Energy MGMT Case Study - Kumana, Chemical News, Nov 2010

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 10

CORPORATE ENERGY MANAGEMENT

PROGRAMS: A CASE STUDY


Jimmy D Kumana, MS ChE price stability was restored, and the economies adjusted
Kumana & Associates, Houston, Texas to higher oil prices, energy concerns receded into the
Tel 281-437-5906, jkumana@aol.com background once again.
After just over three decades, energy supply security
and costs have recently returned into the limelight, with
ABSTRACT international oil and gas prices more than doubling
This paper identifies the critical elements of a successful from mid-2007 to mid-2008. As high prices begin to
energy management program for energy-intensive process adversely impact corporate bottom lines, especially for
industries. It describes the organizational structure, energy-intensive industries such as oil & gas, chemicals,
strategies employed, resources required, and results and pulp/paper, “energy conservation” has once again
achieved at a national oil company in a middle-eastern begun to attract the attention of company management
country, drawing upon the author’s extensive experience. and government policy makers. Unfortunately there is
It also describes some of the challenges encountered, no magic quick-fix to this situation. Successful energy
both expected and unexpected, especially with respect to conservation (or more appropriately, energy optimization)
non-technical issues such as culture change, knowledge is a long-term effort. Success requires a genuine and
sharing, human resources, project financing, and politics. sustained strategic commitment, not just passing concern,
The paper provides valuable insights into how to organize ad hoc measures, or lip-service. An energy program
and successfully execute a comprehensive energy undertaken with the primary objective of boosting the
management program for large bureaucratic corporations company’s public image is doomed to failure.
with multiple plants and that should be of interest to On the positive side, the past three decades have
corporate energy managers and government energy policy seen significant innovation in the efficient conversion and
makers. use of energy. Many new products, design techniques,
and operating practices have been developed both
in academia and industry that offer the potential to
INTRODUCTION significantly slash the energy intensity of virtually all
Back in the mid-1970s, in the aftermath of the first manufacturing processes, reducing the carbon footprint
“oil shock”, energy efficiency first entered the public (ie. greenhouse gas emissions) of their end-products in
consciousness as the consequent high inflation severely the bargain.
eroded the purchasing power of the average family in There is now an established body of literature that
oil-importing nations. However, once some modicum of documents the methods and benefits of what could be

38 z chemical news november 2010


called “conventional” technical approaches that address compressors, turbines, boilers, furnaces, heat
the more obvious areas for improvement: exchangers, etc – for the same service or application)
a) Insulation of equipment and piping b) Monitoring fouling rates in critical heat exchangers, and
b) Steam-trap management – proper selection, optimum cleaning schedules
monitoring, and maintenance c) Floating-discharge-pressure compressor control
c) Compressed air management –leak detection and d) Multi-variable control (MVC)
repair, pressure optimization e) Optimal control of CHP systems – see item 2d below
d) Boiler/furnace efficiency improvement, via excess air f) Optimum driver selection for rotating machinery (fixed-
control, burner modifications, leakage reduction, etc. speed motors, multi-speed motors, motors with VFDs,
e) Multiple effect evaporation – well-known in pulp/paper steam turbines, gas turbines)
but less well in other industries g) Monitoring & Targeting, including development of
f) Heat pumps (thermal and mechanical) equipment EPIs and overall process/product/plant
g) Preventive maintenance of rotating machinery (pumps, energy KPIs. Data collection and quality is a critical
compressors, steam turbines) based on condition and issue.

To capture truly
significant savings, on
the order of 15-50%,
advanced process
optimization techniques
developed over the
past 20 years, and
encompassing both
design and operational
best practices, must be
employed

efficiency monitoring 2. Design Optimization


h) Motor replacement – right-sizing, high-efficiency motors a) Identifying relatively minor process modifications,
i) HVAC upgrades – better controls such as small adjustments in operating pressure or
j) High-efficiency lights and lighting management temperature of critical reactions and separations
k) Power factor correction (eg. distillation, evaporation) that could have a major
l) New types of equipment design, eg. dryers, low-P filters, impact on the energy targets for the process
etc. b) Optimum design of heat exchanger network (HEN)
The vast majority of industrial energy programs that structures, using Pinch Analysis combined with
have been undertaken over the past 25 years have mathematical programming (MILP, Genetic Algorithms,
focused on the foregoing tools and techniques. While etc)
these are undoubtedly good measures to take, in most c) Identifying the optimum combination of site utilities
cases the cumulative savings potential is limited to a (cogeneration type, steam pressure levels, hot oil loops,
relatively meager 5-10% of the base-case energy intensity. refrigeration levels and refrigerant selection, etc) that
will result in the lowest operating cost, using Pinch
MODERN CORPORATE ENERGY PROGRAMS Analysis
To capture truly significant savings, on the order of d) Optimum design of the Combined Heat and Power
15-50%, advanced process optimization techniques (CHP) system structure, including cogeneration. This is
developed over the past 20 years, and encompassing both done using simulation models based on the results of
design and operational best practices, must be employed: item 2c. A key element is introducing new degrees of
freedom to support items 1e and 1f above.
1. Operational Optimization e) Evaluation of Adjustable Speed Drive applications –
a) Optimum load management (for series/parallel whether VFDs for existing motors, or replacement with
networks of multiple equipment – pumps, a steam turbine drive.

chemical news November 2010 z 39


Probably the most significant development of the past
30 years since the first oil shock has been Pinch Analysis.
It burst onto the scene in the late 1970s, and captured
the imagination of the international chemical engineering
community with its elegant synthesis of thermodynamic
rigor and graphical techniques to solve the hitherto
intractable “structural optimization” problem, using
simple heuristics. Imperial Chemical Industries (UK) and
Union Carbide Corp (USA) were the early pioneers. By the
mid 1980s, a torrent of literature on new advances and
industrial success stories was pouring out, both from the
universities and from industry.
Many companies jumped on to the new bandwagon,
attempting to develop in-house expertise, but most
of them found success elusive. Gradually, but not
surprisingly, Pinch Analysis developed an undeserved Pinch Analysis - Basic Concepts
reputation for being just another passing fad that had All chemical manufacturing processes require energy in
been oversold by unscrupulous consultants posing as the form of heat and power. Power is consumed both
experts and seeking only a quick buck. for shaftwork and for cooling. The individual process
Although it is undeniable that some of the “copycat” heating duties can be combined into a single “cold
consultants were indeed under-qualified, it is instructive composite curve” drawn on a temperature-enthalpy
to dispassionately examine the whole range of reasons (T-H) diagram; it represents the enthalpy demand profile
why some companies achieved such spectacular success of the process. Similarly, all the cooling duties can be
while others failed so miserably. From over 20 years of combined into a single “hot composite curve”, which
experience in the energy business, both as a buyer and represents the enthalpy availability profile of the process.
seller, the evidence is clear that most of the failures can When both curves are plotted on the same T-H
be attributed to the following critical mistakes on the part diagram, they show the opportunity for heat recovery
of senior management: as well as the minimum net heating and cooling
z Believing that just because Pinch Analysis is easy to requirements. The point of closest approach, where
understand at a theoretical level, it would be equally available temperature driving forces between hot and
easy to apply at a practical level. Attending a one- cold streams are at a minimum, is called the process
week course on the subject does not instantaneously pinch. It separates the overall process into two distinct
transform the student into an expert; it takes at least thermal domains: (a) a net heat sink above the pinch
2-3 projects worth of experience to use the software temperature, meaning that hot utility must be supplied,
and apply the methodology correctly. and (b) a net heat source below the pinch temperature,
z Failure to become sufficiently knowledgeable to meaning that cooling must be provided.
develop a suitable corporate energy strategy, and The temperature difference between hot and cold
select the right consultants. streams at the pinch is called the Minimum Approach
z Expecting that identification of energy optimization Temperature (MAT). For each value of MAT, there are
opportunities would automatically result in project corresponding values of minimum heating and cooling
implementation. requirements (Qh)min and (Qc)min. These are the
z Focusing on only the supply side (eg. boilers, turbines, energy targets.
motors) rather than taking an integrated approach
that includes the demand side (process energy
consumption efficiency).
z Underestimating the vital importance of reliable data
and a supportive organizational infrastructure.
z Starving their corporate energy teams of the required
resources in terms of adequate authority, staffing,
budget, and time to do the job properly.
Good technology, while necessary, is not sufficient
to ensure success. It must be supported by a
comprehensive organization-wide program that removes
institutional barriers related to entrenched legal, financial,
and bureaucratic practices.

40 z chemical news november 2010


CASE STUDY – NATIONAL OIL & GAS COMPANY
This government-controlled NOC is one of the largest
oil and gas producers in the world. The Company owns
(wholly or partially) more than 20 large Gas-Oil Separation
Plants (GOSPs), about a dozen oil refineries across three
continents, half a dozen gas-processing plants, and two
condensate fractionation plants.
From a standing start in 2001, the Company reduced
its energy intensity by 25% within six short years (Figure
1) and was on track to reaching 40% reduction by the end
of 2008. How did it manage to achieve such spectacular
success despite an economic environment of low
Composite Curves (a) without heat recovery (b) with energy costs ($1-2 per MMBtu for gas and 3-4 c/kwh for
heat recovery purchased power), high capital costs (about 1.3-1.5 times
In order to achieve the targets, the HEN design must US Gulf Coast), and an accounting system that did not
satisfy three criteria: even include fuel and power as line-item operating costs?
1. No hot utilities used below the pinch temperature
2. No cold utilities used above the pinch temperature Figure 1: Corporate Energy Intensity Index
3. No heat transfer from hot streams above the pinch to
cold streams below the pinch
From these fundamental rules, it is possible to derive
a number of useful design guidelines. For example:
z Heat engines must not cross the pinch, i.e., the supply
and exhaust temperatures should both be either
entirely above or entirely below the process pinch
temperature.
z Heat pumps must be placed across the pinch, i.e., the
supply temperature must be below the pinch, and the
exhaust temperature must be above the pinch.
z Distillation and evaporation operations must not cross
the pinch.
These and other corollary rules and guidelines help It all started in 1997, when one of the Company’s
the engineer to design the process for maximum overall engineers attended an energy conference and came to
efficiency, achieving the optimum balance between the realization that their corporate policies and practices
capital costs, energy consumption, operating flexibility, were based on incorrect assumptions that urgently
and environmental emissions. needed to be revamped in light of a changing economic

chemical news November 2010 z 41


environment (Figure 2). With support from a far-sighted manpower needs through the use of external consultants.
Vice President, he obtained approval for an internal A new Energy Systems Unit (ESU) was established at
company-wide survey to compile actual fuel and power corporate engineering, with funding approval for 9-12 full-
consumption data. Even at the low values assigned to time engineers to help develop and implement the EMSC’s
energy by the accounting department the total cost proved strategic plan.
to be staggering, approaching a billion US dollars per year.
When this hitherto unreported information was brought Figure 4: EMSC Organizational Structure
to the attention of senior management, they committed
the required internal manpower and budget to conduct
a more comprehensive and detailed study by a team of
specialized energy/management consultants.

Figure 2: External Environmental Forces

The EMSC’s 10-year goal (publicized company-


wide) was to reduce corporate energy intensity by 50%
compared to the year-2000 baseline, and rolling 5-year
plans to achieve this target. The results as displayed in
Figure 1 are a testament to the success of the program.
The projected reduction in energy intensity index was 40%
The 8-month study (1998-99) included verification of by the end of 2008, from projects that had already been
energy consumption data, an estimate of economically identified and approved by the end of 2006. Additional
feasible savings potential based on quick week-long audits projects scheduled for completion in 2009-10 should
of 12 representative facilities, and an assessment of comfortably enable meeting the original target of 50%
company policies and practices that should be instituted reduction in energy intensity.
or modified to ensure success. The Company’s senior The EMSC’s strategy was simple but comprehensive,
management understood, accepted and supported including a blend of technical, organizational and cultural
virtually all of the consulting team’s recommendations. factors:
A corporate energy policy was promulgated in 2000 1. Optimize facility design and operation through
(Figure 3). An Energy Management Steering Committee deployment of industry-accepted best practices and
(EMSC) was formed, with representation at the plant- economically-sound leading edge technologies
manager level, to oversee the program (Figure 4). They Energy optimization of existing facilities (retrofit)
decided to develop core in-house expertise to manage Energy optimization of new plant designs
the program and to supplement short-term peaks in 2. Build a supportive organizational infra-structure
3. Promote transparency and accountability through
Figure 3: Corporate Energy Policy development and deployment of energy KPIs and EPIs
4. Develop in-house technical expertise supplemented by
outsourcing as needed
Energy Optimization of Existing Facilities (retrofit basis)
was a critical first step in establishing credibility for the
technical approach, and demonstrating that the targets
set by EMSC were indeed realistic and achievable. To start
with the Energy Systems Unit was staffed by one energy
experienced energy consultant recruited from the US and
four engineer-trainees. The first few energy optimization
studies were conducted exclusively by this in-house team,
principally as a means to gain experience and

42 z chemical news november 2010


build in-house technical expertise. As the workload grew, Pinch Analysis to address the less obvious optimization
additional engineers were transferred in to ESU from other opportunities.
parts of the company, and a second US-trained energy The actual overall implementation rate (in terms of
specialist with Pinch Analysis experience was recruited. dollars) was 54%. However, the energy KPIs showed
This multi-year effort helped to foster close working unambiguously that there was a huge variation in
relationships and build trust between the plant engineers performance among the 21 business units, with some
and the corporate staff. When the workload began to having implementation rates over 90%, while others were
exceed the in-house capacity, some of the detailed energy below 5%. Clearly there was a problem with acceptance
studies were outsourced to qualified consulting firms from of the technical solutions, which was identified as a high
the US, UK and India. priority concern. In 2007, the Company initiated an
One of the key requirements for successful extensive internal survey to determine the root causes
outsourcing is that the buyer should be able to specify for poor implementation rates, and to identify the key
the proper scope of work, be able to judge consultant predictors of success. Two success criteria stood out:
qualifications and capabilities correctly, and to z Having high level support (viz. from the Plant Managers
negotiate a fair price. It took 2-3 years for the trainees and business unit VPs) for energy projects
to develop the skills to become sophisticated buyers, z Empowerment of plant engineers, by providing
viz. to understand data requirements, and know what adequate resources to the energy teams in terms of
to expect in terms of quality of work, schedule, and qualified manpower, training, and budgets that would
cost. They were able to redirect the consultants’ work if enable them to prepare credible well-documented
they felt the project was on the wrong track, and could capital budget requests to corporate engineering
make contractual workscope changes on the fly. They Strictly speaking, if capital and energy prices are
knew when to allow more time or money and when to
not. Unless the buyer is knowledgeable, or engages a
trustworthy consultant, outsourcing can easily turn into a
disastrous experience.
Between 15-20 retrofit studies were carried out
over 9 years by ESU. During this period, more than100
Company engineers, mostly from the plants, were put
through 1-2 week training courses in energy optimization
that included both technical and management issues. Of
these, those who showed interest and promise were given

Unless the buyer is knowledgeable,


or engages a trustworthy consultant,
outsourcing can easily turn into a
disastrous experience.

further training via 1-2 year internship programs where rational and consistent with thermodynamic principles,
they each participated in conducting two or three retrofit they will change at approximately the same rate as long-
energy optimization studies. They then returned to their term inflation, and so the optimum design structure for
respective facilities as leaders of newly established plant the process plant should remain stable. Nevertheless, it
energy teams. is good practice to review and update the optimum design
The results achieved speak for themselves. From for every plant whenever there is a significant revision
2001 through 2006 a total of 380 project ideas were of capital and energy costs, particularly during times of
identified, with net energy savings potential of 148 MBD economic volatility.
(oil equivalent) and CO2 emissions reduction of 50,300 Energy Optimization of New Plants. Once the credibility
TPD. Of these, projects worth 90 MBDoe savings passed of the technical approach had been established through
the company’s hurdle rates for implementation. More retrofit studies, ESU turned its attention to new projects
than 50% of the project ideas, mostly falling into the being planned for construction by the company – both
“conventional” category, came from the plant energy new process units at existing sites, and greenfield sites
teams themselves, with technical support from corporate – to try and build energy efficiency into the design from
engineering only as needed. The corporate energy the start. While the concept makes eminent sense in
group focused on more advanced techniques such as principle, the team encountered unexpected hurdles

chemical news November 2010 z 43


rooted in established company practices. Historically, the z Creation of a virtual Community-of-Practice for
Company had never developed process designs internally; knowledge sharing, via the company intra-net
rather the policy was to rely on technology licensors and z Revision of company equipment standards to reflect
EPC contractors to provide them. Further, design/build current best practices with respect to energy-efficiency
responsibility rested entirely with the Company’s project z Revision of company engineering and construction
management organization, where the path to promotion standards/procedures to require energy optimization of
was through just two performance measures (a) beating any new plants that are to be built
the schedule and (b) completing construction under z Development of a standardized simulation-based
budget. No consideration was ever given to optimizing life- procedure for computing site-specific average and
cycle costs. Energy consumption, therefore, did not even marginal prices of intermediate utilities such as steam
enter into the equation. The entire organizational culture (at various pressure levels), boiler feed water, hot-oil
was heavily biased towards tried-and-true technologies circuits, cooling water, refrigeration, and cogenerated
(which necessarily implies out-dated) and towards electric power.
sacrificing energy efficiency in order to minimize initial Promoting Transparency and Accountability. When
capital cost. There were even instances of EPC contractors the idea of energy KPIs was initially broached within the
being pressured to simply re-use old design drawings company, it found no audience, as it was not considered
from other projects in other countries, without so much as to be common industry practice during the early years
changing the title blocks!! of the program. In fact, when the energy team surveyed
Not surprisingly, all attempts by ESU to introduce the industry, we could not find a single company who
modern energy-efficient design practices met with
determined resistance, on the grounds that they might
extend the design schedule or increase capital costs.
Despite providing many real-life examples where energy
optimization led to shortened schedules as well as lower
capital costs, it took three years of lobbying with key
influential people just to gain grudging acceptance of the
idea that the correct way to optimize a design was on the
basis of Life-Cycle costs, not first cost.
Once this was accomplished, though, it paved the way for
introducing the concept of optimizing process and utility
designs for site-specific conditions, with energy costs
included among the economic parameters. Ultimately,
the requirement for an integrated process-CHP energy
optimization study during the FEED stage was accepted
as an internationally recognized value-improving practice,
and written into the company standards.
Building a Supportive Organizational Infrastructure. were using such KPIs. Even high-priced management
These activities generally fall into the categories of consultants we spoke to had very limited experience
awareness, training, knowledge management, and in this area. Almost overnight, though, it seemed that
standards/procedures: the situation changed dramatically, with all the top
z Annual company-wide “Energy-Awareness” events international management consulting firms promoting
including technical exchange of successes and failures, the virtues of company-wide KPIs for a wide range of
vendor exhibits, etc. critical company performance metrics for the corporate
z Quarterly energy newsletter, distributed both in print “dashboard”. One of them was retained by senior
and electronically management in 2005 to develop such a dashboard. They
z Regularly scheduled 3-10 day training courses became ESU’s ally in jointly developing a corporate Energy
on various aspects of energy optimization and Efficiency Index for the new dashboard. It put everyone in
management, offered several times a year the middle echelons of company management on notice
z Preparation of around a dozen Best Practice Manuals that the energy efficiency of their business units was going
for equipment/process design as well as operations to be on the radar-screen from that point onwards.
z Corporate memberships in international energy research Despite their clear potential to introduce transparency
consortia and benchmarking organizations, eg. the and accountability, KPIs in general can be problematic
PIRC at the University of Manchester, the Refining Best to implement in practice. The mathematical formulation
Practices consortium, Solomon Associates (for refinery of KPIs must keep in mind the ultimate objective(s). In
operations), and IPA (project execution) our case we had multiple applications in mind. One was

44 z chemical news november 2010


to monitor progress towards the EMSC goal by keeping (to be used by the operators and engineers), process
tabs on overall plant and corporate energy intensity. EPIs for troubleshooting (to be used by plant engineers),
Another was to provide a diagnostic tool to help plant and overall plant EPIs for reporting (for use by senior
engineers troubleshoot problems and identify areas for management). While process and equipment EPIs are
improvement – both regarding process efficiency and relatively easy to formulate, product EPIs are not. For
equipment efficiency. One example of a process problem example – how should the energy cost of a distillation
might be steady deterioration in the inlet temperature to a column that is separating two saleable products be
crude oil distillation column, which would suggest gradual allocated between them? A common first reaction is to
HX fouling in the preheat train, and the need for cleaning. prorate costs on the basis of either value or volume, but
If on the other hand there was a sudden drop, it might both can lead to absurd conclusions. The only logically
suggest a HX tube rupture. A third (future) objective was consistent way that gave sensible answers was to do the
to provide guidance in making dispatching decisions – ie. allocation on a value-added basis. This created a new
what the product mix should be at each manufacturing problem – computing transfer prices for each stream
plant. within a process unit. After several months of trial and
Each application requires a different formulation error, we succeeded in developing a procedure that gave
for the energy KPI, which we called EPIs for short. We reasonable and meaningful results.
classified them into four categories – product EPIs for Formulating an overall corporate energy intensity index
dispatching (to be used by the planning staff), equipment also proved to be a challenge, as our goal was to measure
EPIs for condition monitoring and preventive maintenance the effectiveness of the energy program itself – ie. How

Another was to provide a diagnostic


tool to help plant engineers troubleshoot
problems and identify areas for
improvement – both regarding process
efficiency and equipment efficiency.

much difference did it make compared to doing business


as usual? This was in fact the single global metric that was
initially proposed to management (with the management
consultant’s approval) for use on the corporate dashboard,
and is shown in Figure 1. The consultant independently
developed an alternative simplified formulation that was
designed specifically for commercial benchmarking only.
Data availability and quality turned out to be two
other difficult issues. When plants are designed by
EPC contractors, they rarely include instrumentation to
measure all the parameters that are needed to compute
KPIs. So there was a need for considerable additional
instrumentation such as temperature and pressure
gages (which are relatively cheap) and flow meters
(which are not). Then there is the cost of programming
all the equations and testing the system for bugs, adding
graphing/display capability, and designing report formats
for printing. But that was the easy part.
The real challenge lay in reconciling discrepancies in
the metered mass and energy balances. For that the team
turned to a small high-tech Belgian software company that
we felt was the world leader in on-line data reconciliation
techniques. Two field trials lasting nearly two years overall
were conducted – one at an oil refinery and one at a gas
processing plant – which made clear that it took a very
high level of technical skill to get reliable results, and that

chemical news November 2010 z 45


long-term technical support from the vendor would be Human Resources, and Law Dept all operate in
required before our engineers would be sufficiently trained alignment towards the common objective.
to take over. The original proposal was to purchase a 20- z Linking selected plant energy KPIs to overall
plant license of the software, but given our concern about performance evaluation and compensation of key
the vendor’s ability to provide long-term technical support, employees/positions.
the project was put on hold until a satisfactory solution These are not easy things to accomplish in an
could be found. Despite these difficulties, the foregoing organization with tens of thousands of direct employees
problems are not intractable, and can be solved given and contractors on the payroll, but they have to be done.
enough time, talent and budgets. As an example, bullet item two above has internal
The most difficult problem of all turned out to be non- organizational implications that had to be cleared with
technical: getting agreement from all facility managers the Law and Human Resources departments. In addition
on a set of common metrics and a common GUI. Expect there were difficult technical issues with respect to
to encounter various delaying tactics by powerful measurement and verification of savings, legal issues
vested interests who may feel threatened by increased with respect to dispute resolution with the ESCO, and
transparency. The principal hurdle, in short, is likely to be insurance/security issues if the ESCO is a foreign
political, for which there is no easy solution. company whose employees must be given access to
Determining the right level of in-house technical company plant sites.
expertise and management capability is the final strategic Similarly, bullet item four requires breaking down
decision. It is not necessary to do all the work in-house, long-established boundaries and building trust between
but it is absolutely essential that the corporate energy rival organizations that may have had a prior history of
group should have sufficient expertise to effectively internal power struggles and mutual suspicion. The criteria
outsource the work to outside consultants. For those for economic evaluation of energy projects may have
companies who do not have sufficiently high energy to be revised to include concepts such as capital cost
bills to justify maintaining a fully staffed energy unit, offsets, environmental credits, and risk-adjusted hurdle
one option might be to appoint a single full-time energy rates. And last but not least, the technical career path
“guru”, reporting directly to a VP, and then to retain a has to be made sufficiently attractive to retain competent
trusted energy management consultant to help select and engineering talent by providing them with a viable
supervise other consultants, EPC contractors and ESCOs. alternative to the management track.
Various options for accelerating the implementation
rate for energy projects were considered that included CONCLUSIONS AND RECOMMENTATIONS
heretofore revolutionary ideas such as: One solution does not fit all, but the experience of others
z Establishing a separate capital budget for energy can provide useful insights. The key elements for a
projects, similar to what had already proven successful successful energy program can be summarized as follows:
for environmental compliance projects. 1. Unwavering and sustained support of top management,
z Empowering VPs to sign contracts with Energy Service demonstrated by formal policy statements,
Companies (ESCOs) for shared savings contracts, making energy at least as important as safety and
as a mechanism to effectively bypass the internal environmental issues in the organizational structure,
competition for limited capital funds with higher-priority and allocating adequate manpower and budgets.
safety, environmental, or capacity projects. 2. Selecting the right technical approach, including a mix
z Changing the mission of the EMSC from being an of conventional and advanced technologies for design/
advisory to an executive committee, with company-wide operating practices.
responsibility for implementing energy projects. 3. Ensuring that there is a clear plan and mechanism for
z Streamlining company procedures and practices to effective implementation of projects identified through
ensure that the Operating plants, Engineering Services, energy studies – whether via internal funding or ESCOs.
Environmental Dept, Corporate Planning, Finance, 4. Creating a culture of transparency and accountability

46 z chemical news november 2010


by instituting a system of EPIs and energy KPIs REFERENCES
for performance monitoring (preferably linked to 1. J D Kumana and Ali H Al-Qahtani, “Optimization of Process Topology
Using Pinch Analysis”, Proc of First International Symposium on Exergy,
compensation). Energy and Environment, Izmir, Turkey (July 13-17, 2003).
5. Building a supportive organization infrastructure in 2. J D Kumana and Majid M Al-Gwaiz, “Pricing Steam and Power from
terms of awareness and internal communication Cogeneration Systems using a Rational Allocation Procedure”, Proc of
26th Industrial Energy Technology Conference, Houston, Tx (April 2004).
programs, making energy management an attractive 3. J D Kumana and Ahmed S Aseeri, “Electrical Power Savings in
career path, personnel development and training, Pump and Compressor Networks via Load Management”, Proc of 27th
rational pricing procedure for intermediate utilities, Industrial Energy Technology Conference, New Orleans, La (May 2005).
4. J D Kumana and Khalid D Al-Usail, “Energy Performance Indices as a
proper project evaluation procedures, and recognition/ Process Diagnostic Tool”, presented at Process Performance Monitoring
removal of bureaucratic hurdles. and Data Analysis Symposium, Manama, Bahrain (Nov 7–8, 2006).
5. J D Kumana, Ali H Al-Qahtani, and Abdullah Y Al-Juhani, “Energy
Optimization Experience at Yanbu Refinery”, paper 655a, presented at
It may sound daunting, but it is well worth doing. The AIChE Annual Meeting, San Francisco, Ca (Nov 12-17, 2006).
results prove it. 6. J D Kumana, Ali H Al-Qahtani, and Faiz H Al-Farsi, “Power Savings via
Load Management at Rabigh Refinery”, presented at 2nd Saudi Arabian
Energy Conservation Forum, Dammam (Nov 28-29, 2006).
ABBREVIATIONS 7. G T Polley and J. D. Kumana, “Energy Saving Retrofit of an FCC Plant”,
Abbreviation Description paper AM-07-30 presented at NPRA annual meeting, San Antonio, Tx
AIChE American Institute of Chemical Engineers, NY (Mar 18-20, 2007)
8. J D Kumana, “Success Factors for a Corporate Energy Program”,
ASD Adjustable Speed Drive presented at 29th Industrial Energy Technology Conference, New
bpd Barrels per day Orleans, La (May 9-10, 2007).
CHP Combined Heat and Power
This article was reprinted, in part, from the November and December
EPC Engineering, Procurement and Construction 2008 issues of Insulation Outlook magazine with permission from the
EPI Energy Performance Index National Insulation Association. Copyright 2008. All rights reserved.
EPRI Electric Power Research Institute, Palo Alto,
California
ESCO Energy Services Company
FEED Front-End Engineering Design
GUI Graphical User Interface
GW Gigawatts (= 106 kilowatts)
HEN Heat Exchanger Network
HVAC Heating, Ventilating and Air-Conditioning
HX Heat Exchanger
IPA Independent Project Analysis Inc, Ashburn, Va
K Thousand (as prefix)
KPI Key Performance Indicator
MBD (oe) Thousand barrels per day (oil equivalent)
MILP Mixed Integer Linear Programming, a
mathematical technique for optimizing resource
allocation
MM Million (as prefix)
NPRA National Petrochemical and Refiners
Association, Washington DC
PIRC Process Integration Research Consortium,
Manchester, UK
scfd Standard cubic feet per day (of gas)
TPD Tons per day
VFD Variable Frequency Drive (subset of ASD)

Mr. Kumana holds a masters degree in chemical engineering from the University of Cincinnati. He has been professionally
active in Energy Optimization and management for over 20 years with both operating companies and consulting firms.
Before that he spent 15 years in process design with several EPC companies catering to the oil/gas/chemical, food/
beverage, and pulp/paper industries. Through his company he has provided consulting services to blue-chip international
clients including Amoco (BP), Union Carbide (Dow), Dupont, Enron, General Motors, IBM, Maharashtra Sugar, Mitsubishi
Heavy Industries, Monsanto (Solutia), SASOL, SABIC, Saudi Aramco, as well as to the US Dept of Energy, Canadian ministry
of Natural Resources, EPRI, and IFC (World Bank Group). He is a member of AIChE, and has authored or co-authored over
65 technical papers and book chapters.

chemical news November 2010 z 47

You might also like