12db FOR 19, 22, &

6d
6db FOR 10, 12, &
25

HOOK

b
6d
HOOK
16

H
H
NOTES:

DETAILING
DETAILING

DETAILING
1. THESE DEVELOPMENT LENGTHS APPLY TO REGULAR CONCRETE. MULTIPLY

DIMENSION
A or G

DIMENSION

DIMENSION
THE SPECIFIED DEVELOPMENT LENGTH BY 1.3 FOR LIGHTWEIGHT CONCRETE.
2. THESE DEVELOPMENT LENGTHS SPECIFIED FOR CONCRETE AND "DIAPHRAGMS"
db db db
ARE APPLICABLE IF THE HOOK BAR IS WITHIN THE CONFINED CONCRETE CORE
OF A BOUNDARY MEMBER.
3. REFER TO SECTION FOR ADDITIONAL REQUIREMENTS FOR ALL OTHER MEMBERS.

GENERAL USE

HOOKED BAR DEVELOPMENT LENGTH (Ldh) SCHEDULE


L dh
50mm Min. TYP. HOOPS & SUPPLEMENTARY TIE DETAIL
Fc' = 211 kg/cm
BAR SIZE
(3000psi)

db
10
NOTES:
b
° -4d COLUMN HOOPS
10 Ø 160 135 L.D

db
HOOK AT EACH END
12 Ø 210 FOR 10Ø, 12Ø, 16Ø
16 Ø 260
20 Ø 310
25 Ø 410

d b
28 Ø 460

10
NOTES:
32 Ø 510 ALTERNATIVE 90°

6db
°

db

°
135

90
50mm MIN. COVER AT & 135° ENDS ON
36 Ø 560
EACH SIDE OF BAR CONSECUTIVE CROSSTIES

SUPPLEMENTARY DETAIL
CROSSTIE OVERLAPPING HOOPS

RECOMMENDED END HOOKS, ALL GRADES


180 DEGREE HOOK 180 DEGREE HOOK
FINISHED BEND
BAR SIZE
DIAMETER, D IN. (mm.) A OR G J A OR G
(mm.) (mm.) (mm.) STIRRUPS AND TIE HOOKS, ALL GRADES
10 Ø 60 130 80 115 BAR D GENERAL USE SEISMIC USE
12 Ø 80 155 105 155 SIZE (mm) 90° HOOK 135° HOOK 135° HOOK
16 Ø 100 180 130 255 A OR G A OR G H APPROX. A OR G H APPROX.
20 Ø 115 205 155 305 10 Ø 40 105mm 105mm 55mm 130mm 90mm
25 Ø 155 280 205 410 12 Ø 55 115mm 115mm 80mm 170mm 145mm
28 Ø 247 285 300 485 16 Ø 65 155mm 140mm 100mm 205mm 140mm
32 Ø 275 435 340 560 20 Ø 145 305mm 200mm 145mm 275mm 170mm
36 Ø 307 485 375 610 25 Ø 155 410mm 265mm 145mm 365mm 230mm
GENERAL USE SEISMIC LOAD

BAR BENDING DETAILS


6d
100mm MIN. TYPICAL STANDARD HOOK DETAIL

.
IN
d

d
.

d
IN

IN

M
6

6
M

6
ALL CROSSTIE ALL CROSSTIE

m
m

0m
END IN ALL END IN ALL

m
0

10
10
CASES

10
CASES DETAILING HOOK

90
Ø12
DIMENSION A OR G

db
D

50mm MIN.

50mm MIN.
6d

6d
D
d

J
d D
180°
4 db
BEAM & JOIST STIRRUPS
SPANDREL & BEAM SUPPLEMENTARY TIE COLUMN & SPANDREL TIE
D=4d FOR 12Ø THRU 16Ø DETAILING
DETAILING DETAILING
WIRE TOGETHER
EACH END DIMENSION DIMENSION
D=5d FOR 20Ø THRU 25Ø DIMENSION

D=8d FOR 28Ø THRU 36Ø

EXTENSION U.N.O.

A OR G
200mm MIN.

12db
72 d
D
D
4d

TIE LAP DETAIL STD. BAR HOOK DETAIL

PROJECT TITLE & LOCATION PROJECT OWNER SHEET CONTENT REVISIONS ENGINEER SHEET NO.
AS SHOWN REV DATE BY DESCRIPTION

S-1
LOCATION:

DATE REVISED:
w

ANCHORAGE LENGTH
SEE TABLE OF

825
(TYPICAL)
550

WALLS LESS THAN


200 mm THK.

H
550
(TYP.)

H
WALLS LESS THAN 1050
200 mm THK.

3 WINDOW OPENING DETAIL


SCALE N.T.S.

550
30 BAR DIA.

(TYP.)
WINDOW OPENING DETAIL

550
2 (MIN.)
30 BAR DIA.
SCALE N.T.S.
(MIN.)

DEPRESSION
D=FOR BEAM
550

t=FOR SLAB

VERIFY
(TYP.)

1 WALL CONNECTION DETAIL

SLAB
30 BAR DIA.

"t"
SCALE N.T.S.

VERIFY
(MIN.)

D=FOR BEAM
2t=FOR SLAB

BEAM SLAB SOFFIT


5 DETAIL
300 300 SLAB OF GRADE
VARIES

SCALE N.T.S.
250 DIAMETER

250 DIAMETER
(TYP.) (TYP.)
DOWELS

DOWELS
30 BAR

30 BAR
4 CONSTRUCTION JOINT DETAIL
DIAMETER
DOWELS
30 BAR

SCALE N.T.S. CHB "t"


600 (MIN.)

250

400 400
400

12mm GAP
(MIN.)
6 WALL FOOTING DETAILS (WHERE APPLICABLE)
SCALE N.T.S.
7 PIPE SLEEVE THRU WALL DETAILS
SCALE N.T.S.

PROJECT TITLE & LOCATION PROJECT OWNER SHEET CONTENT REVISIONS ENGINEER SHEET NO.
AS SHOWN REV DATE BY DESCRIPTION

S-2
LOCATION:

DATE REVISED:
200 200 200 200 BAR DEVELOPMENT LENGTH
(Ld) SCHEDULE
Fc" = 21 N/mm (3000psi)
BAR
DIAMETER IN IN
(mm) TENSION COMPRESSION
(mm) (mm)
10 Ø 300 200
12 Ø 400 200
16 Ø 650 250

H
20 Ø 1000 350
25 Ø 1550 500
28 Ø 2000 450
32 Ø 2550 500
H

36 Ø 3200 550

SILL HEIGHT
ADDITIONAL DOWEL
FOR MASONRY WALL
TYPICAL COLUMN AND BEAM CONNECTION
a 480 480
240
NO. 3 BAR @ 100mm MAX.
O.C. EXTRA TIES
BEAM / SLAB

Y
50 MIN. 50 MIN. 50 MIN.

50 MIN. 50 MIN. 50 MIN.


DOOR OPENING ELEVATION WINDOW OPENING ELEVATION

a
TOP OF SLAB

1 2
SCALE N.T.S. SCALE N.T.S.
BEAM OR GIRDER

480
Y

Y
Y = 1/6 STOREY HEIGHT OR MAXIMUM
COLUMN DIMENSION WHICHEVER IS
GREATER
NOTES: 12MM BARS
1. CONFINEMENT TIES SHALL BE PROVIDED ON ALL COLUMNS AT BEAM COLUMN INTERSECTION AS (TYPICAL CHB
SHOWN UNLESS OTHERWISE SHOWN IN STRUCTURAL PLANS. REINF.)
TYPICAL CHB WALL STIFFENER COLUMNS 2. COLUMN TIES AND SPIRAL SHALL BE PROTECTED EVERYWHERE BY A COVERING OF CONCRETE
MONOLITHICALLY CAST WITH THE CORE OF MINIMUM THICKNESS OF 38mm AND NOT LESS THAN
320 320 1 1/2 TIMES THE SIZE OF COARSE AGGREGATE.

H
CHB
3. WHERE COLUMNS CHANGE SIZE VERTICAL REINFORCEMENTS SHALL BE OFFSET AT A SLOPE OF
NOT MORE THAN 1:6 AND EXTRA No. 3 BAR TIES @ 100mm O.C. SHALL BE PROVIDED THROUGHOUT
16 mm Ø REBAR
200 THE OFFSET REGION.
120
16 mm Ø REBAR
32 10 mm Ø AT 200
ADDITIONAL
320

320

120
O.C.
10 mm Ø AT 200 16 mm Ø REBAR 12MM BARS
O.C. a + H/4 LENGTH
150

10 mm Ø AT 200
O.C. ADDITIONAL
10MM BARS
a + L/4 LENGTH

1.20 0.12
AT MIDSPAN (TYP. AT EVERY 3 M) AT CORNERS AT INTERSECTION

a
BEAM / WALL FOOTING /
a = EMBEDMENT LENGTH FOOTING TIE BEAM

L
TYPICAL DETAIL OF MASONRY TO COLUMN

60
320 320

0
320 320
320 320 320
320

200

600
600

OUTSIDE AREA INSIDE AREA INSIDE AREA OUTSIDE AREA

3 CORNER SLAB DETAIL


SCALE N.T.S.

PROJECT TITLE & LOCATION PROJECT OWNER SHEET CONTENT REVISIONS ENGINEER SHEET NO.
REV DATE BY DESCRIPTION P.R.C. NO. :
AS SHOWN
0136300
DATE OF VALIDITY:
12-02-2020
P.T.R. NO. :
4080368
S3
DATE ISSUED :
LOCATION: 01-15-2020
T.I.N. :
DATE REVISED:
322-208-883
A B
A B A A 4.75
4.75
4.75
F1/C1 F1/C1
WF B1 LC 100X50X20X2
3 3 3
WF
WF

WF
3.88

3.88

3.88
B1

B1

B1
S1 S1
WF LC 150X65X20X2
100MM THK. CONCRETE
SLAB ON 100MM THK.
GRAVEL BASE AND
10MMØ TEMPERATURE
7.75

7.75

7.75
2 BAR SPACED @ 300MM
O.C. BOTH WAYS;
SUBGRADE COMPACTED
TO 95% MDD
2 B1 2 12MMØ SAG ROD

F1/C1 F1/C1
3.88

3.88

3.88
B1

B1

B1
WF

WF

S1 S1

WF
1 1 B1
1
F1/C1 F1/C1

1 FOUNDATION PLAN 2 SECOND FLOOR FRAMING PLAN 1 ROOF FRAMING PLAN


SCALE 1:50 MTS. SCALE 1:50 MTS. SCALE 1:50 MTS.

PROJECT TITLE & LOCATION PROJECT OWNER SHEET CONTENT REVISIONS ENGINEER SHEET NO.
REV DATE BY DESCRIPTION P.R.C. NO. :
AS SHOWN
0136300
DATE OF VALIDITY:
12-02-2020
P.T.R. NO. :
4080368
S-4
DATE ISSUED :
LOCATION: 01-15-2020
T.I.N. :
DATE REVISED:
322-208-883
L/4
Ld
SHORT SPAN "SA" SHORT SPAN "SB" SHORT SPAN "A" = SA SHORT SPAN "B" = SB

L
L/4 SPAN "A" * L/4 SPAN "A" * L/4 SPAN "A"
OR L/4 SPAN "B" OR L/4 SPAN "B"

VERIFY
L/4
S/4

VARIES

MODULE OF 200mm
LONG SPAN "L"

250
SPAN "A" SPAN "B"
2 STAIRS DETAIL 400 400

SCALE N.T.S. TREADS

LC L1 L2

0.75 LC OR 0.25 L1 0.25 L1 OR 0.75 LC 0.25 L2 OR 0.25 L1 SPLICE ZONE FOR 0.25 L2
(GREATER GOVERNS) 0.25 L1 OR 0.25 L2 (GREATER GOVERNS) GIRDER TOP BARS
(GREATER GOVERNS)
SPLICE LENGTH SPLICE LENGTH
SEE TABLE SEE TABLE

1 ONE WAY SLAB DETAIL EQ. EQ. EQ. EQ.

SCALE N.T.S.

EQUAL EQUAL EQUAL

(SEE SCHEDULE)
H

d
250
2d
40 170 40 2d EQ. EQ. NO SPLICE EQ. EQ.
SHALL BE
2d ALLOWED 2d
NO SPLICE

40
FROM THE
SHALL BE FACE OF THE
0.165 L1 ALLOWED 2d
W SUPPORT
(SEE SCHEDULE) FROM THE

250

170
FACE OF THE
SUPPORT 0.165 L2
50mm MAX.
AT SUPPORT

HOOP REINFORCEMENT HOOP REINFORCEMENT HOOP REINFORCEMENT


40 SEE SCHEDULE SEE SCHEDULE SEE SCHEDULE

VERTICAL BARS : 6 - 16mmØ


TIES: 3 SETS
HOOPS
JOINT

10Ø - 2 @ 50mm
(SEE SCHEDULE)

10Ø - 3 @ 75mm
4 BEAM DETAIL
COL. HOOPS

10Ø - REST @ 100mm


SCALE N.T.S.
C1
H/4
CLEAR HEIGHT OF COLUMN ("H")

min.
600
COLUMN
(LOCATIONOFCOUPLERS)

1000
FOOTING SCHEDULE
TIES
H/2

FOOTING FOOTING SIZE REINFORCING


DESIGNATION L W T BOTTOM BARS
(mm) (mm) (mm)

F1 1100 1100 200 5-16MMØ BOTH WAY


F2 1600 1600 200 7-16MMØ BOTH WAY
COL. HOOPS

1 SET 10mmØ TIES


H/4

BEAM SCHEDULE 6 - 16mmØ VERTICAL BARS


LENGTH (m) MAIN BARS
REBAR
MARK B D LEFT SUPPORT MIDSPAN RIGHT SUPPORT STIRRUPS SPACING (mm)
Ø(mm)

VERIFY
MM MM TB BB TB BB TB BB
B1 200 350 16 3 2 2 3 2 3 1 set 10Ø 1 @ 50 2 @ 75 3 @ 100 BAL @ 250

SLAB SCHEDULE
SLAB THICKNESS REBAR ONE-WAY SLAB REINFORCEMENT
MARK
MM Ø(MM) TOP BARS BOTTOM BARS SEE FOOTING SCHEDULE
SHORT SPAN LONG SPAN SHORT SPAN LONG SPAN
3 COLUMN DETAIL S1 100 10 500 500 200 200
5 BEAM DETAIL
SCALE N.T.S.
SCALE N.T.S.

PROJECT TITLE & LOCATION PROJECT OWNER SHEET CONTENT REVISIONS ENGINEER SHEET NO.
AS SHOWN REV DATE BY DESCRIPTION

S-5
LOCATION:

DATE REVISED:

You might also like