Engineering LLC.

Line Walk QC Punch-List


CLIENT OMAN INC. CONTRACT NO. CA-2021

CONTRACTOR ENGINEERING L.L.C PROJECT NO. 9K7


12" OIL PRODUCTION HEADER FROM NEW DING
SYSTEM CONSTRUCTION OF FLOW LINE PROJECT NAME
MANIFOLD TO DONG MANIFOLD

CONTRACTOR CLIENT QC
Sl no# Description Category Status Date Closed QC Signature Signature

1 NDT completion of weld joints A

2 Hydro-test package A

3 The flange ratings are as per the ISO drawing. A

4 Bolt size identification and torquing(After final installtion) B

5 Saddles, shoes, shims, supports are installed / erected N/A


Barricade the Locations and restrict any unauthorized entry at
6 A
the time of hydro-testing.
All temporary Supports, blind/caps/plugs/gaskets are installed for
7 A
hydro-test
8 Visual check of pipe Line Routing / Laying A

9 Provision of Launcher and Receiver in the position A

10 Calibration Certicates for the Gauges & Pressure recorder. A

Marker plate to be clamp for RDX1,2,3,4,5 and WDX 1,DING


11 B
Manifold and DONG Manifold.

Pipe is not rest on sleeper near


12 jt143,165,167,176,202,205,188,206,240A,285,286,298,315,381,4 B
20,476,483,522,525,526,610,653,673

Line alignment to be done from j130 to 132,212 to 215,291 to


13 B
293,348 to 351,419 to 421,528 to 530,656 to 658

14 Extra pipes,scrap,bends and wooden pieces remove from line B

15 Guide angle welding to be done for throughout line B

Note:
Punch-List Category "A" - To Be Completed Prior To Hydro-Test
Punch-List Category "B" - Can Be Attended After Hydro-Test
Prepared By: Approved By:
Name: SWAMINATHAN NATARAJAN Name: Kuppuswamy
Position QC Inspector AWS-CSWIP CWI Position QA/QC Engineer
Signature Signature
Date Date