Masjid Finshing: Coridor and Floor Finishing (Wayso)

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 6

ID Task Task Name Duration Start Finish

Jan 16, '22 Jan 23, '22 Jan 30, '22


Mode F S S M T W T F S S M T W T
1
2
3
4
5 masjid finshing -
6 Furniture compeleting 7 days Mon 1/24/22 Tue 2/1/22
7 parpet wall pLASTERING 3 days Mon 1/24/22 Wed 1/26/22
8 s blocks closing female parts 3 days Mon 1/24/22 Wed 1/26/22
9 external plustering 8 days Mon 1/24/22 Wed 2/2/22
10 external furniture completing 16 days Sun 2/13/22 Fri 3/4/22
11 all cheching furniture 4 days Thu 2/17/22 Tue 2/22/22
completing
12 CORIDOR AND FLOOR FINISHING
(WAYSO)
13 sand filling 2 days Tue 1/25/22 Wed 1/26/22
14 hard cord placing 7 days Wed 2/2/22 Thu 2/10/22
15 lean concrete boring 3 days Sat 2/5/22 Tue 2/8/22
16 seting out wayso design 3 days Wed 2/9/22 Fri 2/11/22
17 blocks with wayso design 4 days Sat 1/22/22 Wed 1/26/22
18 finshing wayso design 13 days Tue 1/25/22 Thu 2/10/22
19 GRADE BEAM
20 GRADE BEAM LAY OU T 4 days Sat 1/22/22 Wed 1/26/22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Sat 1/22/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 1
ID Task Task Name Duration Start Finish
Jan 16, '22 Jan 23, '22 Jan 30, '22
Mode F S S M T W T F S S M T W T
21 GRADE BEAM REBAR 3 days Mon 1/24/22 Wed 1/26/22
22 GRADE BEAM FORM WORK 6 days Sun 1/23/22 Fri 1/28/22
23 GRADE BEAM STRIP FORM 1 day Sat 1/29/22 Sat 1/29/22
WORIK
24 GROUND FLOOR SLAB
25 SLAB LAY OUT 2 days Sun 1/23/22 Mon 1/24/22
26 SLAB REBAR 5 days Tue 1/25/22 Mon 1/31/22
27 SLAB FORM WORK 10 days Sun 1/23/22 Thu 2/3/22
28 SLAP CONCRETE 1 day Fri 2/4/22 Fri 2/4/22
PLACEMENT
29 Stair Case
30 Stair case lay out 3 days Sat 1/22/22 Tue 1/25/22
31 Stair form work 1 day Mon 1/24/22 Mon 1/24/22
32 Stair Rebar 3 days Wed 1/26/22 Fri 1/28/22
33 Stair Concret Placement 1 day Fri 2/4/22 Fri 2/4/22
34 INSIDE PLASTERING 4 days Wed 2/23/22 Mon 2/28/22
35 OUTSIDE PLASTERING 3 days Mon 2/28/22 Wed 3/2/22
36 staircase PLASTERING 2 days 2/29/22
37
38 PARPET WALL
39 BRICKLAYING 2 days Sun 2/20/22 Mon 2/21/22
40 PARPET WALL PLASTERING 4 days Thu 2/24/22 Tue 3/1/22
41

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Sat 1/22/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 2
ID Task Task Name Duration Start Finish
Jan 16, '22 Jan 23, '22 Jan 30, '22
Mode F S S M T W T F S S M T W T
42
43 SEPTIC TANK
44 DIGGING SEPTIC TANK
45 SEPTIC TANK FORM WORK 4 days Thu 1/27/22 Tue 2/1/22
46 SEPTICTANK REBAR 1 day Fri 1/28/22 Fri 1/28/22
47 SEPTIC TANK CONCRET 1 day Tue 2/1/22 Tue 2/1/22
PLACEMENT
48
49 Ceilling ground floor and 4 days Sun 2/20/22 Wed 2/23/22
second floor
50 DOORS INSTALATION 3 days Thu 2/17/22 Mon 2/21/22
51 Finishes 3 days Sat 2/19/22 Tue 2/22/22
52 Electrical wirring 3 days Tue 2/22/22 Thu 2/24/22
53 plumbing 5 days Fri 2/25/22 Thu 3/3/22
54 primer paint 7 days Thu 2/24/22 Fri 3/4/22
55 Paint 8 days Sat 3/5/22 Tue 3/15/22
56 windows 3 days Sat 3/5/22 Tue 3/8/22
57 Tiles 3 days Wed 3/9/22 Fri 3/11/22
58 MINARAH 1 day Mon 1/24/22 Mon 1/24/22

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Sat 1/22/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 3
22 Feb 6, '22 Feb 13, '22 Feb 20, '22 Feb 27, '22 Mar 6, '22 Mar 13, '22
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Sat 1/22/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 4
22 Feb 6, '22 Feb 13, '22 Feb 20, '22 Feb 27, '22 Mar 6, '22 Mar 13, '22
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Sat 1/22/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 5
22 Feb 6, '22 Feb 13, '22 Feb 20, '22 Feb 27, '22 Mar 6, '22 Mar 13, '22
T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T

Task Inactive Summary External Tasks

Split Manual Task External Milestone

Milestone Duration-only Deadline


Project: Project2
Summary Manual Summary Rollup Progress
Date: Sat 1/22/22
Project Summary Manual Summary Manual Progress

Inactive Task Start-only

Inactive Milestone Finish-only

Page 6