Work Procedure For The Construction of CO2 Cylinder House
Work Procedure For The Construction of CO2 Cylinder House
`Contractor
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 2 of 51
TABLE OF CONTENTS
1.0 PURPOSE………………………………………………………………….. 3
2.0 SCOPE……………………………………………………………………… 3
1.0 Purpose
This work procedure describe the method for the construction of CO2 Cylinder House located
2.0 Scope
It will cover the procedure and methodology that will be implemented at the Construction
Site for the construction of the CO2 Cylinder House. This will cover construction of the
Concrete Mat Foundation and the Structural Steel Frame Installation and Panel Covering
Installation .
VPCI Project Manager shall be the overall responsible for the implementation of this
procedure ensuring that works are completed on schedule and in conformity with the
procedure, drawings and specifications.
3.2 VPCI
VPCI Project EHS Manager shall ensure the safe implementation of this procedure promoting
an Incident and Injury Free environment.
3.3 VPCI
3.4 GTC
GTC Global Inc. Site Manager – shall have the overall responsibility for the proper
planning and work implementation at site.
3.5 GTC
GTC Global Inc. Construction Manager – shall be responsible for the proper
implementation of work at site.
3.6 GTC
GTC Global Inc. HSE Supervisor along with the Safety Officer shall ensure
implementation of all safety procedures, safety measures related to the nature of works
being carried out and in accordance with the HSE Plan.
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 4 of 51
3.5 GTC
GTC Global Site Supervisor shall be directly involved in the planning and execution
of the activities. He shall be responsible for the preparation of work plan, safety action
plan and safety.
3.7 GTC
GTC Global QA/QC Engineer – carry out inspection and checking for all quality procedures
in the site and ensure activity at site area as per approved work procedure and inspection test
plan.
4.0 Resources
Site Manager 1
Construction Manager 1
Site Engineer 1
QA/QC Engineer 1
Safety Supervisor and Officer 1
First Aider 1
Foreman 1
Scaffolding Installer 10
Carpenter 8
Steel man 10
Mason 8
Helper 5
Operator 2
Driver 2
Item Description
1 Scaffolding Materials – Tubular &
Coupler
2 Scaffolding Installer / Carpenter / Steel
man Tools
3 Panel Form , Wood , Steel
Reinforcing bars
4 Water Truck – 1 Unit
5 Pump Car 55 Meters – 1 Unit
6 Concrete Transit Mixer – 2 Units
7 Service Stake Truck – Forward
8 Hi Lux Pick Up
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 5 of 51
5.0 Procedure
After the handing over of the Area , Excavation for the subgrade preparation for Mass Lean
Concrete shall be executed including removal of loose soil materials , polyethylene sheet
installation and form installation as required . Mass Lean Concrete will follow and commence
Reinforcing Steel Bar will be installed accordingly for the Mat Foundation Slab Type
considering the installation of Anchor Bolts for the Steel Structure Installation.
Accordingly Structural Concrete pouring of the Mat Foundation Slab should follow after the
completion of Rebar , Form , Anchor Bolts Installation and the Inspection respectively.
Note :
Access going to the CO2 Cylinder House is either from the CCB South Side or from the
Boiler Area .
Install the Structural Framework for the entire shelter consider the installation of the CO2 Gas
After the Installation of the Structural steel frame work of the entire shelter , proceed for the
installation of the Roof Panel & Perimeter Side Panel Wall . The Panel Opening shall be
After the Structural Steel & Panel Installation , consider the work of other discipline prior to
Masinloc Power Plant Expansion Project Doc. No 0-WD884-CA731-00383
Work Procedure for the Rev. No. A
Construction of CO2 Cylinder Page
House 6 of 51
finishing work.
Note :
6.0 Attachment
Attachment #1 :
9 of 51
Attachment #2 :
34 of 51
Attachment #3 :
Risk Assessment