BCC Risk Analysis Register - Cleaning of Cooling Water Lines
BCC Risk Analysis Register - Cleaning of Cooling Water Lines
1 Excavations Underground Utilities Low Low Low Utilities Drawings Checked. TOM MILLER
Trench Collapse Low Moderate Moderate Excavation Sides Battered Back
With Spoil placed away from edge.
2 Electrics Electrocution Low Moderate Moderate Correct GFCI Circuit Protection To TOM MILLER
Be Installed
Weatherproof Temporary ROSS WHILEY P/T
Distribution Board to be Available
Cabling To Be Elevated
3 Lifting Unstable Ground Low Low Low Crane Survey TOM MILLER
Dropped Load Low High Moderate Only Trained Persons Used RUSTY TURPIE P/T
Persons Under The Load Low High Moderate Installation of Barricades
Overhead Obstructions Low High Moderate Lifting Supervisor in Place
Poor Lifting Equipment Low High Moderate Compliance With Colour Code
Note: All personnel will attend coordination meeting, pre work & tool box talk. All details will be discussed and duties allocated as required & as per IMT requirements. Standard and
specialist PPE will also be as per IMT requirements. Anchor points, equipment inspections, and other associated inspections will also be conducted. All personnel involved with
confined space will recieve a Toolbox Talk from the responsible person prior to the start of each shift.
Likelihood Description
Frequency Description for a Likelihood or Consequence Severity
Total Site (Example only)*
Frequency /
Consequence expected to occur in most Probability Low Minor Moderate Major Critical
Almost Certain Occurs weekly
circumstances
Consequence will probably occur in most Almost Certain High High Extreme Extreme Extreme
Likely Occurs every month
circumstances
Possible Consequence should occur at some time Occurs once every 6 months
Likely Moderate High High Extreme Extreme
Unlikely Consequence could occur at some time Occurs once every 5 years Possible Low Moderate High Extreme Extreme
Consequence may occur under exceptional
Rare Occurs once every 10 years Unlikely Low Low Moderate High Extreme
circumstances
Consequence Injury Description Cost Estimation Rare Low Low Moderate High High
Multiple fatalities and irreversible disability
Critical >US$1 Million NOTE: Basic Tasks should not be included in the 14 day look ahead. Instead, the focus should be on
(>30%) to one or more personnel
Single fatality and/or severe irreversible
Major
disability (>30%) to one or more personnel.
>US$100,000 those tasks identified during the period which pose a significant risk/hazard etc. The look ahead should
Moderate
Irreversible damage or impairment (,30%) to
>US$10,000
represent the actual work being completed or scheduled for completion within the next 14 day period.
one or more personnel
Reversible disability/impairment or injuries Tasks identified as having a consequence severity of High or above should be supported with written
Minor >US$1,000
requiring medical treatment
procedures and or detailed work method statements. Assistance in the development of this look ahead
Low level damage/injury . No medical
Low >US$100
treatment. (First Aid etc) may be sort from the relevant IMT Safety Engineer.
BCC RISK ANALYSIS REGISTER - CLEANING OF COOLING WATER LINES
Responsible
No Task Hazard Probability Consequence Risk Rating Control Measure
Person
Welders Mask and PPE Tom Miller
Arc Eye Burns Unlikely Moderate Moderate
Adequate Ventilation
Atmospheric
Unlikely Moderate Moderate
content change
3
Competant and certified
operator .
Machinery Pressure Surge Unlikely` Moderate Moderate
Note: All personnel will attend coordination meeting, pre work & tool box talk. All details will be discussed and duties allocated as required & as per IMT requirements.
Standard and specialist PPE, Rescue equipment,Radio Communications and Application of Permit to Work will be in accordance with the Cleaning Procedure.
Likely
Consequence will probably occur in most
Occurs every month Almost Certain High High Extreme Extreme Extreme
circumstances
Possible Consequence should occur at some time Occurs once every 6 months Likely Moderate High High Extreme Extreme
Unlikely Consequence could occur at some time Occurs once every 5 years
Possible Low Moderate High Extreme Extreme
Consequence may occur under exceptional
Rare Occurs once every 10 years
circumstances Unlikely Low Low Moderate High Extreme
Consequence Injury Description Cost Estimation
Rare Low Low Moderate High High
Multiple fatalities and irreversible disability
Critical >US$1 Million
(>30%) to one or more personnel NOTE: Basic Tasks should not be included in the 14 day look ahead. Instead, the focus should
Single fatality and/or severe irreversible
Major >US$100,000 be on those tasks identified during the period which pose a significant risk/hazard etc. The look
disability (>30%) to one or more personnel.
Irreversible damage or impairment (,30%) to ahead should represent the actual work being completed or scheduled for completion within the
Moderate >US$10,000
one or more personnel
Reversible disability/impairment or injuries next 14 day period. Tasks identified as having a consequence severity of High or above should be
Minor >US$1,000
requiring medical treatment
supported with written procedures and or detailed work method statements. Assistance in the
Low level damage/injury . No medical
Low >US$100
treatment. (First Aid etc) development of this look ahead may be sort from the relevant IMT Safety Engineer.
Consequence Injury Description Cost Estimation
Multiple fatalities and irreversible disability
Critical >US$1 Million
(>30%) to one or more personnel NOTE: Basic Tasks should not be included in the 14 day look ahead. Instead, the focus should
Single fatality and/or severe irreversible
Major >US$100,000 be on those tasks identified during the period which pose a significant risk/hazard etc. The look
disability (>30%) to one or more personnel.
Irreversible damage or impairment (,30%) to ahead should represent the actual work being completed or scheduled for completion within the
Moderate >US$10,000
one or more personnel
Reversible disability/impairment or injuries next 14 day period. Tasks identified as having a consequence severity of High or above should be
Minor >US$1,000
requiring medical treatment
supported with written procedures and or detailed work method statements. Assistance in the
Low level damage/injury . No medical
Low >US$100
treatment. (First Aid etc) development of this look ahead may be sort from the relevant IMT Safety Engineer.
BCC RISK ANALYSIS REGISTER - CLEANING OF COOLING WATER LINES
Probability Consequence Risk Rating
No Task Hazard Control Measure Responsible Person
Note: All personnel will attend coordination meeting, pre work & tool box talk. All details will be discussed and duties allocated as required & as per IMT requirements. Standard and
specialist PPE will also be as per IMT requirements. Anchor points,
Likelihood Description
Frequency Description for a Likelihood or Consequence Severity
Total Site (Example only)* Frequency /
Consequence expected to occur in most Probability Low Minor Moderate Major Critical
Almost Certain Occurs weekly
circumstances
Consequence will probably occur in most Almost Certain High High Extreme Extreme Extreme
Likely Occurs every month
circumstances
Possible Consequence should occur at some time Occurs once every 6 months
Likely Moderate High High Extreme Extreme
Unlikely Consequence could occur at some time Occurs once every 5 years Possible Low Moderate High Extreme Extreme
Consequence may occur under exceptional
Rare Occurs once every 10 years Unlikely Low Low Moderate High Extreme
circumstances
Consequence Injury Description Cost Estimation Rare Low Low Moderate High High
Multiple fatalities and irreversible disability
Critical >US$1 Million NOTE: Basic Tasks should not be included in the 14 day look ahead. Instead, the focus should be on
(>30%) to one or more personnel
Single fatality and/or severe irreversible
Major
disability (>30%) to one or more personnel.
>US$100,000 those tasks identified during the period which pose a significant risk/hazard etc. The look ahead should
Moderate
Irreversible damage or impairment (,30%) to
>US$10,000
represent the actual work being completed or scheduled for completion within the next 14 day period.
one or more personnel
Reversible disability/impairment or injuries Tasks identified as having a consequence severity of High or above should be supported with written
Minor >US$1,000
requiring medical treatment
procedures and or detailed work method statements. Assistance in the development of this look ahead
Low level damage/injury . No medical
Low >US$100
treatment. (First Aid etc) may be sort from the relevant IMT Safety Engineer.