Professional Documents
Culture Documents
3210-8110-PD-0004 - Rev A1 - Process Engineering Design Guideline
3210-8110-PD-0004 - Rev A1 - Process Engineering Design Guideline
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 2 OF 24
DESIGN GUIDELINES REV A1
CONTENTS
1.0 INTRODUCTION.................................................................................................................... 3
2.0 VESSELS............................................................................................................................... 3
2.1 Drum Surge Capacity and Hold-up Volume ....................................................................... 3
2.2 Tower Bottoms Surge Capacity and Hold-up Volume ........................................................ 4
2.3 Knockout Drum Surge Capacity and Hold-up Volume ....................................................... 4
2.4 Minimum Auxiliary Nozzle Size .......................................................................................... 5
2.5 Towers and Columns.......................................................................................................... 5
3.0 HEAT EXCHANGERS ........................................................................................................... 7
3.1 Fouling Factors................................................................................................................... 7
3.2 Fluid Allocation ................................................................................................................... 7
3.3 Heat Exchanger Pressure Drops........................................................................................ 8
4.0 PUMPS ................................................................................................................................ 10
5.0 LINE SIZING ........................................................................................................................ 11
5.1 Liquid Flow ....................................................................................................................... 11
5.2 Vapour Flow ..................................................................................................................... 14
6.0 CONTROL VALVES............................................................................................................. 15
7.0 EQUIPMENT DESIGN LIVES.............................................................................................. 15
7.1 Design Life........................................................................................................................ 15
7.2 Corrosion Allowances....................................................................................................... 15
8.0 EQUIPMENT DESIGN TEMPERATURE AND PRESSURE................................................ 16
8.1 Design Temperature......................................................................................................... 16
8.2 Design Pressure ............................................................................................................... 17
8.3 Design Pressure and Temperature Example ................................................................... 19
9.0 EQUIPMENT DESIGN MARGINS ....................................................................................... 21
9.1 Columns ........................................................................................................................... 21
9.2 Pumps .............................................................................................................................. 21
9.3 Heat Exchangers .............................................................................................................. 22
10.0 EQUIPMENT SPARING ................................................................................................... 22
10.1 General ......................................................................................................................... 22
10.2 Heat Exchangers .......................................................................................................... 22
10.3 Pumps........................................................................................................................... 22
10.4 Compressors, Fans and Blowers.................................................................................. 22
11.0 VALVE LEAKAGE CLASSIFICATION.............................................................................. 23
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 3 OF 24
DESIGN GUIDELINES REV A1
1.0 INTRODUCTION
The purpose of this document is to ensure consistency of approach to design of
equipment across the Paradip Refinery Project. Where the process design has
developed more than one heat and material balance (eg. multiple cases), all equipment
and piping shall be specified for the most onerous case.
2.0 VESSELS
In case hold-up must be provided for both product and reflux, the larger volume is
used, not the sum of the two volumes.
When the discharge rate is unimportant, a nominal hold-up time of approximately two
(2) minutes is provided.
The normal operating liquid level should be taken as the midpoint between the high
and low levels. Level control should span between the high and low levels. Where
high and low level trips are required, these should be located at a reasonable elevation
above and below the high and low levels respectively, to allow operator intervention
before a trip occurs.
Low liquid level shall be at least 200 mm above the bottom (for horizontal vessels) or
bottom tangent line (for vertical vessels).
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 4 OF 24
DESIGN GUIDELINES REV A1
For water settling the above applies but this may need to be increased. Where there
may be solids in the drum, which are not to be drawn off, the liquid outlet may be
raised and the low liquid level shall be increased accordingly
For horizontal vessels, the highest liquid level shall be at least either 300 mm or 20% of
the drum diameter below the top, whichever is the greater. Note: if a crinkled wire
mesh pad is present then highest liquid level shall be at least 300 mm below the
bottom of the pad.
For vertical vessels, if vapour flow is present the highest liquid level shall be at least
300mm below the bottom of the inlet arrangement. If little or no vapour is present, the
highest liquid level shall be at least 300 mm or 15% of the drum diameter below the top
tangent line, whichever is the greater.
The minimum time between a HHLL alarm and trip and between a LLLL alarm and trip
shall be no less than 2 minutes.
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 5 OF 24
DESIGN GUIDELINES REV A1
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 6 OF 24
DESIGN GUIDELINES REV A1
Towers with L/D greater than 25 shall be avoided, if possible, due to support problems.
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 7 OF 24
DESIGN GUIDELINES REV A1
The above principles may conflict in some instances and alternative designs shall be
investigated. In these cases the most economical design shall be selected.
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 8 OF 24
DESIGN GUIDELINES REV A1
3.3.1 Liquids
Total Pressure Drop (kg/cm²) for Liquid Flow Through Exchangers in Series
3.3.2 Gases
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 9 OF 24
DESIGN GUIDELINES REV A1
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 10 OF 24
DESIGN GUIDELINES REV A1
4.0 PUMPS
The available NPSH shall exceed the required NPSH by at least 0.6 m up to design
(rated) capacity for boiling liquids, dissolved gases, foaming liquids and other fluids.
For Boiler Feed Water Pumps the available NPSH shall exceed the required NPSH by
a minimum 2.0 m margin up to design capacity at the initial calculation stage. When
accurate pump suction layouts are known this margin may be reduced to 1.5 m
following review of the calculation.
Process engineers shall identify on the process specification turndown flows below
50% of the design capacity, when such flows are possible during long-term operating
conditions covered by guarantees of plant performance.
The reference levels for setting NPSHA shall be the bottom tangent line for vertical
vessels, the bottom of the vessel for horizontal vessels, the low-low level for tanks, and
the pump impeller centre line for pumps.
The following elevations for pump impeller centreline shall be assumed if no pump
vendor details are available:
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 11 OF 24
DESIGN GUIDELINES REV A1
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 12 OF 24
DESIGN GUIDELINES REV A1
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 13 OF 24
DESIGN GUIDELINES REV A1
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 14 OF 24
DESIGN GUIDELINES REV A1
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 15 OF 24
DESIGN GUIDELINES REV A1
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 16 OF 24
DESIGN GUIDELINES REV A1
Vessel/Equipment – shells
Carbon Steel and Low Alloys (incl. 0.5 Mo steel) 3 mm minimum
High Alloy steel 0.75 mm minimum
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 17 OF 24
DESIGN GUIDELINES REV A1
where:
Maximum suction = Suction vessel design + Vessel static head
pressure pressure taken @ HLL
(or RV set pressure)
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 18 OF 24
DESIGN GUIDELINES REV A1
and:
Maximum differential = F x Net differential pressure @ rated capacity
pressure
where F is:
• 1.25 for motor driven pumps
• 1.38 for turbine driven or variable speed pumps
Note: calculation shall be based on maximum operating SG.
For reciprocating pumps, these should be provided with discharge relief valves, the set
pressure of which should be specified to avoid the pump over-pressuring any system
into which it discharges.
≤ 1.8 3.5
1.8 < MOP < 17 MOP + 1.7
17 ≤ MOP <100 110% of MOP
100 ≤ MOP <195 MOP + 10.0
≥ 195 105% of MOP
For all process equipment (with the exception of storage tanks and certain offsites
facilities) the minimum design pressure shall be 3.5 kg/cm²g.
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 19 OF 24
DESIGN GUIDELINES REV A1
exchanger in the event of a tube rupture. However, the potential for propagation of
high pressure into the piping system and other equipment connected to the low
pressure side must also be considered from a design pressure viewpoint.
3. Pump discharge:
PO3 is Net Discharge Pressure
Pd3 is Maximum Discharge Pressure
Pd3 = Maximum Pump Differential Pressure + Pd2
Pd3 should be checked against the design pressure of the downstream equipment. If,
for example, a downstream column has a design pressure higher than expected, say to
contain a runaway reaction, this pressure may be taken as the design pressure back to
a suitable break point, say the pump’s suction block valve.
The method for setting the control valve pressure drop is given in Section 6 above.
4. Exchanger:
In certain circumstances the low pressure side design pressure may be increased to
77% of the high pressure side design pressure to allow for the burst tube case as
defined in API 520 & 521. Certain codes dictate the provision of relief protection on
heat exchangers.
Above matters must be agreed with FW and/or PMC Contractor prior to
implementation.
W:\Project\IOCL\3210\DMGInbox\NAGA'S WORKING FOLDER\3210-8110-PD-0004 REV A1 .doc
DSN : 131
PARADIP REFINERY PROJECT
PROJECT SPECIFIC PROCEDURES
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 20 OF 24
DESIGN GUIDELINES REV A1
5. Column:
Top: Pd6 = Pr2
Bottom: Pd7 = Pr2 + P across internals
Pd7 does not include the liquid static as this will be added by the vessel design group
based on the high level.
6. Reboiler:
Pd8 = Pd7 + Ph4 + Ph5
FIGURE 1
EXAMPLE PRESSURE PROFILE FOR A PUMPED SYSTEM SET @ P r2
Pd3 Pd6
Po6
Pd6
SET @ P r1
H 3 (P h3)
Po1 HLL
Pd1
H2 NLL
(Ph2)
LLL
Po7
HLL Pd7
H4
H1 BREAK POINT
(Ph4)
(Ph1 ) FOR PUMPS IN
PARALLEL Po3
Pd3
Pd2 Pd3
H5
(Ph5)
cL Po4 Po5
Po2
Pd2 FOR SINGLE PUMP Po8
Pd8
Pd2 Pd3
Po = OPERATING PRESSURE
Pd = DESIGN PRESSURE
Ph = PRESSURE DUE TO STATIC
DPTDFIG1.DRW
STANDBY
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 21 OF 24
DESIGN GUIDELINES REV A1
9.1 Columns
Columns shall generally be sized according to vapour/liquid loads specified by the
material balance. Over design on vapour and/or liquid loads must be agreed on a case
to case basis, depending on the service and on whether foaming etc. may occur. The
factors shall be specified on the equipment data sheets.
The following design criteria shall apply.
Trayed columns
Columns with a diameter under 900 mm shall be designed to a maximum 70% of
flooding rate
All other columns shall be designed to a maximum 80% of flooding rate
Packed columns
Packed sections shall be designed to a maximum of 70% of flooding rate and shall be
within the maximum pressure drop specified for the packing.
9.2 Pumps
Unless otherwise stated, the sizing of pumps shall be in accordance with the material
balance and the following overcapacity rates on flow rate:
Overcapacity, %
Centrifugal Pumps
- Reflux & pumparound pumps 20
- Offsites product pumps Zero
- All other pumps 10
- Intermittent services Zero
Reciprocating Pumps
- All 10
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 22 OF 24
DESIGN GUIDELINES REV A1
10.1 General
Installation of standby spare equipment shall be included where justified for safety,
reliability or economic reasons. All refinery units are scheduled for turnaround once
every five years for planned maintenance. Running equipment requiring more frequent
turnarounds shall justify a spare.
Whilst aiming to minimise standby equipment care should however be taken to ensure
that unit operations are not rendered vulnerable to failure of relatively inexpensive
equipment (e.g. lube oil and seal oil pumps for large turbo-compressor units).
10.3 Pumps
All pumps with an immediate influence on the process must have a spare. However,
consideration shall be given to the use of common installed stand-by pumps
performing two duties.
Sparing of pumps with a delayed influence on the process (e.g. inhibitor feeding
pumps) will be evaluated on an individual basis.
In general, both the main pump and the spare are to be motor driven. However,
consideration is to be given to steam turbine drive for main and/or spare pumps where
significant relief load reduction can be achieved.
Consideration is also to be given to having steam turbine drives and motor drives in
critical services, such as BFW. For critical services such as firewater, the use of diesel
drives on pumps shall be considered.
PROCESS ENGINEERING
3210-8110-PD-0004
PROCESS ENGINEERING PAGE 23 OF 24
DESIGN GUIDELINES REV A1