Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 9

WORK PROCEDURE FOR THE CONSTRUCTION TOTAL 51 PAGES

OF CO2 CYLINDER HOUSE (Including Cover)

● PROJECT CODE : B50532EA Purpose


● PROJECT NAME : MASINLOC POWER PLANT EXPANSION
□ For Information
PROJECT
□ For Review
● DOCUMENT NO. :0-WD884 – CA731 - 00383
● TITLE : Work Procedure for the Construction of CO2 □ For Approval
CYLINDER HOUSE
□ For Construction
● OWNER : MASINLOC POWER PARTNERS CO.,LTD.
□ As Built

E.R. E.R. S.K


Feb. 09, 2018 D.W. Choi J.H.LEE H.S.WOO
A For Approval CORTEZ CORTEZ HWANG

Rev. PREPARED REVIEWED APPROVED CHECKED REVIEWED APPROVED


DESCRIPTION DATE
No. GTC Global Inc. VPCI
Owner

`Contractor
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 2 of 51

TABLE OF CONTENTS

1.0 PURPOSE………………………………………………………………….. 3

2.0 SCOPE……………………………………………………………………… 3

3.0 ROLES AND RESPONSIBILITIES……………………………………… 3

4.0 RESOURCES ……………………………………………………………… 4

5.0 PROCEDURE ……………………………………………………………… 5

6.0 ATTACHMENT …………………………………………………………….. 6

Attachment #1 : Approved Plan Drawing of CO2 Cylinder House :


3 - WD884-EA120-10010 Rev. 1
Attachment #2 : Job Environmental Safety Analysis

Attachment #3 : Risk Assessment


Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 3 of 51

1.0 Purpose
This work procedure describe the method for the construction of CO2 Cylinder House located

at the South of the Central Control Building – North of Boiler Area .

2.0 Scope
It will cover the procedure and methodology that will be implemented at the Construction
Site for the construction of the CO2 Cylinder House. This will cover construction of the
Concrete Mat Foundation and the Structural Steel Frame Installation and Panel Covering
Installation .

3.0 Roles and Responsibilities


3.1 VPCI

 VPCI Project Manager shall be the overall responsible for the implementation of this
procedure ensuring that works are completed on schedule and in conformity with the
procedure, drawings and specifications.

3.2 VPCI

 VPCI Project EHS Manager shall ensure the safe implementation of this procedure promoting
an Incident and Injury Free environment.

3.3 VPCI

 VPCI QA/QC Engineer shall be responsible for the implementation of construction


specification and standards and see to it that this written procedure and method
statement of the construction of CO2 Cylinder House shall be carried out correctly and
properly including the implementation of inspection as required.

3.4 GTC

 GTC Global Inc. Site Manager – shall have the overall responsibility for the proper
planning and work implementation at site.

3.5 GTC

 GTC Global Inc. Construction Manager – shall be responsible for the proper
implementation of work at site.

3.6 GTC

 GTC Global Inc. HSE Supervisor along with the Safety Officer shall ensure
implementation of all safety procedures, safety measures related to the nature of works
being carried out and in accordance with the HSE Plan.
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 4 of 51

3.5 GTC

 GTC Global Site Supervisor shall be directly involved in the planning and execution
of the activities. He shall be responsible for the preparation of work plan, safety action
plan and safety.

3.7 GTC
 GTC Global QA/QC Engineer – carry out inspection and checking for all quality procedures
in the site and ensure activity at site area as per approved work procedure and inspection test
plan.

4.0 Resources

4.1 Manpower & Equipment Plan

Site Manager 1
Construction Manager 1
Site Engineer 1
QA/QC Engineer 1
Safety Supervisor and Officer 1
First Aider 1
Foreman 1
Scaffolding Installer 10
Carpenter 8
Steel man 10
Mason 8
Helper 5
Operator 2
Driver 2

4.2 Equipment, Tools & Materials

Item Description
1 Scaffolding Materials – Tubular &
Coupler
2 Scaffolding Installer / Carpenter / Steel
man Tools
3 Panel Form , Wood , Steel
Reinforcing bars
4 Water Truck – 1 Unit
5 Pump Car 55 Meters – 1 Unit
6 Concrete Transit Mixer – 2 Units
7 Service Stake Truck – Forward
8 Hi Lux Pick Up
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 5 of 51

5.0 Procedure

5.1 Mat Foundation Construction

After the handing over of the Area , Excavation for the subgrade preparation for Mass Lean

Concrete shall be executed including removal of loose soil materials , polyethylene sheet

installation and form installation as required . Mass Lean Concrete will follow and commence

once the inspection is conducted.

Reinforcing Steel Bar will be installed accordingly for the Mat Foundation Slab Type

considering the installation of Anchor Bolts for the Steel Structure Installation.

Accordingly Structural Concrete pouring of the Mat Foundation Slab should follow after the

completion of Rebar , Form , Anchor Bolts Installation and the Inspection respectively.

Note :

Access going to the CO2 Cylinder House is either from the CCB South Side or from the

Boiler Area .

5.2 Installation of Structural Steel

Install the Structural Framework for the entire shelter consider the installation of the CO2 Gas

Cylinder and Piping Network respectively.

5.3 Roof and Side Panel Installation = 4.8 Meters High

After the Installation of the Structural steel frame work of the entire shelter , proceed for the

installation of the Roof Panel & Perimeter Side Panel Wall . The Panel Opening shall be

considered accordingly as required.

5.4 Post Installation Works

After the Structural Steel & Panel Installation , consider the work of other discipline prior to
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 6 of 51

finishing work.

Note :

1 ) Survey Works will be implemented during the course of Construction relative to

Elevation and Alignment requirement on – site.

6.0 Attachment

Attachment #1 : Approved Plan Drawing of CO2 Cylinder House : 3 - WD884-EA120-10010 Rev. 1

Attachment #2 : Job Environmental Safety Analysis

Attachment #3 : Risk Assessment


Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 7 of 51

Attachment #1 :

Approved Plan Drawing of CO2 Cylinder House : 3 -


WD884-EA120-10010 Rev. 1
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 8 of 51

9 of 51

Attachment #2 :

Job Environmental Safety Analysis


Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 9 of 51

34 of 51

Attachment #3 :

Risk Assessment

You might also like