QUALITY INVESTIGATION REPORT

PROJECT : Hinulugang Taktak STP DATE INSPECTED : January 24,2022


PRODUCT : Rock wool Installation on Site Office Ext. Walls FABRICATOR :
BED ID : QIR NUMBER : 003

PRODUCT ID QTY NATURE OF DEFFECTS POSSIBLE CAUSE RECOMMENDED REMEDIES ACTION TAKEN

Rock wool
No rock wool insulation is installed Revision of temfacil site office
Installation on
1 on temfacil site office exterior walls. Unavailability of materials plans (if actual installation is
Site Office Ext.
It is changed to insulation foams. accepted).
Walls

FIGURE:

ACTION TAKEN ACCEPTABLE NOT ACCEPTABLE

Prepared / Inspected by: Checked and Verified by: Noted by: Received by:

June Kristian Esico Jaymar T. Isorena Paul Vincent B. Setias


Q. C. Inspector QC Supervisor Manager / Head Operations Rep.
FFC-FM-QC-14_rev.1_iss.1