LAPORAN PRESTASI PEKERJAAN PEMASANGAN ELEVATOR

Nama Proyek : PT. ECLAT TEXTILE INTERNATIONAL - KENDAL, SEMARANG.


Elevator : Unit 1 - Elevator Yusaki (Machine Roomless)

1 Ags - 11 Ags 2021 15 Nov - 20 Nov 2021


NO. ITEM PEKERJAAN BOBOT
BOBOT (% ) BOBOT (% ) BOBOT (% )
I A. Site preparation
1. Onsite 4,94 4,94 100% 4,94 100%
2. Handling Material 3,29 3,29 100% 3,29 100%
3. Scaffolding/Steger 3,25 3,25 100% 3,25 100%
4. Template/Plumb Line 4,94 4,94 100% 4,94 100%
II B. Hoistway Installation
1. Angle Bracket 4,94 4,94 100% 4,94 100%
2. Buffer Footing 1,65 1,65 100% 1,65 100%
3. Main Rail/CWT Rail 4,7 4,7 100% 4,7 100%
4. Lining Rail 4,94 4,94 100% 4,94 100%
5. Limit Switch 1,65 1,65 100% 1,65 100%
III C. Entrance
1. Sill Support 3,7 3,7 100% 3,7 100%
2. Sill 4,94 4,94 100% 4,94 100%
3. Jamb 4,94 4,94 100% 4,94 100%
4. Header Operator 3,7 3,7 100% 3,7 100%
5. Hall Door 4,94 4,94 100% 4,94 100%
IV D. Car / CWT Rail
1. CWT Frame 0,82 0,82 100% 0,82 100%
2. Stile, Buttom, & Top Chanel 2,06 2,06 100% 2,06 100%
3. Platform 0,82 0,82 100% 0,82 100%
4. Ceiling Car 1,65 1,65 100% 1,65 100%
5. Car Wall 1,92 1,92 100% 1,92 100%
6. Entrance Coulom 0,82 0,82 100% 0,82 100%
7. Door Motor, Car Junction Box 1,00 1,00 100% 1,00 100%
8. Car Door 0,41 0,41 100% 0,41 100%
V E. Machine Room
1. Base Plate 1,02 1,02 100% 1,02 100%
2. Machine Beam 2,03 2,03 100% 2,03 100%
3. Machine Foundation 1,32 1,32 100% 1,32 100%
4. Traction Machine Set 2,00 2,00 100% 2,00 100%
5. Control Panel 0,82 0,82 100% 0,82 100%
6. Ducting Cable 1,84 1,84 100% 1,84 100%
7. Governor 1,84 1,84 100% 1,84 100%
8. ARD 1,23 1,23 100% 1,23 100%
9. Rooping 2,50 2,50 100% 2,50 100%
VI F. Test Commisioning
1. Bongkar Steger/Scaffolding 1,25 1,25 100% 1,25 100%
2. Wiring Control Panel 2,15 2,15 100%
3. Low Speed 1,65 1,65 100%
4. Wiring Hoistway 2,49 2,49 100%
5. Wiring Car 3,29 3,29 100%
6. High Speed 2,25 2,25 100%
7. Final 3,00 3,00 100%
VII H. Clean Up 1,65
IX I. Serah Terima 1,65
TOTAL 100 81,87 82%

Denpasar, 28 November 2021


Dibuat Oleh,

Yuzannir
Teknisi
LAPORAN PRESTASI PEKERJAAN PEMASANGAN ELEVATOR
Nama Proyek : PT. ECLAT TEXTILE INTERNATIONAL - KENDAL, SEMARANG.
Elevator : Unit 2 - Elevator Yusaki (Machine Roomless)

11 Ags - 22 Ags 2021 21 Nov - 26 Nov 2021


NO. ITEM PEKERJAAN BOBOT
BOBOT (% ) BOBOT (% ) BOBOT (% )
I A. Site preparation
1. Onsite 4,94 4,94 100% 4,94 100%
2. Handling Material 3,29 3,29 100% 3,29 100%
3. Scaffolding/Steger 3,25 3,25 100% 3,25 100%
4. Template/Plumb Line 4,94 4,94 100% 4,94 100%
II B. Hoistway Installation
1. Angle Bracket 4,94 4,94 100% 4,94 100%
2. Buffer Footing 1,65 1,65 100% 1,65 100%
3. Main Rail/CWT Rail 4,7 4,7 100% 4,7 100%
4. Lining Rail 4,94 4,94 100% 4,94 100%
5. Limit Switch 1,65 1,65 100% 1,65 100%
III C. Entrance
1. Sill Support 3,7 3,7 100% 3,7 100%
2. Sill 4,94 4,94 100% 4,94 100%
3. Jamb 4,94 4,94 100% 4,94 100%
4. Header Operator 3,7 3,7 100% 3,7 100%
5. Hall Door 4,94 4,94 100% 4,94 100%
IV D. Car / CWT Rail
1. CWT Frame 0,82 0,82 100% 0,82 100%
2. Stile, Buttom, & Top Chanel 2,06 2,06 100% 2,06 100%
3. Platform 0,82 0,82 100% 0,82 100%
4. Ceiling Car 1,65 1,65 100% 1,65 100%
5. Car Wall 1,92 1,92 100% 1,92 100%
6. Entrance Coulom 0,82 0,82 100% 0,82 100%
7. Door Motor, Car Junction Box 1,00 1,00 100% 1,00 100%
8. Car Door 0,41 0,41 100% 0,41 100%
V E. Machine Room
1. Base Plate 1,02 1,02 100% 1,02 100%
2. Machine Beam 2,03 2,03 100% 2,03 100%
3. Machine Foundation 1,32 1,32 100% 1,32 100%
4. Traction Machine Set 2,00 2,00 100% 2,00 100%
5. Control Panel 0,82 0,82 100% 0,82 100%
6. Ducting Cable 1,84 1,84 100% 1,84 100%
7. Governor 1,84 1,84 100% 1,84 100%
8. ARD 1,23 1,23 100% 1,23 100%
9. Rooping 2,50 2,50 100% 2,50 100%
VI F. Test Commisioning
1. Bongkar Steger/Scaffolding 1,25 1,25 100% 1,25 100%
2. Wiring Control Panel 2,15 2,15 100%
3. Low Speed 1,65 1,65 100%
4. Wiring Hoistway 2,49 2,49 100%
5. Wiring Car 3,29 3,29 100%
6. High Speed 2,25 2,25 100%
7. Final 3,00 3,00 100%
VII H. Clean Up 1,65
IX I. Serah Terima 1,65
TOTAL 100 81,87 82% 96,7 97%

Denpasar, 28 November 2021


Dibuat Oleh,

Yuzannir
Teknisi
VISUAL IMAGE INSPECTION
UNIT 1 & 2 - PROJECT SEMARANG

No. Tanggal Kegiatan Dokumentasi

Pemasangan
1. 02-Agust-21
Scaffholding

Pemasangan
2. 02-Agust-21
Template

3. 04-Agust-21 Pemasangan Angel


4. 05-Agust-21 Pemasangan Bracket

Pemasangan Rell
5. 07-Agust-21 Sangkar dan Rell
CWT

6. 08-Agust-21 Pemasangan Sill Pintu


Pemasangan dudukan
7. 07-Agust-21
kuvernur

Pemasangan Dudukan
8. 07-Agust-21
Mesin

9. 07-Agust-21 Pemasangan Mesin


10. 09-Agust-21 Ropping

11. 11-Agust-21 Dinding Sangkar


LAPORAN PRESTASI PEKERJAAN PEMASANGAN ELEVATOR
Nama Proyek : PT. ECLAT TEXTILE INTERNATIONAL - KENDAL, SEMARANG.
Elevator : Unit 3 Elevator Yusaki (Machine Roomless)

20 Okt - 29 Okt 2021 30 Okt - 04 Nov 2021


NO. ITEM PEKERJAAN BOBOT
BOBOT (% ) BOBOT (% ) BOBOT (% )
I A. Site preparation
1. Onsite 4,94 4,94 100% 4,94 100%
2. Handling Material 3,29 3,29 100% 3,29 100%
3. Scaffolding/Steger 3,25 3,25 100% 3,25 100%
4. Template/Plumb Line 4,94 4,94 100% 4,94 100%
II B. Hoistway Installation
1. Angle Bracket 4,94 4,94 100% 4,94 100%
2. Buffer Footing 1,65 1,65 100% 1,65 100%
3. Main Rail/CWT Rail 4,7 4,7 100% 4,7 100%
4. Lining Rail 4,94 4,94 100% 4,94 100%
5. Limit Switch 1,65 1,65 100% 1,65 100%
III C. Entrance
1. Sill Support 3,7 3,7 100% 3,7 100%
2. Sill 4,94 4,94 100% 4,94 100%
3. Jamb 4,94 4,94 100%
4. Header Operator 3,7 3,7 100%
5. Hall Door 4,94 4,94 100%
IV D. Car / CWT Rail
1. CWT Frame 0,82 0,82 100%
2. Stile, Buttom, & Top Chanel 2,06 2,06 100%
3. Platform 0,82 0,82 100%
4. Ceiling Car 1,65 1,65 100%
5. Car Wall 1,92 1,92 100%
6. Entrance Coulom 0,82 0,82 100%
7. Door Motor, Car Junction Box 1,00 1,00 100%
8. Car Door 0,41 0,41 100%
V E. Machine Room 100%
1. Base Plate 1,02 1,02 100%
2. Machine Beam 2,03 2,03 100%
3. Machine Foundation 1,32 1,32 100%
4. Traction Machine Set 2,00 2,00 100%
5. Control Panel 0,82 0,82 100%
6. Ducting Cable 1,84 1,84 100%
7. Governor 1,84 1,84 100%
8. ARD 1,23 1,23 100%
9. Rooping 2,50 2,50 100%
VI F. Test Commisioning
1. Bongkar Steger/Scaffolding 1,25 1,25 100%
2. Wiring Control Panel 2,15
3. Low Speed 1,65
4. Wiring Hoistway 2,49
5. Wiring Car 3,29
6. High Speed 2,25
7. Final 3,00
VII H. Clean Up 1,65
IX I. Serah Terima 1,65
TOTAL 100 42,94 43% 81,87 82%
Note : Unit 3 dan 4 belum masuk elektrikal dikarenakan dari pihak gedung belum menarik listrik ke Lift 3 dan 4

Denpasar, 28 November 2021


Dibuat Oleh,

Yuzannir
Teknisi
LAPORAN PRESTASI PEKERJAAN PEMASANGAN ELEVATOR
Nama Proyek : PT. ECLAT TEXTILE INTERNATIONAL - KENDAL, SEMARANG.
Elevator : Unit 4 Elevator Yusaki (Machine Roomless)

05 Nov - 12 Nov 2021 13 Nov - 18 Nov 2021


NO. ITEM PEKERJAAN BOBOT
BOBOT (% ) BOBOT (% ) BOBOT (% )
I A. Site preparation
1. Onsite 4,94 4,94 100% 4,94 100%
2. Handling Material 3,29 3,29 100% 3,29 100%
3. Scaffolding/Steger 3,25 3,25 100% 3,25 100%
4. Template/Plumb Line 4,94 4,94 100% 4,94 100%
II B. Hoistway Installation
1. Angle Bracket 4,94 4,94 100% 4,94 100%
2. Buffer Footing 1,65 1,65 100% 1,65 100%
3. Main Rail/CWT Rail 4,7 4,7 100% 4,7 100%
4. Lining Rail 4,94 4,94 100% 4,94 100%
5. Limit Switch 1,65 1,65 100% 1,65 100%
III C. Entrance
1. Sill Support 3,7 3,7 100% 3,7 100%
2. Sill 4,94 4,94 100% 4,94 100%
3. Jamb 4,94 4,94 100%
4. Header Operator 3,7 3,7 100%
5. Hall Door 4,94 4,94 100%
IV D. Car / CWT Rail
1. CWT Frame 0,82 0,82 100%
2. Stile, Buttom, & Top Chanel 2,06 2,06 100%
3. Platform 0,82 0,82 100%
4. Ceiling Car 1,65 1,65 100%
5. Car Wall 1,92 1,92 100%
6. Entrance Coulom 0,82 0,82 100%
7. Door Motor, Car Junction Box 1,00 1,00 100%
8. Car Door 0,41 0,41 100%
V E. Machine Room 100%
1. Base Plate 1,02 1,02 100%
2. Machine Beam 2,03 2,03 100%
3. Machine Foundation 1,32 1,32 100%
4. Traction Machine Set 2,00 2,00 100%
5. Control Panel 0,82 0,82 100%
6. Ducting Cable 1,84 1,84 100%
7. Governor 1,84 1,84 100%
8. ARD 1,23 1,23 100%
9. Rooping 2,50 2,50 100%
VI F. Test Commisioning
1. Bongkar Steger/Scaffolding 1,25 1,25 100%
2. Wiring Control Panel 2,15
3. Low Speed 1,65
4. Wiring Hoistway 2,49
5. Wiring Car 3,29
6. High Speed 2,25
7. Final 3,00
VII H. Clean Up 1,65
IX I. Serah Terima 1,65
TOTAL 100 42,94 43% 81,87 82%
Note : Unit 3 dan 4 belum masuk elektrikal dikarenakan dari pihak gedung belum menarik listrik ke Lift 3 dan 4

Denpasar, 28 November 2021


Dibuat Oleh,

Yuzannir
Teknisi
VISUAL IMAGE INSPECTION
UNIT 3 DAN 4 - PROJECT SEMARANG

No. Kegiatan Dokumentasi

1. Scaffholding Instalation

2. Template Installation

3. Angle bar installation


4. Bracket Installation

5. Guide Rell Installation

6. Guide Rell Lining job


7. Door Sill Installation

8. Hall door jamb Installation

9. Machine C/P Setting


10. CWT Installation

11. Cabin Installation

12. Ropping