Gantt Chart & Pert CPM
Gantt Chart & Pert CPM
Gantt Chart & Pert CPM
A Gantt chart is a type of bar chart that illustrates a project schedule. This chart lists the tasks to be performed on
the vertical axis, and time intervals on the horizontal axis. The width of the horizontal bars in the graph shows the
duration of each activity. Gantt charts illustrate the start and finish dates of the terminal elements and summary
elements of a project
From <https://teams1.pressbooks.com/chapter/gantt-chart/>
CMPM Page 1
PROBLEM 1
Table 1 shows the list of activities for making up a network diagram to carry out the required works of a certain
project. Provide the following:
1. Number of days needed to carry out the work.
2. Provide the critical path
3. Total cost of the project
ACTIVITY DURATION (DAYS) COST (P)
A (0-1) 4 6000
B (1-3) 10 5000
C (1-2) 12 10000
D (3-2) 3 2500
E (2-6) 12 6200
F (2-5) 6 4000
G (2-4) 10 15000
H (5-4) 3 1200
I (4-7) 4 3600
J (7-8) 8 4800
K (6-8) 11 8000
L (8-9) 2 2100