kg of Reflectorized Thermoplastic paint shall be taken for every
100 bags or fraction thereof.
136.6 Testing
The material shall be tested in accordance with AASHTO T 250 or with the appropriate
method in ASTM designation.
136.7 Packing and Marking
The material shall be packaged in a suitable container to which it will not adhere during
shipment and storage. The blocks of cast thermoplastic material shall be approximately
300 × 915 by 51mm and shall weigh approximately 23kg. Each container label shall
designate the color, manufacturer’s name, batch number and date of manufacture. Each
batch manufactured shall have its own separate number. The label shall warn the user that
the material shall be heated to 211 ± 7°C during application.
136.8 Measurement and Payment
136.8.1 Method of Measurement
The quantity of pavement markings to be paid for shall be the area as shown on the
Drawings of painted traffic line of the stated width and the area as shown on the Drawings
of symbols, lettering, hatching and the like, completed and accepted.
The quantity shown in the Bill of Quantities represents the approximate quantity in square
meter of pavement markings, with width as shown applied at the centerline of the road
pavements to which may be increased or decreased depending on the Engineer’s decision
whether to require additional markings or delete parts of it.
Other markings representing symbols, lettering, hatching and others in locations where
they may be required by the Engineer shall, likewise, be implemented by the Contractor
using reflectorized thermoplastic pavement markings as approved and directed.
136.8.2 Basis of Payment
The quantities measured as determined in Section 136.8.1, Method of Measurement, shall
be paid for at the appropriate contract unit price for the Pay Items shown in the Bid
Schedule which price and payment shall constitute full compensation for furnishing and
placing all materials, sampling and packing, for the preparation of the surface, and for all
labor, equipment, tools and incidentals necessary to complete the Item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
136 (1) Reflectorized Thermoplastic Pavement Markings Square Meter
(White)
136 (2) Reflectorized Thermoplastic Pavement Markings Square Meter
(Yellow)
- END OF SECTION -
TS100 - 172
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 173
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Requirements
Properties
Hot-Poured Elastic Type Cold-Applied Type
Pour Point At least 11ºC lower than the safe The material shall pour or
heating temperature, which is extrude readily at a temperature
the maximum temperature to of 21ºC immediately after
which the material may be preparation for use and shall
heated and still conform to this remain in a condition suitable
specification’s requirements. for application for at least 1
hour.
Penetration Non-immersed at 25ºC and 150 The sealing compound, after
grams for 5 seconds shall not curing shall have a penetration,
exceed 90 when tested in at 25ºC and 150 grams for 5
accordance with ASTM D 5329. seconds, not greater than 235.
Flow At 60ºC shall not exceed 5mm The sealing compound, after
when tested for 5 hours in curing, shall show a flow not in
accordance with ASTM D 5329. excess of 5mm.
Bond Non-immersed of the sealant The sealing compound, after
shall be tested at -17.8ºC for 5 curing, shall not fail in adhesion
complete cycles. The or cohesion after testing in
development at any time during accordance with ASTM D1851.
the test procedure of a crack,
separation, or other opening that
at any point is over 6.40mm
deep, in the sealant or between
the sealant and the concrete
block, shall constitute failure of
the test specimen. The
measurement for depth of the
crack, separation or opening
shall be perpendicular to the
side of the sealant showing the
defect.
At least 2 test specimens in a
group of 3 representing a given
sample of sealant shall meet this
requirement for bond when
tested in accordance with ASTM
D 5329.
TS100 - 174
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 175
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
and sealed with a suitable field-molded sealant to prevent damage to the structure.
An additional problem occurs where water is flowing through the crack and the
upstream face cannot be reached for sealing. Before sealing can be successfully
undertaken, the water flow must be stopped. If the source of water cannot be cut
off by dewatering, then depending on the circumstances one of the many
alternatives such as cutting back the crack deeper and plugging with a quick
setting or dry-pack mortar or cement, chemical or epoxy resin grouting may be
tried. External plates are sometimes bolted to the concrete, or keyed grooves are
filled with mortar to hold the sealant in case water pressure redevelops as the joint
moves.
TS100 - 176
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Restriction on joint width and pavement temperature at the time of joint sealer
application shall be shown on the Drawings. In the absence of temperature range,
applications above 32ºC shall not be permitted.
137.4 Delivery and Storage
Joint sealer shall be delivered in manufacturer’s original unopened containers and
packaging, with labels clearly identifying product name and manufacturer. The joint
sealer shall be stored in dry and shaded area in accordance with manufacturer’s
instructions. Containers shall be sealed until it is ready for use. Expired joint sealer
shall be removed from the site.
137.5 Sampling and Testing
Sampling shall be taken at the plant or warehouse prior to delivery or at the time of
delivery. If sampling is done prior to shipment, the Engineer shall have the access to
the materials to be sampled. The Engineer shall be provided all reasonable facilities
for inspection and sampling shall be conducted so as not to interfere unnecessarily
with the operation of the works.
Samples shall consist of one of the manufacturer’s original sealed containers selected
at random from the lot or batch of finished material that was manufactured
simultaneously or continuously, as a unit between the time of compounding and the
time of packaging or placing in shipping containers.
Obtain the hot-poured type sealant portion for testing from the selected
manufacturer’s original sealed container in accordance with ASTM D 5167. The
sample portion added to and heated in the melter shall weigh 800 ± 50g.
Heat the material in accordance with ASTM D 5167.
Testing for hot-poured type sealant shall be in accordance with ASTM D 5329.
Samples for testing of cold application type shall consist of sufficient quantities of
each component to provide 3.785 liters of sealant material. Testing shall be in
accordance with ASTM D 1851.
137.6 Measurement and Payment
137.6.1 Method of Measurement
The quantity to be measured and paid for will be the length in linear meters of any
joint sealant applied in the accepted pavement or structure.
137.6.2 Basis of Payment
The accepted quantity measured as prescribed in Section 137.6.1, Method of
Measurement shall be paid for at the contract unit price of the joint sealant, which
price and payment shall be full compensation for furnishing and placing all materials,
including all labor, equipment, tools and incidentals necessary to complete this item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
137(1) Concrete Joint Sealant (Hot-Poured Elastic Linear meter
Type)
137 (2) Concrete Joint Sealant (Cold-Applied Type) Linear meter
TS100 - 177
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 178
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
138 WATERSTOPS
138.1 The Work
The works in this section shall consists of furnishing and installing waterstop to prevent
water seepage at the expansion and construction joints of concrete structures, in
conformity to the details shown on the Drawings and in accordance with this
Specification.
Waterstop are precision engineered concrete devices for vertical and horizontal
expansion joints between cast-in-place concrete units where conditions may subject the
concrete to hydro-static pressure or moisture seepage.
138.2 Material Requirements
138.2.1 Waterstop
Waterstop shall be in conformity to the type, shape and dimension and other details
shown on the approved Drawings and in accordance with this Specification. They shall
be dense, homogeneous and without holes or other defects.
138.2.1.1 Copper Waterstop
Sheet copper shall conform to AASHTO M 138M. The resistivity test shall not be
required.
138.2.1.2 Rubber Waterstop
Rubber waterstop shall be furnished molded or extruded rubber with a uniform cross-
section that is free from porosity or other defects. If approved, an equivalent standard
shape shall be furnished.
It shall be fabricated from a compound of natural rubber, synthetic rubber, or a blend
of the two, together with other compatible materials. Reclaimed material shall not be
used. A certification from the manufacturer showing the composition of the material
shall be furnished.
Samples taken from the finished rubber waterstop when tested shall conform to the
following requirements:
Property Method of Test Requirement
Hardness (shore durometer) ASTM D 2240 60 – 70
Tensile Strength Elongation at ASTM D 412 17Mpa, min.
breaking ASTM D 412 450%, min.
Water Absorption by (% by weight) ASTM D 570 5%, max.
Tensile Strength after accelerated aging, 80% of original, min.
ASTM D 572
oxygen-pressure method
138.2.1.3 Plastic Waterstop
Plastic waterstop shall be fabricated from a homogeneous, elastomeric plastic
compound of basic polyvinyl chloride (PVC). The compound shall contain any
additional resins, plasticizers, stabilizers, or other materials needed to ensure that when
the material is compounded it will meet the performance requirements of this
Specification. Reclaimed polyvinyl chloride shall not be used. It shall be formed to a
uniform cross-section that is free from porosity or other defects. If approved, an
equivalent standard shape shall be furnished.
TS100 - 179
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Samples taken from the finished plastic waterstop when tested shall conform to the
following requirements:
PROPERTY METHOD OF TEST REQUIREMENT
Tensile strength ASTM D 638M 9.6 MPa, min.
Elongation at breaking ASTM D 638M 250%, min.
Hardness (shore durometer) ASTM D 2240 60 to 75 Note(1)
Specific gravity ASTM D 792 Note (1)
Resistance to alkali(2) ASTM D 543
Mass change -0.10 to +0.25%
Hardness change (shore durometer) ±5, max.
Tensile strength change 15%, max.
Water absorption (48 hours) ASTM D 570 0.50%, max.
Volatile loss ASTM D1203 Note(3)
Low temperature brittleness ASTM D746 Passed at –350F
Notes:
1) Manufacturer’s value ±0.02.
2) Use a 10% solution of NaOH for a 7-day test period.
3) Not more than manufacturer’s value.
Furnish the manufacturer’s test results for the above properties with the certification. If
directed, furnish samples in lengths adequate for performing the specified tests.
138.2.2 Delivery and Storage
Waterstop delivered and placed in storage shall be stored off the ground and protected
from moisture, dirt, and other contaminants.
138.2.3 Acceptance of Material
Material for waterstop shall be evaluated by visual inspection for compliance with the
approved contract. Material or packaging shall be clearly marked with unique product
identification or specification standard to which it is produced. Material accepted by
certification may be sampled and tested at any time and if found not in conformance to
the requirement of the contract, the material shall be rejected even if they are already
installed in placed.
138.3 Construction Requirements
138.3.1 General
Waterstops shall be installed in the locations as shown on the approved Drawings,
where movement at the joint is provided for. The waterstops shall be of a type
permitting such movement without injury. They shall be spliced, welded, or soldered
to form continuous watertight joints.
Waterstops shall be furnished in full length for each straight portion of the joint, without
field splices. Splices shall be installed at changes in direction, as may be necessary to
avoid buckling or distortion of the web or flange. Field splices for the waterstop shall
be performed so as to provide watertight connection by such means as specified by the
manufacturer.
TS100 - 180
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Carefully place and support waterstops. Waterstops shall be securely held in position
by the use of spacers, supporting wires or other approved devices that will not injure or
puncture the waterstops. It shall be positioned allowing clearance between waterstops
and reinforcing steel at a minimum of two times the largest size to prevent rock pockets
and air voids. Waterstops shall be centered on joint, with approximately one-half of
waterstop width to be embedded in concrete on each side of the joint. During pouring,
concrete shall be thoroughly and systematically vibrated in the vicinity of the joint to
maximize intimate contact between concrete and waterstop. Prevent waterstops from
being displaced or damaged by construction operations or other activities. Suitable
guards shall be provided to protect exposed projecting edges and ends of partially
embedded waterstops from damaged when concrete placement has been discontinued
for the first pour. Keep all surfaces of waterstops free from oil, grease, dried mortar,
laitance, or any other deleterious material until embedded in concrete. Special care shall
be taken in concreting operations around waterstops to preserve their shape and position
in the joint. Ensure that embedded portions of the waterstops are completely enclosed
in dense concrete. If, after placing concrete, waterstops show indication of having been
substantially out of position or shape, the surrounding concrete shall be removed, the
waterstop shall be reset or replaced if damaged, and the concrete replaced at the
Contractor’s expense.
138.3.1.1 Copper Waterstops
Copper sheet of the required thickness, mass, width, and shape shall be used. Joints
shall be soldered for a continuous watertight unit.
138.3.1.2 Rubber Waterstops
Before installation, the following shall be submitted for approval:
1) Performance test data
2) One-meter sample of each type of waterstop required
3) At least one preliminary field splice if splices are used
Waterstops shall have a cross-section that is uniform in width and web thickness.
Straight strips shall not be spliced.
Full-mold all junctions in the special connection pieces. Provide well-cured, dense,
homogeneous special connection pieces that are nonporous and are free from other
defects.
Fabricate splices that are dense and homogeneous throughout the cross-section.
Fabricate splices watertight by vulcanizing or by mechanical means. Fabricate splices
so that they have a tensile strength of at least 50% of the reported tensile strength of the
unspliced rubber water stop.
138.3.1.3 Plastic Waterstops
Before installation, submit for approval at least one preliminary field splice sample. Heat
splices shall be in conformance to the manufacturer’s instructions to make them
watertight. A thermostatically controlled electric source of heat shall be used to make
all splices. The heat shall be sufficient to melt but not to char the plastic. Fabricate
splices so they have a tensile strength of at least 80% of the reported tensile strength of
the unspliced plastic waterstop.
TS100 - 181
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 182
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 183
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
139.3.1.2 Pattern
The Contractor shall lay out a reflectorized thermoplastic rumble strips test pattern
prior to the start of construction for approval by the Engineer. Pattern shall be balanced
to provide adequate warning to drivers without being so severe that they startle drivers
or upset motorcycles.
The pattern of reflectorized thermoplastic rumble strips shall finish within 50m of any
hazard it is associated with.
139.3.2 Composition
It shall conform to the requirements of Section 136.3.1, Composition of Section 136
– Reflective Thermoplastic Stripping Materials (Solid Form) Qualitative
It shall conform to the requirements of Section 136.3.2, Qualitative of Section 136
– Reflective Thermoplastic Stripping Materials (Solid Form).
139.4 Application Properties
It shall conform to the applicable requirements of Section 136.4, Application
Properties of Section 136 – Reflective Thermoplastic Stripping Materials (Solid
Form).
Reflectorized thermoplastic rumble strips shall be placed transverse to motor vehicle
traffic movement. It shall not adversely affect overall pavement skid resistance under
wet or dry conditions and shall not be placed on sharp horizontal or vertical curves. It
shall not be applied over deteriorating existing reflectorized thermoplastic rumble
strips or pavement surface.
A sign warning the drivers of the onset of reflectorized thermoplastic rumble strips may
be placed in advanced of rumble strips installation.
139.5 Sampling
It shall conform to the requirements of Section 136.5, Sampling of Section 136 –
Reflective Thermoplastic Stripping Materials (Solid Form).
139.6 Testing
It shall conform to the requirements of Section 136.6, Testing of Section 136 –
Reflective Thermoplastic Stripping Materials (Solid Form).
139.7 Packing and Marking
It shall conform to the requirements of Section 136.7, Packing and Marking of Section
136 – Reflective Thermoplastic Stripping Materials (Solid Form).
139.8 Measurement and Payment
139.8.1 Method of Measurement
The area to be paid for under this Item shall be the number of square meters (m2) of
reflectorized thermoplastic rumble strips applied and accepted.
139.8.2 Basis of Payment
The accepted quantity measured as prescribed in Section 139.8.1, Method of
Measurement shall be paid for at the contract unit price of the Reflectorized
thermoplastic rumble strips, which price and payment shall be full compensation for
TS100 - 184
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
furnishing and placing all materials, including all labor, equipment, tools and
incidentals necessary to complete this item.
Payment will be made under:
Pay Item Description Unit of
139 Reflectorized Thermoplastic Rumble Square meter
Strips
- END OF SECTION -
TS100 - 185
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
≤ 20 ≤ 60 12
30-50 60-120 24
60-70 120-210 36
80-90 210-300 48
> 90 > 300 60
The above spacing distances shall apply to points within the curve. Approach and
departure spacing distances shall be twice those shown above.
140.2.3 Types of Chevron Signs
Two (2) types of chevron signs are provided for in this section and each type shall be
used as called for on Contract Documents. The typical sizes are shown in Table 140-2.
TS100 - 186
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 187
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 188
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 189
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 190
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Material Woven Netting made from High Strength 100% Coconut fiber
Color twine
Tensile Strength, N/twine Natural Earth Tone 150 Min.
141.3.3 Backfill
Backfill shall be in accordance with the approved Drawing and shall conform to the
requirements of Section 103 – Embankment.
141.3.4 Bamboo Stakes
Bamboo stakes shall be mature and shall be 30 to 40mm in width and 300mm long.
141.3.5 Live Plant Stakes (Live Kakuate or Ipil-ipil or Equivalent Species)
Live plant stakes shall be kept moist and installed the same day they were prepared and
shall be 50 to 150 mm in diameter and 500mm to 1000mm in length.
141.4 Construction Requirements
141.4.1 Quality Control
The coconut geonets manufacturer shall be responsible for establishing and
maintaining a quality control program to assure compliance with the requirements of
this specification.
141.4.2 Equipment
Equipment and tools necessary for handling materials and performing all parts of the
works shall be approved by the Engineer as to design, capacity and mechanical
TS100 - 191
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
condition. The equipment shall be at the jobsite sufficiently ahead of the start of
construction operations.
141.4.3 Site Measurement
Site measurements shall be done to prepare specific lengths of the coco-nets to
conform the necessary area requirements and the necessary length for coco-logs to be
installed/placed.
141.4.4 Preparation of Bed
Site for net installation shall be graded and sloped to the approved design and any
runoff control such as diversions, dikes and berms shall be completed prior to
installation. All depression/gullies and eroded portions shall be backfilled for the coco-
nets to snugly come in contact with the soil surface. The face of the slope shall be
smoothened. Rocks, clods, vegetation (deemed detrimental to the erosion control
system to be installed), and other obstructions shall be removed from tip to toe of the
slope to ensure complete contact of the coco-nets with the soil.
Existing vegetations that are considered not detrimental shall be retained, but shall be
trimmed down to facilitate the installation of the coconut geonets.
141.4.5 Anchoring
1) Common Soil
The coconut geonets shall be secured to the ground using bamboo pegs. An
average of 3 pegs per square meter shall be used to ensure uniform contact of coco-
net to the ground surface. For loose soils, longer pegs shall be used to have
sufficient ground penetration to resist pullout.
2) Compacted Soil
A combination of bamboo pegs and U-shaped wire staples may be used for
compacted, hard to penetrate soil. An average of 3 pegs/staples per square meter
shall be used to ensure uniform contact of coco-net to the ground surface.
3) Hard Rock
The coconut geonets shall be anchored to solid rock surfaces using metal stake pins
with a minimum diameter of 8.0mm and length of 200 to 300mm.
141.4.6 Installation/Placing of Coconut Geonets
The coconut geonets shall be used on critical cut slopes, embankments and disturbed
soils generally steeper than 3:1, where water velocities are likely to wash out soils and
new vegetation. Coco-nets shall be placed and anchored on the graded surface of the
slope to maximize net contact with the slope surface. Installation shall begin at the top
of the slope with the coco-net laid down and securely anchored 1.0 meter from the
edge of the slope by folding underneath the leading edges of the coco-net to ensure
that no twines would come loose. After which the coco-nets shall then be unrolled
downslope in the direction of the water flow. Adjacent coco-nets shall be installed
side-by-side and shall be sewn together using coco coir twine. The coco-nets shall be
laid loosely (not stretched) on the ground. Coco-net shall then be fastened and secured
firmly to the ground in accordance to Section 141.4.5, Anchoring. Anchoring shall be
at right angle to the ground surface.
TS100 - 192
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 193
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
141.5 Certification
The manufacturer shall file with the purchaser a certificate stating the name of the
manufacturer, the composition of the coconut geonets as bioengineering materials and
other pertinent information so as to fully describe the coir materials. The manufacturer
shall include in the certificate a guarantee stating that the bioengineering materials that
are furnished meet the required specifications. The certificate shall be attested by a
person having legal authority to bind the company. Either mismarking or
misrepresentation by the manufacturer shall be reason to discontinue acceptance under
these specifications. The discontinuance of acceptance will be considered to be notice
to all wholesaler, jobbers, distributors, agents and other intermediates handling the
manufacturer’s product.
141.6 Measurement and Payment
141.6.1 Method of Measurement
The area to be paid for under this Item shall be the number of square meter (m2) of
coco-net, linear meter for coco-log, square meter (m2) of live vetiver grass hedgerow
and square meter (m2) of effective vegetative growth for grass cover, installed/placed
and accepted into the completed project.
141.6.2 Basis of Payment
The accepted quantity, measured as prescribed in Section 141.6.1 shall be paid for at
the contract unit price for coconut geonets, which price and payment shall be full
compensation for preparation of bed and furnishing of all materials for
placing/installation of coconut geonets and for furnishing all labor, maintenance of
plants, equipment, tools and incidentals necessary to complete the Item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
141 (1) Coco-net Square meter
141 (2) Coco-logs/Fascine Linear meter
141 (3) Vegetation Square meter
- END OF SECTION -
TS100 - 194
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
142 HANDRAIL
142.1 The Work
The works in this section consists of the furnishing of materials and labor including
equipment necessary to complete the installation of handrails in accordance with the
Drawings or as directed by the Engineer. The work shall include the furnishing and
placing of mortar or concrete, anchor bolts, reinforcing steel anchor bars, or other
devices used to attach the railing to the structure.
142.2 Materials
Steel pipe for rails and posts shall conform to ASTM A 53. Pipe shall be galvanized after
fabrication in accordance with the requirements of AASHTO M 111. Handrail materials
shall obtain from a single manufacturer.
All exposed welds shall be finished by grinding or filing to give a smooth surface.
Grout for anchoring the pipe posts shall conform to Section 206.
142.3 Installation, Fabrication and Finish
Fabrication of handrails shall conform to the dimensions and details shown on the
Drawings or as directed by the Engineer.
Top railing shall be continuous throughout entire length of railing, except as noted in
3.8.4.
Welding shall conform to ANSI/AWS D1.1 Chapter 10, Tublar Structures. At tee and
cross connections notch ends of intersecting members to fit contour of pipe to which
wind is joined and weld all around interconnected handrail members by butt- welding
or welding with internal fittings.
Metal railings shall be carefully adjusted prior to fixing in place to ensure proper
matching at abutting joints, correct alignment, and camber throughout their length.
Holes for field connections shall be drilled with the railing in place on the structure at
proper grade and alignment.
Unless otherwise specified in the contract documents, anchor bolts, nuts, and all steel
portions of railings shall be galvanized. Galvanizing of rail element shall conform to
the requirements of AASHTO M 111M/M 111 (ASTM A123/A123M) and galvanizing
of nuts and bolts shall conform to the requirements of AASHTO M 232M/M 232
(ASTM A153/A153M). Minor abrasions to galvanized surfaces shall be repaired with
zinc-rich paint. After erection, all sharp protrusions shall be removed and the railing
cleaned of discoloring foreign materials.
Store handrails and railing systems in clean, dry location, away from uncured concrete
and masonry, protected against damage of any kind. Cover with waterproof paper,
tarpaulin, or polyethylene sheeting; allow for air circulation inside the covering.
Adjust railings prior to anchoring to ensure matching alignment at abutting joints.
Space posts at spacing indicated, or if not indicated, as required by design loadings.
Plumb posts in each direction.
Coordinate setting drawings, diagrams, templates, instructions, and directions for
installation of anchorages, such as sleeves, concrete inserts, anchor bolts, and
miscellaneous items having integral anchors, which are to be embedded in concrete and
TS100 - 195
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 196
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 197
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
143.4 Execution
143.4.1 Pipes and Gate Valves
The Pipes shall be installed in accordance with Section 607, Pipework and Accessories,
Section 614, Water Supply and Distribution Systems, Section 619, Plumbing Fixtures,
and Section 623, Wet Standpipe System of TS 600, Mechanical, Sanitary and Plumbing.
Excavation and backfill shall be done in accordance with Section 201, Structure
Excavation of TS 200, Bridges and Viaducts.
143.4.2 Valve Boxes
The works for valve boxes shall conform to the provisions specified in Section 206,
Concrete Structure, and 207, Reinforcing Steel, of TS 200, Bridges and Viaducts.
Excavation and backfill shall be done in accordance with Section 201, Structure
Excavation of TS 200, Bridges and Viaducts.
143.4.3 Fire Hydrant
The fire hydrant works shall be executed in accordance with Section 607, Pipework and
Accessories, Section 614, Water Supply and Distribution Systems, Section 619,
Plumbing Fixtures, Section 623, Wet Standpipe System, and Section 630, Fire Fighting
system, of TS 600, Mechanical, Sanitary and Plumbing.
The fire hydrants shall be installed conforming to the requirements of National Building
Code of the Philippines and Fire Code of the Philippines.
A minimum 3-foot radius unobstructed working area shall be provided around all
hydrants. The sidewalk flange shall be set 2 inches above finished grade.
After all installation and testing is complete, the exposed portion of the hydrant shall
be painted with one field coat. The type and color of paint will be designated in the
drawings or directed by the Engineer.
143.4.4 Hose Bibbs
The hose bibbs shall be installed in accordance with Section 614, Water Supply and
Distribution Systems, and Section 619, Plumbing Fixtures, of TS 600, Mechanical,
Sanitary and Plumbing.
TS100 - 198
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Measurement for all testing, inspections and commissioning shall not be made, it shall
be considered as include in the related Pay Item
143.6.2 Basis of Payment
The accepted quantity, measured as prescribed in Section143.6.1, Method of
Measurement, of the Pay Items in the Bill of Quantities will be paid for at the contract
unit price, which shall constitute full compensation of furnishing and placing all
materials and for all labor, equipment, tools, and incidentals necessary to complete the
Item.
Payment for excavation, bedding and backfill for water distribution pipe shall be
TS100 - 199
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
considered as included in the payment for the water distribution pipe and for valve box
shall be considered as include in the payment for Gate Valve with Valve Box.
Payment will be made under:
Pay Item Number Description Unit of Measurement
Each
143(5) Water Meter
Each
143(6) Service Connection; with box and fittings
Each
143(7) Air Release Valves
Each
143(8) Blow off Valves
TS100 - 200
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION -
TS100 - 201
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 202
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
144.4 Execution
144.4.1 Pipe
The Pipes shall be installed in accordance with Section 607, Pipework and Accessories,
and Section 618, Waste Water Treatment plants, of TS 600, Mechanical, Sanitary and
Plumbing.
Excavation and backfill shall be done in accordance with Section 201, Structure
Excavation of TS 200, Bridges and Viaducts.
144.4.2 Oil Separator
The oil separators shall be installed in accordance with Section TS206, Concrete
Structure, and TS207, Reinforcing Steel, of TS 200, Bridges and Viaducts, and Section
618, Waste Water Treatment plants, of TS 600, Mechanical, Sanitary and Plumbing.
Excavation and backfill shall be done in accordance with Section 201, Structure
Excavation of TS 200, Bridges and Viaducts.
144.4.3 Testing, Inspections and Commissioning
The Testing, Inspections and Commissioning shall be done in accordance with Section
613, Testing, Inspections and Commissioning, of TS 600, Mechanical, Sanitary and
Plumbing.
The contractor shall obtain, at his own expense, all the necessary permits and Certificate
of Plumbing and Sanitary Inspection from the proper government authorities required
both for the performance of his work involved and the operation of the system upon
completion of work.
144.5 Measurement and Payment
144.5.1 Method of Measurement
Waste water pipe for the different types and sizes will be measured by the linear meter
in place.
The pipe for depot sanitary system with different types and sizes pipes will be measured
by the linear meter in place. Maintenance hole, elbows, and other materials will be
included in the length measurement for waste water flow pipe.
Oil separator with cover and septic tank will be measured by the number of units
installed.
Waste Water Treatment Plant will be measured by Lump sum and payment will be made
by the table below,
Percentage Item Deliverables
Payment
10% Of the Contract Price upon award, acceptance, signing, notice to proceed
TS100 - 203
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
10% Retention
Measurement for all testing, inspections and commissioning shall not be made, it shall
be considered as include in the related Pay Item
144.5.2 Basis of Payment
The accepted quantity, measured as prescribed in Section144.6.1, Method of
Measurement of the Pay Items in the Bill of Quantities will be paid for at the contract
unit price, which shall constitute full compensation of furnishing and placing all
materials and for all labor, equipment, tools, and incidentals necessary to complete the
Item.
Payment for excavation, bedding and backfill for waste water flow pipe shall be
considered as included in the payment for the water distribution pipe.
Payment will be made under:
Pay Item Number Description Unit of Measurement
144(1)a PVC Waste Water Flow Pipe 100mm Diameter Linear Meter
144(1)b PVC Waste Water Flow Pipe 150mm Diameter Linear Meter
144(1)c PVC Waste Water Flow Pipe 200mm Diameter Linear Meter
144(1)d PVC Waste Water Flow Pipe 250mm Diameter Linear Meter
144(1)e PVC Waste Water Flow Pipe 300mm Diameter Linear Meter
144(2)a Oil Separator (7.5m x 2.4m) Set
144(2)b Oil Separator (7.0m x 3.4m) Set
144(2)c Oil Separator (6.4m x 3.4m) Set
144(2)d Oil Separator (6.4m x 2.4m) Set
144(2)e Oil Separator (5.9m x 3.4m) Set
144(2)f Oil Separator (4.8m x 2.4m) Set
TS100 - 204
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
144(16) Waste Water Treatment Plant for Training Center Lump sum
- END OF SECTION -
TS100 - 205
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
The conduit body shall be made of flame retardant high-density polyethylene mixed
with carbon black for weatherproofing purpose.
Material shall meet the requirements specified in the following specifications:
Item Standard Required Performance
The relative deflection of the outside diameter
Compressive strength JIS C 3653 or approved shall be 3.5% or less and no crack or crevice
equivalent shall appear in any part
Flame retardance JIS C 3653 or approved Must self-extinguish within 30 second
equivalent
Tensile Strength Proposed by the 19.6N/mm2 or more
Contractor and
Flexure resistance approved by the Deformation ratio shall be 5% or less
Engineer
145.3 Construction Requirements
145.3.1 Trenches Excavation
Trenches shall be excavated in accordance with the requirement of Section 201,
Structural Excavation, to a width sufficient to allow for proper jointing of the conduit
and thorough compaction of the bedding and backfill materials under and around the
conduit. Where feasible, trench wall shall be vertical.
The completed trench bottom shall be firm for its full length and width.
When so specified on the Drawings, the excavation for conduits placed in embankment
fill, shall be made after the embankment has been completed to the specified or directed
height above the designed grade of the conduit.
145.3.2 Installing and laying
All works specified this section shall be in complying with MLIT-J Electrical
TS100 - 206
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Construction Guide Books and/or equivalents. The installation of conduit, joints and
space separators according to manufacturers printed instructions and recommendations.
1) Installing and Bedding
Spacers or space separators shall be placed not more than 2m apart and shall
transmit no vertical load on the conduit.
Horizontal and vertical interval of the conduit shall be 70mm or direction by the
Engineer and the depth of conduit shall be more than 2m from the planed ground
surface or road surface.
The conduit shall be pulled using drum installed at the edge of the trench, and laid
carefully not to meander, drag or twist on the spread sand or good-quality soil more
than 5cm thickness not to no contact with stones and pebbles. The sand and soil
should be smooth and compacted well to satisfy the Engineer.
During construction, partially completed duct lines shall be protected from the
entrance of debris by means of suitable caps or plugs.
A 1/4 Nylon inch pulling rope shall be installed in all ducts.
Warning tapes shall be installed above all ducts and shall comply with the
Philippines Electrical Code.
2) Cleaning and Testing
The trench shall be backfilled provisionally by sand through until 5 to 10cm cover
of the conduit and tamp down lightly while straightening each conduit.
As provisionally backfill between manholes is completed, the Contractor shall clean
particles of earth, sand or gravel inside the conduit by drawing a brush with stiff
bristles through the conduit and carry out passing test that a test rod with pilot wire
which installed inside conduit beforehand is drawn through each conduit. Passing
test shall be done after final backfilling for conduit trench is completed for the
Engineer’s approval. Conduit caps or plugs shall then be immediately installed after
confirmed the pipe has been laid correctly.
145.3.3 Backfilling
Materials for provisionally backfilling shall be done each side of the conduit for the full
trench width and to an elevation of 5 to 10cm above the top of the conduit shall be fine,
readily compactible soil or granular material not contain stones that would be retained
on a 19mm sieve.
Granular backfill material shall have not less than 95 percent passing a 12.5mm sieve
and not less than 95 percent retained on a 4.75mm sieve. Oversized material, if present,
shall be removed at the source of the material, except as directed by the Engineer.
The backfill shall be filled up evenly on both sides of the conduit for the full required
length. Compaction to the density specified in Section 103.3.3 Compaction shall be
achieved by use of mechanical tampers or by rolling.
145.4 Measurement and Payment
145.4.1 Method of Measurement
Conduit for underground electrical cables shall be measured by the linear meter for pipe
TS100 - 207
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION –
TS100 - 208
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 209
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 210
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
7) Specific gravity of neat cement grout shall not be less than 1.95.
The water used in the grout shall be potable, clean, and free of injurious quantities of
substances known to be harmful to the materials used of the anchor bars.
146.4.2 Construction
Prior to commencing work, details of the Anchor bars, grouting materials, results of
grouting trials and methods of installation, including the equipment necessary to drill
the hole, to clean out the drilled hole, to grout the anchor bar in the hole shall be
submitted to the Engineer.
146.4.2.1 Drilling
Drill the hole so that its diameter is not smaller than the diameter shown on the plans
or established by test anchors.
Holes for anchor bars may be formed by driving or drilling method. The selection of
drilling method by the Contractor shall ensure that the works do not cause and problem
to adjacent properties and services. The drilling method used shall be submitted and
approved by the Engineer.
Full temporary casing shall be installed to maintain a clean and open shaft and prevent
wash out of fines outside the casing in all holes. Grouting shall be carried out with the
temporary casing inside the hole and after fresh grout emerge from the hole, then only
the temporary casing can be slowly retrieved while grouting continue. Any alternative
method shall be approved by the Engineer.
Drill holes for ground anchor bars shall be provided in accordance with the Drawings.
The drill hole entry point shall be positioned within a tolerance of
±75mm. Deviation from straight shall not exceed 20mm in any 3m length of drill hole.
The Contractor shall keep a record of all drilling procedures and times, which shall be
made available to the Engineer.
146.4.2.2 Installation of Anchor Bar
The procedure for the installation of anchor bars shall be adhered to but not limited to,
notwithstanding other requirements:
1) Anchor bars shall be furnished complete with all accessories and with other
pertaining materials necessary for their proper installation, as well as for
stressing (where required) and grouting.
2) Prior to installing an anchor bar, the drilled hole shall be checked for obstructions
and depth. The hole shall be adjusted, if necessary with timber inserts or anchor
bar, to ensure that the anchor bar protrudes a sufficient amount to allow the
installation of the end hardware, but not more than 100mm.
3) The drill hole for an anchor bar shall be thoroughly cleaned with an air/water jet
prior to introducing the anchor bar or resin or grout (from the bottom outward),
into that hole.
4) The anchor bars shall remain in an undisturbed condition until the necessary
grout strengths have been achieved.
TS100 - 211
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
146.4.2.3 Grouting
1) The material shall be mixed in accordance with the manufacturer's
recommendations.
2) Cement grout shall be mixed in suitable equipment which can handle the mix
proportion proposed.
3) A trial grout mix shall be carried out using the designed water cement ratio and
admixtures (if any) and the proposed grouting equipment to be used for the
ground anchor bar. One sample of the grout from the trial mix shall be divided
into three specimens and each specimen shall be tested to show compliance with
the strength bleeding, free expansion and fluidity requirements stated 146.3.1.2.
4) The grout shall be injected through a suitable adopter attached to the anchor head
until grout return is observed. The quantity of grout available for immediate use
shall be sufficient to grout a whole anchor bar without interruption.
5) Withdraw the pipe slowly while grouting continues, filling the void left by the
grout pipe. Grout each ground anchor bar within 8 hr. of the completion of
drilling.
6) Grout before anchor bar insertion in the hole only with approval.
7) The grout shall not remain in the mixer for a period exceeding 45 minutes,
failing which it shall be rejected.
8) A record giving full details of the grouting operation for each anchor shall be
supplied to the Engineer prior to a request seeking his acceptance of the anchor.
Record the following information concerning the grouting:
a) Type of mixer
b) Type of cement
c) Water-cement ratio
d) Types and volume of additives
e) Working ground anchor bar
f) Time and Volume of grout
g) Others requested by the Engineer
146.4.3 Testing
146.4.3.1 Anchor Bar
Anchor bar shall conform to Standard Test Methods and Definitions for Mechanical
Testing of Steel Products (ASTM A370)
146.4.3.2 Grout
The test method of shall apply table below:
Property Test Method
Total Chloride Ions ASTM C1152/C1152M
Compressive Strength 7, 14, 28 day
ASTM C109
(average of 3 cubes)
Volume Change at 28 days ASTM C1090
TS100 - 212
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
TS100 - 213
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
g) problems encountered.
146.5 Pump Systems
146.5.1 Product
146.5.1.1 Pipe
The materials of pipes shall conform to the provisions specified in Section 607,
Pipework and Accessories, of TS 600, Mechanical, Sanitary and Plumbing.
146.5.1.2 Pump System
The pump system shall be conform to the provisions specified in Section 615, Pumps,
of TS 600, Mechanical, Sanitary and Plumbing.
Pumps specifications are as below.
Location Detention Basin 1 Detention Basin 2
146.5.2 Execution
146.5.2.1 Pipe
The Pipes shall be installed in accordance with Section 607, Pipework and
Accessories, of TS 600, Mechanical, Sanitary and Plumbing.
Excavation and backfill shall be done in accordance with Section 201, Structure
Excavation of TS 200, Bridges and Viaducts.
146.5.2.2 Pump System
The pump system shall be executed in accordance with Section 615, Pumps, of TS
600, Mechanical, Sanitary and Plumbing.
146.6 Testing, Inspections and Commissioning
The testing, inspections and commissioning shall be done in accordance with Section
613, Testing, Inspections and Commissioning, of TS 600, Mechanical, Sanitary and
Plumbing.
146.7 Measurement and Payment
146.7.1 Method of Measurement
1) Detention Basin Structure
Concrete and reinforcing steel will be paid in accordance with Section 206,
Concrete Structure, and Section 207, Reinforcing Steel of TS 200, Bridges and
Viaducts.
Expansion joint will be paid measured linear meter in placed and approved by the
TS100 - 214
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
Engineer.
Excavation and backfill will be paid in accordance with Section 201, Structure
Excavation, of TS200, Bridges and Viaducts.
2) Ground Anchor Bars
The quantity to be measured and paid for will be the number of Anchor bar
completed and accepted. All associated works and costs shall be considered as
include in the payment for this Pay Item.
3) Pump System
The works for detention basin pump system include pipe will be measured Lump
Sum. Measurement for all testing, inspections and commissioning shall not be
made, it shall be considered as include in the related Pay Item.
Metal frame and covers, and ladder rungs shall be considered as include in the
payment for Pump system for detention basin.
146.7.2 Basis of Payment
The accepted quantities, determined as provided in Section 146.6.1, Method of
Measurement of the Pay Items in the Bill of Quantities will be paid for at the contract
unit prices, which shall constitute full compensation for furnishing and placing all
materials and for all labor, equipment, tools and incidentals necessary to complete this
Work Item.
Payment will be made under:
Pay Item Number Description Unit of Measurement
146(1) Ground Anchor Bar L=12m Nos.
- END OF SECTION –
TS100 - 215
Bidding Documents Part II – Requirements
Malolos – Clark Railway Project – Civil & Building Works Section 6 – Part 1
Package CP N–05 Book 2 – TS 100
- END OF SECTION –
TS100 - 216