1 06-08-2012 For APPROVAL First Issue R. M. Javidh C.H.Lim S.K.

Oh
PREP.CHECKED BY CHECKED BY APPROVED BY APPROVED BY
REV. DATE STATUS DESCRIPTION HIDADA DOOSAN DOOSAN PB

OWNER

RABIGH POWER PLANT NO.2 PROJECT


UNITS #.1,2,3 & 4
CONTRACT NO.31021001/00

OWNER'S ENGINEER

CONTRACTOR

SUBCONTRACTOR

DOCUMENT TITLE NAME DATE


PREPARED BY RASHEED 6-Sep-12 HIDADA
Inspection & Test Plan for CHECHED BY R. M. JAVIDH 6-Sep-12 HIDADA
Shop Fabrication of Bottom Heater(Header Coils)
CHECKED BY C.H.LIM DHI CONST.
for HFO Tanks
APPROVED BY S.K.OH DHI QAQC
DOCUMENT NO. TOTAL PAGES REV. NO:

31021001/00-Z-RPP2-WE001884 3 1
(HIDADA ref : 31021001/00-Z-RPP20WE009547- 1 of 2)
DOCUMENT STATUS
□ FOR INFORMATION ■ FOR APPROVAL □ FOR REVIEW □ FOR CONSTRUCTION □ AS BUILT
Doc.No. 31021001/00-Z-RPP2-WE001884
Inspection & Test Plan for
Shop Fabrication of Bottom Heater (Header coils)
Title
for HFO Tanks
Project Rabigh Power Plant No.2

Inspection and Test Activities

No. Inspection process Applicable Codes Subcon./ Quality Report/Cert. Remark


Doosan Company
Doosan
QC Engineer
Const.

1 DOCUMENT PREPARATION

Design Calculation,
Review of Inspection & Test Plan - Indication of Hold,
1.1
Review & Witness
Drawings & ASME sec. H R R ITP
VIII, Div. 1

ASME Sec. IX /
1.2 Review of WPS, PQR & WPQ. Drawing
H R R WPS/PQR/ WPQ

Approved NDE
1.3 Review of NDE and Hydrostatic Test Procedure. ASME Sec. V & VIII-1 H R R
Procedure

2 MATERIAL INSPECTION

Receiving Inspection for all materials


2.1 Drawings H R R MTC
(Pipes & other relevant materials)

Doc. No. 3102100/10-z-RPP2-WE009547, Rev. 0


Doc.No. 31021001/00-Z-RPP2-WE001884
Inspection & Test Plan for
Shop Fabrication of Bottom Heater (Header coils)
Title
for HFO Tanks
Project Rabigh Power Plant No.2

Inspection and Test Activities

No. Inspection process Applicable Codes Subcon./ Quality Report/Cert. Remark


Doosan Company
Doosan
QC Engineer
Const.

3 SHOP FABRICATION

3.1 Fit up Inspection and Record Joint Numbers Drawing H W R YES

DPT Procedure
3.2 MT After Root Welding and Record Welder Numbers H R R YES

3.3 Final welding and Visaul & dimensional check Drawing H W R YES

4 DISPATCH

Packing List, Delivery


4.1 Shipping Inspection & Release for Shipment Note & Inspection H R R YES
Release Certificate

4.2 Manufacturing Data Book Inspection Reports H R R YES

General Note : 1. R : Review(RFI not required) H : Hold Point W: Witness Point