Professional Documents
Culture Documents
5.3.2 Test Procedure
5.3.2 Test Procedure
2 Test procedure
The testing process can be divided into system performance, project scope, and
application. See Appendix A for checklists for FAT.
- start-up test;
- verification of documentation;
The documents listed below serve as the basis for testing functionality:
- functional plan;
- management description;
- interface documentation;
- information about color coding (colors of technological streams, block states, etc.);
The filled in signs are marked, and the received documents are considered the FAT
protocol.
Before testing the control loop, check the static parts of the HMI displays.
- symbols for designating vessels, technological lines, valves, sensors, motors, pumps,
etc .;
- the colors of the designation of static positions, for example, manual valves,
technological lines, etc.;
Prior to posting the FAT, a master document must be defined to ensure that all
characteristics are checked. It is preferable to use the instrumentation designation as the main
document, including all DCS related features and all subsystems included in the DCS (ESD,
PLC, on-board controllers, analyzer subsystems, etc.).
- relevant trends.
Verify that the graphical display of the feature coordinates for the corresponding location
is occurring and that the colors of dynamic objects such as valves, motors, bar charts, etc. are
changing appropriately.
Checking the distribution of alarms: sorting criteria (priority, equipment zone, etc.).
Testing of complex functions and interlocks is carried out after checking the corresponding
signs.
The relevant functions are checked in accordance with the requirements of the feature
check.
In addition to testing the application, the following system characteristics are verified:
- crash recovery;
- reservation;
In addition to testing the application, the following system characteristics are verified:
- crash recovery;
- reservation;
Elimination of comments and subsequent re-checks are carried out during the FAT. If this
is not possible, such work is carried out after completion of the FAT by mutual agreement and
includes:
- re-check;
- end notification.
b) the date and signature of the remaining documents drawn up during the FAT;
6.1 General
SAT is carried out after delivery / installation of the system at the buyer's site of operation.
The purpose of the SAT is to confirm the functionality of the system after delivery and
installation.
Prior to testing, the appropriate HW / SW components must be delivered to the site and
properly installed. Before testing and during installation of the DCS / PLC, carry out the
following work:
- installation of network communication facilities (for example, hubs, switches, fiber optic
cables, the Internet).
The test program (activities and schedule) is agreed between the buyer and the supplier.
The program includes, among others, the following activities:
Item Name
number
3 Inventory HW and SW
6 Loading SW
7.1 General
SITs are conducted by the purchaser after the successful completion of the SAT for each
system.
The goal of SIT is to test the integration of two or more independent systems to achieve
the functionality envisioned by the basic management principles of a project. For example,
SITs can and should be conducted when integrating the following types of systems:
- packaging units with their own DCS / PLC controllers or unit controllers;
- analyzer systems interacting with DCS / PLC using non-standard input / output signals;
SITs must ensure that both systems work together to achieve the results envisaged by the
management principles. SITs include checking the communication and interoperability
between the automation system and subsystems to ensure proper and sufficient performance
of functions.
The test program (activities and time schedule) is agreed between the buyer and the
supplier. The program includes, among others, the following works:
Item Name
number
Appendix A
(informative)