Professional Documents
Culture Documents
Energy Isolation Procedure - HSE-SFT-000-IN-PRO-00005-01
Energy Isolation Procedure - HSE-SFT-000-IN-PRO-00005-01
Energy Isolation Procedure - HSE-SFT-000-IN-PRO-00005-01
November, 2022
Page 1 of 53
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Document Control
Revision record.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 2 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Table of Contents
1.0 INTRODUCTION 4
4.0 DEFINITIONS 5
APPENDICES
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 3 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
1.0 INTRODUCTION
Energy Isolation is a key Golden Safety Rule. It states that any isolation of energy
systems – mechanical, electrical, process, hydraulic, chemical, thermal and others –
cannot proceed unless:
The methods of isolation and discharge of stored energy are agreed and
executed by competent person(s)
Any stored energy is discharged
A system of locks and tags is utilized at isolation points
A test is conducted to ensure the isolation is effective
Isolation effectiveness is periodically monitored
The main objective of this procedure is to give each individual, a better understanding
of the golden rule on Energy Isolation with a view to avoid Energy Isolation related
incidents. Compliance to this procedure is mandatory to people involved in working for
UEP.
The purpose of this document is to describe procedure for the safe isolation and
reinstatement (de-isolation) for safe and reliable operations.
This document specifies energy isolation and relevant modalities, e.g. lockout/tagout
etc. that will be used when servicing and performing maintenance on machines and
equipment, in which unexpected energizing, start-up, or the release of stored energy
could cause: breach to UEP HSE policy or the Golden Rule on Energy Isolation This
document specifies minimum requirements for the control of hazardous energy.
It shall apply to all UEP facilities where work is carried out by UEP employees or
contractors and/or their subcontractors.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 4 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
This procedure has linkages with the following UEP procedures, practices, standards
and documents.
4.0 DEFINITIONS
Area Authority (AA) The Area Authority confirms that work activities conducted in his area
of responsibility are consistent with CoW Policy, PTW procedures and
requirements.
He may be the Permit Issuer (PI) for his area, but normally, this
task would be delegated t o his team members except for hot work in
the ‘hazardous area’. AA would be contacted f or any advice,
clarifications, conflicts resolutions, or any other matter pertaining to
issue of PTW in the area of influence.
ALARP “As Low as Reasonably Practicable." level of the risk at which a job
can proceed.
Permit Issuer (PI) The PI issues permits consistent with associated procedures and
permit requirements. The PI also confirms that work planning and
hazard assessments are completed on appropriate work permit forms.
The PI is accountable for control and safety activities within the
permitted work task, including PTW issuance and approval.
Permit to Work (PTW) An a u t h o r i z i n g document approved by a r e s p o n s i b l e
person, specifying the conditions under which potentially hazardous
or interacting activities can take place. Suitable precautions are
given to ensure that the work is done safely.
Energy Isolation (EI) EI is the process of ensuring:
(1) That all means of energy such as electrical, mechanical, hydraulic,
pneumatic, chemical, and thermal etc. have been disconnected and
unintended re-energizing is impossible. (2) That entire system under
consideration has been purged, flushed, drained and depressurized in a
way that all hydrocarbon fumes, vapors, mists, sludge, chemicals and
remnants of toxic, flammable and hazardous, do not exist.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 5 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Isolation Authority (IA) A person who has received necessary training, certification, has
completed relevant On-the-Job (OJT) modules, and has been tagged
‘competent’ by the approved authority. IA is responsible for isolation
/ de-isolation ([a]either electrical or [b]mechanical/process) of specific
sections of plant or items of equipment to the highest quality and for
the security and integrity of isolation, as indicated in the PTW/IC.
Isolation Boundary The set of valves, electrical switchgear or other similar devices used
to establish an area i s c o m p l e t e l y safe from hazardous fluids
or electrical power or pressure in which work may take place.
Isolation Certificate Certificate detailing Process, Mechanical and Electrical Isolating
(IC) requirements.
Electrical Isolation The secure, proven disconnection and separation of an electrical
circuit from a piece of equipment. Such isolations may involve
electrical, instrument and communication circuits.
Mechanical Isolation Involves the disconnection of plant equipment and systems from
sources of mechanical energy to protect against inadvertent
activation of the equipment.
Process Isolation Involves blinding, blanking or closing and locking of valves to
prevent the fluid flow. This may include depressurizing, flushing and
purging, and proving that the system is free from hydrocarbon,
chemical and other flammable or toxic vapors, and fumes etc.
Blinding / Spading / Placing a blank flange at the end of an open pipe or placing a blind
Blanking (e. g. spectacle spade) between two flanges in order to stop flow
and prevent hazardous (flammable or toxic etc.) situation(s) arising.
Energy Isolation A mechanical device that physically prevents transmission or
Device release of energy, including but not limited to: electric circuit
breakers, disconnect switches, slide gates, blinds, line valves, seals
and similar devices.
NOTE: For electrical isolations; push buttons, selector switches and
other control circuit type devices are not energy isolating devices. For
process / mechanical isolations; mud plugs & inverted check valves
and are not isolation devices.
Energy Source Any of electrical, mechanical, hydraulic, pneumatic, chemical,
thermal, radioactive or other energy sources.
Energized Connected to an energy source or containing r esidual or stored
energy.
Bleed or Vent Valve A valve for draining liquids or venting gas/vapors from pressurized
system.
Double Block and An isolation method consisting of arrangement of two block valves
Bleed in series with a bleed valve located in between.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 6 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
The responsibilities of each role are described in the sections below; for complete
details, refer Permit to Work Procedure.
PA
Sr. Process Requirements PM AA FLL PI & IA
PR
1 Have a lists of non-compliant isolations - A/R - - - -
Ensure P&IDs are labelled with ERV's & LO/LC
A/R I I I I
2 valves
Ensure effective communication between IA's,
- - - A/R C C
3 PA & PR
Sign on the IC to verify isolation before
- - - A R R
4 commencement of work
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 7 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Manager
Advisor
Field
HOO
ECA
HSE
HSE
FLL
AA
Rev. No.
ENERGY ISOLATION PROCEDURE
01
The Head of Operations (HOO) is the Owner and operational custodian of the Energy
Isolation Procedure. The HOO shall be responsible for providing assurance to UEP
Leadership that the correct procedure is being followed and is responsible for its
overall operation, upgrading and training. The HOO is the principal resource to provide
support and advice on Energy Isolation procedure and its implementation. The HOO
shall:
Note: Low residual risk jobs; involving non-compliant isolations, covered in the list of
‘Risk Based Procedure’ or for which risk assessed procedures exist; may not require
HOO approval. For example: working on separator LVs, corrosion coupon retrieval,
Orifice plate change, pigging operation & filter replacement etc.
The Area Authorities confirm that work activities conducted in their areas of
responsibility are consistent with CoW & PTW procedures and requirements.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 9 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
As a whole, the Area Authority (AA) shall be the concerned Team Leader. For
complete list of Area Authorities, refer Section 5.2 of the Permit to Work Procedure
(HSE-SFT-000-IN-PRO-00007).
The AA shall have a list of non-compliant isolations, both process & electrical,
available with an action plan for their phased and prioritized permanent engineering
solution.
The AA shall have a prioritized plan for having OJTs prepared. Once the OJTs are
prepared, the AA shall conduct the OJTs of the team and tag them ‘competent’.
The AA shall liaise with Engineering Services to ensure that P&IDs are duly labelled
with Emergency Response (ER) valves and Lock Open & Lock Close (LO/LC) valves.
Note: This particular responsibility can be delegated to respective First Line Leaders
(Production Supervisor, Maintenance Team Leaders, Maintenance Supervisors,
Assistant Production Supervisors and Senior Production Operators).
Overall responsibility for the safe control of work activities within the designated area
lies with Permit Issuer. This includes the issue of Cold & Spark Potential Permits
(except issuance of Hot Work). For further details, refer Section 5.3 of PTW Procedure
(HSE-SFT-000-IN-PRO-00007). In the context of EI, PI shall be responsible for:
Ensuring that effective communication between Issuing, Performing and Isolation
Authorities is maintained.
Coordinate the discussion and agree the design of the isolation with Isolating
Authorities.
Define control measures on the IC associated with isolation/de-isolation activity
such as purging, flushing, draining, and getting rid of all remnants and residuals
of toxic, hazardous or flammable products etc.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 10 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
When work on a Permit is finished, or the Permit reaches the end of its authorization
period, the PI shall ensure that controls are reinstated and isolations are removed.
Complete any associated certificates required with the PTW (except for the
Isolation Certificate which shall be completed by the designated Isolation
Authorities) and review these with the PI.
Performing Authority shall get assurance from IAs that:
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 11 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
The IA is responsible for the isolation/ de-isolation of systems ([1] electrical and [2]
mechanical or process) within their area. The IA shall be a competent person with
verified competence in the particular area of isolation. (For further details on
competence, training and certification requirements, refer Section 8 TNA of this
Procedure).
Examine the work site, with the PR, PA and PI, to identify the types of isolation
required and to ensure that all hazards associated with the isolating work activity
have been identified in the TRA and the controls are specified within the Isolating
Certificate (IC).
Confirm on the Isolation Certificate (IC) that any stored and residual energy has
been effectively discharged / released.
Define, in agreement with the Permit Issuer, on the IC any special / specific
controls associated with the isolation / de-isolation work activity such as: de-
pressurization, draining, venting, flushing, purging, and similar things.
Define, in agreement with Permit Issuer, a risk based frequency for the on-going
monitoring of isolation effectiveness and integrity as part of the risk assessment
and permitting process with a minimum frequency of once per shift.
Verify that isolation plans reference current and up-to-date engineering drawings
such as Process and Instrumentation Diagrams. Obtain the approval for long-
term isolation from PI.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 12 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
That the work does not commence until the system to be worked on has been
completely isolated, depressurized and rendered completely free from: fumes,
chemicals, sludge and remnants of hydrocarbons or other toxic and flammable
substances.
Effective coordination exists between Electrical and Mechanical IAs.
That isolation design and type selected is safely commensurate with practical
requirement.
The Electrical IA shall make sure that adequate controls are put in place as per TRA
to ensure that:
Energy has been completely discharged before the start of the job.
Chances of producing static charges, arcing and spark generation are properly
taken care of before commencement of work.
Electrical Competent Authority is contacted for advice if an exception is to be
obtained.
Permit Issuer is taken in loop about the exception requirement and the consent is
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 13 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
sought.
Effective coordination exists between Electrical and Mechanical IAs.
Policy
It is UEP policy that the highest quality and security of isolation, which is reasonably
practicable in the prevailing circumstances, shall always be used. This policy will be
applied at every point of isolation.
No person shall enter a vessel or confined space unless all directly connected
sources of process and utilities fluids have been positively isolated from the vessel or
confined space.
Any isolation that does not meet the minimum recommended isolation standard,
including the application of the mandatory safeguards, shall be the subject of Level-2
Risk Assessment before the isolation is approved.
No work shall be performed unless all contributing energy sources have been
positively proven dead and/or immobilized by locking / removing / de-coupling or
effective equivalent means. This specifically implies assurance on following:
1. All direct and indirect sources of energy - that may cause re-energizing of the
system to worked on - are isolated, drained, de-pressurized, purged, flushed
and rendered completely free from: hydrocarbon vapors, fumes, sludge,
chemicals and remnants of other hazardous (flammable and toxic etc.) material.
2. The circuitry to worked on has been proven dead and stored energy has been
completely discharged.
3. A system is in place to ensure that any inadvertent re-pressurization/re-
energization, of the system to be worked on, is impossible.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 14 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
All key participants in the implementation of this procedure shall be competent in the
safe isolation and reinstatement of plant.
Following key principles and requirements are essential for safe energy isolation:
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Each isolation methodology shall include the required isolation equipment and
methodology described below, including pressure monitoring required by the site
operating practice for isolation.
Spool removal - removal of a pipe work section and securing a blank (blind) flange
rated for full line design specification installed onto each live end.
Spade isolation - insertion of a steel blank plate between bolted flanges or
replacement of a spacer with a line blind. Figure 1 illustrates typical positive isolation
installation.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 16 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
This installation can include a spectacle blind or an insertion blind, either which should
be properly designed and clearly tagged.
The blank flange, spade, or spacer should be clearly marked to indicate design service
and shall be periodically inspected to verify that it is in good condition.
Bolting shall be the correct length to accommodate any extra thickness of the spade.
Area Authority should have a list of short bolting for his area of influence available with
a prioritized rectification plan.
Joint faces shall be square and fully bolted (full threads through the nuts) and
tightened.
Design shall consider the amount of flange spread necessary to remove and insert
spades (blinds) and the orientation of flanges. Consideration for inclusion of spacers at
difficult essential spading points should be made.
P E P E
Legend
Pressure indication
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 17 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Vent Vent
P E
Bleed
Valve isolation - One valve with integral DBB Valved isolation - single valve isolation
arrangement
P E P E
Bleed
Legend
Pressure indication
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 18 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Tight shutoff
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 19 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
In all arrangements, the vent (bleed) valve and pipe work shall be of sufficient
size to vent the body cavity or spool quickly (especially important in gas service)
and carry away anticipated leakage past the upstream valve or seat without
incurring a pressure rise in the body cavity.
Single Valve Isolation (SVI) consists of the closure of a single block valve.
a. Movement of machinery
Any inadvertent movement of machinery or sudden release of potential
energy in mechanical, electrical, or pressure form is a hazard to workers.
Hydraulic, pneumatic, and process powered machinery shall be isolated by
using appropriate isolation valves.
Supply and return pipes shall then be disconnected or otherwise made
safe to prevent any potential for movement of machinery.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 20 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
b. Engine driven machinery shall be isolated by shutting off the engine fuel supply,
then isolating all starting systems.
c. Electrically driven machinery shall be made safe by switching off the power
supply to the motor, then isolating all electrical supplies.
d. Any residual mechanical, electrical, or pressure energy should be safely
released as follows:
Mechanical - high and low speed rotating elements need to be run down
and springs should be released.
Hydraulic - accumulators and pressurized pipe work should be
depressurized.
Pneumatic - system should be depressurized.
Services - steam, gas, or fuel may need to be depressurized, vented,
purged, or drained.
e. After machinery power systems have been disconnected or engines/motors
prevented from starting, there may still be a foreseeable risk to people working
on machinery if it were to move. If so, a device, such as a properly engineered
check or scotch, should be installed to lock machinery in a safe position.
The highest quality and security of isolation, which is reasonably practicable in the
prevailing circumstances, shall always be used.
Positive isolation is regarded as the most secure method and shall always be
considered as the first choice, when planning maintenance work. It is mandatory
for entry into confined spaces and recommended in the following situations:
Long duration isolations.
Where equipment is to be mothballed.
Where naked flame or hot work is to be undertaken.
For process fluids at or above auto-ignition temperature or are corrosive / toxic.
The key safeguards for both low-risk and high-risk isolations (Categories A and B
respectively, as mentioned in Appendix – A) are the pressure build-up tests on the
integrity of each valve immediately prior to breaking containment, together with the
appropriate level of regular monitoring of the isolation integrity. The PI shall control and
prevent nearby work and ensure gas monitoring on defined intervals at the worksite.
PI or his competent nominee shall be present during breaking containment and any
other critical phases of the task.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 21 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Other precautions that shall be considered when breaking containment are as follows:
Bolts shall be slackened off in the correct sequence. No bolts are to be removed
until they have all been slackened and the joint cracked, and until it has
been confirmed that the line contents will not be released in an uncontrolled
manner and any appropriate gas testing has been carried out.
Particular care should be taken with clamp lock type fittings. With nuts
slackened, the fitting should be physically dislodged to confirm there is no
residual pressure, before final disassembly.
The person who opens the flange, shall do so in a way as to minimize the
possibility of contact with the contained fluids and of sudden escape of large
quantities. Suitable and adequate PPE shall be worn and the person shall stand
upstream of the wind direction or possible direction of leakage. Availability and
reliability of the wind sock has to be mentioned in the risk assessment and in the
PTW as ‘additional control’.
The Area Classification system used for the selection of electrical equipment in
hazardous areas does not consider abnormal operations when breaking
containment. Consideration shall be given to restricting the use of electrical (and
other) equipment during breaking containment due to the risk of releasing
flammable gas.
Impact of SIMOPS shall be given due diligence and consideration. The details of
SIMPOS along with adequate hazard harnessing measures shall be clearly
mentioned on PTW, cross referenced and communicated to people involved.
6.5 Shifting of empty containers, equipment & valves etc. potentially containing
trapped energy and/or hazardous material
Any isolation that does not meet Minimum Recommended Standard, including the
application of the mandatory safeguards, shall be approved as per following risk based
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 22 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Positive isolation shall be effected on all live lines for any task requiring entry into a
vessel or other confined space. Spool removal is the preferred method, although
spade isolation may be used where it is not reasonably practicable to remove pipe
work sections.
It should be noted that, in some cases it may not be reasonably practicable to comply
with this requirement in making entry to mud tanks, pump pits, or other utility systems
etc. Here, a rigorous and specific Level-2 Risk Assessment shall be undertaken and
Section 9.0 of Confined Space Entry Procedure (Documentum #) shall be referred.
Vessel nozzles should normally be left open to assist with free ventilation. Air movers
or ducted fans may also be used to create a flow of clean air through the vessel.
The manway doors / flanges on a vessel being prepared for entry shall be removed
last and reinstalled first to reduce the risk of unauthorized entry.
6.8.1 Security
Any isolation shall achieve and maintain effective containment of the relevant fluid for
as long as required. Valves shall be locked or immobilized mechanically or otherwise
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 23 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
When isolating any valve that cannot be locked and may inadvertently be opened by
accidental contact, the valve handle should be removed.
Electrically operated devices shall have the power supply positively isolated and any
hand jack/means of system overrides manually locked. If the valve cannot be
physically immobilized, it shall not normally be used for isolation purposes.
‘Fail closed’ type pneumatically and hydraulically operated valves, shall have their
control lines isolated and physically disconnected.
‘Fail open’ type pneumatically and hydraulically operated valves, should not normally
be considered for isolation purposes. If no other alternative is reasonably practicable,
the valve shall be reliably prevented from moving as per this Energy Isolation
Procedure. The method used should be determined by local assessment. Depending
on circumstances and type of valve, methods such as the application of a local
Nitrogen supply, use of a special locking mechanism or removal of the operating
mechanism may provide the optimum solution to allow positive isolation to be affected.
All valves, spades and blank flanges used for isolation purposes shall be identified by
means of labels / tags. A sequential number should be allocated to each individual
isolation point and be clearly marked on:
The Isolation Certificate (IC).
The drawing showing the location of each isolation point.
The label applied at the isolation point.
The label shall also show the IC number. Bleed points shall also be labelled.
Where padlocks are used, the individual key number should be listed on the IC and a
means of referencing the correct key to the isolation point included. Keys should be
held centrally in a secure fashion, and controlled by the Permit Issuer.
Where there are overlapping isolations, where some of the isolation points are
common to more than one isolation, then these points shall have a separate locking
device and tag from each isolation. Each isolation shall be registered and controlled by
its own individual IC.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 24 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
The Isolation Certificate (IC), cross-referenced to all relevant Permits to Work, shall be
the principal means of control once isolations are in place. The IC performs the
following functions:
Identifies the plant concerned and the reasons for isolation.
Authorizes isolation by disciplines.
Records the complete list of isolations and valve tag numbers used for a
particular task.
Confirms that the isolations have been effected.
Authorizes any temporary de-isolations and isolations necessary for testing.
Authorizes and records de-isolation on completion of the task.
The IC shall indicate or refer to a complete list of isolations and valve tag numbers. A
marked-up P&ID or other suitable drawing shall be attached to the IC, together with a
record of the Isolation Level 2 Risk Assessment where this is needed.
Where an area of plant is isolated such that several activities can safely take place
within this common set of strategically placed isolation points then this can be termed
as a 'Boundary Isolation'. It shall be clearly identified that the isolation is appropriate
for all the individual tasks to be carried out against the Boundary Isolation. An
Isolation Certificate is raised and identified as Boundary Isolation and all individual
Permits to Work are cross-referenced to this Boundary Isolation.
Once work is in progress and subsequent Permits to Work are applied for within the
recognized framework of the Boundary Isolation, they can be added providing it
is clearly established that the existing isolation is appropriate for the task. However,
this should be avoided, if possible, and it is preferable to identify all activities
when the Boundary Isolation is being planned.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 25 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
If for any reason work, on a particular piece of plant within the Boundary needs to be
suspended (e.g. while awaiting spares), a separate isolation must be implemented and
an IC raised before the Boundary Isolation can be cancelled.
Long-term isolations (LTIs) are defined as those that no longer have work performed
against them. Each site shall maintain a detailed register of long-term isolations.
Before any work is recommenced against a long-term isolation, a full integrity check of
the isolation shall be carried out.
For integrity reasons, certain process and drain valves shall be in the normally locked
open (LO) or locked closed (LC) position. It is vital that the position and security of
these valves is carefully controlled. It is important that these valves are in their correct
position after de-isolation where they have been part of isolation. If these valves are
moved from their normal position as part of isolation, then the subsequent return to
their normal position should be ensured through an isolation checklist.
It is also required to have updated list of LO/LC valves available in the control rooms.
Personal isolations are intended for short duration tasks of relatively low risk; for
example replacing pressure gauges, filters or small valves, or other such tasks where
the completion of an IC is considered to add no significant value in terms of risk
reduction. It shall be recorded on the PTW that Personal Isolation is authorized. The
rules for approval of a Personal Isolation are as follows:
Rev. No.
ENERGY ISOLATION PROCEDURE
01
The same isolation standards apply to Personal isolations as to isolation under an IC.
This includes LoTo procedure.
Following guideline is recommended for considering Personal Isolation:
Consider
Go For IC Personal
Isolation
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 27 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
All isolations shall be tested and shown to be effective before containment is broken.
Typical valve isolation integrity tests for DBB and single valve isolations are described
in Appendix B. It is important that all bleeds (vents/drains) are checked free
from obstruction prior to testing. It is also important to realize that a bleed, which is
hard- piped to a closed drain or flare line, will provide single valve isolation only
from the drain/flare line (refer to Appendix B).
Once the IA is satisfied with the integrity of the valved isolation and that the system is
depressurized, drained, and rendered free from hydrocarbon fumes, vapors and
remnants of chemicals, sludge and other hazards; the IA shall provide such assurance
to PA and IA. Then, containment may be carefully broken to effect positive isolation.
All precautions, as identified in the risk assessment, shall be taken regarding
complying with the draining procedure including taking care of grounding to avoid
static charges, H2S, pyrophoric scale, low specific activity (LSA) scale, naturally
occurring radioactive materials (NORM) or hydrates etc.
The integrity of each isolation point shall be monitored at suitable intervals to detect
any actual leakage or deterioration in condition caused, for example, by
vibration or disturbance (or changing pressure upstream). This monitoring may
involve partial testing of valved isolations as suggested in Appendix B. The results of
any monitoring of isolation integrity shall be recorded and form part of the shift
handover.
Electrical isolation is required when any person may come into contact with either
electrical conductors that have been charged electrically or get energized through any
other unguarded equipment that is driven by electrical motors, with exception of taking
measurements. This procedure does not need to be followed for instrument supplies at
voltages less than 50 Volt AC or DC. Isolation through switch or wire disconnection is
required for instrument supplies at voltages less than, 50 Volt AC or DC e.g., Battery
(24V) should be disconnected through switch or wire disconnection at Jet Pumps
or on any equipment before starting PM or CM jobs. While there may be negligible
personnel hazard at these voltages, personnel making such isolations are expected to
follow good working practice in both the method of isolation, and ensuring that no
hazard arises.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 28 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Note: It is mandatory to remove the key from battery switch to ensure that no one
accidently starts the engine.
Electrical work is defined as any work that may result in access to potentially live
conductors. This shall also include non-electrical work near live conductors.
For adequate electrical isolation, the switch or other means of disconnection shall
have an isolating gap sufficient for the voltage levels present or likely to occur. (For
further details refer Appendix C). To prevent accidental or inadvertent re-energization,
adequate measures listed in Appendix C, shall be taken. A voltage test shall be carried
out after isolation to ensure that the contacts on all phases have been opened or
separated. Where the supply to the electrical equipment is controlled using a circuit
breaker or contactor, the circuit breaker or contactor shall be opened and steps taken
to prevent re-closure, e.g. withdraw control fuses, push stop buttons in etc. before
isolation is carried out.
Also ensure that there are no other interlocking systems or auto / emergency / standby
energization circuits which could start up the equipment from these alternate energy
sources.
The appropriate method must be used depending on the means of supply and the
work that is to be carried out.
Lockout locks and tagout tags should be as per following recommended specification.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 29 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
lock is not available. The AA shall ensure that a near miss report is raised if a
master key gets lost.
Lockout and Tagout devices should be durable and capable of withstanding the
environment to which they are exposed for the maximum period of time that
exposure is expected. It will be a good practice to have the devices oiled
periodically to ensure their durability.
Tagout devices shall be constructed and printed so that exposure to weather
conditions or wet and damp locations will not cause the tag to deteriorate or the
message on the tag to become illegible.
Tags should not deteriorate when used in corrosive environments such as areas
where acid and alkali chemicals are handled and stored.
Tags shall be affixed to the lockout or isolation device by a means of a fastening
device (e.g., wire or cable ties etc.) and shall include a legend such as the
following:
Utility systems supplied to instruments (e.g., purge air, cooling water, and
hydraulic oil) should have isolation valves for each user.
Motor operated valve actuators shall have isolation apparatus. The choice of
which isolation system to be used shall be based on operational requirements of
the system.
Fiscal metering systems shall be capable of being isolated in the same way as
plant used for non-fiscal purposes.
Air supply to individual instruments, both in the control panel and in the field,
shall be isolatable by a suitable block valve.
Dual input filter regulators feeding instrument air to a pneumatic panel shall have
isolation upstream and downstream of each filter regulator set.
All discrete electrical equipment (e.g., controllers, indicators, and enunciator
units) shall be individually isolatable.
Each panel section or rack of equipment shall be isolatable.
In process facilities, the “Operations Lock” shall be considered the “Control Lock”
and be the first lock on and the last lock off. Personnel working on isolated
equipment shall be protected by an Individual Lock in addition to the Control
Lock. In process facilities, there shall usually be a minimum of two locks on all
isolation locations - the Operations Control lock and the worker's Individual lock.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 30 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
If more than one craft teams are performing different tasks on the same
equipment, then each team shall install their own Individual locks in addition to
the Operations Control lock.
If an energy-isolating device is incapable of being locked out, some other means
equivalent to placing a lock shall be adopted, e.g., removing the handle from a
manual block valve or physically removing and taping off the output electrical
wires from a circuit breaker or removing the fuse etc.
In addition, a tag shall be attached at all isolation points.
Each person working on equipment shall ensure their own safety by keeping
their locks and tags on the energy source while working on equipment. The key
to such individual lock shall be held and controlled by the respective individuals.
Every valve, spade, switch, breaker etc. used in an isolation shall be marked with
correct type of tag.
The tag label is to identify the number of the Isolation Certificate authorizing
the isolation.
Each valve/switch etc. used as part of more than one Isolation Boundary is to have a
tag label for each Isolation Certificate. It is not necessary to fit additional physical
securing devices for each Isolation Certificate (except where this is required for
electrical isolations). All electrical isolation shall be secured by a minimum of two
locks.
When isolation is complete, the Isolating Authorities shall prove that the area within the
isolation is fully isolated from pressure and electricity. This can normally be done by
checks at vent or by the checks to prove electrical equipment dead.
If more than one Permit is to be worked on within the same isolation boundary, each
permit is to be recorded on the IC, and labels for each permit applied to the isolation
points. This will minimize the risk of isolation being removed before all work is
complete.
When work is complete, the PA shall inform the PI. The PI ensures that all relevant
PTWs have been closed, will then sign the Isolation Certificate to instruct the IAs to
carry out de-isolation.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 31 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
2. Carry out the de-isolation. If any of the valves or switches is part of another
isolation boundary, the tag for the current de-isolation is to be removed, but
other tags are to be left in place. The securing device shall not be
removed until all ICs on the valve/ switch have been signed for deisolation.
3. Remove the tags from the valves/ switches.
4. Sign the Isolation Certificate to confirm that the de-isolation is complete.
When testing is required to confirm that the work is complete, de-isolation for testing is
allowed:
If a Permit reaches the end of its Validity Period (after extension) and work is
to continue under a new Permit, the Isolations can be transferred between the Permits.
The old Permit is to be signed by the PI to show that de-isolation has not been done
and work is not complete.
If work is completed or suspended beyond the Work Permits period of validity but the
work site requires the continued projection of the IC the following procedure shall
apply:
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 32 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Remove the Long Term Isolation Certificate from the LTI display. Carry out a
review of the isolation at the worksite to confirm the integrity of the boundary for
the proposed work.
Raise a new work permit and cross reference to the IC.
Complete the work under the Permit to Work procedure.
There are two levels of audit, which should be carried out in relation to the Energy
Isolation system:
The Entity shall review the safe system of energy isolation control in relation to the
guidelines in this document at least annually. This audit can also be made part of CoW
or PTW audit. This system compliance audit should cover the overall application of
the system to identify any shortfalls and remedial actions required. Particular emphasis
shall be given to equipment design and specifications to ensure provision for effective
isolations, security, tagging. Also number and frequency of non-compliant isolations
shall be analyzed and permanent engineering solutions developed and implemented
according to a plan.
Entity Audit shall be conducted annually and be initiated by HOO in consultation with
HSE Manager.
Field personnel should carry out audits of individual tasks covering both the Permit
and the Isolation per frequency defined in PTW Procedure (HSE-SFT-000-IN-PRO-
00007).
A Permit / Isolation audit shall be entered in KMI. The Area Authority shall endorse the
audit findings, and if deficiencies are found, may:
Please note that the audit is a function of Isolation activity; if there is no isolation, the
audit shall be based on activities like checking of long term isolations, going through
Isolation register and reviewing previous certificates etc.
An Isolation Register shall be maintained at all facilities for IC’s issued by the
Production team. Similar Isolation Registers shall be maintained by Construction,
Maintenance and other departments for the IC’s issued by these departments. The
details contained in the register, from the left hand side are:
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 33 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Date
Isolation Certificate Number
Connected PTW Type and number
Location
Work Description
Date and Time Cancelled
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 34 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 35 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Be able to advise on
electrical isolation
queries conflicts
Not Applicable
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 36 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
I…………………………………………………………………………………………………
…………have thoroughly read and understood the Energy Isolation Procedure
on……………………………….
I…………………………………………………………………… (Signature)…………….
(The TA shall ensure to keep a documentary proof such as work pack etc. of the
assessee)
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 37 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Appendix -A:
Guidance on Minimum Recommended Isolation Method
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 38 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Appendix-B
Testing of Isolations
Typical valve Isolations Integrity Tests for DBB and SVI are described below:
It is important to check that all bleeds (vents/drains) are free from obstruction before testing
– beware of any lines such as flare headers in which deposits may be present.
Note that a bleed, which is hard-piped to a closed drain or flare line, will provide SVI only
from the drain/flare line.
Once the PI is satisfied with the integrity of the valved isolation and that the system is
depressurized and drained, containment may be carefully broken, either to effect positive
isolation or to perform the required task.
The witnessed installation of positive isolation supplies additional security in those instances
where the positive isolation is untested. Along with the valved isolation used to effect the
positive isolation, this is normally acceptable for most confined space entry tasks. However,
for longer term positive isolations (e.g. a week or more), or where the valved isolation used
to effect the positive isolation needs to be removed for operational reasons, then integrity
testing of the positive isolation is required. This shall be done by service leak testing, or
formal leak testing of the joint, depending on the level of risk.
Removal of any blank flanges, reinstatement of removed pipe work, or swinging of spectacle
plates must be preceded by the integrity testing of the valved isolation. The valved isolation
may still be in place, or it may be necessary to re-effect and re-test the valved isolation, if it
was removed. Pressure or leak testing of the system shall be performed, as necessary.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 39 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
(1) Valve de-isolation does not necessarily involve any opening or closing of the
valves; it may only require the removal of locking devices and/or other
immobilizing equipment. Particular care should be taken with electrically,
pneumatically or hydraulically operated valves, which may open or close on
reinstatement of the power source/medium.
(2) Some isolation shall require prior disconnection of ICCP/TR. Such requirements
shall be indicated prominently on the relevant IC and PTW. In De-isolation switching
ICCTP/TR on, will be the last action to be taken.
(3) Blinds, pressure indicators, etc. that are installed as part of the isolation shall
have the same pressure class as the pipes/equipment to which they are connected.
(4) When a mechanical or hydraulically expandable plug is used for pressure or leak
testing, the following requirements apply:
Only plugs with double seals that allow for a pressure increase up to the
maximum operations pressure between the seals must be used. The plug
must have been leak tested up to this pressure before the work is started. It
must be possible to drain the chamber between the seals to the atmosphere
and to monitor the pressure in it.
Work on a pipe plug must only be carried out by personnel who have been
trained and tagged competent in the use of this particular plug. There must be
a user manual/written procedure for the plug, and it shall be followed.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 40 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
B.1.1 General
M1 M2
V1 V2 Break
B
Key:
V1 First (upstream) isolation valve from live system.
M1 Live side monitoring point (pressure gage or vent/drain).
V2 Second (downstream) isolation valve from live system.
M2 Monitoring point between valves and break point (pressure gage or
vent/drain).
B Bleed point between isolation valves.
P Process.
a. If possible, ensure that tappings at M1, M2, and B are not blocked and that
pressure gauges, if installed, are operating.
b. Close downstream valve V2 and secure in closed position.
c. Note pressure at monitoring points M1 and M2.
d. Vent/drain section of line to be broken into and monitor at M2 until pressure is
zero.
e. Close vent/drain at break point and monitor at M2 for at least 10 min. No
pressure buildup at M2 indicates integrity of downstream valve V2.
f. Close upstream valve V1 and secure in closed position.
g. Note pressure at M1 and B.
h. Vent/drain between V1 and V2 (B) and monitor at B until pressure is zero.
i. Close vent/drain (B) and monitor at M1 and B for at least 10 min. No pressure
buildup at B indicates integrity of upstream valve V1.
j. Continue monitoring isolation effectiveness by closing vent/drain (B) and
measuring pressure buildup or by another suitable monitoring methodology.
k. The two block valves are now closed and secured. Pressure buildup between
the two block valves needs to be regularly monitored to confirm isolation
condition. A suitable pressure gage may be fitted to the bleed to monitor
pressure.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 41 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
B.2.1 General
Figure B.2 illustrates DBB isolation integrity test (double sealed, single valve).
Figure B.2 - DBB isolation integrity test (double sealed, single valve)
M1 Vent M2 Vent
Break
C
Key:
M1 Live (upstream) side monitoring point.
M2 Monitoring point between valve and break point (downstream).
C Cavity drains (between seals).
P Process.
a. If possible, ensure that tappings at M1, M2, and C are not blocked and that
pressure gauges, if installed, are operating.
b. Close isolation valve and secure in closed position.
c. Note pressure at M1, C (in cavity), and M2.
d. Vent/drain downstream section of line to be broken into and monitor pressure
at M2 until pressure is zero.
e. Close vent/drain at break point and monitor at M2 and C for at least 10 min.
No pressure buildup at M2 and no pressure falloff at C indicate integrity of
downstream seal.
f. Note pressure at M1 and C.
g. Vent/drain off fluid in cavity (between seals) and monitor at C until pressure is
zero.
h. Close cavity vent/drain (C) and monitor at M1 and C for at least 10 min. No
pressure buildup at C indicates integrity of upstream seal.
i. Continue monitoring isolation effectiveness by closing cavity vent/drain (C)
and measuring pressure buildup or by another suitable monitoring
methodology.
j. The double sealed, single block valve is now closed and secured. Pressure
buildup within the single body valve needs to be regularly monitored to
confirm isolation condition. A suitable pressure gage may be fitted to the
bleed to monitor pressure.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 42 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
B.3.1 General
Vent Vent
M1 M2
Break
Key:
M1 Live (upstream) side monitoring point.
M2 Monitoring point between valve and break point (downstream).
P Process.
a. Ensure that tappings at M1 and M2 are not blocked and that pressure
gauges, if installed, are operating.
b. Close isolation valve and secure in closed position.
c. Note pressure at M1 and M2.
d. Vent/drain downstream section of line to be broken into and monitor at M2
until pressure is zero.
e. Close downstream vent/drain and monitor at M2 for at least 10 min. No
pressure buildup at M2 indicates integrity of single valve.
f. Continue monitoring isolation effectiveness by closing downstream vent/drain
valve and measuring pressure buildup or by another suitable monitoring
methodology.
g. The single isolation valve is now closed and secured. Any fluid passing
through the single valve seal would be monitored by means of mandatory
additional safeguards listed in Appendix A.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 43 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Appendix-C
Methods of Isolating Electrical Equipment
General Guidelines:
Rack out the circuit breaker from cubicle and apply LOTO. If locking device is not available
use Disconnect Method.
Rack out the circuit breaker from cubicle and apply LOTO. If locking device is not available
use Disconnect Method.
DO NOT REFER C.1 Contact Electrical Competent Authority (ECA) for safe isolation
DO NOT REFER C.1 Contact Electrical Competent Authority (ECA) for safe isolation
Work involving
exposure to
conductors, i.e.
changing light fitting
Plug and socket Mechanical Work Withdraw plug from the socket. 1. PA
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 44 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
All work and source Rack out the circuit breaker from
above 1000 VAC cubicle and apply LOTO. Contact Electrical
If locking device is not available use Competent Authority
Disconnect Method. (ECA) for safe isolation
After proving circuit as dead,
discharge stored energy by
grounding stick.
DO NOT REFER C.1
Multiple All work Isolate if practicable or use Put a caution tag 1. IA
Sources Disconnect Method clearly stating that (Electrical)
multiple sources have 2. PA
been disconnected
inside
Generator All work Generators shall have their fuel and Fuel volume/driving 1. IA
starter valves (in case of pneumatic energy between shut- (Electrical)
starting system) locked and tagged off valve and 2. PA
in shut position. generator shall be bled
off completely.
Isolate generator by isolator/circuit
breaker to open position
Apply LOTO
Battery All Work Switch off and take out the key Keep the key secure 1. IA
where applicable, if not practicable, with IA (Electrical)
use Disconnect method. Make sure connections 2. PA
Isolate Battery charger through are not loose before de-
isolator where applicable. isolation.
Make sure that
connected load (such
as starting motor) is not
switched on.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 45 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
UPS/UPS Batteries All Work Switch off the isolators of UPS and UPS ISOLATION 1. IA
battery charger. Apply LOTO JOBS NEEDS HIGHER (Electrical)
Ensure stored energy is completely LEVEL OF APPROVAL 2. PA
discharged and verified by testing. AND SPECIAL 3. PI
ATTENTION. PI TO
ENSURE THAT
SPECIAL
PROTOCOLS ARE
FOLLOWED
Before isolation, the IA
to ensure that system is
running on by-pass.
PA Performing Authority
IA Isolating Authority
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 46 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Appendix C.1
For following activities, OSHA has given exception to lockout requirements while maintaining
tagout requirement:
Defeating/bypassing security.
Working on equipment that can be unplugged.
Changing of bulbs.
Routine adjustment activities by operation that does not involve possibility of contact
with live circuit.
Where adequate procedure exist to maintain protection to worker that is intended by
LOTO.
When the energy isolating devices are not lockable, tagout may be used, provided
the employee complies with the provisions of the standard which require additional
training and more rigorous periodic inspections. (OSHA 1910.147 App A: Typical
minimal lockout procedures under standard CRF 29).
Appendix C.2
If circuit breaker has proper locking provision, normal LOTO procedure is sufficient and
should be followed.
If locking provision is not given, following steps shall be taken according to prevailing
condition by the electrical IA:
Disconnect the cable/wire from down stream of the breaker and tag it.
Disconnect the cable from down stream of the Magnetic contactor.
If the cable size is bigger enough to disconnect easily from magnetic
contactor then remove the control fuses of magnetic contactor and keep them in a
box installed in MCC room/Control room for this purpose and apply LOTO on this
box.
If working on upstream of the breaker, primary / upstream breaker must be off and
locked and tagged.
Cable ends to be bolted together and connected to ground with in a JB or plastic
bag.
A voltage test shall be done before start working on electrically isolated equipment/feeder. A
test shall also be made after isolation using an appropriate test instrument to ensure that
contacts have been broken. The test instrument should be checked before and after the test
to ensure that it is functioning properly.
The electrical IA shall make sure that he does not use measuring device as testing device.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 47 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Isolation
Certificate-Sep-2019.xlsx
Others (Specifiy)________________attached
ISOLATION REQUEST
I, PI, declare that the above plant / system is in a safe condition for isolations to be made.
I request that the system be isolated in the following ways:
Valve Positive Electrical Other
LOCKED
OTHER
POSITIVE ISOLATION
PI
IA (Proces s )
PI
IA (Proces s )
PI
IA (Proces s )
PI
IA (Proces s )
PI
IA (Proces s )
PI
IA (Proces s )
PI
IA (Proces s )
PI
IA (Proces s )
Is olating Amendment to Isolation//Sanction to Test Is olating
FUSE REMOVED
DISCONNECTED
Authority Authority
PROVED DEAD
ISOLATION. USE ADDITIONAL SHEET(S) IF item ) I, Isolating Authority, certify that the following items have been De-isolated / Isolated as counter item )
LOCKED
Name, P.No.Certif No. & Sign of PA Name, P.No.Certif No. & Sign of PI
Date: Time : Hrs . Date: Time: Hrs .
DE-ISOLATION CONFIRMATION Regis try of IC Clos ure
We, PA & IA declare that all is olations have been removed from the Sys tem Specified on this (a) Copies of IC and attached documentation returned to Control Room.
certificate. Normal operations may be s afely res umed. (b) IC Clos ed & plant normalized
Updated Permit Regis ter accordingly
Name, P.No.Certif No. & Sign of PA Name, P.No.Certif No. & Sign of IA Name, P.No.Certif No. & Sign of PI
Date : Time: Hrs . Date: Time: Hrs .
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 48 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Appendix-E
A Double Block and Bleed isolation consists of closing two block valves in series with an
intermediate bleed valve led to a safe location. The bleed, in this arrangement, has two
primary functions to perform.
The safe location, to which the diverted fluid is led, may vary according to location and
circumstance. Open drain, closed drain, flare, or vent may satisfy the requirement in a
particular situation. Closing off the bleed with a low range pressure gauge and vent, in
conjunction with clear instructions regarding monitoring and bleed down, may provide a
solution on some occasions.
The provision of the bleed allows for accommodating a degree of leakage across the outer
block valve. However, no leakage is acceptable across the inner block valve.
An acceptable leakage rate across the outer block valve must be determined locally.
Factors governing this determination could include:
However, the primary factor remains, with the two block valves closed, and the bleed open,
NO PRESSURE ACCUMULATION SHOULD OCCUR BETWEEN THE BLOCK VALVES.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 49 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Whenever plant or equipment is removed from service (to carry out any work related to
repair, maintenance, modification, replacement, etc) all sources of related energy shall be
securely isolated to eliminate or minimize the risk of fatalities, injuries and incidents arising
from the uncontrolled release of energy or hazardous materials.
REQUIREMENTS
Safe isolation and reinstatement of plant and equipment should use a risk-based
process to determine the appropriate method and level of isolation. This shall include,
but not be limited to:
There is a written process for the control of plant and equipment isolation and
reinstatement.
All personnel with assigned responsibilities for the control of plant and equipment
isolation and reinstatement are suitably trained and competent to carry out those
responsibilities.
Plant and equipment isolation requirements are identified during the work
planning phase and appropriate risk assessment conducted to identify hazards
and recommend controls for the implementation, security, monitoring and testing
of energy isolation as well as for its safe de-isolation and reinstatement of plant
and equipment including temporary engineering and operating changes,
emergency procedures, personal protective equipment, etc.
The highest quality of isolation which is reasonably practicable is applied to every
isolation.
Isolations which do not meet the minimum requirements are subjected to a level-
2 risk assessment before approval by appropriate authority based on acceptable
level of residual risks.
All isolations and de-isolations are approved, implemented and recorded by
suitably trained, competent and authorized personnel with specific procedures for
communication and transfer of responsibilities between shifts, different
workgroups or different areas / facilities affected.
All isolations are protected by a system of locks and tags.
Stored energy is safely discharged by a responsible person and tested to confirm
the plant and equipment are at zero state of energy.
Isolation effectiveness is tested and periodically monitored to ensure continued
effectiveness during the entire duration of work.
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 50 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Appendix-F
S. Status
Description Remarks
No. (Yes/No)
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 51 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 52 of 53
PRO-00005-01
United Energy Pakistan Limited
Rev. No.
ENERGY ISOLATION PROCEDURE
01
Sys tem :
De-is olate
Hot Work Cold Work Is olation Date Date
Job No.: Des cription for Tes t Com m ents
Perm it Perm it Certificate Opened Clos ed
Certificate
HSE-SFT-000-IN-
Document No. Issue Date: November, 2019 Page 53 of 53
PRO-00005-01