Arch 242: Materials and Methods

of Building Constrictions I
Fall 2021-2022
Dr. Emad Al Qattan

Week 1
Ghaliah Al Mutawa
2182161357
Phase one

• Introduction:
to start with the project and after being introduced to its
objectives, I’m building a 4x4 room at scale 1:10 using actual
building materials with different building methods and
techniques learned from this course.

• Week 1 requirement:
1. Prepare site
2. Excavate
3. Excavation support

• Dimensions:
1. Scale 1:10

2. Box A:
50x50x20

3. Box B:
B
40x40x15

A
• Weekly schedule:

Tasks Week 1 Week 2


Day Day Day Day Day Day Day
1 2 3 4 5 6 7

Research Foundation
(Framework –
footing
Materials reinforcement -
preparation column neck –
concrete
Site pouring -
preparation waterproofing)

Excavation
and shoring

report

• Construction process:
1. Site Preparation:
The first step was constructing the wooden box in
preparation for the excavation. The model is made
from two boxes; the first being 50 cm * 50 cm *20 cm
that serves as the site, and the second box is 40 cm * 40
cm * 15 cm serving as the room. Then the preparation
of the site began by filling it with sand

2. Excavating:
After constructing the model and having the site
ready, the excavating process begins.
3. Excavation Support:
The excavation support type that I used while
constructing the model was the wall pile shoring. A
shoring structure is built to prevent soil movement and
cave-ins during construction and excavation, and is
temporary in nature, but can be left as a part of the
permanent structure.

• Conclusion:
The site is prepared, excavated, and supported in
preparation for the footing and ready for next week's
continuation which will include 1) footing2) footing neck,
3) waterproofing, and all concrete elements will be
reinforced.