Name of Project : Bill of Materials for the Repair of the Roofing on the Kitchen Area
Appropriation : P21,652

ESTIMATED COST OF PROPOSED PROJECT

PART OF STRUCTURE / DESCRIPTION


UNIT QTY UNIT COST TOTAL COST GRAND TOTAL
MATERIAL LABOR MATERIAL LABOR
.4 X 12 ft. Corrugated Sheet pcs. 15 535 128.4 8025 1926 9951
.4 x 10 Corrugated Sheet pcs. 15 450 108 6750 1620 8370
Teckscrew 1 1/2 pcs. 1000 1.5 0.375 1500 375 1875
Vulca Seal can 3 380 95 1140 285 1425

Total Cost: P21,621.00

Prepared by:
Home Owner
Quoted and Checked by:
Carpenter