Department of Civil Engineering Date: 18.11.2020 Duration: 60 Mins

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

Roll. No.

JSS MAHAVIDYAPEETHA
JSS SCIENCE AND TECHNOLOGY UNIVERSITY
JSS Technical Institutions’ Campus, Mysuru– 570 006
DEPARTMENT OF CIVIL ENGINEERING

Semester: Vth BE- ‘A & B’ Sec. Date: 18.11.2020 Duration: 60 Mins.


Sub. Code: HU510
Sub. Name: CONSTRUCTION MAGEMENT PLANNING EQUIPMENTS AND ENTREPREUNERSHIP
Test No.: II Max. Marks: 20

Name of the Paper Setter: RAHUL Name of the Student:

Course Outcome:
The student has the
 Ability to plan and schedule the construction projects using CPM and PERT (CO2).

Q. Cognitive
CO Question Marks
No. Domain
a) Write the characteristics features of a project 04

b) A project consists of 16 activities having their


predecessor relationship as follows:
i) A is the first activity of the project
ii) B, C and D follow A and can be done
concurrently.
iii) E and G cannot begin until C is
completed and can be performed
simultaneously.
iv) F is the immediate successor to 06
Remembering activities B and E.
1. CO2 & v) H and K run in parallel, and both
Applying succeed G.
vi) L succeeds F and H
vii) I and J are immediate successor
activities to activity D.
viii) M and N are immediate successor to I
and K. However, both M and N can be
performed concurrently.
ix) Activities O and P are the last
activities. Activity O is the immediate
successor to N and L. Activity P is the
immediate successor to M and J. Draw
the network and numbers the events.
a) Write a note on project planning, project 06
scheduling and project controlling.

b) Write the D R Fulkerson rule for numbering 04


the events.
2. CO2 Applying

Target: 65%