Professional Documents
Culture Documents
Appendix' Table Update
Appendix' Table Update
Appendix' Table Update
Tradeoffs I -Structural
Reinforced concrete is a strong durable building material that can be formed
into many varied shapes and sizes ranging from a simple rectangular column,
to a slender curved dome or shell. Its utility and versatility is achieved by
Reinforced Concrete (Normal combining the best features of concrete and steel. It has good thermal mass,
Weight) and is inherently fire resistant. Rebar is generally made from 100% recycled
scrap, and at the demolition stage, the concrete and rebar are capable of
being separated so that the steel can be recycled.
Precast concrete is a construction product produced by casting concrete in a
reusable mold or form which is then cured in a controlled environment,
transported to the construction site and erected into place. Precast has lower
Reinforced Concrete (Lightweight) lifetime costs than any other building solution and minimizes structural
maintenance needs during years. It was found that structural construction cost
efficiency around 5-10% was generally obtained by replacing conventional
structural system with precast concrete. It has also been proved that the
construction speed was able to be increased significantly in-line with the
achievement of better quality works and more eco-friendly construction
projects.
Steel structure is a metal structure made of structural steel connected with bolts or
Steel weld to carry loads. Since structural steel possesses high strength, steel structures
requires less raw material than other types of structure like reinforced concrete
structure and steel structure.
Tradeoffs II - Geotechnical
Dynamic Compaction is a ground improvement technique that densifies soils
and fills by using a drop weight. The drop weight, typically hardened steel
Dynamic Compaction plates, are lifted by a crane and repeatedly dropped on the ground surface.
Dynamic compaction technique is used to increase bearing capacity, and
decrease settlement and liquefaction potential for planned structures. The
technique will be effective in silts, clayey silts and sandy silts.
Stone Column is a ground improvement method that's being used to increase
the load bearing capacity of the foundation and tend to reduce the settlement
Grout Compaction of foundation at allowable loads. This generally consists of water-jetting a
vibroflot into the soft clay layer to make a circular hole that extends through the
clay to firmer soil. The hole is then filled with imported gravel. The gravel in the
hole is gradually compacted as the vibrator is withdrawn.
Ground consolidation using The Rapid Impact Compaction is an innovative dynamic compaction technique
Prefabricated Drains that is used to compact sandy soil, where silt and clay contents are low.
Standards Structural
1. National structural code The purpose of this code is to provide minimum load requirements for
of the Philippines the design of the buildings, towers and other vertical structures and minimum
(NSCP) standards and guidelines to safeguard life or limb, property and public welfare by
regulating and controlling the design, construction, quality of materials pertaining
to the structural aspects of all buildings and structures within its jurisdiction.
2. American Society for Testing ASTM's geotechnical engineering standards are instrumental in specifying,
and Material - International testing, and investigating the physical/mechanical properties and characteristic
Standard (ASTM) behaviors of surface and subsurface earth materials that are relevant to a
construction project. Such earth materials include soil, dimension stones, slate,
soil-cement mixtures, ground water, bituminous geomembranes, and slurry, rock
mass, aquifers, and geotextiles. These geotechnical engineering standards
allow engineering firms and construction companies to examine the elastic
characteristics, flow, and erosion behavior of the said earth materials to ensure
safety and prevent unforeseen hazards related to the erection of civil structures.
3. Philippine Port Authority In designing port and harbor facilities, the design condition shall be based on the
- Engineering Standards for environmental considering, characteristics of materials, construction condition,
Port and Harbor Structures and social requirements for the facilities.
Unit Weights of Materials, PPA-ESPHS, Chapter 15, Table 15.2.1 Static
Friction Coefficient, PPA-ESPHS, Chapter 16, Table 16.1.1 Load
Combination, PPA-ESPHS, Chapter 17, Table 17.1.1
Modern Tools/Techniques
STAAD Pro V8i SS6 STAAD Pro is one of the most widely used structural analysis and design
software worldwide. Basically STAAD helps structural engineers automate tasks
by removing the tedious and long procedures of the manual methods. STAAD
Pro can also be used to analyzed bridges based on the codes and provisions
from the design standards. The designers used the software to create an
analytical model to analyze and measure the initial deflection of each trade-offs.
Standards Geotechnical
1. American Society for ASTM’s geotechnical engineering standards are instrumental I specifying,
Testing and Material - testing, and investigating the physical/mechanical properties and characteristic
International Standard behaviors of surface and subsurface earth materials that are relevant to a
(ASTM) construction project. Such earth materials include soil, dimension stones, slate,
soil-cement mixture, ground water, bituminous geomembranes, and slurry, rock
mass, aquifers, and geotextiles. These geotechnical engineering standards
allow engineering firms and construction companies to examine the elastic
characteristics, flow, and erosion behavior of the said earth material to ensure
safety and prevent unforeseen hazard related to the erection of civil structures.
2. National Structural Code The purpose of this code is to provide minimum load requirements for
of the Philippines (NSCP) the design of the buildings, towers and other vertical structures and minimum
standards and guidelines to safeguard life or limb, property and public welfare by
regulating and controlling the design, construction, quality of materials pertaining
to the structural aspects of all buildings and structures within its jurisdiction.
Modern Tools/Techniques
DC - Settle A software that is intended to provide settlement analysis of several foundations.
CE 509
CE Design Project 2
PREPARED BY:
Adriano, Neil Vinzon S.
An, Marianne R.
Paraiso, Joyce Ann E.
Reyes, David Dwight
CE52FC3
SUBMITTED TO:
ENGR. Rhonnie C. Estores
Instructor
October 2019
ACKNOWLEDGEMENT
The completion of this Capstone Design Project will not be possible without those people who
helped us in the design, analysis, and presentation of our project. We would like to take this opportunity, to
express our deepest gratitude our instructors, advisers, the Capstone defense panel, our families, and
friends for all their patience, guidance and support for this project to be possible.
To our internal adviser, Engr. Jerome Tadiosa, for advising us on how to design our trade-offs and
for helping us in doing the construction management part and costing of the project, thank you so much Sir
for making time despite your busy schedule!;
To our external adviser, Engr. Elmer Cabulisan Jr., who helped us in coming up with our trade-offs
and for advising us in the design of our trade-offs, thank you Sir for making time for us!;
To our class adviser, Engr. Rhonnie C. Estores, for his unending patience with our persistent
questions and his valuable inputs and guidance throughout duration this project, thank you so much Sir!;
To our guest panel, Dr. Amelia T. Marquez, for making time for our capstone defense despite her
hectic schedule, thank you for guiding us and correcting our project, Ma’am!;
To our families, especially to our parents, who are very understanding and supportive, for their
continuous moral and financial support;
To our friends, who helped us towards the completion of this project and who stayed with us
through those sleepless nights;
To Amo Yamie Crib and High Grounds Cafe, for letting us stay in their establishment until late nights;
Our school, the Technological Institute of the Philippines, for giving us the opportunity to do this kind of
project;
Lastly, we would like thank God Almighty for giving us the gifts of patience, perseverance, and knowledge;
without You Lord, this project would never be possible.
Our most heartfelt “Thank You!” to all the people, whom we failed to mention, who has been part for making
this Capstone Design Project possible.
Thank you!
#GraduateOctober2019
Table of Contents
ACKNOWLEDGEMENT......................................................................................................................................... 2
APPENDICES.................................................................................................................................................... 113
APPENDIX A: CODES AND STANDARDS..................................................................................................................113
APPENDIX B: INITIAL ESTIMATES...........................................................................................................................123
APPENDIX C: FINAL ESTIMATES..............................................................................................................................125
FINAL ESTIMATES COMPUTATION FOR CONTEXT I...........................................................................................125
APPENDIX D: FINAL ESTIMATES COMPUTATION FOR CONTEXT II....................................................................130
APPENDIX E.DESIGN OF GEOTECHNICAL TRADE-OFFS......................................................................................212
Notations:....................................................................................................................................................... 216
Binangonan is the bounded North-Northwest by Angono Rizal. The lakeside park referred by the locals as
Wawa is located at A. Ibañez St., Brgy. San Vicente, Angono Rizal is the place to go especially when dusk
looms where the townsfolk hang out and enjoy the views of the sunset, the Laguna de Bay and the Metro
Manila skyline. Popular among local bathers and promenades alike; the lakeside park, along with the forest
park, is part of municipal government’s plan to provide affordable and yet beautiful places of relaxation for
residents and visitors.
Lack of port is one of the problems in the province of Binangonan Rizal. Port in Binangonan Rizal
undergoes congestion that’s why people always experience delays going to the Barangay of Talim Island.
The main objective of this project is to design an industrial-strength port terminal at A. Ibañez St., Bgy. San
Vicente, Angono Rizal to avoid people congestion in Binangonan, to provide alternative route and to help
the community and near provinces to have an easy access going to Talim Island.
1
1.2 Project Location
The location of our project will be along A. Ibañez St., Bgy. San Vicente, Angono Rizal having the
coordinates of 14°31'09"N and 121°08'32"E. The total lot area is 11 meters by 45 meter for a total of 495
square meters. The project location was near Laguna de Bay. The photo below shows the exact location of
the project.
2
Side View Front View
Upon the completion of the project, the designers aim to accomplish the following general and
specific objectives:
1.3.1 General Objectives
The main objective of this project is to design an industrial-strength port, affordable but safe access at A.
Ibañez St., Bgy. San Vicente, Angono, Rizal to provide alternative route and to help the community to have
an easy access going to Talim Island by designing a structure based on engineering methods and
application, by analyzing and comparing the options based on the constraints such as accessibility,
3
economy, usability, risk assessment and other demand of the client.
1.3.2 Specific Objectives
The Client of this project is the Local Government represented by Mr. Gerardo V. Calderon, Mayor of
Angono Rizal and headed by Engr. Emilnor B. Passion; Municipal Engineering Office Head wants the
project to be done in more than a year. The lifespan of the project is depended on the designer’s output.
The purpose of this project is to provide transportation services for the residents of Angono Rizal and near
provinces
The following were the scope and limitations of the design project:
1.5.1 Scope
a) Provide architectural plans (floor plan and elevation Plan) using the specification and standards of
the National Building Code of the Philippines.
b) The design project must be in accordance to National Structural Code of the Philippines 2010
(NSCP 2010).
c) Analyze the structure using Staad pro software.
d) Estimate the quantity cost of materials required in the project, and also the duration required that
will finish the project.
1.5.2 Limitation
a) Detailed activities of the construction, estimate of labor cost and types of machinery during
construction of the port are not included.
b) The project is only based on the resources available in some studies or research that has been
done.
c) The project only provide the design of the port terminal and not the port itself.
1.6 Project Development
The following design scheme was used as a guide for the phase development of project to reflect the series
of stages that will take upon the progress of the project completion.
1. Identifying the Problems. Identifying the existing problem that the designers intend to address for
the designers to share pieces of idea and formulate solutions on the existing problem.
4
2. Conceptualization. The phase from the development of the project is conceptualization, in which
the designer is considering the client’s needs and demands.
3. Data Gathering. Related data are gathered after conceptualizing the details of the project through
preliminary interviews and first-hand data. A site investigation will be also conducted to help gather
additional information including the underlying problems and status of soil in the location.
4. Design Constraints and Standards. The designers will identify the different challenges that will limit
the design of the project with the help of the client. This includes the rules and standards set henceforth by
the law in the Philippines.
5. Evaluation of Results. The results from this study will be compared and analyzed using trade-off
analysis to determine the best possible solutions for soft soil improvement design of proposed multi- storey
hotel building.
6. Final Result. The final design will be derived by the designers based on the most effective result
with regards on the significant of constraint in line with the trade-offs.
5
Figure 1- 4. Design Flow Chart
To be able to properly design a port terminal at Angono Rizal, the following data were gathered
to serve as the design basis.
2.1.1 Geotechnical Data
The table is composed of the soil classification, the clay soils are the dominant types found
within Angono Rizal. Most notable are the Antipolo clay, San Luis clay and Baras clay soil types,
which cover the greater portion of the municipality.
Slope Classification
00 – 18 74.36%
18 – 50 24.28%
00 > 50 1.35%
Total: 99.99%
Table 2-3 Slope Classification of Angono
Source: NAMRIA
7
Figure 2-2 Slope Map
Source: Bureau of Soils and Water Management
8
2.1.3 Hydrological Data
The figure shows the average rainfall amount of Angono Rizal. The rainfall regime in the area is dominated
by the monsoon which renders a seasonal variation in precipitation. It receives sufficiently abundant rainfall
annually with total annual levels amounting to 2,406.2 millimeters.
The prevailing wind direction that occurs more frequently is the Northeasterlies, which is mostly because of
the influence of the Northeast Monsoon. On the other hand, the winds are not quite strong. The annual
average wind speed is only 2 meters per second (or approximately 7.2 kph).
Figure 2-5 Angono Average and Maximum Wind Speed and Gust
9
Source: World Weather
2.1.5 Design Loads
The design load stated will be based on Philippine Port Authority - Engineering Standards for Port and
Harbor Structures based on section 15.1 of chapter 15 when designing port and harbor facilities, loads shall
be taken into consideration as necessary. For port and harbor facilities design, loads are divided into
deadweight and surcharge.
Based on Philippine Port Authority - Engineering Standards for Port and Harbor Structures concrete
structures for piers and wharves may be proportioned using the load resistance factor design (ultimate
strength) method.
Vacant 1 2 3 4 5 6 7 8
D 1.4 1.2 1.2 1.2 1.2 1.2 0.9 0.9
L 0 1.6 1 0 1 1
B 1.4 1.2 1.2 1.2 1.2 1.2 0.9 0.9
Be 0 0 0 0 0 0
C 1.4 1.2 1.2 1.2 1.2 1.2 0.9 0.9
Cs 0 0 0 0 0 0
E 0 1.6 0 0 0 0 1.6 1.6
Eq 0 0 0 0 0 1 1
W 0 0 0 0.8 1.6 0 1.6 0
Ws 0 0 0 0 0 0 0 0
E 1.6 0 0 0
Eq 0 0 0 1
10
W 0 0 1.6 0
Ws 0 0 0 0
Mooring 1 2 3 4 5 6 7 8
D 1.4 1.2 1.2 1.2 1.2 1.2 0.9 0.9
L 0 1.6 1 0 1 1 0 0
B 1.4 1.2 1.2 1.2 1.2 1.2 0.9 0.9
Be 0 0 0 0 0 0 0 0
C 1.4 1.2 1.2 1.2 1.2 1.2 0.9 0.9
Cs 0 1.2 1.2 1.2 1.2 1.2 0.9 0.9
E 0 1.6 0 0 0 0 1.6 1.6
Eq 0 0 0 0 0 1 0 1
W 0 0 0 0.8 1.6 0 1.6 0
Ws 0 0 0 0.8 1.6 0 1.6 0
Berthing 1 2 3 4 5 6 7 8
D 1.2 1.2 1.2 1.2
L 1.6 1 1 1
B 1.2 1.2 1.2 1.2
Be 1.6 0 0 0
C 1.2 1.2 1.2 1.2
Cs 0 0 0 0
Table 2-5 Load Combination
Source: Philippine Port Authority - Engineering Standards for Port and Harbor Structure
The friction coefficient for materials used in calculations of the frictional resistance force shall be static
friction coefficient as the standard. The friction coefficient shall be appropriately determined after taking into
consideration the characteristics of the structure and the characteristics of the materials.
11
2.2 Related Literature
2.2.1 Port are points of convergence between land and maritime domains
According to (Dr. Jean Paul Rodrigue and Dr. Theo Notteboom, 2017), Ports are points of convergence
between two geographical domains of freight circulation (sometimes passengers);
the land and maritime domains. While the maritime domain can involve substantial geographical coverage
related to global trade, the land domain is related to the port’s region and locality. The term port comes
from the Latin portus, which means gate or gateway. Historically, ports emerged as safe harbors for fishing
and those with convenient locations became trade hubs, many of which of free access and designed to
protect trade. As such, they became nexus of urbanization with several becoming the first port cities playing
an important role in the economic welfare of their regions. Today, many of the most important cities in the
world owe their origin to their port location. The port is a multidimensional entity at start anchored within
geography, but also dependent on its operations, governance structure and embedded within supply
chains.
As stated by (Martin Minogue and Ledivina Cariño, 2006), The Philippines is an archipelagic country,
consisting of more than 7000 islands. These islands need to be linked together by an efficient and
seamless transport system. Unfortunately, the country’s sea transport and distribution system, mainly the
ports system, is plagued by inefficiency that causes high domestic transport costs.
12
CHAPTER 3: DESIGN CONSTRAINTS, TRADEOFFS AND STANDARDS
In this chapter, design constraints are factors that limit the range of potential design solutions that can
be adopted. In the early stage of a project, only some of these constraints may be known, while others
become apparent as the design progresses. Constraints have to be managed. Practically, the design can
only improve when the constraint is improved.
In order to meet and achieve the requirements of the client must be design in line with the needs and
necessities given by the client and also the judgement of the designer. These factors are the quantitative
constraints; are those constraints that can be measured using engineering methods (estimation). The
following are the constraints faced by the designers in the “Design of a Port Terminal in A.Ibañez St., Brgy.
San Vicente, Angono Rizal”.
Economic constraint has a great effect in designing the structural details of the proposed Port Terminal
because budget is one of the relevant things to be considered in any design process. The cost of the
materials to be used in any design process is an important parameter that must be taken into consideration.
This constraint is an important part of the design because the client wants a low cost structure but efficient
to use. In consideration of economic, the designer takes into consideration of the effectiveness of cost but
does not compromise the quality of the work or project. In this case, construction cost inclusive of material
cost, labor and construction cost that the designer will consider in evaluating As a result, the designer come
up with three possible trade-offs per specialization which are Structural and Geotechnical Engineering. The
six trade-offs will be evaluated by the cost of the materials needed
3.1.1.2 Sustainability (Maintenance Cost)
The sustainability constraint takes into account the problem on how long the design life of a project is with
respect to its design strength. One of the basic ideas in engineering design is that with greater design
strength, there is an equivalent increase in cost due to the need of higher quality material. In line with this
constraint, sustainability of the structure is considered for the reason that the client from the Municipal
Engineering Office are up to design a terminal structure with a higher longevity with minimum cost of
maintenance. The port terminal should be used by the public through its maximum lifespan providing
maintenance. The designers, in consideration with this constraint, will only focus on the maintenance cost
for the structure that will be taken into account and will be used as the value for evaluation.
The designer has considered environment as a constraint on the design of the Port Terminal. Environment
is a great factor in designing the structure, because of the different calamities brought by Mother Nature.
There are natural calamities like floods, earthquakes and even tsunamis considering the location of the port
which is near lakeside area happens unexpectedly that might affect the strength of the ground and its
13
properties as well. That is why the designers think of a way and evaluate which of the six trade-offs is the
most sustainable and at the same time can contribute better or lessen the possible soil settlement and
foundation failure. The three structural designs and three geotechnical designs will be evaluated according
to its capacity to resist the loads.
Main concern of the client is the duration of the work in particular to the possible shortest period of time in
terms of accomplishment of construction. In order to have harmonious work together with the client the
designer should conform to that constraint. The duration of the project will be an issue in designing the port
terminal. The site of the construction, Angono, is lying near the Laguna de Bay and is highly affected by
unpleasant weather systems such as rains, storms and winds that can cause flooding in the area that could
delay the project duration. The designers, in consideration with this constraint, will only focus on the project
duration and on how it affects the total cost of the project. The project should be finished in less than 100
days, as set by the client and in discretion of the designers. For the evaluation, the designers will use the
labor cost as the value for this constraint
The three structural designs and three geotechnical designs will be evaluated according to its safety
requirements. The trade-offs, Reinforced Concrete (Normal Weight), Reinforced Concrete (Lightweight),
and Steel Structure will be investigated naturally through the member’s deflection and stiffness and
evaluate according to the ability to carry the loads. The design which appears to be stiffer than the other will
be considered to be a safe Port design. The designers, in consideration with this constraint, needs to
design the structure with consideration to the environmental loads, which relates to the buckling effect,
considering the slenderness factor of the structure after certain years.. The consideration of environmental
loads shall reduce the risk present in the structure.
3.2 Trade-Offs
To address these multiple constraints, the designers came up with two specialization of trade-offs;
Structural and Geotechnical. There are three alternatives for each specialization that were chosen by the
designer to satisfy the constraints and also, this will help the client to decide for the best option that will be
using for the design. The designer chose this following trade-offs:
This field deals with the design of structures that support or resist loads.
3.2.1.1 Reinforced Concrete (Normal Weight)
Reinforced concrete is a strong durable building material that can be formed into many varied shapes
and sizes ranging from a simple rectangular column, to a slender curved dome or shell. Its utility and
versatility is achieved by combining the best features of concrete and steel.
14
Figure 3-1 Reinforced Concrete Column
Source: https://www.flickr.com/photos/
Advantages Disadvantages
Fire and weather resistance of reinforced The cost of the forms used for casting is
concrete is fair. relatively higher.
The reinforced concrete building system For multi-storied building the RCC
is more durable than any other building column section for is larger than steel
system. section as the compressive strength is
lower in the case of Shrinkage causes
crack development and strength loss.
Reinforced concrete, as a fluid material,
in the beginning, can be economically
molded into a nearly limitless range of
15
shapes.
Concrete is a mixture of sand, gravel, crushed rock, or other aggregates held together in a rocklike mass
with a paste of cement and water. As with most rocklike substances, concrete has a high compressive
strength and a very low tensile strength. Reinforced concrete is a combination of concrete and steel
wherein the steel reinforcement provides the tensile strength lacking in the concrete. Steel reinforcing is
also capable of resisting compression forces and is used in columns as well as in other situations.
Reinforced concrete is not just a material for buildings but also for bridges, dams, retaining walls,
pavements, tanks, and so on.
A Reinforced Concrete Structure is the most commonly used type of structure and it is defined as a
structure with its beams, columns, and other components composed of both concrete and steel working
together to resist forces. Among the trade-offs, it is the cheapest option.
Table 3-1. Advantages and Disadvantages of Reinforced Concrete
Advantages Disadvantages
16
Fire and water resistant. The properties of concrete vary widely
Very rigid. because of variations in its proportioning and
Low-maintenance material. mixing. Furthermore, the placing and curing
Compared with other materials, it has a of concrete is not as carefully controlled as is
very long service life. the production of other materials, such as
Strength of concrete increases with time. structural steel and laminated wood.
Only economical material available for Production of cement is not environment
footing, floor slabs, basement walls, and friendly.
other similar applications. More dead weight.
Has an ability to be cast into an Consumes more concrete and
extraordinary variety of shapes from simple reinforcements.
slabs, beams, and columns to great arches Has long construction duration.
and shells.
Lower grade of skilled labor is required for erection.
Lightweight concrete is defined as a type of concrete which includes an expanding agent which increases
the volume of the mixture while giving additional qualities such as lessened dead weight. The density of this
type of concrete ranges from 1440 to 1840 kg/m3. Lightweight aggregate concretes can be used for
structural applications, with strengths equivalent to normal weight concrete. The elastic modulus of
lightweight concretes is lower than the equivalent strength normal weight concrete, but when considering
the deflection of a slab or beam, this is counteracted by the reduced self-weight.
Table 3-2. Advantages and Disadvantages of Lightweight Concrete
Advantages Disadvantages
Structural steel is a category of steel construction material that is produced with a particular cross section
or shape, and some specified values of strength and chemical composition. Structural steel composition,
strength, size, shape, strength, and storage are controlled in most advanced countries.
17
Figure 3-3 Steel Curved Truss
Source: https://www.123rf.com/
Advantages Disadvantages
The market price of steel is way lower Structures and machines made of structural
compared to other metals. It has steel require timely maintenance. Repairs
achieved huge productivity advances and small fixtures can incur high costs.
throughout the steel supply chain thereby It is a scientific fact that steel tends to lose its
reducing cost. strength at high temperatures. It is for this
Structural steel has a high strength to reason that fabricators engage in fireproof
weight ratio which makes it suitable for treatment for structural steel. In addition to
constructing huge structures. It is tensile, that buildings have to be installed with
ductile and malleable. Buildings made of sprinkler systems. These measures are
structural steel have high endurance; they expensive and add to the overall cost of the
can withstand strong winds, earthquakes, construction project.
and storms. Steel is susceptible to corrosion as it reacts
Structural steel buildings can be constructed with atmospheric oxygen to form rust. This
easily and at a rapid pace. Steel frames for deteriorates the quality of the structure.
buildings can be erected in no time. Various expensive treatments are done
Construction projects usually cause over structural steel to prevent it from
disruption to nearby buildings and roads. corrosion; some of them are dry abrasive
Speedy construction reduces this and also blasting, water blasting, and coal tar
leads to savings in site preliminaries. paintings.
Structural steel can be easily modified to Steel structures tend to get fatigued over a
suit any design. They are more adaptable period of time. After being exposed to
than other framing systems. It is easy to different kinds of pressures, there are
incorporate last minute additions and variations in the tensile strength of the
changes in a steel frame structure. frames. This can lead to buckling of the steel
structure.
Source: http://northern-weldarc.com/
18
3.2.2 Geotechnical Engineering
Geotechnical engineering largely involves defining the soil's strength and deformation properties.
Consolidation of soft ground using vertical drains and preloading is a technique used since the 1920s. The
vertical drains provide a shortened pathway for water to exit the soils while fill preloading surcharges the
foundation soils. Initially sand drains were used, and then cardboard drains followed by geotextile-encased
drains (prefabricated vertical drains). The most common vertical drain at present is the use of prefabricated
vertical drains (PVDs).
PVDs are band shaped (rectangular cross-section) products consisting of a geotextile jacket surrounding a
plastic core with drainage channels. The configuration permits pore water in the soil to seep into the drain
for collection and transmittal up and down the length of the core. While there are some variations, the size
of a PVD is typically 4 inches wide by 1/8 to 3/8 inches thick.
The most common transportation use of PVDs is to accelerate consolidation for approach embankments at
bridges or other embankment construction over soft soils, where the total post construction settlement
would otherwise be unacceptable.
Advantages Disadvantages
Economy - For typical projects, the cost for Headroom Limitations - PVD installation
PVDs is much less than available alternatives equipment must be 5 to10 feet taller than the
such as aggregate drains. depth of installation which can limit their use
Improved Quality Control - The quality control for some sites.
and assurance for PVD construction is quite Materials must be Stored Properly - PVD
simple. Because continuity of the drain is material can degrade in sunlight and,
assured during installation, the major duties therefore, must be stored properly. While
of inspection are to ensure proper drain most specifications require the material to be
anchorage and proper depth attainment. covered during storage, the effect of sunlight
Continuity of Drain - PVDs provide an on the geotextile will not be significant unless
assurance of a permanent drainage path, the material is on site for more than a month.
even with considerable lateral displacement
or buckling under vertical or horizontal soil
movements.
Installation - Generally, the production rate for
PVDs will average between 15,000 to 20,000
lineal feet per day per rig.
Equipment Flexibility - PVDs are generally
installed with a static or vibratory installation
force, and normal equipment can be adapted
for a minimal amount of jetting, where
necessary.
19
Low Material Storage - PVDs come in reels
usually containing 450 to 1,000 feet of
material. Each roll is approximately 3.3 feet in
diameter, 4 inches thick, and can be easily
stored.
No Water Required- Except in unusual
cases, PVDs are installed without jetting.
Even if a minimum amount of jetting is
required, the resulting surface runoff is
minimal
Advantages Disadvantages
Compacts large areas of loose granular fills Vibro Compaction cannot compact soils with.
Reduces the volume of landfill waste more than 12 % to 15 % fines content.
20
Increases in situ density and the voids are Vibro Compaction requires a minimum
collapsed vertical stress in the soil in order to be
Increased bearing capacity effective, which means that in the upper 90
Reduces post-construction settlements cm from the surface there is no improvement
so this surface layer
has to be roller compacted.
Compaction grouting was pioneered on the West Coast in the 1950s, and is the only grouting technique
to have its origins in the United States. It was first used to rectify structural settlements through the
controlled injection of a very stiff, low mobility mix (Warner 1982). In the late 1970s, compaction grouting
was introduced as a preventative, rather than a remediate, measure when the technique was used in
lieu of conventional underpinning to protect surface structures from settlement during the installation of
Bolton Hill Tunnel, part of the Northwest Line of the Baltimore Region Rapid Transit System (Baker et
al. 1983.
Advantages Disadvantages
Compaction grouting causes minimal disruption The one main disadvantage of this technique
to the landscape, surrounding soils, and nearby is that it is a bit messy and may require
structures. cleanup.
This technique can be utilized for projects that
have limited access and require more delicate
installations.
It is cost-effective and easy to install compared
to some other soil stabilization and ground-
shoring methods.
Engineered Solutions has used this versatile
technique on a variety of projects, and it has
successfully strengthened ground soils in each
instance.
Ranking scale was formulated by Kevin N. Otto and Erik K. Antonsson, it is a Trade-off
strategies in engineering design that allows the designer team to formally and explicitly
make a decisions in choosing which of the trade-offs presented has strongest overall
21
performance considering each weaknesses. The importance factor and the satisfactory
scale for each constraint are from 0 to 10, where 10 are the highest. The tradeoff will be
determined based on the computation results of criteria set by the client and the
designers.
Figure 3-7 Ranking Scale for Importance and Satisfactory FactorFor computing the ranking in
satisfying the criterion, the equations to be used are the following:
Therefore, to satisfy the criterion, the governing trade-off that satisfies different constraints was subjectively
ranked higher. And then the sub trade-off which accounted higher cost was computed its rank in
accordance with Equation 3-1 and Equation 3-2.
The designer provided initial estimates for the (6) six trade-offs. Through this estimates, the designer can
be able to come up which of the following trade-offs will be the best for economic, sustainability,
environmental and constructability constraint.
22
The data stated in the table shows the initial estimate for the structure. The initial estimates were based on
the cost data gathered from the websites cited on the references for each constraint. The researchers had
Design of Constraints
Economic Environmental Constructability Sustainability Risk
Tradeoffs
Cost (30% of
Structural Maintenace Risk Cost
Cost (Php) the economic Duration (Days)
Cost (Php) (Php)
cost) (Php)
Reinforced
Concrete 3,901.54
1,170.462 94 days 1,503,897.98 25,278.75
(Normal (per sq.meter)
Weight)
Reinforced 4,250.00
Concrete (per sq. 1,275.00 94 days 1,998,761.12 28,009.21
(LightWeight) meter)
Steel 4,057.57 1,217.271 80 days 3,755,332.76 31,981.34
Structure (per pieces.)
considered construction statistics from approved building permits related to administrative-based data on
new constructions and additions, alterations and repairs of existing residential and non-residential buildings
and other structures proposed to be constructed in all cities and municipalities of the country in a specific
period. The designers researched the prices for the economic cost and it was converted from natural
Design of Constraints
Economic Environmental Constructability Sustainability Risk
Tradeoffs
Cost (30% of
Geotechnical Maintenace Risk Cost
Cost (Php) the economic Duration (Days)
Cost (Php) (Php)
cost) (Php)
Ground
consolidation
using 200,000.00 60,000.00 20 days 354,044.47 402,445.29
Prefabricated
Drains
Dynamic
310,000.00 93,000.00 30 days 512,098.08 405,554.22
Compaction
Grout
257,500.00 77,250.00 20 days 203,099.93 385,076.43
Compaction
currency to Philippine Peso.
23
Reinforced Reinforced
Importance(on
Concrete (Normal Concrete Steel
scale of 0 to 10)
Weight) (LightWeight)
Economic
(Php) 10 10 9.18 9.18
Environmental 7 10 9.18 9.18
Constructability
(Duration - Months) 8 7.98 9.38 9.38
Risk
Risk Cost (Php) 9 10 8.57 7.14
Sustainability
Maintenace Cost 9 10 8 6
(Php)
Over-all Rank 413.84 380.23 361.8
Criterion's Ground
Design Criteria
Importance(on consolidation
scale of 0 to 10) Dynamic Grout
using
Compaction Compaction
Prefabricated
Drains
Economic
(Php) 10 0.28 10 6.36
Environmental 7 0.28 10 6.36
Constructability
(Duration - Months) 8 5.56 8.33 10
Risk
Risk Cost (Php) 9 9 8.5 10
Sustainability
Maintenace Cost 9 7.14 5.57 10
(Php)
Over-all Rank 229.24 364.53 333.38
The table below shows the initial cost estimate of the given tradeoffs. Through this initial result, the
designers may find out which tradeoff has the lower price of materials and which is the most economical
among the three.
24
3.4.1.1 Structural Economic Cost Ranking
25
3.4.1.2 Geotechnical Economic Cost Ranking
26
Grout Compaction vs. Dynamic Compaction
27
3.4.2 Environmental Constraint (Environmental Cost)
The designers made an initial estimate of the equipment and labor cost of the project. The designers
considered the number of man-hour and time rent to discern which tradeoff governs in terms of labor and
equipment cost. According to the book of Elbelatgi, the labor costs and equipment costs is approximately
30% of the estimated value for material cost. The book discussed the basic principle for estimating labor
costs, equipment costs, operating costs, and preparing detailed cost estimate.
1,275.00 − 1,170.462
% 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
1,275.00
%𝑫𝒊𝒇𝒇𝒆𝒓𝒆𝒏𝒄𝒆 = 𝟎. 𝟖𝟐
28
Reinforced Concrete (Light weight) vs. Reinforced Concrete
(Normal Weight)
1,217.271 − 1,170.462
% 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
1,217.271
%𝑫𝒊𝒇𝒇𝒆𝒓𝒆𝒏𝒄𝒆 = 𝟎. 𝟑𝟖
% 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =
29
93,000 – 60,000 93,000
× 10
%𝑫𝒊𝒇𝒇𝒆𝒓𝒆𝒏𝒄𝒆 = 𝟑. 55
Based on existing project schedules as per provided on the reference located in the appendix. Each
duration of each type of was considered. It was based on existing or finished projects with detailed project
schedule as per provided on the reference
30
3.4.3.1 Structural Constructability Ranking
31
Reinforced Concrete (Light weight) vs. Reinforced Concrete (Normal Weight)
32
3.4.3.2Geotechnical Constructability Ranking
33
Dynamic Compaction vs. Grout Compaction
Subordinate Rank 10 6 8
34
Since the long term deflection of each tradeoff can only be computed if the structural components are
designed and if the dimensions are already finalized. The ranking of each tradeoff for the initial estimate is
based on the maximum allowable deflection for concrete (L/360) and (L/350) for steel according to the data
gathered in the reference. Each tradeoff was analysed and determined with the advantages and
disadvantages of each. The designers weighed in each advantage and chose the reinforced concrete as
the highest rank.
1,100 − 956
% 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 = × 10
1,100
%𝑫𝒊𝒇𝒇𝒆𝒓𝒆𝒏𝒄𝒆 = 1.30
35
𝑯𝒊𝒈𝒉𝒆𝒓 𝑽𝒂𝒍𝒖𝒆 −
𝑳𝒐𝒘𝒆𝒓 𝑽𝒂𝒍𝒖𝒆
%
𝑫𝒊𝒇𝒇𝒆𝒓𝒆𝒏𝒄𝒆
=
𝑯𝒊𝒈𝒉𝒆𝒓 𝑽𝒂𝒍𝒖𝒆
× 𝟏𝟎
956 − 900
% 𝐷𝑖𝑓𝑓𝑒𝑟𝑒𝑛𝑐𝑒 =
956
× 10
36
3.4.5 Risk (Risk Cost)
The designers made an initial estimate of the initial maximum displacements of each trade-off to determine
which framing system will govern in terms of safety.
37
Reinforced Concrete (Light weight) VS. Reinforced Concrete (Normal Weight)
38
39
Dynamic Compaction vs. Grout Compaction
40
TRADE-OFF ASSESMENT
Structural:
Economic 10
.23 10 9.18
Constraints (Cost) 9.18
Sustainability 7
(Maintenance .18 10 9.18
9.18
Cost)
Environmental 8
.18 7.98 9.38
Constraints (Cost) 9.38
Constructability
Constraints 9 .21 10 8.57
7.14
(Duration)
Risk Assessment
9 .20 10 8
(Cost of Risk) 6
Geotechnical:
41
Ability to satisfy the criterion (on a scale 0 to 10)
Criterion's
% Ground
Design Criteria Importance(on
WEIGHT consolidation
scale of 0 to Dynamic Grout
10) using
Compaction Compaction
Prefabricated
Drains
Economic
(Php) 10 .23 6.36 10 0.28
Environmental 7 .18 10 6.36 0.28
Constructability
(Duration - 8 .18 10 8.37 5.56
Months)
Risk
Risk Cost (Php) 9 .21 9 8.5 10
Sustainability
Maintenace Cost 9 .20 7.4 5.57 10
(Php)
Over-all Rank 1 42.76 38.8 26.12
The designers will be designing the project with accordance to the following codes and standards:
42
• NSCP – National Structural Code of the Philippines 2015
The purpose of this code is to provide minimum load requirements for the design of the buildings, towers
and other vertical structures and minimum standards and guidelines to safeguard life or limb, property and
public welfare by regulating and controlling the design, construction, quality of materials pertaining to the
structural aspects of all buildings and structures within its jurisdiction.
• Philippine Port Authority - Engineering Standards for Port and Harbor Structures
In designing port and harbor facilities, the design condition shall be based on the environmental
considering, characteristics of materials, construction condition, and social requirements for the facilities.
43
CHAPTER 4: DESIGN OF STRUCTURE
The Design of a Port Terminal in A. Ibanez St., Brgy San Vicente, Angono Rizal City was done according
with the aforementioned design standards in chapter 3. In this project, the designers proceeded with the
design of Port Terminal based on the governing system, thus considering six (6) trade-offs, in which the
designers shall be using different materials as trade-offs.
The material to be used will be chosen among the material trade-offs for the design of storm water drainage
system which Reinforce Concrete, Precast Concrete, and Steel, Jet Grouting, Prefabricated Vertical Drains,
and Vibro Compactions. The design was done in accordance with the codes and standards appropriate for
this structure. The figure below shows the step by step process of the design of the building.
The designers will follow the flow chart for the process of designing the structure given the trade-offs.
The design starts with the conceptualization of the structure plan that will also consider the multiple
constraints, trade-offs and design standards for the final design.
Port Layout
Design
Determination of
Material Property
Computation
of Loads
Cost Estimates
Considering the
Design Constraints
Final
Ranking
Selection of Final
Design Trade-off
44
4.2.1 Design Flow Chart for Reinforced Concrete Port (Normal Weight)
START
INPUT:
Material Specification (Philippine Ports Authority – Engineering
Standards for Ports and Harbor Structures)
Concrete Properties
INPUT:
Geometric Data of Column
INPUT:
Beam dimension
Flexural reinforcement
Shear reinforcement
END
45
4.2.2 Design Flow Chart for Structural Steel Port
START
INPUT:
Steel Properties (NSCP Vol. II Section 10.2.2)
Section Properties (ASEP Steel Hand Book 2004, Vol. I)
Bolts Properties (Specifications of Highway Bridges –
AASHTO, Section 1.7.5)
Compute for the reinforcement and other design details (NSCP Vol. II,
Section 10)
Angles
Fasteners and Bolts
Diaphragm
Shear Connectors
END
46
4.2.3 Design Flow Chart for Reinforced Concrete Port (Lightweight)
START
INPUT:
Material Specification (Philippine Ports Authority – Engineering
Standards for Ports and Harbor Structures)
Concrete Properties
INPUT:
Geometric Data of Column
INPUT:
Beam dimension
Flexural reinforcement
Shear reinforcement
END
47
4.2.4 Design Flowchart for Ground Consolidation
START
INPUT:
Soil Properties
Borehole detail
Time of consolidation
Amount of settlement
END
48
4.2.5 Design Flowchart for Dynamic Compaction
START
INPUT:
Borehole details
Type of fill
END
49
4.2.6 Design Flowchart for Grout Compaction
START
Void ratio
Unit weight
Moisture
Diameter of grout
Grout hole spacing
Grout quantities
END
50
4.3 Structural and Architectural Plans
The following figures show the structural plans prepared by the designers. These plans were used
by the designers to be able to model and design the building structure using the STAAD Vi8 Pro software
51
52
53
54
4.4. Design Loadings
The following are the different types of design loadings used in the structural analysis of the port.
All these loadings are in accordance to the NSCP Vol. 2 of 2010 and are used to determine the
load combinations. This governing load combination will then be used to calculate the member
forces of the port.
4.4.1. Load Models
The loads considered in this project are the dead load, live load, wind load and seismic loads. Load
combinations were also applied to these loads. The load combinations that were utilized were those that
are written in Section 203 of NSCP 2010.
ROOF
INSULATION, ROOF BOARDS (per mm thickness) 0.004 KPA
POLYSTYRENE FOAM
FRAME PARTITIONS
MOVABLE PARTIONS (STEEL) 0.19 KPA
WOOD OR STEEL STUDS, 13mm GYPSUM BOARD EACH 0.38 KPA
SIDE
Total 4.48 KPA
Table 4.1. Chapter 2 Section 207
56
4.5. Design Models
The following figures show the design models of the port which are designed in accordance
to the standards and retrieved from Staad Pro V8i.
Wind Intensity
Wind Intensity
57
Figure 4.7. Earthquake Load (+X)
The following Trade-offs for this project were modeled using a computer software called STAAD.ProV8i
where in the computation for the acting forces of the structure are identified due to the iterations of methods
of the program. Upon specifying the design parameters for each design, the software will perform analysis
and provide valuable data that may contribute in manual computation of the design
58
4.5.1.2 Structural Steel Port Structural Analysis
4.5.2.1.1 Design Details for Reinforced Concrete (Normal Weight) Port Column
a. Steel Reinforcement
Tension Reinforcement: 6 – 32 mm dia. bar
Shear Reinforcement: 10 mm dia. stirrup @ 450 mm spacing on center
Transverse Reinforcement:
a. bottom = 6 -16 mm diameter bar @ 170 mm spacing per meter width of slab
b. top = 10 -16 mm diameter bar @ 100 mm spacing per meter
Shrinkage and Temperature Reinforcement:
c. 3 – 10 mm diameter bar @ 350 mm spacing per meter
a. Lateral bracing are not needed according to NSCP Vol. II – Section 10.21.1.
b. Transverse stiffeners are not needed according to NSCP Vol. I – Section 506.6.1
c. Cover plates:
60
Thickness of 25 millimeters d Diaphragm
- Spacing of 2 meters
.d. Fasteners
Spacing of 90 millimeter
Inside Diameter:27 mm
Thickness: 7.92 mm
e. Shear Connectors
- Transverse spacing of 150 mm center to center and 39.3 mm on edge in each side.
- Longitudinal spacing 300 mm center to center and 200 mm on edge in each side.
1. Transverse Reinforcement:
bottom = 6 -16 mm diameter bar @ 170 mm spacing per meter width of slab
L = 20,300 = 21 M
61
2. Longitudinal Reinforcement:
L = 22M
L = 23 M
4.5.2.1.3 Design Details for Reinforced Concrete (Light Weight) Port Column
f. Steel Reinforcement
Tension Reinforcement: 8 – 32 mm dia. bar
Shear Reinforcement: 10 mm dia. stirrup @ 450 mm spacing on center
Transverse Reinforcement:
a. bottom = 6 -16 mm diameter bar @ 170 mm spacing per meter width of slab
b. top = 10 -16 mm diameter bar @ 100 mm spacing per meter
Shrinkage and Temperature Reinforcement:
c. 3 – 10 mm diameter bar @ 350 mm spacing per meter
BOREHOLE PROPERTIES:
DESIGN DETAILS:
BOREHOLE 1:
64
Spacing between impacts of 4.5 meter for depth of 30 meter.
Depth of Treatment
D = 14.14 meters
After the design process, the design results on a specific constraint during the conceptualization
phase has been assessed and evaluated. These constraints greatly affect the output of the design
and small variations in these constraints can lead to a significant change in the final output.
To validate the initial designer‟s raw ranking in Chapter 3, a final cost estimate is presented to
measure the overall ranking of the design trade-offs compared to the initial estimate. These
comparisons show the difference in terms of multiple constraints.
Environmental Cost
(30% of the economic Php 182,635.5 Php 818,051.4 Php 141,959.69
cost) (Php)
Constructability
(Duration - Days) 67 Days 64 Days 67 Days
Risk (Risk Cost) Php 22,800.00 Php 22,800.00 Php 22,800.00
Sustainability
(Maintenace Cost) Php 153,557.68 Php 818,051.4 Php 161,317.75
65
Finals Estimates for the Trade-
offs
Constraint Deep
Ground
Dynamic Grouting Compaction
Consolidation
Compaction
Economic (Cost) PHP 198,259.06 PHP 263,557.37 PHP 203,084.61
Environmental Cost
(30% of the economic PHP 59,477. 718 PHP 19,067.211 PHP 60,925.383
cost) (Php)
Constructability PHP 208,910.00 PHP 106,210.00 PHP 83,460.00
(Duration) (26 Days) (26 Days) (21 Days)
Risk (Risk Cost) Php 12, 000. 00 Php 12, 000. 00 Php 12, 000. 00
% Difference = 7.75
%Difference = 0.48
Subordinate Rank = Governing Rank − %Difference
66
Subordinate Rank = 10 – 0.48 = 9.52
Php 818,051.4−Php153,557.68
%Difference= x 10
Php 818,051.4
%Difference = 8.12
Subordinate Rank = Governing Rank − %Difference
Subordinate Rank = 10 – 8.12 = 1.88
%Difference = 0.48
Subordinate Rank = Governing Rank − %Difference
Subordinate Rank = 10 – 0.48 = 9.52
67−64
%Difference= x 10
68
%Difference = 0.45
67
Subordinate Rank = Governing Rank − %Difference
Subordinate Rank = 10 – 0.45 = 9.55
67−64
%Difference= x 10
67
%Difference = 0.45
Subordinate Rank = Governing Rank − %Difference
Subordinate Rank = 10 – 0.45 = 9.55
%Difference = 0.24
0 1 2 3 4 5 6 7 8 9 10
68
Ground Consolidation vs Deep Dynamic Compaction
%Difference = 2.71
69
PHP 62,673.00−PHP 25,038.00
%Difference= x 10
PHP 62,673.00
%Difference = 6.01
%Difference = 2.14
%Difference = 3.46
70
Subordinate Rank = Governing Rank − % Difference
Subordinate Rank = 10 − 3.46 = 𝟔. 𝟓𝟒
0 1 2 3 4 5 6 7 8 9 10
%Difference = 1.24
0 1 2 3 4 5 6 7 8 9 10
Structural:
Decision C riteria Criterion’s Ability to Satisfy the Criterion
Importance
(Scale of 0 to Reinforced Reinforced Structural Steel
10) Concrete (Normal Concrete
Weight) (Lightweight)
Economic 10 10 100 9.52 95.6 2.25 22.5
Constructability 8 9.55 76.4 9.55 76.4 10 80
Sustainability 9 10 90 9.52 85.68 1.88 16.92
Risk Assessment 9 9.52 85.68 10 90 6.54 58.86
Over-all Rank 352.08 347.68 178.28
71
Geotechnical:
Sensitivity analysis is a method to prove that the final design choice is indeed the best choice regardless of
the distribution of importance criterion. In this section, designers will manipulate the values wherein the
given importance criterion for the constraints will be redistributed and the designers will assess whether this
affects the governing tradeoff.
Sensitivity Analysis
Trial 1
Constraint Importance Criterion
Economic 10
Constructability 9
Sustainability 10
Risk Assessment 10
72
Final Ranking for Trial 1 (Structural)
Decision Criteria Criterion's Ability to Satisfy the Criterion
Importance
(Scale of 0 Reinforced Reinforced Structural Steel
to 10) Concrete (Normal Concrete
Weight) (Lightweight)
Economic 10 10 100 9.52 95.2 2.25 22.5
Constructability 9 9.55 85.95 9.55 85.95 10.00 90
Sustainability 10 10 100 9.52 95.2 1.88 18.8
Risk Assessment 8 9.52 76.16 10 80 6.54 52.32
Over-all Rank 362.11 356.35 183.62
The table above shows that despite redistributing value of the importance factors among the constraints,
Normal Weight Reinforced Concrete Design and Grout Compaction still govern as the best choice.
Trial 2
Constraint Importance Criterion
Economic 8
Constructability 10
Sustainability 10
Risk Assessment 9
The table above shows that despite redistributing value of the importance factors among the constraints,
Normal Weight Reinforced Concrete Design and Grout Compaction still govern as the best choice.
Based on the trade-off analysis done in the previous chapter, the designers have come up with the result
for what design to use. For addressing the economic, sustainability, safety, environmental and
constructability constraints the design that will be used is Reinforced Concrete
With the aid of manual computation using Microsoft excel and staad, the designers were able to design a
Port Terminal to control and prevent the congestion that causing delays to passengers going to the
Barangays of Talim Island.
The design analysis for each trade-off is adequate and the final raw ranking and sensitivity analysis were
validated to choose which trade-off fits in the project in Angono Rizal.
74
P 5532 kN
My 17.318 kN-m
B 650 mm
T 650 mm
cc 50
D 574
f'c 28 MPa
fy 254 MPa
Φbar 32 mm
Φtie 10 mm
Part 2. Designing the Vertical Stirrup
Step 1. Calculate the Shear Strength by Concrete
(Vc) RESULTS
Vc = sqrt(f'c)*b*d/6
* If Vu > ΦVc, stirrups needed, go to Step II Vc 106.712 kN
* If Vu < ΦVc, but Vu > .5*ΦVc Stirrups needed ΦVc 96.04077 kN
* If Vu < .5*Φ*Vc, stirrups are not needed .5ΦVc 48.02039 kN
Stirrups Needed
Step 2. Calculate the Shear Strength by Stirrup (Vs)
Vn = Vu/Φ Vn 61.69067 kN
Vs = Vn - Vc Vs -45.0213 kN
paramete
* If Vs < 0.67*sqrt(f'c)*b*d, go to Step 3. r 428.9821
* If Vs > 0.67*sqrt(f'c)*b*d, redesign.
Step 3. Spacing of Stirrups
77
Si = Av*fy*d/Vs, Av = pi*(Φtie^2)/4 160 Av 78.53982 mm2
For Smax, 80 Si -130 mm
If Vs < 0.33*sqrt(f'c)*b*d, Smax = d/2 or 600mm (get paramete
* smaller) r 211.2897 mm
If Vs > 0.33*sqrt(f'c)*b*d, Smax = d/4 or 400mm (get
* smaller) Smax1 160 mm
Smax2 mm
Epoxy Light Sf 220 mm
Zinc Normal
Uncoated
Part 3. Development Length
The following are the supplementary
data.
cc 75 mm
Bar Coat Epoxy
Step 1. Determine the Value of the Coefficients (ψt,ψe,ψs,λ) RESULTS
ψt = 1.0 for all other situations
ψe = 1.5 for epoxy-coated bars with cover less than 3d or
6d ψt 1
= 1.2 for all other epoxy-coated bars ψe 1.2
= 1 for uncoated or zinc coated bars ψs 1
ψt = .8 for 20 mm bars and smaller λ 1
= 1 for 25 mm bars and larger
λ = 1 for normal weight concrete
Atr 157.0796 mm2
Step 2. Compute for the development
length Ktr 7.139983
ld = (fy*ψt*ψe*ψs*d)/(1.1*λ*sqrt(f'c)*((cc+Ktr)/d)) ld 398.4453 mm
Ktr = 40*Atr/(S*N), Atr = 2*pi*(Φtie^2)/4
Part 4. Checking the Beam in Deflection
Step 1. Calculate the Gross Moment of Inertia and the Cracking Moment of the Beam
RESULTS
Ig = b(t^3)/12
Mcr = Ig*fr/ϒt, fr = 0.62*λ*sqrt(f'c), yt =
t/2 Ig 2133333333 mm4
78
3.28073162
fr 6 MPa
yt 250 mm
27.9955765
Mcr 4 kN-m
Step 2. Calcualte the Moment of Inertia of the
Cracked Section
63417231.0
Icr = b*(d^3)/12 + nAs(d-c)+nAs'(c-d') Icr 1 mm4
Step 3. Calculate the Effective Moment of Inertia
Ie = ((Mcr/Mu)^3)*Ig + ((1- 521958902.
(Mcr/Mu)^3)*Icr) Ie 3 mm4
Step 4. Determine and Check the
Deflection
Mu = W(L^2)/8, W=____ W 14.80576 kN/m
0.00356424
δ = 5*W*(L^4)/(384*Ec*Ie) δ 5 mm
13.8888888
δmax = L/360 δmax 9 mm
OK
79
Compression Φ tie
spacing
GF to Roof
Truss
C1 650mm X650mm 10 pcs - 32mm bars 10mm 480 mm
80
Figure5.2. Column Details
APPENDICES
1. Rooms for Human Habitations. 6.00 square meters with at least dimensions of 2.00
2. Kitchens. 3.00 square meters with at least dimension of 1.50 meters;
3. Bath and toilet. 1.20 square meters with at least dimension of 0.90 meters.
General. The construction of stairs and exits shall conform to the occupant load requirements of
buildings, reviewing stands, bleachers and grandstands:
7 Determinations of Occupant Loads. The Occupant load permitted in any building or portion
thereof shall be determined by dividing the floor area assigned to that use by the unit area allowed
per occupant as determined by the Secretary.
8 Exit Requirements. Exit requirements of a building or portion thereof used for different purposes
shall be determined by the occupant load which gives the largest number of persons. No
obstruction shall be placed in the required width of an exit except projections permitted by this
Code.
H = loads due to weight and pressure of soil, water in soil, or other materials, or related internal moments
and forces.
h = overall thickness of member, mm.
I = moment of inertia of section beam about the centroidal axis, mm 4.
83
I cr = moment of inertia of cracked section transformed to concrete, mm 4.
I e = effective moment of inertia for computation of deflection, mm 4.
I g = moment of inertia of gross concrete section about centroidal axis, neglecting reinforcement, mm 4.
β 1 = factor
ε t = net tensile strain in extreme tension steel at nominal strength.
Φ = strength-reduction factor.
The following are the sections and codes that are followed in conceptualizing and designing the structural
plan of the apartment building:
Section 203 - Combination of Load
84
a.Minimum densities for design loads from materials
b.Minimum design loads
c. Minimum uniform and concentrated live loads
Wind Load
Section 207.5.4 Wind Directionality Factor
The wind directionality factor, K d, shall be determined form Table 207-2. This factor Shall only be applied
when used in conjunction with load combinations specified in Section 203.3 and 203.4.
Section 207.5.5 Importance factor
An importance factor Iw, for the building or other structure shall be determined from Table 207-3
based on building and structure categories listed in Table 103-1.
Section 207.5.6 Exposure
For each wind direction considered, the upwind exposure category shall be based on ground
surface roughness that is determined from natural topography, vegetation, and constructed
facilities.
Section 207.5.7 Topographic factor
The wind speed up effect shall be included in the calculation of design wind loads by using the
factor kzt. If site conditions and locations of structures do not meet all the conditions specified in
Section 207.5.7.1 the kzt= 1.0
85
Section 207.5.8 Gust Effect factor
The gust effect factor shall be calculated as permitted in Sections 207.5.8.1 to 207.5.8.5, using
appropriate values for natural frequency and damping ratio as permitted in Section 207.5.8.6.
Section 207.5.9 Enclosure Classifications
For the purpose of determining internal pressure coefficients, all buildings shall be classified as
enclosed, partially enclosed, or open as defined in Section 207.2.
Section 207.5.10 Velocity Pressure
Velocity pressure, qz, evaluated at height z shall be calculated by the following equation qz=
47.3x10-6 kz kzt kd V2 Iw.
Section 207.5.13 Design Wind Loads on Open Buildings with Monoslope, Pitched, or Troughed
Roofs
Plus and minus signs signify pressure acting toward and away from the top surface of the roof,
respectively.
Section 207.5.14 Design Wind Loads on Solid Freestanding Walls and Solid Signs
The design wind force for solid freestanding walls and solid signs shall be determined by the
following formula:
F= qhGCfAs
Section 207.5.15 Design Wind Loads on other Structures
The design wind force for other structures shall be determined by the following equation:
F=qzGfCfAf
Earthquake Load
87
Material Density (KN/m3)
Masonry, Concrete 16.5
Table 204-2 Minimum Design Dead Loads
Soil Profile Soil Profile Name Ave. Properties for Top 30 m Soil Profile
Shear Wave Velocity SPT Undrained Shear Strenght
Zone 2 4
Z 0.2 0.4
88
Table 208-3 Seismic Zone Factor Z
Seismic Zone
Soil Profile Type 2 4
Z=0.2 Z=0.4
SA 0.16 .32Na
SB 0.2 .40Na
Sc 0.24 .40Na
SD 0.28 .44Na
SE 0.34 .44Na
SF See Footnote 1 of Table 208-8
Table 208-7 Seismic Coefficient, Ca
Seismic Zone
Soil Profile Type 2 4
89
Z=0.2 Z=0.4
SA 0.16 .32Na
SB 0.20 .40Na
Sc 0.32 .56Na
SD 0.40 .64Na
SE 0.64 .96Na
SF See Footnote 1 of Table 208-8
Table 208-8 Seismic Coefficient, Cv
91
APPENDIX B: INITIAL ESTIMATES
Initial Estimates
Structural Trade-offs
Economic Constraint (Material Cost)
Inputs:
Average cost per square meter of non-residential constructions is Php 9,210.00
Plan Area = 40 x 10 sq. m
Reinforced Concrete Design (Pure Lightweight Concrete) is 13.9% cheaper than Normal Concrete
Structural Steel Design is= 38.19% higher than Normal Weight Concrete
92
Cost =Php1 , 330,000.00
b t L Quantity Volume
B-1 FINAL
400 ESTIMATE 400 COST ESTIMATE
5 – REINFORCED
16 12.8 CONCRETE NORMAL WEIGHT
C-1 650 650 4 CONCRETE
18 WORKS
30.42
TOTAL VOLUME 43.22 SAN GRAVE
Member L b t pcs V CEMENT D L
3
Assuming that 500% (m) of Total (m)
Volume of (m)
Concrete Works is equal(mto)Total Man(bags)
Days, (m) (m)
AddingB-1200% For Rebar
5 Works0.4and 350%0.4For 16 12.8 115.2 6.4 12.8
C-1
Finishing 4 0.65 0.65 18 30.42 273.78 15.21 30.42
TOTAL 388.98 21.61 43.22
TOTAL MAN DAYS = 5(43.22) + 2(43.22) +
3.5(43.22) PRICES
ITEM TOTAL
TOTAL MAN DAYS = 541 per pc ITEM LABOR
days
CEMEN 101134.
T 388.98 bags 260 8 40453.92 GRAND
Given that
SAND there will
21.61 be 8 workers
m 3
50 1080.5 432.2 TOTAL
TOTAL
GRAVEL MAN DAYS
43.22 = 68 Days m 3
800 34576 13830.4
136791.
TOTAL PRICE 3 54716.52 191507.8
REBAR WORKS
BAR Ø As L N- Total W
Member N bars
(mm) (mm )2
(m) members (kg)
490.873
B-1 25 9 7 8 16 3408.628
804.247
10
C-1 32 7 3 18 3365.777
PRICE
ITEM TOTAL
per kg ITEM LABOR TOTAL
6774.40 35226 70453.8
Steel 5 52 9 1 422722.9
PRICES
ITEM TOTAL
per pc ITEM LABOR
CEMEN 123306.
T 388.98 bags 317 7 49322.66 GRAND
SAND 21.61 m3 50 1080.5 432.2 TOTAL
GRAVEL 43.22 m3 800 34576 13830.4
158963.
TOTAL PRICE 2 63585.26 222548.4
REBAR WORKS
BAR Ø As L N- Total W
Member N bars
(mm) (mm2) (m) members (kg)
490.873
B-1 25 9 7 8 16 3408.628
804.247
10
C-1 32 7 3 18 3365.777
PRICE
ITEM TOTAL
per kg ITEM LABOR TOTAL
6774.40 35226 70453.8
Steel 5 52 9 1 422722.9
b t L Quantity Volume
B-1 400 400 5 16 12.8
C-1 650 650 4 18 30.42
TOTAL VOLUME 43.22
Assuming that 500% of Total Volume of Concrete Works is equal to Total Man Days,
Adding 200% For Rebar Works and 350% For
Finishing
95
TOTAL MAN DAYS = 5(43.22) + 2(43.22) +
3.5(43.22)
TOTAL MAN DAYS = 541
days
Maintenance Cost
Material Cost Factor (5%) Life Span/10 Years Maintenance Cost
Trade-off1 ₱614,230.7 0.05 5 ₱153,557.68
Trade-off2 ₱2,726,838 0.05 6 ₱818,051.4
Trade-off3 ₱645,271.3 0.05 5 ₱161,317.75
Cost of Risk
Displacement Cost per mm Cost of
(mm) displacement Risk
Trade-off1 1.14 ₱20,000.00 ₱22,800.00
Trade-off2 1.11 ₱20,000.00 ₱22,200.00
Trade-off3 1.14 ₱20,000.00 ₱22,800.00
96
APPENDIX D: FINAL ESTIMATES COMPUTATION FOR CONTEXT II
97
D.1.3.Sustainability Final Cost Estimates
References: https://www.fhwa.dot.gov/engineering/geotech/pubs/nhi16027.pdf
http://www.epa.ie/licences/lic_eDMS/090151b2805f4ceb.pdf
98
D.2.3. Sustainability Final Cost Estimates
References: https://www.fhwa.dot.gov/engineering/geotech/pubs/nhi16027.pdf
http://www.epa.ie/licences/lic_eDMS/090151b2805f4ceb.pdf
https://www.researchgate.net/publication/305384064_Benefit-
Cost_Analysis_and_Application_of_Intelligent_Compaction_for_Transportation
99
D.3.2. Constructability Final Cost Estimates
211
APPENDIX E.DESIGN OF GEOTECHNICAL TRADE-OFFS
Notations:
t = time required to achieve desired average degree of consolidation
dc = diameter of the cylinder of influence of the drain (drain influence zone)
ch = coefficient of consolidation for horizontal drainage
BORING PROFILE:
A. BOREHOLE 1
Summary of borehole details: (Data from DPWH)
Depth (m) n-values (water content)
1.5 23
3 28
4.5 26
6 31
7.5 7
9 6
10.5 6
12 5
13.5 0
15 6
16.5 35
18 42
19.5 64
21 71
22.5 63
24 62
25.5 74
27 79
28.5 93/20
30 96/25
212
DEPTH OF BOREHOLE = 30 meter or 98.42 ft
Liquid Limit = Average of Moisture Content
23+28+26+31+7+6+6+5+6+35+42+64+71+63+62+74+79+ 93 96
20 +25+0
Liquid Limit = = 32.33%
20
Some assumptions are made in this design because of the lack of data.
This method will only be effective for rough
estimation Total settlement = 12 inch for 10 years
Time Needed to Accelerate the Settlement: within 1 year
Formula relating time to the drain dimension: (USDoT - Ground Modification Methods Reference
Manual – Vol. 1)
𝑐2 1
𝑡 = 𝑑 [𝐹 𝑛 + 𝐹 + ]ln[ ]
𝑠 𝑟
8𝑐 1 − 𝑢
𝑑𝑐 whrere d = 2.5 inch
𝐹 𝑛 = ln − .75 w
𝑑𝑤
Uh = 90%
𝑐2
𝑑𝑐
365 = 𝑑 [(ln − .75 ) + 𝐹 + ]ln[ 1 ]
𝑠 𝑟
8(.6) 2.5 1 − .9
dc = 22.82 ft @ 21.73 ft spacing for equilateral triangular pattern
B. BOREHOLE 2
213
Summary of borehole details: (Data from DPWH)
Depth (m) n-values (water content)
1.5 24
3 21
4.5 27
6 30
7.5 6
9 6
10.5 6
12 4
13.5 0
15 5
16.5 41
18 45
19.5 68
21 73
22.5 66
24 73
25.5 74
27 80
28.5 96/20
30 95/20
Some assumptions are made in this design because of the lack of data.
This method will only be effective for rough
estimation Total settlement = 12 inch for 10 years
Time Needed to Accelerate the Settlement: 1 year
Formula relating time to the drain dimension: (USDoT - Ground Modification Methods Reference
Manual – Vol. 1)
𝑐2 1
𝑡 = 𝑑 [𝐹 𝑛 + 𝐹 + ]ln[ ]
214
𝑠 𝑟
8𝑐 1 − 𝑢
𝑑𝑐 where d = 2.5 inch
𝐹 𝑛 = ln − .75 w
𝑑𝑤
Uh = 90%
Ch = 2(.5) = 1 ft2/day
215
E.2. Design of Dynamic Compaction
Notations:
D = Depth of Treatment (m)
K = Soil constant that varies with respect to soil type
W = Weight of drop in (metric tons)
BOREHOLE 2
Summary of borehole details: (Data from DPWH)
Depth (m) USCS (Soil Type)
1.5 SP
3 SP-SM
4.5 SM
6 SM
7.5 SM
9 ML
10.5 CH
12 CH
13.5 CL
15 ML
16.5 ML
18 ML
19.5 ML
21 MH
22.5 ML
24 ML
25.5 ML
27 SM
28.5 ML
30 SC-SM
Design Parameters:
The result will be used for both boreholes because of almost same soil properties based on
borehole details which Is inorganic silt.
- After every 1 meter depth of soil depth the hole is backfilled then compacted again.
D = K WH
Dr = relative density
Properties of Silt soil are based on typical values - Saturated Unit Weight: 19 KN/m3
BOREHOLE PROPERTIES:
1. Borehole 1
γm kn
γd = ; γm = γd 1 + MC = 16 . 79 + 1 = 28.64
1 + MC
m3
220
G + GMC G + GMC γw − γm
γm = γw ; emax 1 = = .64
γm
2. Borehole 1+e
γ kn
2 γ ; = 1 + MC =
1 + MC
16 . 8 + 1 =
28.80
G+γγGMC m3
md
G +
GMC
γw −
γm
γ = .64
1 γm
- em
m +
i =
n e
1. B
;
o
r
e ema
x2
h
o =
l
e
1
e 1. Bo G +
re γm GMC
2. B 1 hol =
e1 1+
o γw
r e
e ;
h emin
o2. B γm
1=
l o =
e r
2 e
h G +
γm GMC
o
=
l
1+
-e e γw
e
1. B 2 ;
o emax
r γm
= 2=
e
h - G +
o D GMC
l r
221
G Th
G + 1M
GMC
GC+γwGMC
= e
. soil
+ − γ 21 on
1
+γm w bot
− h
e γm
bor
eh
γγ γ =
ww
ole
G + GMC m . is
;
; γw γ 18 me
diu
e− m m
emγm
max
de
i 2 γm nse
n= = the
. n
1
42 gro
G + GMC
= γw utin
g is
− pos
γm sibl
G = e.
+ γm .
41
Dr = e .
m
6
4
ax −
− .
4
e 2
=
e 51
.6
− 4 −
.2
e 1
2. B min
Dr = e .
m
6
4
ax −
− .
4
e 1
e =
5 .
6
− 4 −
.1
e 8
max min
222
B. Design Details: (Compaction Grouting Guide - Committee of the Geo-Institute of the ASCE 2007)
Dimension and sizes used are based on average and minimum requirements due to lack of data of
in- situ soil.
1. The grout that will be used should be evaluated by ASTM C 827 to have non-shrink grout at the plastic
state.
2. Mass diameter (Grout)
- Use Type V2 with 4 meter diameter at 180L/min.
3. Grout Hole Spacing
S = 3(mass diameter) = 3(4m) = 12 meter
4. Grout Quantities
- Use a total of 8 grout – 4 on each embankment
Dr = relative density
1. Borehole 1
𝛾𝑚 𝑘𝑛
𝛾𝑑 = ; 𝛾𝑚 = 𝛾𝑑 1 + 𝑀𝐶 = 16 . 79 + 1 = 28.64
1 + 𝑀𝐶 3
𝐺 + 𝐺𝑀𝐶 𝐺 + 𝐺𝑀𝐶 𝛾𝑤 − 𝛾𝑚
𝛾𝑚 = 𝛾𝑤 ; 𝑒𝑚𝑎𝑥 1 = = .64
1+𝑒 𝛾𝑚
2. Borehole
2
𝛾𝑚 𝑘𝑛
𝛾𝑑 = ; 𝛾𝑚 = 𝛾𝑑
1 + 𝑀𝐶 1 + 𝑀𝐶 = 16 . 8 + 1 = 28.80
𝑚3
𝐺 + 𝐺𝑀𝐶 𝐺 + 𝐺𝑀𝐶 𝛾𝑤 − 𝛾𝑚
𝛾𝑚 = 𝛾𝑤 ; 𝑒𝑚𝑎𝑥 2 = = .64
1+𝑒 𝛾𝑚
- emin
1. Borehole
1
𝐺 + 𝐺𝑀𝐶 𝐺 + 𝐺𝑀𝐶
𝛾𝑚 = 𝛾𝑤 ; 𝛾𝑤 ;
1+𝑒 1+𝑒
- Dr 𝑒𝑚𝑖𝑛 1 = 𝑒𝑚𝑎𝑥 2 =
2. Borehole
2
𝛾𝑚 = 𝐺 + 𝐺𝑀𝐶
𝛾𝑤 ;
1+𝑒
-e 𝑒𝑚𝑎𝑥 2 =
1. Borehole
1 𝛾𝑚 =
𝐺 + 𝐺𝑀𝐶
𝛾𝑤 ;
1+𝑒
2. Borehole 𝛾𝑚 =
𝑒𝑚𝑖𝑛 1 =
2
𝐺 + 𝐺𝑀𝐶 𝛾𝑤 𝛾𝑚 − 𝛾𝑚
− 𝛾𝑚 𝛾𝑚 = .21
𝛾𝑚
= .42
𝐺 + 𝐺𝑀𝐶 𝛾𝑤 − 𝛾𝑚
𝐺+ = .18
𝐺 + 𝐺𝑀𝐶 𝛾𝑤 𝛾𝑚
𝐺𝑀𝐶
− 𝛾𝑚
𝛾𝑤
= .41
3. Borehole 1
𝑒𝑚𝑎𝑥 − 𝑒 . 64 − .42
𝐷𝑟 = 𝑒 −𝑒 = . 64 − .21 = .51
4. Borehole 1 𝑚𝑎𝑥 𝑚𝑖𝑛
𝐷𝑟 = 𝑒𝑚𝑎𝑥 − 𝑒 . 64 − .41
𝑒𝑚𝑎𝑥−𝑒𝑚𝑖𝑛 = . 64 − .18 = .5
The soil on both borehole is medium dense then grouting is possible.
D. Design Details: (Compaction Grouting Guide - Committee of the Geo-Institute of the ASCE 2007)
Dimension and sizes used are based on average and minimum requirements due to lack of data of
in- situ soil.
5. The grout that will be used should be evaluated by ASTM C 827 to have non-shrink grout at the plastic
state.
6. Mass diameter (Grout)
- Use Type V2 with 4 meter diameter at 180L/min.
7. Grout Hole Spacing
S = 3(mass diameter) = 3(4m) = 12 meter
8. Grout Quantities
- Use a total of 8 grout – 4 on each embankment
APPENDIX F: REFERENCES
Abeysuriya, N., & Jayasinghe, T. (n.d.). Deflection Related Serviceability Issues in Steel Buildings With Large Span Girders.
Retrieved from •
https://www.academia.edu/8339157/DEFLECTION_RELATED_SERVICEABILITY_ISSUES_IN_STEEL_BUILDINGS_WITH_L
ARGE_SPAN_GIRDERS
Construction Statistics from Approved Building Permits: First Quarter 2018 (Preliminiaty Result). (2018). Retrieved from
Philippine Statistics Authority: • https://psa.gov.ph/content/construction-statistics-approved-building-permits-first-quarter-2018-
preliminary-results
Fagan, A. J., & Lurie, D. J. (2005). Annual Reports on NMR Spectroscopy. Reinforced Concrete Structures.
Glass, G. (2003). Comprehensive Structural Integrity. Reinforced Concrete Structure.
Kumar, S., Babu, R. K., Kumar, S. K., & Kumar, K. (2010). Experimental Study on Lightweight Aggregate Concrete. Retrieved
from https://www.academia.edu/22082708/Experimental_Study_on_Lightweight_Aggregate_Concrete
Mohit, & Haider. (2015). A Comparaive Study on Structural Performance Between Steel and Reinforced Concrete Building.
Retrieved from http://www.duet.ac.bd/DUET_Old_Website/ce/template/IICSD2015/Sustainable%20Infrastructure%20and
%20Environment/SIE-005.pdf
N.Subramanian. (2013). Design of Reinforced Concrete Structures. Maryland: Oxford University Press.
Rizal Province Bid Results on Civil Works and Services. (2018). Retrieved from • http://rizalprovince.ph/old
%20database/engineering/BID%20RESULTS%20ON%20CIVIL%20WORKS/3rd%20Qtr%202018%20Bid%20Results%20on
%20Civil%20Works%20Goods%20and%20Services%20and%20Consulting%20Services.pdf
Sadat, T. N. (2014, March). Comparative Study on Reinforced Concrete and Steel Framed Buildings with Various Floor .
Retrieved from http://lib.buet.ac.bd:8080/xmlui/bitstream/handle/123456789/633/Full%20Thesis.pdf?sequence=1’
Sangave, P., Madur, N., Waghmare, S., Shete, R., Mankondi, V., & Gundla, V. (2015, February). Comparative Study of
Analysis and Design of R.C and Steel Structures. Retrieved from https://www.ijser.org/researchpaper/Comparative-Study-of-
Analysis-and-Design-of-R-C-and-Steel-Structures.pdf
Sastri, V. (2010). Shreir's Corrosion. Reinforced Concrete Structure.
227
APPENDIX G: CURRICULUM VITAE
228
MARIANNE AN
CIVIL ENGINEERING
Technological Institute of the Philippines (TIP) QC
Address: Blk. 8 Lot 11 Dividend Homes Santol St. Taytay, Rizal
Email Address: mariannereyesan08@gmail.com
Cellular No.: +639997103880
To apply OBJECTIVE
CAREER the learning and abilities learned from school into a real employment condition which will give me an adequate
chances to profession development that will make me a successful person.
Sales Lady
Chichalax Printing
Service Cainta Rizal
November 10, 2014 - April 10, 2015
Chichalax company is a printing service (Pictures, T-shirts) and photocopy service.
Analyze complex problems and identify and define the computing requirements
appropriate for solution Use modern techniques and tools of the computing practice in
complex activities.
Easy to cope up with other people.
T.I.P. Mountaineering
Club Member
March 18, 2018 - October 18, 2019
Philippine Institute of Civil
Engineers Member
July 04, 2018 - July 04, 2019
OTHER SKILLS
230
NEIL VINZON ADRIANO
CIVIL ENGINEERING
Technological Institute of the Philippines (TIP), Quezon City
Address: 287 Sumulong Street, Barangay Bagumbayan, Angono, Rizal
Email Address: neil_19_25@yahoo.com.ph
Cellular No.: +639155093441
CAREER OBJECTIVE
5th year Civil Engineering student, seeking for a position where I can apply and improve my knowledge in
engineering and gain further experience while enhancing the company’s productivity and reputation.
● Professional competence
● Communication skills
● Critical thinking and problem solving skills
EDUCATION
OTHER SKILLS
● Proficient in AutoCAD, MS Word,MS Excel
REFERENCES
EDUCATIONAL BACKGROUND
WORK EXPERIENCES
PERSONAL INFORMATION
ACHIEVEMENTS
Dean’s Lister 2nd Semester A.Y 2015-2016 Technological Institute of the Philippines
President Lister 1st Semester A.Y. 2014-2015 Technological Institute of the Philippines
Best in Christian Formation Batch of A.Y. 2013-2014 Cainta Catholic College
Champion 2014 Robotics Competition Cainta Catholic College
Third Runner Up 2013 Cooking Contest Cainta Catholic College
First Runner Up 2002 Little Miss St. Joseph St. Joseph Subdivision Cainta, Rizal
DAVID DWIGHT REYES
CIVIL ENGINEERING
Technological Institute of the Philippines (TIP) QC
Address: 52 Banaba Street Twin River Subdivision Nangka Marikina
Email Address: davidreyes0321@gmail.com
Cellular No.: +6309392322101
OBJECTIVE
To establish a career in engineering where I can demonstrate the learning outcomes of the Civil
Engineering program of the Technological Institute of the Philippines (TIP), a program accredited by the
US - based outcomes-oriented ABET (Accreditation Board for the Engineering and Technology),
Engineering Accreditation Commission.
REFLECTIVE ESSAY
Marianne R. An
Before I took this I am very curious about this course because when I was a lower year, I have a friends
who was taking this course and I see them always upset and stress, sometimes I encountered them
fighting in their design because CAPSTONE DESIGN 2 is not an easy course. So when the class started, I
also started to love the subject, the learnings in the subject and also the method of teaching of our
professor Engr. Estores, it looks easy when he teaches us. We can follow in every lecture we got, taking
notes every meeting. We enjoy it. When designing of the projects time we thought it is easy just like the
lesson, at first doing it was fun but when we started in the middle of chapter 4 and revising some chapters
from 1 to 3, from Capstone 1, we realized it is not easy at all. We do not sleep just to finish it, go overnight
sometimes, and sometimes we came up from misunderstanding each other so we ask for help on our
advisers who already a licensed civil engineer. We have a hard time finishing the chapter 4, so that we
can’t start chapter 5. But we did it, even though it is not that good because it is just our first time to take and
the time is not enough.
Capstone Design is a difficult subject but I just need to be more focus and disciplined, I need more efforts
to pass this subject but this subject is very exciting and thrilling actually. Because of this experience in
taking Capstone Design 2 I learned that it is not about the knowledge at all, it’s about how can you handle
one another, your groupmates, how you will solve your project dependently without blaming each other for
the only reason that he/she has many contribution to that project. It only teaches us in our Next Level as
soon to be Civil Engineer to be professional in every problems we encountered.
Engr. Estores is an influential person. He does not only teach but also he teaches us the life lessons behind
engineering, or how to become a Civil Engineer. Every meeting, he always reminds us that we should bring
to best to ourselves in order to appreciate one’s profession. In which, I could say that being dedicated to
your position means Act and Example.
236