Professional Documents
Culture Documents
Typical Reports To Aid The Progress Review: Cost Control
Typical Reports To Aid The Progress Review: Cost Control
Typical Reports To Aid The Progress Review: Cost Control
Tied to contract terms of payment: In this method, the progress and contract terms of pay-
ments are related.
Two-point measurement: This method of measurement of progress is limited to two
predefined measurement points—for example, 50 per cent when all the materials required
for the work are on site, and 50 per cent on completion of the activity. Another example
could be 60 per cent on supply part of the activity and 40 per cent on the erection part.
Single-point measurement: This method is employed when there are numerous small-
value activities in a project. Here, the measurement point could be 100 per cent on completion
only.
16.5 C O ST C O N T R O L
There are different ways in which cost control can be exercised for a construction project. As
mentioned earlier, the important points that must be emphasised while devising cost control
for a construction project are the simplicity of the system and the response time. There is no
point in having a cost control system that is complicated and involves a number of staff to man
it, while the response time is very high.
Harris and McCaffer (2005) quote the example of a thermostat while illustrating the
cost control process. A thermostat observes the outside temperature, compares it with some
predefined standard, exercises control majors and adjusts the temperature. As described previ-
ously, the project cost control also can be thought of as a three-step process:
1. Observe the cost expended for an item, an activity, or a group of activities
2. Compare it with available standards. The standard could be a predefined accepted cost
estimate (ACE) or it could be the tender estimate
3. Compute the variance between the observed and the standard, signalling a warning sign
immediately to the concerned people so that timely and possible corrective measure can
be taken
Pro jec t Mo nito r in g an d Co n tro l Syste m | 579 |
This is where the simplicity of the system comes into the picture. The more complicated
the system, the more number of people it requires to be involved and possibly the more the
response time needed to pinpoint the variation between the observed and the standard. The
response time becomes very important since there is no point in finding the variance at a time
when the activity showing variance is already completed, although this data can be useful for
other projects.
The collection of cost for a project needs involvement of a number of people including
planning engineer, billing engineer, plant and equipment engineer, timekeeper, storekeeper,
accountant and head-office staff. The process of recording cost data against different cost codes
and analysing them against these codes, descriptions, quantities, rates, etc., and then compar-
ing them with some standard such as accepted cost estimate, detecting variances, if any, and
taking timely corrective measures may all look simple in the beginning. However, the process
is not as easy in real-world projects, as we shall see shortly. There are different control systems
that can be adopted depending on the requirement. These are explained below.
16.5.4 S-Curve
S-curve can be used to monitor the cost of a construction project. The S-curve very nearly
depicts the progress profile of a construction project, which is characterized by slow progress
at the beginning and rapid progress towards the middle, followed by slow progress again
towards the end. The amounts planned to be invoiced (billed) and the actual bill amount
raised can also be monitored, through a graph (S-curve). A similar graph can also be plotted
for the amount planned to be spent vis-à-vis the amount actually spent.
Once the contracts have been awarded, it is relatively easier to estimate the ‘bill value’ for
each activity on a detailed bar chart. By analysing the nature of each activity, one can estimate
the way in which this value will be distributed on, say, a monthly basis. These amounts will then
be summed to give the total estimated monthly value, and the figure plotted on a graphic form
as shown in Figure 16.9. Now, a second curve (shown as dotted line) can be drawn based on
the work that is actually performed.
| 580 | c o nstr uct ion pr oj ect manage me n t
Under spend
Overall delay
Time
It is clear from Figure 16.9 that the amount that should have been billed as on the day of
monitoring has not been done, and that is the reason the second curve is running below the
first curve. This is an ‘under spend’ situation. Similarly the second curve is also showing a shift
towards the right. This shows an ‘overall delay’ indicating that the project is running behind
schedule. Thus, the financial value may be used as a single general measure of the progress of
a project.
The continuous curves shown here can, of course, be drawn only if it is possible to estimate
the value of the work done in detail as in case of contracts based on bill of quantities. The proj-
ect manager’s ability to obtain a single and reasonable objective measure of overall progress is
diminished where the contract payments are based on some other method.
After the bar chart has been derived from the project network, the estimated cost for
different activities is calculated on either a monthly or a weekly basis. This could be based
on either early start of activities or late start of activities. Accordingly, we will have two sets
of cost. At this point of time, let us leave the discussion of cost based on early start and late
start. The planned cost month-wise for a project is given in Column 3 of Table 16.1 and
the cumulative value is given in Column 4 of the same table. As can be seen, the project is
planned for 12 months duration, from January 2007 to December 2007. These planned or
estimated costs have been arrived at by estimating labour, material, plant and equipment,
and subcontractor costs—also known as direct cost for all the activities. Certain proportions
of total indirect cost for the project are added as well.
In a very unlikely situation, the work will be executed exactly as per the plan. In most of
the situations, though, the work will consume either more than the estimated duration or less
than the estimated duration. For our example, consider the situation in which the project is
estimated to take more than the originally estimated duration. The completion is now sched-
Pro jec t Mo nito r in g an d Co n tro l Syste m | 581 |
Estimated Revised
cost of estimated
activities Cumulative cost of Cumulative Actual cost Cumulative
on cost at activities cost at of activities actual cost
S. monthly the end of on monthly the end of on monthly at the end
No. Month basis month basis month basis of month
(` lakh) (` lakh) (` lakh) (` lakh) (` lakh) (` lakh)
(1) (2) (3) (4) (5) (6) (7) (8)
1 January 2007 5 5 5 5 5 5
2 February 2007 10 15 10 15 10 15
3 March 2007 20 35 20 35 25 40
4 April 2007 25 60 20 55 25 65
5 May 2007 35 95 25 80 25 90
6 June 2007 50 145 30 110 30 120
7 July 2007 50 195 40 150 45 165
8 August 2007 40 235 40 190 50 215
9 September 30 265 30 220 30 245
2007
10 October 2007 20 285 25 245 30 275
11 November 10 295 20 265 20 295
2007
12 December 5 300 15 280 15 310
2007
13 January 2008 10 290 10 320
14 February 2008 5 295 10 330
15 March 2008 5 300 5 335
uled at the end of March 2008. The revised monthly cost is shown in Column 5 of Table 16.1.
Notice that total estimated cost is still the same, which is equal to the earlier value (refer to
Column 6).
It is interesting to note that the actual cost incurred for a particular activity will have
very less likelihood of exactly matching the estimated cost. For this example, consider the
actual cost month-wise as given in Column 7 of Table 16.1. The cumulative cost now stands
at ` 335 lakh as given in Column 8 of the same table.
The cumulative cost figures given by columns 4, 6 and 8 have been drawn against time
and presented in Figure 16.10. It can be observed that the project is behind schedule and over
budget.
| 582 | c o nstr uct ion pr oj ect manage me n t
350
s 300
250
ost in Rs la
200
50 Budgeted cost
0
Jan
Feb
Mar
Apr
May
Jun
July
Aug
Sep
Oct
Nov
Dec
Jan
Feb
Mar
Mont s
Figure 16.10 S-curves for budgeted cost, revised cost and actual cost
1
As soon as the project is awarded to the contracting organization and the letter of intent issued by the client, the
contractor appoints a project manager and a planning engineer for the project. The two then go through the entire
contract document and prepare the estimates of executing each bid item. They also prepare the estimate for the over-
heads of the project.
Cost codes are established and the budgeted estimates for each of the cost codes are prepared. These budgeted esti-
mates are scrutinized by the top management of the contracting organization and a mutually agreeable budgeted
estimate is agreed to. This is called the accepted cost estimate (ACE) or zero cost by the contracting organization.
Pro jec t Mo nito r in g an d Co n tro l Syste m | 583 |
cost, material cost, plant and equipment cost, subcontractor cost and overhead cost. The details
are worked for the month and till the time of the monitoring. Further, the total cost for each of
the cost codes is worked out using the following relation:
The way to extract cost of labour, material, plant and subcontractor has already been dis-
cussed. Provision for expenses and deferred expenses are explained below.
Deferred Expenses
For some activities, the initial investment required would be very high. The investment is made
for completing the entire activity. For instance, if the activity is only 10 per cent complete, it
would be unfair to book the total investment for the activity in the cost statement. In such
cases, only a part of the expenses, preferably on a pro rata basis, is shown in the cost statement
and the remaining amount is taken as deferred expense, which is adjusted afterwards in propor-
tion to the progress of activity.
Adding up the total cost for each of the cost codes gives the total project cost for the
month and up to the month. This information is passed on to the planning engineer for further
processing.
• Estimate to date
This is found as follows:
Calculate the quantity done to date. Let it be Qd. Take cost to date data for this cost code
from the cost statement. Let it be Cd. Compute the unit cost to date. This is denoted by
Ed. Hence,
Cd
Ed (16.2)
Qd
| 584 | c o nstr uct ion pr oj ect manage me n t
• Revised estimates
The revised estimate for a cost code is computed by first adding the quantities Qd and
Qb. The revised total cost is the sum of Cd and Cb. The revised unit cost (Er) is calculated
by dividing the revised total cost, Cr, by the revised total quantities, Qr. Expressed math-
ematically,
C (C d + Cb )
Er ___r (16.4)
Qr (Q d + Q b )
• Original estimate
Original estimate, Eo, is the estimated cost for a particular cost code. This is computed
by dividing the original estimated cost (Co) by original quantities (Qo). This is expressed
mathematically as,
C
Eo ___o (16.5)
Qo
The variance (V) for each of the cost code is the difference of Eo and Er. That is, variance
V Eo Er (16.6)
The process is repeated for all the cost codes of the project to arrive at the total project cost
at the time of monitoring. This information tells us whether the total project is over-running
the budgeted cost or under-running the budgeted cost.
The typical format of a project cost report is given in Figure 16.11 and a small example
is worked out to illustrate the approach. We take up the example of boundary wall construc-
tion discussed earlier in Chapter 6. Let us suppose that the contractor has been awarded the
contract of constructing a boundary wall at a price of ` 4,979,375, and that he has agreed to
complete the contract in about two months (62 days to be precise). The unit rate payable to
the contractor for different activities is as given in Column 5 of Table 16.2.
Step 1
For illustrating the method, let there be seven cost codes for our example project correspond-
ing to earthwork, formwork, reinforcement, concrete, structural steel, barbed wire and over-
head. The cost codes of these are given in Table 16.3.
Step 2
Prepare the budgetary cost estimate for all activities of the project according to the cost codes. As
mentioned earlier, this is the time to prepare the ACE or zero cost. This is shown in Table 16.4
for the mentioned activities.
Pro jec t Mo nito r in g an d Co n tro l Syste m | 585 |
Table 16.2 Extract from bill of quantity for the boundary wall construction project
It may be noted that the estimate to complete could be the same as the unit cost to date,
or it could be more or it could be less than the unit cost to date. This depends on a number
of factors such as the nature of balance work the likely changes in cost component, and the
escalation. Also, the revised quantity should be used in case there is a change in quantity
against a particular cost code from the tendered quantity.
Total cost is arrived at by adding up the different cost components as mentioned above,
and is entered in the project cost report (see Figure 16.12) under the column ‘project status to
Accepted cost
estimate
Rate Amount
EW 80 40,000 36,500 3,500 40,000
CC 3,000 120,000 8,000 100,000 12,000 120,000
CR 6,833 819,960 70,000 450,000 217,964 81,996 819,960
date’, against the various cost codes. The quantities of work done are then posted against each
cost code to derive the unit cost. The unit costs derived should be compared with the ACE.
The derived unit costs assist in identifying areas where there is an overrun, and further review
will highlight the necessity of cost control measures. These unit costs are consulted to arrive at
unit rates for ‘estimates to complete’ for the balance portion of work.
Thereafter, ‘estimates to complete’ unit costs are determined keeping in mind the unit cost
to date, the nature of balance work, the quantities involved and the likely changes in compo-
nents of cost, escalations, etc., for carrying out works at future dates.
The revised estimate is arrived at by adding ‘project status to date’ and ‘estimates to com-
plete’. The original estimate will comprise of revised quantities as reflected in revised estimates
columns.
The revised contract price has to be arrived at based on revised quantities and agreed rates
as per the contract. All escalations payable by the client and other claims as and when raised
have to be included in the revised contract value. The revised contract value for the revised
quantities minus revised cost estimates gives the estimated site contribution (profit) at the end
of the project as on date.
Sl. No. CODE DESCRIPTION COST COST COST COST COST COST COST COST
2 200 Formwork m2 1,060 185,500 175 1,890 425,250 225 2,950 610,750 207 2,950 908,600 308 297,850
3 300 Reinforcement t 12.60 478,800 38,000 19.40 814,800 42,000 32 1,293,600 40,425 32 1,280,000 40,000 −13,600
4 400 Concrete m3 205.75 617,250 3,000 266.75 800,250 3,000 472.50 1,417,500 3,000 472.50 1,431,675 3,030 14,175
5 500 Structural steel t 0 0 0 3 165,000 55,000 3 165,000 55,000 3 135,000 45,000 −30,000
6 600 Barbed wire m 0 0 0 500 450,000 900 500 450,000 900 500 425,000 850 −25,000
The performance measurement parameter could be cost, schedule or any other technical
parameter such as man-hour. The comparison is done in terms of a common monetary term
(such as rupees or dollar) or in terms of man-hour, equipment hour, ‘quantity of material’, etc.,
assigned to the work.
Earned value is based on the idea that the value of the product of the project increases as
tasks are completed. Therefore, the earned value is a measure of the real progress of the project.
The earned value method involves the concepts of work package and earned value to anal-
yse the performance of a project. It not only tells us about the progress to be achieved to be on
schedule, but also clarifies whether the resources being spent are commensurate with the budget.
This aspect will be clearer with the help of an example.
The earned value method is also used for forecasting the likely course of a project by
extrapolating from the amount of work already put into a project. It is possible to forecast the
project cost at completion and also the probable completion date. The forecasts made are also
used to measure variances and define trends. The project manager can take appropriate actions
should there be unwanted variances and unfavourable trends.
The implementation of earned value method involves the following steps:
Defining the scope of the works The scope of the works is frozen at an early stage in the
project life cycle and changes, if any, in due course are suitably addressed.
Setting up a work breakdown structure (WBS) The project is broken down in logical
groupings and levels, and these are shown in a hierarchy. The lowest level is usually made up of
work packages that are the smallest self-contained grouping of work tasks considered necessary
for the level of control needed. The details on WBS can be read in Chapter 6.
Developing a project master schedule The project master schedule contains details of
scheduled start and completion of the entire work package.
Allocating costs to each work package The principal cost elements are labour, materials,
and plant and equipment. These cost elements have been described in detail in previous chap-
ters. The cost components are summed up for each work package.
Establishing a practical way of measuring the actual work completed The different ways
in which the actual work is measured were described earlier. The selection of a particular
method depends on the type of contract, the terms of payment, etc. However, ‘simplicity’ of
the adopted system is the guiding philosophy most of the times.
Setting the performance measurement baseline The baseline indicates the plan to spend
in different time periods for all the work packages, over the planned duration of the project.
The period could be weeks or months.
25 Schedule
Time now completion date
EAC
20
WP
AC BAC
WS
Rupees (thousands)
BC
15 WP
Cost BC
variance Schedule
variance
10
0
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23
Time
Figure 16.13 The three ‘S’ curves
The index is used to compare schedule performance against the budget or plan. In case the
earned value is less than the budgeted value—that is, SPI < 1, it means the project is ‘behind
schedule’.
Cost Performance Index (CPI)
Cost performance index indicates whether the project is spending as per the budget. CPI is a
ratio of earned value and the actual cost of completed works. If the earned value is less than the
actual cost, CPI < 1, it indicates a ‘cost overrun’ situation.
BCWP (16.11)
CPI 5
ACWP
A positive value of VAC means the forecast is for an ‘under-run’, while a negative VAC is under-
stood to have an ‘overrun’ projection for the project.
Example
Suppose that a 5 km length of road is to be constructed in 5 months at a budgeted cost of
` 500 lakh. It is proposed that 1 km of road length will be completed every month and, thus,
` 100 lakh is planned or budgeted for each month. At the end of 2 months, suppose that 1.5
km of road length is completed at an actual cost of ` 180 lakh. Is the project under-spending
or overspending? Is the project behind schedule or ahead of schedule?
The project is clearly behind schedule since only 1.5 km road length has been completed
against a planned progress of 2 km road length. The project appears to be ‘under budget’
because the budgeted cost at the end of month 2 was supposed to be ` 200 lakh (` 100 lakh
for month 1 and ` 100 lakh for month 2) and the actual cost during this period has been ` 180
lakh. However, this seemingly ‘under budget’ schedule scenario is due to the project being
‘behind schedule’, which is why less money has been spent. In fact, according to the earned
value method, there is a ‘cost overrun’ of ` 30 lakh at this point of time and a schedule overrun
of ` 50 lakh. It may be noticed that earned value methodology has measured both schedule
and cost in a common unit of measurement, which in this case is rupees, although convention-
ally the schedule overrun is measured in unit of time.
Let us take another example in which a house is to be constructed and is scheduled to
take 12 months. Its budgeted cost of construction is ` 3,000,000. The month-wise plan for
costs to be incurred in the different activities of house construction is given in Table 16.6.
Also, let us assume that the construction progress is monitored at the end of September. The
budgeted cost of work performed and the actual cost of work performed have been found,
and the values are given in Table 16.6.
Table 16.6 BCWS, BCWP and ACWP values (` ‘000) for house construction example
September
November
December
February
October
January
August
March
April
June
May
July
Budgeted cost of 50 100 200 250 350 500 500 400 300 200 100 50
work scheduled
(BCWS)
Cumulative value of 50 150 350 600 950 1,450 1,950 2,350 2,650 2,850 2,950 3,000
BCWS
Budgeted cost of 50 100 200 200 250 300 400 400 300
work performed
(BCWP)
Cumulative value of 50 150 350 550 800 1,100 1,500 1,900 2,200
BCWP
Actual cost of work 50 100 250 250 250 300 450 500 300
performed (ACWP)
Cumulative value of 50 150 400 650 900 1,200 1,650 2,150 2,450
ACWP
| 592 | c o nstr uct ion pr oj ect manage me n t
350
300
250
200
150
ACWP
100 BCWP
BCWS
50
0
Jan Feb Mar Apr May June July Aug Sep Oct Nov Dec Jan Feb Mar
Figure 16.14 The BCWS, BCWP and ACWP curves for house construction example
The three S-curves drawn corresponding to the cumulative values of BCWS, BCWP and
ACWP given in Table 16.6 are shown in Figure 16.14.
In Figure 16.14, the BCWS curve shows that house construction is planned for accom-
plishment over a 12-month time frame, with a total budget amount of ` 3,000,000. The ‘time
now’ line (end of September) shows that ` 2,650,000 of the project resources was planned
to be completed at this point in the project. Another way to look at this is that the house
construction was planned to be 88.3 per cent complete (` 2,650,000/` 3,000,000) at this
point in time. In this example, the house construction was planned to have accomplished `
2,650,000 worth of work in nine months, but the real accomplishment was only ` 2,200,000,
which is the earned value in this period as shown in Figure 16.14. Comparing the earned value
with the budgeted value measures the rupees value of work accomplished versus the rupees
value of work planned. This difference is ‘schedule variance’. Thus, schedule variance in this
case is ` 2,200,000 2 ` 2,650,000 5 2` 450,000, a ‘behind schedule’ shown appropriately in
Figure 16.14.
As mentioned earlier, the earned value for the work performed compared with the actual
cost incurred for the work performed gives the cost variance and is a measure of cost efficiency.
The actual cost of work has been determined (Table 16.6) and it is found that the actual costs
for performing the ` 2,200,000 work was ` 2,450,000. Thus, there is a variance of ` 2,200,000
2 ` 2,450,000 5 2` 250,000, which is a ‘cost overrun’ condition.
Pro jec t Mo nito r in g an d Co n tro l Syste m | 593 |
The above variances can also be explained in terms of SPI and CPI. Thus, SPI and CPI for
the example problem are:
BCWP
SPI =
BCWS
2,200,000
= = 0.83
2,650,000
Since the SPI is < 1, the project is behind schedule.
BCWP 2,200,000
CPI 5 = 5 0.898
ACWP 2,450,000
The CPI being < 1, the project is over budget.
It may be noted that the earned value approach has reduced both cost and schedule vari-
ance to a common denominator, i.e., Rupees or a ratio. Hence, we can compare the two and
come to a conclusion that the project is behind schedule by ` 450,000 and behind budget by
` 250,000—i.e., it is more behind schedule than it is behind budget.
The estimate at completion using the expression [EAC 5 ACWP 1 ((BAC 2 BCWP)/CPI)
5 2,450,000 1 ((3,000,000 – 2,200,000)/0.898)] is found to be ` 3,340,000, which means
that if the project continues to progress as it has done so far, it will be completed at a cost of
` 3,340,000, i.e., ` 340,000 more than the original budget. The EAC can also be calculated
using the other formulae given in Table 16.5. The result will be different than what we have
using this formulae. The most appropriate method for a given situation must be chosen by the
project manager. Also, it is up to the project manager to assess the reasons for the project being
behind schedule and over budget, and take corrective actions.
The above calculations have been performed for a single work package. A project consists of
a number of work packages. The status of the overall project (whether it is on time and within
budget) can be found out using the same set of formulae illustrated for the performance evaluation
of a work package. For this, the BCWS, BCWP and ACWP values for all the work packages are
summed up and used in the formulas. An example will explain this.
Suppose a project consists of 13 work packages—1, 2, 3, ________, 13. The schedule start
and completion of each work package is shown in the bar chart given in Figure 16.15. The
budgeted cost of each work package is also shown on the bar on a monthly basis. Thus, from
Figure 16.15 it is clear that work package 1 (earthwork) is scheduled to start from month 1 and
get completed in month 6—that is, the scheduled duration is 6 months. In month 1, it is bud-
geted to cost ` 0.25 lakh, while in months 2 to 6, the budgeted costs are ` 0.75 lakh, ` 1.0 lakh,
` 1.25 lakh, ` 1.25 lakh and ` 0.5 lakh, respectively. The budgeted cost of each work package is
shown above the bar of the corresponding work package.
We can now draw a graph (see Figure 16.16) of time versus cumulative cost/price, which
is like the S-curve discussed earlier. Further, let us assume that the progress of the project is
monitored at the end of month 3, and relevant information related to each work package is
captured as in Table 16.7.
In Table 16.7, the project BCWS, BCWP and ACWP have been calculated by adding up the
BCWS, BCWP and ACWP of the thirteen work packages. The project has a schedule variance
of 70.1 2 76.9 5 26.8 lakh and a cost variance of 70.1 2 74.1 5 24 lakh. Thus, at the end
| 594 | c o nstr uct ion pr oj ect manage me n t
Figure 16.15 Bar chart showing the budgeted schedule and cost of all work packages
of month 3, the overall project is running behind schedule and is also over budget. The sched-
ule and cost performance of individual work packages as described earlier is monitored and the
appropriate corrective action taken. It is also possible to forecast the budget at completion and the
estimated cost at completion from the total BCWS, BCWP and ACWP values as described earlier.
Cumulative cost
600
500
Cumulative value in ` lakh
400
300
200
100
0
1 2 3 4 5 6 7 8 9 10 11
Month
Table 16.7 Information related to each work package (BCWS, BCWP and ACWP values in ` lakh)
1
BCWS has been derived from the bar chart given in Fig 16.15
2
BCWP has been derived from (BCWS 3 actual progress 4 scheduled progress)
3
ACWP is based on the record of actual cost incurred in a work package
| 596 | c o nstr uct ion pr oj ect manage me n t
Step 3
Prepare the construction schedule. For the sample project, the initial construction schedule
is given in Figure 16.17.
Step 4
Collect the cost data for each of the cost codes at the time of monitoring. Let’s suppose that
the company is monitoring the project at the end of day 30. The collected cost data is shown
in Table 16.10.
Step 5
Update the progress of the schedule at the end of day 30. The updated schedule is given in
Figure 16.18.
Actual costs at the end of every day up to the end of day 30 are given in Table 16.11, and
the cost-wise expenditure at the end of day 30 are given in Table 16.12.
Table 16.9 Budgetary cost estimate for all the activities of the example project
Activity Cost code 100 200 300 400 500 600 700 Total
ACE
amount
EW 40,000 36,500 3,500 40,000
CC 120,000 8,000 100,000 12,000 120,000
CR 819,960 70,000 450,000 217,964 81,996 819,960
0 4 8 12 16 20 24 28 32 36 40 44 48 52 56 60 64 68 72
Activity
0 10 days 10
EW
4,000/d
2 9 days 11
CC
13,333.33/d
3 35 days 38
CR
23,427.43/d
10 50 days 60
CW
53,600/d
20 42 days 62
FE
10,119.05/d
Step 6
Now calculate the variance cost code-wise by subtracting the value for each of the cost codes
at the end of day 30 and the actual cost for each of the cost codes at the end of day 30. The
variances with the negative sign (refer to Table 16.13) indicate that the actual cost incurred
for the particular cost code is in excess of the budgeted cost and are the areas of concern that
need proper attention.
FE 425,000 0 0 0 0 0
Total 4,084,960 36,500 237,500 567,000 469,878 0 0 145,098 1,455,976
Pro jec t Mo nito r in g an d Co n tro l Syste m | 599 |
they are responsible. Thus, the objectives of the management information system (MIS) are to
provide information relating to actual performance against budgets for the projects, strategic
business units, and the corporate as a whole, and to highlight areas of shortfall in achievement
so that decisions regarding the required remedial actions may be taken.
The comparison of the performance is always made with respect to the budget, which is
normally prepared at a suitable interval at all levels. The budget so prepared at different levels
is basically a sort of commitment by the lower level of hierarchy to its immediate upper level of
hierarchy. Any revision in the budget is very carefully examined and changes are accepted only
if they are well-justified.
The decisions may be required to be taken at strategic, tactical and operational levels of
management, and accordingly, may require different information at these levels. For example,
at strategic level, the information needed would be pertaining to trends in industry, investment
pattern, government regulation and policies, competition strategies, technological changes, etc.
The information at tactical levels of management would be pertaining to short-term planning,
cash-flow projection, financial results, sales analysis, budgetary control, variance statements,
capacity utilization, etc. Finally, the information at operational levels would be day-to-day
progress at project sites, item-wise stock, pending purchases, subcontractor’s performance, etc.
Depending on the type of business, the information type would also vary. A construction
organization executes projects that are characterized by their geographical spread and difficult
terrain. It is a challenge to share and access information vital for the decision-making.
A typical MIS report used in construction industry would consist of monthly progress
report; S-curve for budget invoice, actual invoice, budgeted cost and actual cost; project cost
report; and project performance report giving details of status of invoicing, contribution and
collection. Some of the common reports associated with construction project MIS are monthly
progress report, project cost report and project performance report.
These reports are prepared by the planning engineer in consultation with the project
manager and the project accountant. Normally, the above reports are prepared on a monthly
basis and sent to higher offices such as regional, divisional, or head office, as the case may be.
After reviewing these reports, the higher offices may suggest corrective actions as and when
required.
At least once in three months (more often in the case of large projects or projects requiring
critical managerial attention), the site manager and the site planning engineer meet the higher-ups
(such as regional manager, divisional manager, or general manager, as the case may be) who are
based at higher offices, and discuss the support required by the sites in terms of major resources
to meet the physical targets, resourced deployment, etc. For the subsequent months till the next
review meeting, the actual performance is reported against these revised schedules.
The regional manager will have the responsibility for taking follow-up actions in close coor-
dination with, and under the direction of, his superior, such as the general manager, on the action
plan decided during the review meetings.
At the sites, the site planning and project manager should hold weekly meetings with the site
engineer/supervisor in charge of the various sections. At these meetings, the physical targets for
the various sections for the next week will be set and the resource requirements in terms of materi-
als, manpower equipment, etc., identified. The site planning engineer is normally responsible for
ensuring that these are provided to the various sections on time. The week’s performance against
targets is also reviewed in these meetings and follow-up actions are taken.
| 600 | c o nstr uct ion pr oj ect manage me n t
The MIS system could broadly consist of flash reports and detailed reports. Since timely
action is the essence of any MIS, the flash reports are generated from profit centres as on a
particular date. The major data required from sites for preparing the flash reports are—esti-
mated invoicing, material and labour costs, and actual site overheads. These reports could be
approximate in nature and serve the purpose of promptly reaching out to the top management
professionals of the organization. Construction organizations normally follow a cut-off date for
reporting the data and, accordingly, the date of preparation of flash report or detailed report is
also kept fixed for considering and estimating the quantum of work. The evaluation on these
cut-off dates need not always be based on client certification (since this could lead to delays in
obtaining data), but could be estimated based on the quantum of work actually carried out. The
variation, if any, between the client certification and the estimation has to be corrected in the
subsequent reports when the detailed MIS report is prepared.
Although reports related to schedule progress are not difficult to prepare on a regular basis,
there could be problems in regard to reports related to costs, especially material cost. As was men-
tioned earlier, this is because a number of persons from different departments are involved in some
way or the other in providing the cost data. Coordinating with all of them is a time-consuming
process and most of the times, this is the reason for delay in such reports.
Considering the importance of MIS for decision-making, a large number of organizations are
using information technology tools for gathering data and generating suitable information in a
tailormade manner. In fact, organizations have started maintaining a separate MIS cell to provide
appropriate and accurate information at the right time and at an optimum cost to managers to
monitor the business activities, to avoid information overload, and to avoid generating redundant
information. The personnel in MIS cell collect data, extract relevant information from the data col-
lected, and disseminate the same at different levels of management to assist in their decision-making
process.
REFERENCES
1. Austen, A.D. and Neale, R.H., 1995, Managing Construction Projects: A Guide to Process and
Procedures, International Labour Organization.
2. Chitkara, K.K., 2006, Construction Project Management: Planning, Scheduling and Controlling,
10th reprint, New Delhi: Tata McGraw-Hill.
3. Harris, F. and McCaffer, R., 2005, Modern Construction Management, 5th ed., Blackwell
Publishing.
REVIEW QUESTIONS
1. State whether True or False:
a. The traditional control parameters of construction projects are schedule, cost and quality.
b. Updating can be defined as planning and programming of the remaining portion of an activity
by introducing the latest information available.
17 Construction Claims,
Disputes, and Project
Closure
17.1 C LA IM
During the execution of a project, several issues arise that cannot be resolved among project
participants. Such issues typically involve contractor requesting for either time extension or
reimbursement of an additional cost, or sometimes both. Such requests by the contractor are
referred to as ‘claim’. If the owner accedes to the claim of contractor and grants him extension
of time or reimbursement of additional cost, or both, the issue is sorted out.
However, if the owner does not agree to the claim put out by contractor and there are
differences in the interpretations, the issue takes the form of a dispute. Claims are becom-
ing an inevitable and unavoidable burden in modern projects involving new technologies,
specifications and high expectations from the owner.
The claim mentioned above can also be put up by the owner. It is, therefore, imperative
for all the parties to be fully acquainted with the procedures and systems, including recourse to
certain preventive actions as found necessary and required.
Claim Identification
The contractor studies the instructions in the form of drawings as well as oral or written instruc-
tions provided by the owner/engineer. If it contains extra works, the same is read against the
provisions of the contract.
Claim Notification
After it is established by the contractor that it is an extra work, the contractor is required to
inform the engineer within the time frame stipulated and clarify his intention to claim extra
rates for the same. This is very important because failure on contractor’s part regarding this
shall entail its rejection by the engineer.
Claim Substantiation
The contractor has to fully establish the claim including his entitlement under the contract,
giving reference to the relevant clauses. The claim is supported by necessary backup calcula-
tions. Backup documents like letters, vouchers and drawings are also enclosed. For period-
related claims such as extended stay costs and interest on delayed payments, it is required to
revalidate the claim at periodic intervals and submit the same to the engineer until the end of
the relevant period.
Decision of Engineer/Owner
The owner/engineer is supposed to convey his decision on the claim to the contractor within
a time frame specified in the contract. If the claim is not allowed, the same needs to be stated
along with reasons. The value of claim allowed shall also be stated.
Constr u ctio n Cla i ms, Di spu tes, an d Pro je ct C lo sure | 605 |
1 7 . 2 D ISP U TE
Given the uncertainties involved in a construction project and the magnitude of funds involved,
it is only natural to have disagreements between parties, but these need to be resolved. While
most of such day-to-day differences are resolved in an amicable manner, without having to
resort to a more formal mechanism, the parties at times agree to disagree and seek redressal
through independent intervention. Although, in principle, the discussion falls under the pur-
view of construction law, effort has been made to discuss some of the aspects related to dis-
putes and dispute resolution with as little legalese as possible.
Technically, a dispute implies assertion of a claim by one party and repudiation thereof by
another. Thus, neither a mere claim without repudiation, nor a pair of claim and counterclaim,
can be called a dispute.
Example
In a letter dated June 30, 1998, a contractor makes a claim for ` 5 lakh of additional
work in dewatering of foundations, resulting from unforeseen rains in the month of
March and the item not being provided for in the contract. The details of the rainfall
and the costs incurred in terms of manpower, equipment, power consumption, overtime
payments made, etc., are annexed to the claim along with photographs. In a letter dated
July 13, 1998, the owners acknowledge the receipt of the aforesaid letter from the con-
tractor, and inform them (the contractor) of the owners’ decision to (a) impose LD for
delay of work, and (b) recover ` 2 lakh (towards LD) in the next RA.
Does the matter define a dispute?
From the information given, it is not at all clear whether it is the delay that is attributable
to the rains or it is the liquidated damages. It should also be noted that though the contrac-
tor has asked for an extra payment, he has not asked for an extension of time to complete the
project. The above can be, therefore, considered as basically an example of a claim and coun-
terclaim, and does not constitute a dispute.
the documents are internally consistent, i.e., there is no contradiction in the provisions of
general conditions, special conditions and drawings, and (c) specifications, where required, are
available. Of course, incompleteness, inaccuracy and inconsistency of information are only part
of the reasons for disputes in a construction project. The following paragraphs briefly discuss
some of the common causes of litigation.
Incorrect Ground Data
Such data includes information about ground conditions, depth of groundwater table, rainfall and
temperature data, availability of power and water, etc. The estimates of a contractor are based on
the ground data provided with the tender documents, though depending upon the size of the
project and the means of a contractor, the latter also at times carries out an independent assess-
ment of the data provided. Obviously, any difference between the ground reality during execution
and the conditions provided in the contract could easily be the reason for disputes.
Use of Faulty and Ambiguous Provisions and/or Language in Contracts
The language of the contract should be clear and such that it is not open to different interpreta-
tions. Use of ambiguous language and/or provisions could open a floodgate of avoidable litiga-
tion. It is also important that the contract clearly lays down specific procedures that are to be
adopted in the event of contingencies. A well-defined hierarchy of documents that will prevail
in the event of a discrepancy, often goes a long way in determining the appropriate course of
action without having to resort to arbitration. Also, at times, absence of appropriate provisions
to handle technical inspections by the client or owner, or third parties, could become a source
for litigation, as such inspections themselves require money and at times result in observations
that need appropriate rectification action, which may have financial implications or cause avoid-
able delay. An ill-defined or a vaguely defined hierarchy of documents that will be deemed to
prevail in the event of a dispute could be a cause for dispute, as the following example clearly
brings out.
Some drawings for the material-handling plant showed handrails along only a central walk-
way, whereas some showed similar railings along all other areas where covering plates fabricated
from MS flats were provided. The confusion was compounded by a statement in the special condi-
tions of the contract, which stated that railings were to be provided along the central walkways as
per drawings. The owners insisted that railings should be provided for all covers, which was pro-
vided by the contractor, who, however, made a case that such railings were ‘extra’ and not a part of
the original lump-sum contract. The arbitrator citing confusion in drawings, and precedence in
documents, insisted that the provisions of the SCC prevail. In this case, the ‘natural meaning’ of
the provisions of the SCC was taken as follows—the document implied the existence of other covered
areas where railings need not be provided, and therefore upheld the contractor’s claim.
Deviations
The contract should be so designed that there are as few extra items and/or deviations as pos-
sible. In other words, the scope of work in any contract should be unambiguously defined, and
this obviously calls for thorough preparation on the part of the client/owner before actually
floating an enquiry.
Unreasonable Attitudes
It should be borne in mind that in order to complete the work professionally, it is important that
the parties involved resort to unilateral action to preserve an environment of mutual trust. Thus,
Constr u ctio n Cla i ms, Di spu tes, an d Pro je ct C lo sure | 607 |
both the client and the contractor need to have a professional approach to the project, including
areas where there could be disagreement on interpretation, etc. Measures such as suspension
of the contract or invoking of clauses related to imposition of liquidated damages should be
resorted to only in the most extreme cases, as they vitiate the atmosphere of the project, and also
affect the work on other contracts. Delays in payment of bills should also be avoided to ensure
that the contractor does not get cash-strapped, which will obviously affect his ability to perform.
Contractor Being of Poor Means
It is important that the contractor identified to do a job possesses the required human, finan-
cial and technical resources. In the absence of any of these, it is very likely that the contrac-
tor will look for an escape route for leaving the project, and may try to force a suspension or
determination (termination) of the contract, or take the matter into arbitration/litigation to
cut his losses.
Unfair Distribution of Risk
This could be a major reason for not only avoidable litigation but also increase in the cost of
the project. Indian contracts typically are heavily loaded against the contractor, who obviously
tries to cover the risks he is ‘forced’ to take by either hiking the rates, or taking an approach
of ‘crossing the bridge when we come to it’, and the latter is almost a certain prescription for
litigation if adverse conditions are encountered.
Negotiation
This could refer to a focused discussion on the dispute among the engineers from all interested
parties, with the intention of resolving differences without the involvement of third parties, as
happens in the case of mediation and arbitration. Indeed, this is an informal process in the legal
sense, but if an agreement is reached through the process, it may have the usual legal signifi-
cance. The negotiation process is fast and does not involve additional expenses. The discussions
are held between the parties across the table in a cordial and peaceful atmosphere.
Mediation and Conciliation
Mediation and conciliation are essentially an informal process in which the parties are assisted
by one or more neutral third parties in their efforts towards settlement. These mediators do
not sit in judgement but try to advise and consult impartially with the parties with the object
of assisting in bringing about a mutually agreeable solution to the problem. Naturally, under
the conditions, they have no power to impose an outcome on disputing parties.
Mediation and conciliation are voluntary in the sense that the parties participate of their
own free will, and a neutral third party simply assists them in reaching a settlement. The process
is private, confidential and conducted without prejudice to any legal proceedings. The process
is non-binding unless an agreement is reached. Of course, once an agreement is reached, and
the parties have signed it, the document (or the understanding) is as binding as any other
agreement would be.
Although the process is largely informal, the following could be identified as parts or stages
in a mediation process. In the pre-mediation stage, there has to be a basic agreement among
the parties to the mediation process, including the identification of a mediator. Mediation
could be direct or indirect, and could involve meeting(s) with parties, presentation(s) being
made by them, putting together of facts, negotiations and a settlement. Finally, a mediator may
also like to be involved in the process of compliance with the settlement reached.
Given that mediation is an informal process, it has certain inherent advantages over the more
formal and legal process. For example, it could be a lot less time-consuming and even involve
lesser costs, and the outcome could be more satisfying to the parties, while also minimizing fur-
ther disputes. It also opens channels of communication, and could contribute greatly to preserv-
ing or enhancing a professional relationship. Further, the exercise may be said to empower the
parties and give them greater confidence in their ability to handle disputes.
Arbitration
Arbitration is perhaps the most commonly used mechanism for settlement of technical disputes
in a construction project. It is a quasi-judicial process to the extent that legal protocol is largely
observed, and it is important that the arbitrator, who basically acts as a judge, understands legal
procedures. In India, the Arbitration and Conciliation Act, 1996, provides the legal framework
for the arbitration process. In principle, collection and interpretation of evidence, examination
Constr u ctio n Cla i ms, Di spu tes, an d Pro je ct C lo sure | 609 |
and cross-examination of witnesses, etc., are some examples of essentially legal matters, which
an arbitrator needs to have a sound understanding of. However, a basic belief in principles of
natural justice and a practical approach are the hallmark of a successful arbitrator. He should
be able to guide and provide a direction to the proceedings, which could be quite tough,
especially when the parties to the dispute are represented by professional lawyers. In fact, the
law has now added a new dimension to the arbitration process by empowering the arbitrators
to conciliate and help the parties in arriving at a fair compromise or an equitable settlement of
the case before him.
As far as the number of arbitrators is concerned, much like the judicial system, technical
disputes can also be resolved by single arbitrators, or a panel of several arbitrators, and though
the parties are free to determine the number of arbitrators, it should be ensured that the
number is odd, so that a situation of a ‘tie’ in an award is preempted. Often, one arbitrator each
is nominated by the contractor and the owner, and these individuals together choose a third
colleague (brother) arbitrator, to complete the constitution of a bench of arbitrators.
and place of a hearing are fixed based on the mutual convenience of parties. Since the hearings
are not open to the public, the overall relationships are less affected. This aspect is important
considering the fact that the parties often want to avoid needless publicity as it adversely affects
their professional standing and relationships.
1 7 . 3 C O R R ES P ON D E N C E
Correspondence is defined as communication between parties concerned, either in writing or
in oral form. A communication is said to be complete only when
• Originator is able to make receiver understand his text
• Receiver in turn replies him back
It is imperative that all correspondence with client or engineer must serve the purpose they are
intended for.
Some do’s and don’ts while corresponding with the client/engineer are given below.
Do’s
• Be specific on point to be conveyed
• Inform client/engineer on all matters concerning contract without any delay
• Where required, correlate matter to relevant contractual clause, and explain the case
• Send reply to all letters from client or engineer, however trivial the matter may be
• Put message in simple language
• Make letters easily understandable by the other party
• Must serve building up of records
• Should not consider correspondence as a weapon for warfare
• Matters like extra claims and rate analysis for extra items of work should always be sup-
ported with necessary calculations
• Nature of correspondence should be in a manner paving the way for resolving points/
disputes between parties
| 612 | constr u ction pr oj e ct managemen t
Don’ts
• Tenor of correspondence should not be aggressive
• Should not be overzealous
• Facts should not be misrepresented
• Facts and figures should not be exaggerated
• Be reflective of facts of the case
• Correspondence should not to be made for the sake of record creation
17.4 P R O JEC T C LO SU R E
This is the last phase of a construction project and is as important as any other phase in the
project. This is a process of completing and documenting all the construction tasks required to
complete the project. A poor project closure (or close-out, as it is referred to sometimes) leaves
the client unsatisfied and may prove to be a cause for not getting repeat business. Thus, project
closure should be meticulously planned. Considering the importance of project closure, some
companies have developed certain templates/checklists to assist them in the process of project
close-out. It is helpful for both contractors and owners to have short project-closure time.
While an owner faces least interference in moving in and acquiring the constructed facilities,
the contractor also can quickly move out to other project locations if the project closure does
not become lengthy. A poorly planned project closure may take more than a year to complete.
The outputs from the project closure phase help to execute the next project with much more
efficiency and control, as we will see subsequently.
Project closure consists of a number of tasks. These are given in Figure 17.1.
As can be seen from Figure 17.1, the project closure phase can be divided into the fol-
lowing broad headings:
1. Construction closure
2. Financial closure
3. Contract closure
4. Project manager’s closure
5. Lessons learned from the project
These are briefly discussed in the following sections.
Construction closure
• Preparation of punch list
• Certificate of substantial completion
• Certificate of occupancy
• Demobilization of resources and utilities
Financial closure
• Final payment
• Release of bank guarantees
Contract closure
• Preparation of as-built drawings
• Submission of operation and
maintenance (O&M) manual
• Submission of warranties
• Submission of test reports
Final Payment
The contractor has to apply for the release of final payment after he has attended to all the defi-
ciencies pointed out in the punch list. The request for release of retention money is also made.
Submission of Warranties
It is the duty of the contractor to collect all the warranties and guarantees from vendors, sub-
contractors and suppliers, and submit these to the owner.
Constr u ctio n Cla i ms, Di spu tes, an d Pro je ct C lo sure | 615 |
REFERENCES
1. Iyer, K.C., 1996, Identification and evaluation of dispute-prone clauses in Indian construction
contracts, Doctoral thesis submitted at Indian Institute of Technology Madras, Chennai, India.
REVIEW QUESTIONS
1. State whether True or False:
a. Claims involve both owner and contractor, and are unavoidable in modern projects.
b. Loopholes in the contract document are one of the sources of claim.
c. Modification in the scope of work without notification by the client can be a cause of claim.
d. Claim management involves claim identification and notification to the concerned party.