Professional Documents
Culture Documents
Elevator and Escalator Installation Template
Elevator and Escalator Installation Template
Elevator and Escalator Installation Template
Lifting,
Preparation,
2%
Mobilization
Plumbing
2%
Template
6%
Installation
M/C Room
Installation &
8%
Wiring
Master Rail
4%
Installation
Installation
Car Frame
2%
Installation
Counter Weight
2%
Frame Installation
Car & CW
Balancing &
4%
Roping
Working Platform
2%
Fixing
Balance Bracket
and Rail
8%
Installation
Inspection 2 (Rail
2%
QC)
Entrance Sill,
Jamb & Hatch
6%
Door Fixing
Inspection 3
2%
(Entrance QC)
Wiring
Hall Fixtures
(Button and
4%
Lantern)
Cabin Assembly
8%
2%
COP
Limit Switches
level plate
2%
Installation
Hoistway Cleaning
2%
Internal
Inspection &
2%
Adjustments
Third Party
2%
Inspection
Flooring
Handing Over
2%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
0%
100%
Elevator
Scope Task Name
Entrance Installation
Sub-Contractor
Hoist-way Wiring
Machine work
Abans
Handing Over
Escalator
Scope Task Name
Mobilization and Survey
Escalator void measures & mark chipping and core cutting (if needed)
Bearing plate installation
Phase I Truss joining
(Installation) Escalator hoisting and placing
Escalator leveling and mid support installation (base on budge floor level,
grid line and centre line)
QC inspection
Tack joining, Connecting steps rail and steps chain
Steps removing, lubricating and re-fixing
Truss cleaning and lubricating
QC inspection
Skirt panel installation, steps installation and adjustment and outer deck
Sub-Contractor Phase II installation
(Installation)
Sub-Contractor Phase II
(Installation)
Glass holder allignment and glass installation
QC inspection
Hand rail guard and hand rail installation
Comb plate, Inner deck and platform adjustment
Safety switch installation and adjustment
Automode testing nad programming
Load test
Phase III (T&C) Removing cladding protection and inner deck protection
Outer deck protection, cleaning and polishing
QC inspection
Phase IV
Escalator cladding (Scaffolding and cladding fixing)
(Installation)
Elevator
Percentage of Percentage of
Work Done Payment
80%
Cabin and CWT QC inspection
Final QC inspection
Removing stickers of entrance,jamb,car wall
protection. Cleaning and polishing SUS. Clean
hoisway and cabin
100%
Escalator
Percentage of Percentage of
Task Name
Work Done Payment
nd Survey
measures & mark chipping and core cutting (if needed)
installation
40%
ting and placing
ling and mid support installation (base on budge floor level,
entre line)
0%
Detailed
SCOPE PROGRESS Duration in TeamDays
0%