GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION - CIVIL

CAIET DE SARCINI LUCRARI CONSTRUCTII METALICE

Alin Constantin
02 05.2020 Issue for review Prelipceanu Pahontu
Sorin Ionescu

Alin Constantin
01 02.2020 Issued for Use Sorin Ionescu
Prelipceanu Pahontu
Rev. Date Prepared/ Checked/
Description/ Descriere Approved/ Aprobat
No. Data Intocmit Verificat
Doc.
Phase/
No.: TYP-E-E_PETRO-C-XG-002
Faza

EXECUTE/
Doc. No.:
EXECUTIE
Project Title: Page no.:
Pagina nr.:

1 of 31
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 2 of 31

REVISIONS SHEET

Details of revisions made to this document after approval shall be recorded on this sheet.

Rev. Section Description Page

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 3 of 31

TABLE OF CONTENTS CUPRINS

1.0 INTRODUCTION 1.0 INTRODUCERE


1.1 LANGUAGE AND DEFINITION 1.1 DEFINITII SI LIMBA PROIECTULUI
1.2 SCOPE AND PURPOSE OF DOCUMENT 1.2. DOMENIUL SI SCOPUL DOCUMENTULUI
2.0 CODES, STATUTORY REGULATIONS, 2.0 STANDARDE, NORMATIVE,
STANDARD AND GUIDELINES PRESCRIPTII DE EXECUTIE
2.1 ROMANIAN APPLICABLE STANDARDS 2.1. STANDARDE ROMANESTI APLICABILE
2.2 EURONORMS AND ISO NORMS 2.2. EURONORME SI NORME ISO
3.0 GENERAL 3.0 GENERALITATI
4.0 IMPORTANCE CATEGORY AND 4.0 CLASA DE IMPORTANTA SI
IMPORTANCE CLASS OF STEEL WORKS CATEGORIA DE IMPORTANTA
5.0 MATERIALS 5.0 MATERIALE
5.1 STRUCTURAL STEEL 5.1. STRUCTURI DIN OTEL
5.2 STRUCTURAL HOLLOW SECTIONS 5.2. PROFILE TUBULARE
5.3 BOLTS, NUTS, WASHERS (METRIC) 5.3. SURUBURI, PIULITE, SAIBE
6.0 FABRICATION AND SHOP 6.0 FABRICATIE SI DETALII DE ATELIER
DRAWINGS 6.1 CERINTE TEHNICE PENTRU FABRICAREA
6.1 TECHNICAL REQUIREMENTS FOR SHOP IN ATELIER
FABRICATION 6.2 CONDITII TEHNICE DE CALITATE PENTRU
6.2 QUALITY REQUIREMENTS FOR EXECUTIE
CONSTRUCTION 6.3 IMBINARI CU SURUBURI
6.3 BOLTED JOINTS 6.4 EXECUTIA ELEMENTELOR METALICE
6.4 MANUFACTURING OF WELDED METAL SUDATE
PARTS 6.5 TRASAREA
6.5 MARKING 6.6 EXECUTIA ELEMENTELOR METALICE
6.6 EXECUTION OF STEEL STRUCTURE 6.7 GRATARE METALICE
ELEMENTS 6.8 CONTROLUL CALITATII DUPA DEBITARE,
6.7 STEEL GRATINGS INDREPTARE SI PRELUCRAREA MUCHIILOR
6.8 QUALITY CONTROL AFTER CUTTING, 6.9 ASAMBLAREA
STRAIGHTENING OUT AND MACHINING OF 6.10. SUDAREA SUBANSAMBLURILOR
EDGES METALICE
6.9 ASSEMBLING 7.0 CERTIFICAT DE CALITATE
6.10 WELDING METAL SUB-ASSEMBLIES 8.0 DEPOZITARE SI TRANSPORT
7.0 CERTIFICATE OF QUALITY 9.0 CERINTE TEHNICE PENTRU MONTAJ IN
8.0 STORAGE AND TRANSPORT TEREN
9.0 TECHNICAL REQUIREMENTS FOR SITE 9.1 OBLIGATII ALE EXECUTANTULUI
MOUNTING 9.2 CONDIŢII DE CALITATE PENTRU SANTIER
9.1 CONSTRUCTOR’S RESPONSIBILITIES 9.3 VERIFICAREA ŞI RECEPŢIA ELEMENTELOR
9.2 QUALITY REQUIREMENTS FOR THE MONTATE
CONSTRUCITON SITE 9.4 DIVERSE
9.3 INSPECTION AND ACCEPTANCE OF 10.0 SECURITATEA SI SANATATEA IN MUNCA
MOUNTED ELEMENTS
9.4 MISCELLANEOUS
10.0 HEALTH AND SAFETY AT WORK

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 4 of 31

1.0 INTRODUCTION 1.0 INTRODUCERE


OMV PETROM SA – Member of OMV Group is OMV PETROM SA - Membru al Grupului OMV
the largest Romanian oil & gas group with este cel mai mare grup petrolier din România cu
activities in the business segments of exploration activități în segmentele de activitate de explorare
& production, refining as well as marketing of și producție, rafinare și comercializare a gazelor
natural gas in Romania. The document is the civil naturale în România. Documentul reprezinta
works specifications for steel works. The caietul de sarcini pentru executia lucrarillor de
document has been issued according to the confectii metalice. Documentul a fost elaborat in
legislation in force. conformitate cu legislatia in vigoare.
1.1 LANGUAGE AND DEFINITION 1.1 DEFINITII SI LIMBA PROIECTULUI
All project documents, correspondence Toate documentele proiectului, corespondenta si
communication and deliverables shall be in livrabilele trebuie sa fie in limba engleza. Totusi,
English Language. However, the documents documentele care au nevoie de aprobari de la
required seeking permits and approvals from the autoritati trebuie sa fie produse si in limba
authorities and legislations shall be produced in romana. Toate documentele de executie trebuie
Romanian Language. All detailed execution semnate, stampilate de catre verificatori atestati si
documents shall be signed and stamped by vor trebui traduse in limba romana in conformitate
attested checkers and will be translated in cu legislatia in vigoare.
Romanian language according to legislation in
force.
The following definitions are applicable within this Urmatoarele definitii sunt aplicabile in acest
document: document:
 PROJECT means all the surface facilities  PROIECT inseamna toate instalatiile de
associated as specified in the Scope of suprafata asa cum sunt ele specificate in
execution works. Caietul de Sarcini pentru executia lucrarilor de
construire.
 The definition COMPANY shall mean OMV  COMPANIA inseamna OMV Petrom
Petrom.
 The definition CONTRACTOR shall mean a  CONTRACTOR inseamna o entitate legala de
legal business entity (which includes all its afaceri (care include Subcontractorii sai si/sau
Sub Contractors and / or all its affiliates) to afiliati) caruia COMPANIA poate acorda în
whom COMPANY may formally award in full mod oficial, în totalitate sau parțial, lucrarea
or in part, the work defined in the Scope of definită în contract.
Work document.
These definitions are to simplify understanding, Aceste definitii au rolul de a simplifica intelegerea
and are in no way used to imply or commit si nu sunt utilizate în nici un fel pentru a implica
anything further than such understanding. sau a angaja nimic mai mult decât o astfel de
înțelegere.
‘SHALL’ INDICATES A REQUIREMENT; AND „TREBUIE ” indica o cerinta;
‘SHOULD’ INDICATES A RECOMMENDATION. „AR TREBUI” indica o recomandare.
1.2 SCOPE AND PURPOSE OF DOCUMENT 1.2. DOMENIUL SI SCOPUL DOCUMENTULUI

The constructions executed based on this Constructiile realizate pe baza acestui caiet de
technical specification are included in the sarcini sunt incadrate in categoria de importanta
normal and reduced importance category. For normala si redusa. Pentru alte categorii de
other importance categories shall be added importanta trebuie adaugate prevederi speciale.
special requirements.
This document intends to outline the specification Prezentul document intenționează să contureze

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 5 of 31

for the execution of steel elements of construction caietul de sarcini pentru executarea elementelor
objects identified in the project for the contractor. si obiectelor de constructii metalice identificate în
proiectul contractorului.
2.0 CODES, STATUTORY REGULATIONS, 2.0 STANDARDE, NORMATIVE, PRESCRIPTII
STANDARD AND GUIDELINES DE EXECUTIE
The local statutory and legislative regulations Reglementarile legale si legistalive locale au cea
have the highest precedence. mai mare prioritate.
Codes, standards and regulations referred to Codurile, standardele si reglementarile
below shall be of the latest edition and shall be mentionate mai jos trebuie sa fie in vigoare si sunt
applied in the following order of precedence: applicate in urmatoare ordine a precendetei:
 Local regulations (e.g. Law 10/1995, GP121- Legi si normative nationale (ex. Legea 10/1995,
2013, C150-99 etc.) GP121-2013, C150-99 etc.)
 National standards (SR-EN 1993-1-1-2006, Standarde nationale (SR-EN 1993-1-1-2006, etc.)
etc.)
 The provision of correspondent OMV branch Reglementari OMV PETROM
office standard ( if existing)
 International standards (e.g ISO, EN, etc.) Standarde internationale (ex. ISO, EN, etc.)
2.1 ROMANIAN APPLICABLE STANDARDS 2.1. STANDARDE ROMANESTI APLICABILE
 STAS 767/0-88– Civil, industrial and  STAS 767/0-88- Structuri civile, industriale și
agricultural structures. Steel Constructions. agricole. Constructii otel. Conditii tehnice
General technical quality conditions generale de calitate
 STAS 767/2-78 – Civil, industrial and  STAS 767/2-78 - Structuri civile, industriale și
agricultural structures. Bolted and swaged agricole. Suruburi si conexiuni pentru structuri
connections for steel structures. Execution metalice nituite. Exigenta Executie.
exigence.
 STAS 2350-92 – Foundation bolts. Class C  STAS 2350-92 – Buloane de fundatii. Clasa C
 SR ISO/TR581:2011 – Weldability. Metallic  SR ISO/TR581:2011- Sudabilitatea. Materiale
materials. General principles metalice. principii generale
 STAS 8183-80– Steels for tubes for general  STAS 8183-80 - Oteluri pentru tevi de uz
purposes. Grades and technical quality general. Marci și conditii tehnice de calitate
requirements
 STAS 10128-86 - Protection of overground  STAS 10128-86 - Protectia structurilor de otel
steel, structures against corrosion. supraterane împotriva coroziunii. Clasificarea
Classification of aggressive media medii agresive
 STAS 10166/1-77- Protection of aboveground  STAS 10166/1-77- Protectia structurilor de
steel structures against corrosion. Mechanical otel supraterane contra coroziunii. Pregatirea
preparation of surfaces mecanica a suprafetelor
 STAS 10702/1-83– Protection of steel  STAS 10702/1-83- Protectia otel de mai sus
aboveground structures against corrosion. structurilor supraterane împotriva coroziunii.
Protection coatings. General technical Acoperiri de protectie. Cerinte generale
requirements. tehnice
 P100/1-2013- Code of structures design for  P100/1-2013 - Codul de proiectare structuri
earthquake resistance. pentru rezistenta la cutremur.
 P130-1999- Standard on the behavior in time  P130-1999 - Standard al comportarii in timp a
of construction constructiei
 C56-1985- Normative for quality checking and  C56-1985 - Normativ pentru verificarea calitatii
take over of installation construction works. și receptionarea lucrarilor de constructii
montaj.
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 6 of 31

 C133-2014- Technical instructions on  C133-2014 - Instructiuni tehnice privind


combining elements of metal construction with prinderea elementelor de constructii metalice
high strength bolts tensioned cu șuruburi de înalta rezistenta pretensionate
 C 139-87 - Technical instructions for corrosion  C 139-87 - Instructiuni tehnice pentru protectia
protection of steel construction elements anticoroziva a elementelor de constructii din
otel
 C150-99- Normative regarding the quality of  C150-99 - Normativ cu privire la calitatea
steel welded joints of civil, industrial and imbinarilor de structurilor de otel sudate la
agricultural buildings constructiile civile, industriale si agricole.
 NC 001/1999- Normative regarding the  NC 001/1999 - Normativ privind cerintele
requirements established by Law 10/1995 stabilite prin Legea 10/1995
 GE 054-06- Guidance on monitoring the  GE 054-06 - Ghid privind urmarirea
behavior of the operations of corrosion comportarii în exploatare a protectie
protection to steel structures. Intervention anticoroziva a structurilor metalice. Masurile
measures. de interventie.
 GP 121-2013- Design Guide for steel  GP 121-2013 - Ghid de proiectare pentru
structures corrosion protection protectia structurilor din otel la coroziune
2.2 EURONORMS AND ISO NORMS 2.2. EURONORME SI NORME ISO
 SR EN 287-1:2011 - Qualification test of  SR EN 287-1:2011 - Calificarea sudorilor -
welders - Fusion welding - Part 1: Steels Sudare prin topire - Partea 1: Oteluri
 SR EN ISO 19232-1:2013 - Non-destructive  SR EN ISO 19232-1:2013 - Examinari
testing - Image quality of radiographs - Part 1: nedistructive - Calitatea imaginii radiografiilor-
Determination of the image quality value using Partea 1: Determinarea valorii calitatii imaginii
wire-type image quality indicators (ISO 19232- folosind indicatori de calitate a tipului de
1:2013) sârma (ISO 19232-1: 2013)
 SR EN ISO 19232-2:2013 - Non-destructive  SR EN ISO 19232-2:2013 - Examinari
testing - Image quality of radiographs - Part 2: nedistructive - Calitatea imaginii radiografiilor -
Determination of the image quality value using Partea 2: Determinarea valorii calitatative a
step/hole-type image quality indicators (ISO imaginii cu ajutorul unor indicatori de calitate
19232-2:2013) pas / tip gaura (ISO 19232-2: 2013)
 SR EN 10021:2007 - General technical  SR EN 10021:2007 - Conditii generale tehnice
delivery conditions for steel products de livrare pentru produse din otel
 SR EN 10025-1:2005 - Hot rolled products of  SR EN 10025-1:2005 - Produse laminate la
structural steels - Part 1: General technical cald pentru oteluri de constructii - Partea 1:
delivery conditions Conditii tehnice generale de livrare
 SR EN 10025-2:2004 - Hot rolled products of  SR EN 10025-2:2004 - Produse laminate la
structural steels. Part 2: Technical delivery cald pentru oteluri de constructii. Partea 2:
conditions for non-alloy structural steels Conditii tehnice de livrare pentru oteluri de
constructii nealiate
 SR EN 10029:2011 - Hot-rolled steel plates 3  SR EN 10029:2011 – Table de otel laminate la
mm thick or above - Tolerances on cald de 3 mm grosime sau mai groase-
dimensions and shape Tolerante de dimensiuni și de forma
 SR EN 10034:1995 - Structural steel I and H  SR EN 10034:1995 - Otel pentru structuri cu
sections. Tolerances on shape and sectiuni I si H. Tolerante de forma și
dimensions dimensiuni
 SR EN 10055:2000 - Hot rolled steel equal  SR EN 10055:2000 -Otel laminate T cu aripi
flage tees with radiused root and toes. egale şi cu muchii rotunjite. Tolerante de
Dimensions and tolerance on shape and forma și dimensiuni
dimensions
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 7 of 31

 SR EN 10056-1:2017 - Structural steel equal  SR EN 10056-1:2017 - Otel pentru structuri


and unequal leg angles. Part 1: Dimensions din cornier cu aripi egale și inegale . Partea 1:
Dimensiuni
 SR EN 10056-2:1996 - Structural steel equal  SR EN 10056-2:1996 - Otel pentru structuri
and unequal leg angles. Part 2: Tolerances on din cornier cu aripi egale și inegale: Partea 2:
shape and dimensions Tolerante si de forma si dimensiuni
 SR EN 10204:2005 - Metallic products - Types  SR EN 10204:2005 - Produse metalice - Tipuri
of inspection documents de documente de inspectie
 SR EN 10210-1:2006 - Hot finished structural  SR EN 10210-1:2006 – Elemente structurale
hollow sections of non-alloy and fine grain finisate la cald pentru sectiunile cu goluri de
steels - Part 1: Technical delivery conditions otel nealiate și oteluri cu granulatie fina -
Partea 1: Conditii tehnice de livrare
 SR EN 10279:2002 - Hot rolled steel channels  SR EN 10279:2002 - Profilele U laminate la
- Tolerances on shape, dimensions and mass cald din otel. - Tolerante de forma,
dimensiunile și masa
 SR EN 10346:2015 - Continuously hot-dip  SR EN 10346:2015 – Acoperirea prin imersie
coated steel flat products - Technical delivery a platbandelor - Conditii tehnice de livrare
conditions
 SR EN 14399-1:2015 - High-strength  SR EN 14399-1:2015 - Asamblarea de înalta
structural bolting assemblies for preloading - rezistenta cu șuruburi pretensionate pentru
Part 1: General requirements structuri - Partea 1: Cerinte generale
 SR EN 22553:1995 - Welded, brazed and  SR EN 22553:1995 – Sudarea si lipirea
soldered joints. Symbolic reprezentation on imbinarilor sudate. Reprezentarea simbolica
drawings pe desene
 SR EN ISO 898-1:2013 - Mechanical  SR EN ISO 898-1:2013 - Proprietati mecanice
properties of fasteners made of carbon steel ale elementelor de asamblare din otel carbon
and alloy steel - Part 1: Bolts, screws and și otel aliat - Partea 1: Șuruburi, șuruburi și
studs with specified property classes - Coarse prezoane cu clase de proprietate specifice- -
thread and fine pitch thread (ISO 898-1:2013) filete regulate și filet pas fin (ISO 898-1: 2013)
 SR EN ISO 898-2:2012 - Mechanical  SR EN ISO 898-2:2012 - Proprietati mecanice
properties of fasteners made of carbon steel ale elementelor de asamblare din otel carbon
and alloy steel - Part 2: Nuts with specified și otel aliat - Partea 2: Piulite cu clasele de
property classes - Coarse thread and fine proprietate specificate - Filete regulate și filet
pitch thread (ISO 898-2:2012) pas fin (ISO 898-2: 2012)
 SR EN ISO 1461:2009 - Hot dip galvanized  SR EN ISO 1461:2009 - Acoperiri termice cu
coatings on fabricated iron and steel articles - zinc prin imersare , ale elementelor de fonta și
Specifications and test methods (ISO otel- Specificatii și metode de încercare (ISO
1461:2009) 1461: 2009)
 SR EN ISO 4014:2011 - Hexagon head bolts -  SR EN ISO 4014:2011 - Șuruburi cu cap
Product grades A and B (ISO 4014:2011) hexagonal - clasele de produse A și B (ISO
4014: 2011)
 SR EN ISO 4032:2013 - Hexagon regular nuts  SR EN ISO 4032:2013 - Piulite hexagonale
(style 1) - Product grades A and B (ISO regulate (stil 1) - clasele de produse A și B
4032:2012) (ISO 4032: 2012)
 SR EN ISO 4759-1:2003 - Tolerances for  SR EN ISO 4759-1:2003 - Tolerante pentru
fasteners. Part 1: Bolts, screws, studs and elemente de fixare. Partea 1: Șuruburi,
nuts. Product grades A, B and C. șuruburi, prezoane și piulite. Gradele de
produse A, B și C.
 SR EN ISO 7090:2002 - Plain washers,  SR EN ISO 7090:2002 – Șaibe plate, teșite -
chamfered - Normal series - Product grade A serie normala - calitate de produse A (ISO
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 8 of 31

(ISO 7090:2000) 7090: 2000)


 SR EN ISO 8501-1:2007 - Preparation of  SR EN ISO 8501-1:2007- Pregatirea
steel substrates before application of paints suporturilor de otel înaintea aplicarii vopselelor
and related products - Visual assessment of și produselor similare - Evaluarea vizuala a
surface cleanliness - Part 1: Rust grades and curateniei suprafetei - Partea 1: clasele de
preparation grades of uncoated steel rugina și gradele de pregatire a suporturilor de
substrates and of steel substrates after overall otel neacoperite și a suporturilor de otel dupa
removal of previous coatings (ISO 8501- îndepartarea totala a acoperirilor anterioare
1:2007) (ISO 8501-1: 2007)
 SR EN ISO 8501-2:2002 - Preparation of steel  SR EN ISO 8501-2:2002 - Pregatirea
substrates before application of paints and suporturilor de otel înaintea aplicarii vopselelor
related products - Visual assessment of și produselor similare - Evaluarea vizuala a
surface cleanliness - Part 2: preparation curateniei suprafetei - Partea 2: gradele de
grades of previously coated steel substrates pregatire a suporturilor de otel acoperite
after localized removal of previous coatings anterior, dupa îndepartarea locala a
(ISO 8501-2:1994) acoperirilor anterioare (ISO 8501-2: 1994)
 SR EN ISO 8501-3:2007 - Preparation of steel  SR EN ISO 8501-3:2007 - Pregatirea
substrates before application of paints and suporturilor de otel înaintea aplicarii vopselelor
related products - Visual assessment of și produselor similare - Evaluarea vizuala a
surface cleanliness - Part 3: Preparation curateniei suprafetei - Partea 3: Gradele de
grades of welds, edges and other areas with pregatire a sudurii, margini și alte suprafete cu
surface imperfections (ISO 8501-3:2006) imperfectiuni (ISO 8501-3: 2006)
 SR EN ISO 8501-4:2007 - Preparation of steel  SR EN ISO 8501-4:2007 - Pregatirea
substrates before application of paints and suporturilor de otel înaintea aplicarii vopselelor
related products - Visual assessment of și produselor similare - Evaluarea vizuala a
surface cleanliness - Part 4: Initial surface curateniei suprafetei - Partea 4: Conditii ale
conditions, preparation grades and flash rust suprafetei initiale, clasele de pregatire și
grades in connection with high-pressure water gradele de aparitie rapida a ruginei în legatura
jetting (ISO 8501-4:2006) cu un jet de apa la presiune ridicata (ISO
8501-4: 2006)
 SR EN ISO 13920:1998 - Welding. General  SR EN ISO 13920:1998 - Sudura. Tolerante
tolerances for welded constructions. generale pentru constructii sudate. Dimensiuni
Dimensions for lengths and angles. Shape pentru lungimi și unghiuri. Forma și pozitia
and position
 SR EN ISO 2560-2010 Welding consumables.  SR EN ISO 2560-2010 Materiale pentru
Covered electrodes for manual metal arc sudare. Electrozi inveliti pentru sudarea
welding of non-alloy and fine grain steels. manuala cu arc electric a otelurilor nealiate si
Clasification. cu granulatie fina. Clasificare.
 SR EN 10684 -Fasteners — Hot dip  SR EN 10684 Elemente de asamblare.
galvanized coatings Acoperiri prin galvanizare la cald
 DTR-0595-U.C.05-HQ-TRE-021_Civil and  DTR-0595-U.C.05-HQ-TRE-021_Specificatie
Structural Design Specification - Onshore pentru proiectarea constructiilor si structurilor
3.0 GENERAL 3.0 GENERALITATI
This document contains the technical specification Documentul contine specificatii tehnice pentru
for execution of steel structures, including: executia constructiilor metalice, inclusiv:
 Steel piperaks and pipe supports;  Estacade metalice, suporti metalici pentru
conducte;
 Steel foot bridges, platforms and access  Supratraversarii conducte, platforme si scari
ladders and gratings. de acces si gratare.
 Building steel structures  Structuri metalice pentru cladiri
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 9 of 31

The steel structure shall be constructed and Constructia metalica se va realiza si instala in
installed in accordance with the technical conformitate cu documentatia tehnica
documentation .
The requirements below shall be complied with, Urmatoarele cerinte se vor respecta pe parcursul
during construction and installation: executiei si montajului:
 These technical requirements cover  Cerintele tehnice cuprind specificatii si
specifications and requirements for the shop cerintele pentru executia in atelier si montajul
fabrication and site installation of the steel in teren a constructiilor metalice;
structure;
 Details from technical documentation  Detaliile din documentatia tehnica
Welding shall be electrical in accordance with SR Sudura se va realiza electric in conformitate cu
ISO/TR 581:2011 and the electrodes shall be SR ISO/TR 581:2011 iar electrozii vor respecta
according to SR EN ISO 2560:2010, in SR EN ISO 2560:2010 si specficatiile din
compliance with the technical documentation documentatia tehnica.
specifications.
The technical requirements include: Cerintele tehnice includ:
 technical requirements for construction;  Cerinte tehnice pentru executie;
 technical requirements for installation.  Cerinte tehnice pentru montaj.
Steel structures shall be constructed in Constructiile metalice se vor realiza in
accordance with STAS 767/0-88 and normatives conformitate cu STAS 767/0-88 si normativele C
C 150-99, C 56-85. 150-99, C 56-85.
Fabrication and installation of steel structures Uzinarea şi montajul construcţiilor metalice vor fi
shall be carried out only by entities that meet the făcute numai de unităţi care întrunesc condiţiile
legal requirements for the authorization of such specificate în dispoziţiile legale care
activities. reglementează aceste activităţi.
The fabrication of the steel. The fabrication of the Uzinarea confectiilor metalice se va face exclusiv
steel structures also includes the execution of in fabrica. Uzinarea confectiilor metalice cuprinde
corrosion protection layers. inclusiv aplicarea straturilor de protectie
anticoroziva.
The thickness of gusset plates and stiffening Grosimea guseelor si a placilor de rigidizare va fi
plates shall be identical to the one indicated in the identica cu cea indicate in desenele de proiect
project drawings
The constructor shall supply al auxiliary elements Executantulva , furniza toate elementele
required for site instalation. temporare necesare montajului in teren al
structurilor.
Constructor shall assure acces for mounting of Constructorul va asigura accesul in vederea
steel elements and also for mounting and montajului structurilor metalice precum si pentru
dismantling of auxiliary elements used for montarea si demontarea elementelor auxiliare
structure instalation. utilizate pe durata montajului.
Checks on the quality of the steel structure Verificarea calităţii elementelor construcţiilor
elements shall be carried out in accordance with metalice se va realiza in conformitate cu STAS
STAS 767/0-88, normatives C 150-99, C 56-85 767/0-88, normativele C 150-99, C 56-85 caietul
book XIX and Art. 23 of Law 10/85. XIX si Art. 23 legea 10/85.
The steel structure constructor shall be Executantul constructiei metalice are obligatia sa
responsible to notify the designated authorities anunte autoritatile competente privind participarea
who have to attend the inspection of works at hold la inspectia lucrarilor la fazele determinate si sa
points and ensure the inspection requirements are asigure indeplinirea cerintelor de inspectie in
met in order to obtain the approval to proceed vederea obtinerii acordului pentru continuarea
with the works. lucrarilor.

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 10 of 31

4.0 IMPORTANCE CATEGORY AND 4.0 CLASA DE IMPORTANTA SI CATEGORIA


IMPORTANCE CLASS OF STEEL WORKS DE IMPORTANTA
Importance Category, as per HG 766/1997 is “C”. Categoria de importanta, conform HG 766/1997
este “C”.
Importance Class, as per Cod P100-1/2013 is Clasa de importanta, conform P100-1/2013 este
“III”. “III”.
For a construction that complies with a higher Pentru o constructie avand o categorie superioara
category than above, shall be prepared an Annex celei de mai sus, trebuie elaborata o anexa la
to this specification with specific requirements of aceasta specificatie cu cerintele specifice din
that category.The acceptance level and category aceasta categorie. Nivelul de acceptare si
of execution of welded steel structures are categoria de executie a elementelor sudate sunt
indicated in the drawings and calculation notes. notate in desene si breviarul de calcul.
5.0 MATERIALS 5.0 MATERIALE
All the construction materials shall be new and Toate materialele pentru executie vor fi noi si vor
shall meet the quality requirements stipulated in respecta cerintele de calitate stipulate in
the above standards and the sections below. standardele sus mentionate si in capitolele
urmatoare.
5.1 STRUCTURAL STEEL 5.1. STRUCTURI DIN OTEL
All structural steel for main structures shall be as Otelul pentru structurile metalice este specificat in
specified in the projectin accordance with SR EN proiect in conformitate cu SR EN 10025-2:2006.
10025-2 :2006.
Material test reports shall be in accordance with Rapoartele de teste pe materiale respecta SR EN
SR EN 10021 :2007 and SR EN 10204 :2005. 10021 : 2007 si SR EN 10204:2005.
Plates and sections in thicknesses above 40 mm Placile si profilele cu grosimi de peste 40 mm vor
shall have the resiliance specified in the project. vor avea rezilienta indicata in proiect.
Hot rolled plates shall will have the tickness Placile laminate la cald au grosimea indicata in
specified in the project but no less than 4mm. proiect dar nu mai putin de 4 mm.
5.2 STRUCTURAL HOLLOW SECTIONS 5.2. PROFILE TUBULARE
Structural hollow sections hot finished at and Profilele tubulare laminate la cald si la o
average temperature of 920°C, in accordance temperatura medie de 920°C, in conformitate cu
with SR EN 10210-1 :2006, shall be made of steel SR EN 10210-1:2006, se vor realiza din otel
certified by document of inspection 3.1B, as per certificat prin documentul de inspectie de tip 3.1B,
SR EN 10025-2 : 2006. conform SR EN 10025-2:2006.
5.3 BOLTS, NUTS, WASHERS (METRIC) 5.3. SURUBURI, PIULITE, SAIBE

5.3.1 GENERAL 5.3.1. GENERALITATI


Bolts, nuts, and washers shall be hot-dip Suruburile, piulitele si saibele se vor galvaniza
galvanized according to SR EN ISO 10684:2004, prin scufundare la cald conform SR EN ISO
except the anchorbolts for foundations. 10684:2004, cu exceptia suruburilor de fundatie.
It is preferable to use only one supplier of bolts, Este de preferat sa se foloseasca un singur
nuts and washers for the entire project. Bolts, nuts fabricant de suruburi, piulite si saibe pentru
and washers from different suppliers, if any, shall intregul proiect. Suruburile, piulitele si saibele de
nor be combine and only one type of finishing la producatori diferiti, daca exista, nu vor fi
shall be used for the entire project. combinate, si numai un singur tip de finisaj va fi
folosit pentru intreaga lucrare.
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 11 of 31

Bolt diameter, including length, shall be indicated Diametrul suruburilor, inclusiv lungimea acestora
clearly in the detail design. sunt indicate in mod clar in desenele de executie.
Bolt diameters shall comply with SR EN ISO Diametrele suruburilor respecta SR EN ISO
4014:2011. 4014:2011.
Nut diameters shall comply with SR EN ISO 4032 Diametrele piulitelor respecta SR EN ISO
:2013. 4032:2002.
Round washers for hexagonal bolts and nuts shall Saibele rotunde pentru piulite si suruburi
be beveled and shall comply with SR EN ISO hexagonale sunt sanfrenate si respecta SR EN
7090 :2002. ISO 7090:2002.
5.3.2 TYPE OF BOLTS 5.3.2. TIPURI DE SURUBURI
The follow type of bolts shall be used for fixing Pentru fixarea si imbinarea constructiilor metalice
and/or joining structural steel : se vor utiliza urmatoarele tipuri de suruburi:
Standard Carbon Steel Bolts shall be hot deep Suruburi standard din otel carbon sunt
galvanized galvanizate la cald.
Standard bolts shall be used for steel structures. Suruburi standard de clasa si diametru sunt
specificate in desenesi sunt utilizate pentru
constructii metalice.
The grade of tolerance applies to all the bolts Gradul de toleranta se aplica tuturor suruburilor
according to SR EN ISO 4759-1 :2003. conform SR EN ISO 4759-1:2003.
The class for bolts according indicated in the Clasa de calitate pentru suruburi este indicata in
project drawings according to SR EN ISO 898-1 desene conform SR EN ISO 898-1:2013.
:2013.
Class for nuts is indicated in the project drawings Clasa pentru piulite este indicata in desene
and is according to SR EN ISO 898-2 :2012. conform SR EN ISO 898-2:2012.
Class for washers is indicated in the project Clasa de calitate pentru saibe este indicata in
drawings according to SR EN ISO 7090 :2002. desene conform SR EN ISO 7090 :2002.
6.0 FABRICATION AND SHOP DRAWINGS 6.0 FABRICATIE SI DETALII DE ATELIER
All the fabrication and shop drawings shall comply Toate cerintele de detaliere si fabricatie din atelier
with the general drawings, detail drawings, sunt conforme cu desenele generale, cu
standard drawings and the requirements below. desenele de detaliu, cu desenele standard si
cerintele indicate mai jos.
6.1 TECHNICAL REQUIREMENTS FOR SHOP 6.1 CERINTE TEHNICE PENTRU
FABRICATION FABRICAREA IN ATELIER
The constructor of steel structures (structures, Unitatea care execută construcţii metalice
columns, beams, rails etc.) shall be authorized for (structuri, stîlpi, grinzi, căi de rulare etc.) va fi
the construction of such items. The constructor autorizată pentru execuţia acestor lucrări. Această
shall have the duties and responsibilities provided unitate are obligaţiile şi răspunderile prevăzute la
for in Art. 23 of Law 10/95 and the regulations art. 23 din legea 10/95 şi regulamentele privind
regarding the management and quality assurance conducerea şi asigurarea calităţi în construcţii,
for construction works approved by GO 766/97. aprobate cu H.G.R. 766/97.
The constructor shall check the project quality as Executantul va verifica calitatea proiectului astfel:
follows :
 The project content shall comply with Art.  Continutul proiectului va respecta Art. 1.4.1
1.4.1 of STAS 767/0-88 and Art. 5.1 of SR EN din STAS 767/0-88 si Art. 5.1 din SR EN
1993-1-1 :2006/NA :2008 and the project 1993-1-1:2006/NA:2008 iar desenele de
drawings shall comply with STAS 9773-88. proiect vor respecta STAS 9773-88.
 The constructor shall notify the designer of all  Executantul va notifica proiectantul in legatura
the discrepancies found in the project. cu toate neconcordantele constatate in
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 12 of 31

proiect.
 The constructor shall prepare the technical  Executantul va intocmi documentatia tehnica
documentation for fabrication provided for de uzinare prevazuta in Art. 1.4.2. din STAS
under Art. 1.4.2. of STAS 767/0-88 and Art. 3 767/0-88 si Art. 3 din C 150-99.
of C 150-99.
 The constructor shall comply with the project  Executantul va respecta prevederile
provisions (drawings, written notes on proiectului (desene, note scrise, caiet de
drawings, scope of work and minimum sarcini si numarul minim de specificatii
specifications listed under Art. 1.2.) during enumerate in Art. 1.2.) pe parcursul executiei.
construction. The constructor may add his Executantul poate adauga propriile specificatii
own specifications to such specifications for de fabricatie conform Art. 2.1.3.
fabrication, as indicated under Art. 2.1.3.
 The constructor shall notify the designer of the  Executantul va notifica proiectantul privind
construction start so that the designer can inceperea executiei astfel incat proiectantul sa
organize his own inspection of works. iti poata organiza propria inspectie a lucrarilor.
6.2 QUALITY REQUIREMENTS FOR 6.2 CONDITII TEHNICE DE CALITATE
CONSTRUCTION PENTRU EXECUTIE
Only the materials (types, quantity, quality) Se vor utiliza numai materialele (tipuri, calitate,
specified in the project (drawings and cantitate) specificate in proiect (desene si
documentation) shall be used in compliance with documentatie) conform STAS 767/0-88 Art. 2.1. si
STAS 767/0-88 Art. 2.1. and 2.2. 2.2.
Under this project materials shall not be replaced Nu se vor inlocui materialele fara aprobarea
without the approval of the designer, Modification proiectantului. Modificarea materialelor se va face
of the materiales used in the projects shall be exclusiv de catre proiectant prin dispozitie de
made only by the designer with site instruction santier cu acordul OMV PETROM.
and also with the approval of OMV PETROM.
The shape, size and elevation of designed Nu se va modifica forma, dimensiunea si elevatia
elements shall not be modified. Exceptionally, elementelor proiectate. In mod exceptional,
such data can be modified only with designer and aceste date se modifica de catre proiectant cu
beneficiary approval(for structural and stability acordul beneficiarului. (pentru elementele de
elements). rezistenta si stabilitate).
Permissible deviations from shape and size are Abaterile limita la forma si dimensiuni sunt
shown in STAS 767/0-88 Art. 2.3., unless prezentate in STAS 767/0-88 Art. 2.3. daca nu se
otherwise specified in the project. specifica altfel in proiect.
Construction shall be carried out in accordance Executia se va realiza conform tehnologiei proprii
with constructor’s in-house technology as a executantului conform cap 9.1. Parametrii
indicated under chapter 9.1 Such technology aferenti tehnologiei respective vor fi cel putin egali
parameters shall be at least equal to thise cu cei specificati in STAS 767/0-88 cap. 3 si
specified in STAS 767/0-88 ch. 3 and C150-99 ch. C150-99 cap. 3.
3.
The mandatory requirements for inspection and Cerintele obligatorii privind verificarea si receptia
aceptance are listed in STAS 767/0-88 ch. 4, ch. sunt enumerate in STAS 767/0-88 cap. 4, cap. 5
5 art.5.1, C150-99 ch. 4.5, pct.5.1 – 5.8 and C 56- art.5.1, C150-99 cap. 4.5, pct.5.1 – 5.8 si C 56-85
85 book XIX regarding fabrication. caietul XIX privind uzinarea.
For the main elements to be bolt joined on site, Pentru elementele principale care se vor îmbina
shop preassembly and the size measurement cu şuruburi în şantier, este obligatorie
sheet are mandatory. preasamblarea în uzină, cu fişa de măsurători
pentru dimensiuni.
Upon delivery the shop machined elements shall Expedierea elementelor uzinate în şantier va fi
be accompanied by legal quality documents. însoţită de documentele legale care atestă
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 13 of 31

calitatea.
The minimum documents listed below shall be Dintre acestea menţionăm minim:
delivered as well:
 Quality certificate according to C 150-99;  certificatul de calitate conform C 150-99
 Test reports;  buletinele de încercări
 Size measurement sheets for main  fişele de măsurători dimensionale ale
subassemblies (columns, beams etc). subansamblelor principale (stâlpi grinzi etc)
 List of welders and related stamps;  lista sudorilor cu poansonul fiecăruia
 Reports of hidden works (if applicable).  procesele verbale de lucrări ascunse (pentru
Reperele care au acest caracter)
6.3 BOLTED JOINTS 6.3 IMBINARI CU SURUBURI
The steel column base plate shall have holes up Placile de la baza stilpilor de otel vor avea gauri
to 6 mm larger than the diameter of anchor bolts cu 6 mm mai largi pana la diametrul suruburilor de
M24 and up to 10 mm or larger in diameter for ancorare M24 si cu 10 mm pentru diametrul de
anchor bolts M27 surub de ancorare M 27 sau mai mare.
The diameters of the other bolt holes shall not Diametrul celorlalte gauri pentru suruburi nu va fi
exceed diameter indicated in the project details. mai mare decât diametrul indicat in detaliile
Bolt slots shall be drilled. proiectului. Locasurile pentru suruburi vor fi
gaurite.
Bolts shall not extend beyond a nut or tapped hole Suruburile nu trebuie sa se extinda peste piulita
by 10 mm neither shall they be shorter by 3 mm sau gaura fileata cu 10mm si nu trebuie sa fie mai
than the nut or tapped hole. scurte cu 3mm decat piulita sau gaura filetata.
Prior to tightening any bolts the joint shall be Inainte de strangerea oricaror suruburi, imbinarea
slightly tightened using sufficient bolts to ensure va fi stransa uşor, cu un numar suficient de
the contact of surfaces suruburi, astfel incat suprafetele sa fie in contact.
For screws used in this case: Pentru suruburile utilizate in acest caz:
The tightening torques for structural bolts are Momentul de strangere pentru suruburile
available in C133-2014. structural sunt date in normativul C133-2014.

Nr. Nominal Grade Final 50% from Nr. Diametrul Grupa Momentul 50% din
crt. diameter tightening the final crt. nominal final momentul
torques tightening de final de
(daNm) torques strângere strângere
(daNm) (daNm) (daNm)
1 M12 10.9 25÷50 12.5÷25 1 M12 10.9 25÷50 12.5÷25
2 M16 10.9 50÷80 25÷40 2 M16 10.9 50÷80 25÷40
3 M20 10.9 80÷110 40÷55 3 M20 10.9 80÷110 40÷55
4 M24 10.9 140÷190 70÷95 4 M24 10.9 140÷190 70÷95
5 M27 10.9 185 92.5 5 M27 10.9 185 92.5
6 M12 8.8 10÷25 5÷12.5 6 M12 8.8 10÷25 5÷12.5
7 M16 8.8 25÷40 12.5÷20 7 M16 8.8 25÷40 12.5÷20
8 M20 8.8 50÷75 25÷37.5 8 M20 8.8 50÷75 25÷37.5
9 M24 8.8 85÷125 42.5 9 M24 8.8 85÷125 42.5
÷62.5 ÷62.5
6.4 MANUFACTURING OF WELDED METAL 6.4 EXECUTIA ELEMENTELOR METALICE
PARTS SUDATE
Metal parts have to be inspected in terms of Profilele laminate trebuie sa fie controlate din
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 14 of 31

quality, condition and appearance as well as of punct de vedere al calitatii, starii si aspectului lor,
possible rolling defects precum si al eventualelor defecte de laminare.
The compliance of the data with the project Pe baza numarului de sarja imprimata pe
requirements, standards and metal specification laminate ca si pe baza buletinelor de analiza si
shall be checked based on the heat number incercari mecanice se va verifica corespondenta
marked on the parts and the mechanical analysis datelor cu cerintele proiectului, standardelor si
and mechanical test reports specificatiei de metal.
The condition of parts and their possible rolling Prin examinarea exterioara pe ambele fete se va
defects shall be established following the external stabili starea pieselor si eventualele defecte de
examination of both sides of the parts. laminare.
Parts shall be cleaned from rust, mud, oil or paint Laminatele ruginite, murdare de noroi, ulei sau
prior to machining. vopsea se vor curata inainte de prelucrare.
Parts containing defects such as lamination, Laminatele cu defecte ca: stratificari, suprapuneri,
overlaps, pores, cracks, inclusions and other sufluri, fisuri, incluziuni sau alte defecte
unacceptable defects, as well as those with neadmisibile, ca si cele cu abateri dimensionale
dimensional deviations exceeding those allowed peste cele admise prin standarde sau prezenta
by standards or this specification will not be used specificatie nu vor fi folosite la executia
for the construction of a welded steel structure. constructiei metalice sudate.
The parties may agree to perform an ultrasonic Se poate face si un control ultrasonic, prin
examination if this is necessary and if the intelegere intre parti, in masura in care acest lucru
technical capabilities are available. va aparea necesar si in functie de posibilitatile
tehnice.
Machining of parts without their previous Prelucrarea laminatelor fara indreptarea lor
straightening out is allowed in case the deviations prealabila este admisa in cazul in care abaterile
from the proper geometric form do not exceed the fata de forma lor geometrica corecta, nu
allowances covered in the applicable standards depasesc tolerantele cuprinse in standardele in
(STAS 767-0/88) or detail engineering. vigoare (STAS 767-0/88) sau pe cele indicate in
detaliile de executie.
The parts showing deformations exceeding those Laminatele care prezinta deformatii mai mari ca
mentioned above shall be straightened out before cele mentionate mai sus, trebuie indreptate
marking and cutting. inainte de trasare si debitare.
The parts shall be straightened out in accordance Indreptarea laminatelor se face in conditiile
with the requirements contained in applicable precizate in prescriptiile in vigoare.
specifications.
Cold straightenting is allowed only if deformations Indreptarea la rece este admisa numai daca
do not exceed the values contained in the deformatiile nu depasesc valorile din standardele
applicable standards for such parts. pentru laminate in vigoare
6.5 MARKING 6.5 TRASAREA
The metallic structures shall be constructed in Constructiile metalice se vor executa conform
compliance with the detail engineering using detaliilor din proiect, folosind tehnologia proprie
specialized shop technology. fiecarui atelier specializat.
The marking accuracy shall be 1.00 mm unless Trasarea se va executa cu precizie de 1.00 mm
higher accuracy is provided for in the project. daca in proiect nu se prevede o precizie mai
mare.
Accumulation of tolerances is not allowed for one Nu se admite acumularea mai multor tolerante pe
dimension. aceeasi linie de cotare.
Marking shall be carried out with instruments that Trasarea se efectueaza cu instrumente verificate
have been verified and compared to officially si comparate cu etaloanele de control verificate
verified control gauges or with special equipment. oficial sau cu instalatii speciale.
The templates shall indicate: the project symbol, Pe sabloane se scriu: simbolul lucrarii, numarul
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 15 of 31

drawing number, position of parts, diameter of desenului, pozitia pieselor, diametrul gaurilor,
holes, number of parts of the same size and numarul pieselor cu aceleasi, dimensiuni si
characteristics, etc. caracteristici, etc.
When establishing the size for marking and La stabilirea cotelor din trasare si debitare a
cutting materials it should be taken into account materialelor se va tine seama ca valorile cotelor
that the project size shall be the final size that has din proiect sa fie cele finale, care trebuie realizate
to be achieved at the completion of the entire dupa incheierea intregului proces tehnologic de
machining process. uzinare.
The orientation of parts against the rolling Orientarea pieselor fata de directia de laminare
direction is irelevant unless otherwise stated in poate fi oricare, daca in proiect nu se prevede
the project. altcum.
After marking and before cutting, the heat number Dupa trasare, inainte de executarea taierii se va
of the sheet shall be punched on each marked marca prin poansonare pe fiecare piesa trasata
part. sarja din care face parte tabla.
Also, on the parts shall be painted (or punched) De asemenea, piesele vor fi marcate prin vopsire
the position number according to the project or (sau poansonare) cu numarul de pozitie al piesei
operations plan. conform proiectului sau planului de operatii.
The proper marking of parts shall be inspected Verificarea executarii corecte a marcajului pe
randomly by the QA officer. The tracer shall not piese va fi efectuata prin sondaj de responsabilul
be exempt from liability. AQ, trasatorul nefiind scutit de raspundere.
6.6 EXECUTION OF STEEL STRUCTURE 6.6 EXECUTIA ELEMENTELOR METALICE
ELEMENTS
The parts shall be cut using sheet shears, saws, Taierea pieselor se face cu foarfeca, cu
plasma or laser, the recommended method being fierastraul, cu plasma sau cu laser, folosindu-se
mainly mechanized cutting. cu precadere taierea mecanizata.
Structural steels are usually laser and plasma cut Elementele structurale sunt de regula taiate
in special for steel plates. folosind laser sau plasma in special pentru table.
Thin sheet and plate metals ( < 12 mm ) can be Tablele subtiri si placile metalice ( < 12 mm ) pot fi
cut by guillotine. The shared edge is severely cold taiate folosind ghilotina ( foarfeca). Marginea
strained and in some carbon steel may offer pure taiata este deformata sever prin procedeul de
fracture toughness if welded.This cutting taiere la rece si pentru anumite tipuri de otel
procedure is not recomanded except for plates up carbon se poate produce o crapatura in cazul in
to 4mm thick. care acestea sunt sudate. Acest procedeu nu este
recomandat decat pentru table cu grosimea de
4mm.
Electric arc and oxiacetilenic flame cutting and Nu se admit taierile si prelucrarile cu arcul electric
finishing are not allowed. si flacara oxiacetilenica.
Machining (bevelling) of edges of parts that have Prelucrarea muchiilor (sanfrenarea) pieselor ce
to be weld joined is mandatory and shall be trebuie imbinate prin sudura este obligatorie si se
carried out according to the manufacturing va executa conform procesului tehnologic de
procedure. executie.
Bevelling can be carried out using mechanical Prelucrarea muchiilor se poate executa atat cu
equipment (cutting machines) or mechanized mijloace mecanice (ex, prin aschiere) cat si
equipment. mecanizat.
The edges of shear or saws cuts require no Marginile taieturilor executate cu foarfeca sau
further machining if the quality of cuts complies laser nu mai necesita prelucrarea prin aschiere
with quality class 1.2.1 of SR EN ISO 9013 – daca se asigura taieturi de clasa de calitate 1.2.1
1998. conform SR EN ISO 9013 – 1998.
The parts of which shape shows entering angles Piesele al caror contur prezinta unghiuri intrande
shall be previously bored at the top of the angle se gauresc in prealabil in varful unghiului cu un
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 16 of 31

using a min 25 mm diameter drill. burghiu avand diametrul de minim 25 mm.


If a copy cutting machine is used, the entering In cazul taierii cu o masina de debitat, la
angles have to be provided with a min 25 mm unghiurile intrande trebuie asigurata o racordare
diameter joining passage and then grinded. cu diametrul de minim 25 mm, urmata de polizare.
Each piece cut from a sheet shall be marked in Pe fiecare piesa taiata dintr-o tabla se va aplica
paint or shall be punched as indicated below. un marcaj prin vopsire si poansonare, prin care se
noteaza:
 Part number according to the item number of  Numarul piesei conform marcii din desenele
the shop drawings and the indicative of the deexecutie si eventual indicativul elementului
element it will be be part of: la care se foloseste
 plate mark and quality class;  marca si clasa de calitate a tablei;
 the number of the plate batch.  numarul lotului din care provine.
The joint type shall be provided for in Tipul imbinarii este prevazut in proiect.
documentation.
The manufacturer shall examine such types and Uzina trebuie sa examineze aceste tipuri si sa
propose modifications to the design engineer if faca proiectantului propuneri de modificari, daca
thus manufacturing can be simplified without prin acestea se usureaza executia, fara a
impacting on the seam quality. modifica calitatea cordonului de sudura.
The geometry of joints (angle, size of unbevelled Geometria rosturilor (unghiul, marimea muchiilor
edges, opening of joints, etc) as well as the shape netesite, deschiderea rosturilor, etc.) ca si forma
of edge machining for welding factory are chosen prelucrarii muchiilor in vederea sudarii se alege
depending on the type of joint provided for in the de uzina in functie de tipul imbinarii prevazute in
project,the welding procedure used and the proiect, de procedeul de sudare folosit si de
thickness of the pieces, taking into account the grosimea pieselor, tinand seama de prevederile
requirements of SR EN ISO 9692-1/2004 for din SR EN ISO 9692-1/2004 pentru sudarea cu
manual arc welding. arc electric cu electrod invelit.
Such shapes have to be provided for in Aceste forme trebuie prevazute in tehnologia de
manufacturer’s welding procedure. sudare intocmita de uzina.
The size of the cut parts shall be so designed that Dimensiunile pieselor taiate trebuie astfel
the allowable deviations are not exceeded after realizate incat dupa sudarea definitiva sa nu se
the final welding. depaseasca abaterile admise.

6.7 STEEL GRATINGS 6.7 GRATARE METALICE


Steel grates type SP plain or serrated non-slip Gratarele metalice tip SP antialunecare sau
shall be used for stair treads and steel platform, netede vor fi folosite pentru trepte de scara si
with standard nosing unless otherwise specified platforme din otel, cu dimensiunea ochiurilor
on the drawings. Bearing bars and transversal standard, daca nu se specifica altfel pe desene.
bars will be Ø4 diameter - S235 according to SR Barele de rezistenta si barele transversale vor fi
EN 10025-2/2004 de diametru Ø4 - S235 in concordanta cu SR EN
The cross section: 10025-2/2004.
Bearing (main) bars/ plates different dimensions, Secțiunea transversală:
usually 30 mm × 3 mm and will be spaced 30 mm Barele (plăcile principale) / plăci de dimensiuni
center to center. diferite, de obicei 30 mm × 3 mm și vor fi
Transversal bars twisted round steel will be Ø4. distanțate de 30 mm în centru.
Contractor shall provide only on shop the opening Bare transversale din oțel rotund rotunjit vor avea
dimensions according to the design drawings. Any diametru Ø4. Constructorul trebuie să furnizeze
modification of the gratings on site are not fabricantului dimensiunile de deschidere ale
accepted. graterelor conform desenelor de proiectare. Nu se

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 17 of 31

Additional requirements: acceptă nici o modificare a gratarelor pe santier.


Grating wil be protected using hot deep Cerințe suplimentare:
galvanized 40 microns. Gratarele vor fi galvanizate la cald cu o acoperire
Upend Binding/ Toe Plate: de minim 40 de microni.
Safety binding welded to the bearing bar ends Rigidizare de capat / cu protectie superioara:
and projecting beyond the grating. Prevents Placa de rigidizare va fi sudata de capetele
objects from falling down or skidding. barelor si va fi amplasata in exteriorul grătarului.
All the above additional plates and the Rigidizarea marginala evită căderea obiectelor
reinforcement of the openings will be executed on sau deraparea.
shop. The perimetral plates will be welded on Toate plăcile suplimentare de mai sus și armarea
each of every bearing and transversal bar. The deschiderilor vor fi executate la fabrica. Plăcile
gratings modified on shop will be supplied perimetrale vor fi sudate pe fiecare placa si bara.
untreated and after execution of all modifications Gratarele modificate in fabrica vor fi zincate la
the gratings will be hot deep galvanized. cald după executarea modificărilor.

6.8 QUALITY CONTROL AFTER CUTTING, 6.8 CONTROLUL CALITATII DUPA


STRAIGHTENING OUT AND MACHINING OF DEBITARE, INDREPTARE SI PRELUCRAREA
EDGES MUCHIILOR
The quality assurance responsible shall check: Responsabilul cu controlul calitatii are obligatia sa
verifice urmatoarele:
 Proper and visible marking of parts as per  existenta pe piese a marcajului corect si vizibil
project documentation; conform denumirii din proiect
 Whether the size of cut parts is within the  dimensiunile pieselor debitate in limitele
tolerance limits; tolerantelor;
 Complete cleaning of the scale that forms on  curatirea completa a crustei de zgura, care se
on the bottom of the cut; formeaza pe partea inferioara a taieturii;
 Flatness of surfaces and straightness of  planeitatea suprafetelor si rectilinitatea
edges after straightening, within the tolerance marginilor pieselor dupa indreptare, in limitele
limits; tolerantelor;
 Proper performance of bevels for parts that  executia corecta a sanfrenului la piesele ce
require bevelling. necesita aceasta prelucrare.
Further operations shall be discontinued for parts Nu se admite trecerea la alte operatii a pieselor
which: care:
 Have improper size;  sunt necorespunzatoare dimensional;
 Do not have clear and visible marking;  nu au marcajul corect si vizibil;
 Have cutting defects that can not be  prezinta defecte de taiere ce nu pot fi
remedied. remediate
6.9 ASSEMBLING 6.9 ASAMBLAREA
The surfaces of parts to be assembled shall be Piesele care urmeaza a fi asamblate trebuie sa
dry and clean. aiba suprafetele uscate si curate.
It is forbidden to assemble parts of which surfaces Se interzice asamblarea pieselor ude, acoperite
are wet and not free of ice, grease, mud, rust and cu gheata, unsoare, noroi, rugina etc. prezentand
lamination. exfolieri.
The edges of parts to be welded shall be grinded Marginile pieselor care se sudeaza vor fi polizate
over 20 - 30 mm on both sides to completely pe o latime de 20 - 30 mm pe ambele fete pentru
remove scale and rust. indepartarea completa a tunderului si ruginii.

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 18 of 31

6.9.1 ASSEMBLING OF PARTS FOR WELDING 6.9.1 ASAMBLAREA PIESELOR IN VEDEREA


(PRELIMINARY ASSEMBLY) SUDARII (ASAMBLARE PROVIZORIE)
Parts shall be assembled using assembling Asamblarea pieselor se va executa cu ajutorul
and/or welding equipment. dispozitivelor de asamblare, si/sau sudare.
Such equipment shall ensure the accuracy of Constructia acestor dispozitive trebuie sa asigure
parts assembling within the allowable tolerance precizia de asamblare a pieselor in limitele
limits according to the metal specification and tolerantelor admise de specificatia de metal si sa
shall not prevent the free deformation of parts and nu impiedice deformarea libera a pieselor precum
the performance of welds in proper conditions. si executarea lucrarilor de sudare in bune conditii.
When assembling, it is not allowed to weld the La asamblare nu se admite prinderea cu sudura
parts to the surfaces of pulling devices. pe suprafetele tablelor dispozitivelor de tragere.
Assembling in view of flux welding of butt joints Asamblarea in vederea sudarii automate sub flux
can be done directly on the submerged arc a imbinarilor cap la cap se poate face direct pe
welding machine with electromegnetic stirring dispozitivul de sudare sub flux cu strangere
electromagnetica.
The flux shall be of the same quality as the one In perna se va pune flux de aceeasi calitate cu cel
used for welding the respective steel. intrebuintat la sudarea otelului respectiv.
The flux will have to meet the requested Fluxul va trebui sa indeplineasca conditiile
requirements for parts welding. prevazute.
Assembling shall be carried out so that proper Asamblarea trebuie facuta astfel ca dupa sudarea
size assemblies result following the final welding. definitiva sa rezulte subansambluri cu dimensiuni
corecte.
Local irregularities and deformations of a part that Neregularitatile si deformatiile locale pe care le
exceed those provided for in the metal prezinta o piesa si care depasesc pe cele
specification shall be removed by machining thus prevazute in specificatia de metal, trebuie sa fie
achieving a smooth passage from the machined inlaturate prin prelucrare, realizandu-se
part to the non-machined part. racordarea lina de la portiunea prelucrata la cea
neprelucrata.
The assembling tolerances are shown in STAS La asamblare tolerantele sunt cele din STAS 767-
767-0/88. 0/88.
6.9.2 QUALITY CONTROL AFTER ASSEMBLY 6.9.2 CONTROLUL CALITATII DUPA
AND PROVISIONAL CLAMPING ASAMBLAREA SI PRINDEREA
PROVIZORIE
Before welding operation, check all dimensions Inainte de operatia de sudare, se vor verifica toate
subassemblies. dimensiunile subansamblurilor.
Check all welding points. Se vor controla toate prinderile punctuale de
sudura.
The welding points will be controlled by AQ Acestea vor fi controlate de responsabilul cu
personel. controlul calitatii din schimbul respectiv.
It will proceed to a thorough visual examination of Se va proceda la examinarea vizuala amanuntita
each connection, using for this purpose electric a fiecarei prinderi, folosind in acest scop lampi
lamps and magnifiers with magnification of 2.5. electrice si lupa cu o putere de marire de 2,5 ori.
If there are cracks in connections, those elements Daca se constata fisuri in cordoanele de prindere
must be completely removed, followed by grinding a unor imbinari cap la cap, se vor indeparta
to a complete removal of traces left by electrical complet cordoanele de prindere fisurate, prin
arc on the base material. craituire arc-aer, urmata de o polizare pana la
indepartarea completa a urmelor lasate de arcul
electric pe materialul de baza.
In case of cracks in filled welds, those elements In cazul unor fisuri in cordoanele de prindere a
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 19 of 31

will be removed by grinding (completely remove unor imbinari de colt acestea se vor elimina prin
those elements with cracks). polizare sau craituire mecanica (se elimina
complet cordoanele cu fisuri).
Mechanical cleaning will be followed by polishing. Curatirea mecanica va fi urmata obligatoriu de
polizare.
After polishing the elements that have welding Dupa polizarea portiunilor in care au existat
points with cracks is required to make a thorough sudura in puncte cu fisuri este obligatoriu sa se
check of these areas both visually and with faca un control amanuntit a acestor zone atat
penetrant liquids. vizual cat si cu lichide penetrante.
The producer of steel structure shall have own Fabricantul trebuie sa aiba procedura proprie
procedure for welding remediations. pentru remedierea sudurilor.
In case of non-compliant welds the tests and In cazul in care se constata suduri neconforme
checks will be extended for all welds of the steel testele si verificarile se vor extinde pentru toate
structure. sudurile confectiei metalice.

6.10 WELDING METAL SUB-ASSEMBLIES 6.10. SUDAREA SUBANSAMBLURILOR


METALICE

6.10.1 GENERALS 6.10.2 GENERALITATI


The fabrication of the steel structures shall be Uzinarea confectiilor metalice se va face exclusiv
done exclusively in the factory. The fabrication of in fabrica. Uzinarea confectiilor metalice cuprinde
the steel structures also includes the execution of inclusiv aplicarea straturilor de protectie
corrosion protection layers. anticoroziva.
Performance of welded joints of high quality is Executarea unor imbinari sudate de buna calitate
subject to: este conditionata de:
 use good quality rolled products free of  folosirea unor laminate de buna calitate lipsite
defects such as:layering, overlapping, de defecte ca: stratificari, suprapuneri, sufluri,
cavitation, cracks, inclusions; fisuri, incluziuni;
 cleaning of impurities (grease, paint, rust, etc.)  curatirea de impuritati (grasimi, vopsea, rugina
in the area of joining; etc.) a laminatelor in zona imbinarii;
 drying of areas that apply to welding;  uscarea zonelor din table pe care se aplica
sudarea;
 the use of filler materials (electrodes, rods,  folosirea unor materiale de adaos (electrozi,
beams) corresponding to the base material sarma, flux) corespunzatoare materialului de
welds; baza ce se sudeaza;
 welding in horizontal plane fitting of butt  sudarea in plan orizontal a imbinarilor cap la
welding in the gutter of the corner fitting; cap, respectiv sudarea in jgheab a imbinarilor
de colt;
 welding of the joints unstiffened to avoid  sudarea in stare nerigidizata a imbinarilor
stress concentration, using a correct order of pentru evitarea concentrarii tensiunilor, prin
assembly and welding. folosirea unei ordini de asamblare si sudare
corecte.
Welding of metallic subassemblies will be Sudarea subansamblurilor metalice se va executa
performed in closed halls at a minimum in hale inchise la o temperatura de minim + 5°C.
temperature of + 5 ° C.
Work places will have to be free of permanent air Locurile de munca vor trebui sa fie lipsite de
currents that would influence the quality of the curenti permanenti de aer care ar influenta asupra
welds. calitatii sudurilor.
If for some reason it is necessary to perform some Daca din anumite motive este necesar sa se
joints outdoor manual small lengths, it will perform execute in aer liber unele imbinari manuale, de
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 20 of 31

under the direction of welding engineer of the lungime mica, aceasta se va efectua sub directa
department. indrumare a inginerului sudor al sectiei.
Special measures must be taken to protect the Trebuie luate masuri speciale pentru protejarea
spot welding and welder of wind, rain, snow, locului de sudare si al sudorului, de vant, ploaie,
which would prevent the proper execution of the zapada, care ar impiedica buna executie a
works. lucrarilor.
In these conditions the welding metal parts is In aceste conditii sudarea pieselor metalice este
allowed and at a temperature below + 5 ° C but admisa si la o temperatura sub + 5°C dar nu mai
not less than-5 ° C and only for parts with mica de – 5°C si numai pentru piese cu grosimi
thicknesses under 24 mm, made of rolled steel sub 24mm, executate din laminate de otel cu cel
with a maximum 0,18% Carbon. mult 0,18%C.
Before welding will pre-heat incoming wash parts Inainte de sudare se vor preincalzi muchiile
edges welds at a temperatures indicated in the pieselor ce se sudeaza la temperatura indicata in
fabrication procedure provided by constructor and procedura de fabricatie a executantului si in
also in accordance with the welding procedure conformitate cu procedura de sudare aleasa de
choosen by the constructor. executant.
The cooling of welded areas shall be made such Racirea zonelor sudate se va efectua astfel ca
that the temperature of 100 ° C spare parts to temperatura de 100°C a pieselor sa scada nu mai
drop no sooner than 30 minutes after the devreme de 30 min. de la terminarea sudarii.
completion of welding.
This can be achieved through the protection of Aceasta se poate realiza prin protejarea zonelor
welded areas with thermal isolations boards or by sudate cu placi termoizolante sau prin micsorarea
decreasing the speed of cooling using air-gas vitezei de racire folosind flacara gaz-aer.
flame.
Staff dealing with slow cooling welded fitting will Personalul care se ocupa cu racirea lenta a
be specially trained. imbinarilor sudate va fi special instruit.
The welding electrodes should be used, which will La sudare se vor folosi electrozi, care se vor usca
dry out the binding at a temperature of 250-300 ° obligatoriu la o temperatura de 250 – 300°C timp
C for at least one hour. de minim o ora.
Port-electrodes (clestii), cables, and how to make Port-electrozii (clestii), cablurile si modul de
the contact table will correspond to the provisions realizare a contactului de masa vor corespunde
in force. prevederilor in vigoare.
The equipment used for welding semi-automatic Utilajul folosit la sudarea automata si
and automatic must ensure the stability of welding semiautomata trebuie sa asigure stabilitatea
procedures laid down in the draft process, with regimurilor de sudare fixate in proiectul procesului
the following tolerances: tehnologic, cu urmatoarele tolerante:
 welding speed ± 10%;  la viteza de sudare 10%;
 the welding current intensity ± 3%;  la intensitatea curentului de sudare 3%;
 voltaic arc voltage ± 5%.  la tensiunea arcului voltaic  5%.
Some isolated short term oscillations of the Unele oscilatii izolate de scurta durata ale
measuring apparatus shall not be regarded as a aparatelor de masurat nu vor fi considerate ca o
breach of the established regime, if these nerespectare a regimului stabilit, daca aceste
oscillations do not have a periodic character and oscilatii nu au un caracter periodic si nu dauneaza
do not harm the quality of welding seams. calitatii cordoanelor de sudura executate.
6.10.3 PRE- WELDING OPERATION 6.10.3 OPERATII PREMERGATOARE SUDARII
Welding procedure are established by laboratory Procedurile de sudare se stabilesc in uzina de
welding plant, based on testing. catre laboratorul de sudura, pe baza de incercari.
The goal for establish a normal welding procedure Scopul stabilirii unui regim de sudura normal este
is to obtain a good quality of welded joints. obtinerea unei calitati bune a imbinarilor sudate.
Especially it aims to: Indeosebi se urmareste:
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 21 of 31

 achieving appropriate mechanical properties;  realizarea caracteristicilor mecanice


corespunzatoare;
 proper penetration into the base material;  patrunderea corespunzatoare in materialul de
baza;
 the penetration of the root;  patrunderea la radacina;
 lack of defects (cracks, pores, inclusions,  lipsa defectelor (fisuri, pori, incluziuni, etc.).
etc.).
The welding procedure will take into consideration La stabilirea procedurii de sudare se va avea in
the processing mode of the edges for welding vedere modul de prelucrare a marginilor
manual and automatic welding. recomandate pentru sudura manuala si pentru
sudura automata.
The regimes established are maintained as long Regimurile stabilite se mentin atata timp cat nu se
as it does not change one of the following factors: schimba unul din urmatorii factori: marca
base material, filler material brands, welding materialului de baza, marcile materialelor de
procedures. adaos, procedurile de sudare.
Welding laboratory will communicate the welding Laboratorul de sudura va comunica sectorului de
sector and service AQ the optimal regime for each sudura si serviciului AQ regimul optim de sudura
type of welding seam. pentru fiecare tip de cordon.
All welds, automatic and semiautomatic are Toate sudurile manuale, automate si
executed with the use of the end- plates semiautomate se executa cu folosirea placutelor
terminale
For filled welds will provide, at both ends of the Pentru imbinari de colt se vor prevedea, la
cord, metallic T-shaped ends. ambele capete ale cordonului, placute terminale
in forma de T.
For butt joints will sit, at both ends of the cord end Pentru imbinarile cap la cap se vor aseza, la
plates. ambele capete ale cordonului placute terminale.
Precision terminals will be chamfered the same Placutele terminale vor fi sanfrenate la fel cu
with pieces that combine. piesele ce se imbina, ce vor fi sanfrenate la fel cu
piesele ce se imbina.
In cases where it is not possible to make a In cazurile in care nu este posibila asezarea
terminal location must ensure completion of placutelor terminale trebuie sa se asigure
craters at the ends of welding seams. completarea craterelor de la capetele cordoanelor
de sudura.
After completion of the welding operations, end Dupa terminarea operatiilor de sudare, placutele
plates must be removed and the same ends will terminale trebuie indepartate iar capetele
be processed. codoanelor se vor prelucra.
To carry out the necessary control tests the Pentru efectuarea incercarilor mecanice necesare
mechanical quality of the combination will run the controlului calitativ al imbinarii respective se vor
sample boards base material of the same quality executa placi de proba din material de baza de
as that of the parts to be welded, having the same aceeasi calitate cu cel al pieselor ce trebuie
thickness of processed edges in the same way. sudate, avand aceleasi grosimi cu muchiile
prelucrate in acelasi mod.
Butt joints that will use the sample boards for Imbinarile cap la cap la care se vor folosi placi de
mechanical tests shall be agreed between the proba pentru incercari mecanice se stabilesc de
designer and supplier. comun acord intre proiectant si furnizor.
Sample boards will be hammered on them a Placile pentru probe vor avea poansonat pe ele
number to be able to identify the place where they un numar pentru a putea indentifica locul unde au
were extracted, the number that will correspond to fost extrase, numar care va corespunde cu cel din
the technological procesul tehnologic.
Trial plates shall be welded in the same Placile de proba se vor suda in aceleasi conditii in
conditions in which the parts are welded and by care se executa imbinarea si de catre acelasi
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 22 of 31

the same welder. sudor.

6.10.4 SUBASSEMBLIES CONTROL BEFORE 6.10.4 OPERATII PREMERGATOARE SUDARII


WELDING
Before starting of welding, each welding joint will Inainte de sudare fiecare imbinare va fi controlata
be controlled by the foreman of the shift in de catre maistrul din schimbul respectiv si de
question and by the AQ officer. catre responsabilul cu controlul calitatii.
It will not allow the welding start if: Nu se va permite inceperea sudarii daca:
 each piece of subassembly has no heat  fiecare piesa a subansamlului nu are marcat
number and the number which marks its numarul sarjei si numarul pozitiei sale din
position in operation plan; planul de operatii;
 assemblies and the holes don't match up with  ansamblurile si prinderile nu corespund cu
the plans of execution, with the technological planurile de executie, cu prevederile
process and indications of this specification; procesului tehnologic si cu indicatiile din
prezenta specificatie;
 machining, beveling or assembling tolerances  sunt depasite tolerantele de prelucrare,
are exceeded; sanfrenare sau asamblare, specificate in
prezenta specificatie;
 the edges welded and surrounding areas are  muchiile care se sudeaza si zonele invecinate
not clean; It will check the cleaning of slag; nu sunt curate; se va verifica si curatirea zgurii
 end plates are not well placed or have smaller  placutele terminale nu sunt bine asezate sau
sizes than those shown in the technological au dimensiuni mai mici decat cele indicate in
process. procesul tehnologic
Larger joints such as those admitted must be Rosturile mai mari ca cele admise trebuie
shrunk before starting welding operation. micsorate inainte de inceperea operatiei de
sudare a imbinarilor respective.
If reducing joints cannot be achieved by bringing Daca micsorarea rosturilor nu se poate realiza
parts, it is necessary to make their load through prin apropierea pieselor, este necesar sa se faca
welding. incarcarea lor prin sudura.
6.10.5 WELDING 6.10.5 SUDAREA PROPRIU-ZISA

It is prohibited to priming arcing on surfaces that Se interzice amorsarea arcului electric pe


cannot be covered later with welding. Measures suprafetele ce nu se acopera ulterior cu sudura.
will be taken not to inflict damage of parts through Se vor lua masuri sa nu se produca deteriorari ale
the splashes of molten metal. pieselor prin stropiri de metal topit.
It is prohibited the forced cooling of the welds. Se interzice racirea fortata a sudurilor.
Welding slag is removed only after the normal Zgura de sudura se va indeparta numai dupa
cooling. racirea normala a acestora.
Automatic and semi-automatic welding, flux La sudarea automata si semiautomata,
removal must be done at a distance of at least 1 indepartarea fluxului trebuie sa se faca la o
m from the voltaic arc. distanta de cel putin 1 m de arcul voltaic.
The butt welds, welding on the second front, the La sudurile cap la cap, inainte de sudarea pe fata
first root welds it will clean by mechanical gauging a doua, radacina primei suduri se va curata prin
or just simply arc-air to obtain a clean metal craituirea mecanica sau prin procedeul arc-aer
surface. pana se obtine o suprafata metalica curata.
In case of use of air-arc procedure is required to In cazul folosirii procedeului aer-arc este
grinding the joint surfaces up to complete removal obligatoriu sa se polizeze suprafetele rostului
of the material burned. pana la indepartarea completa a materialului ars.
Weld will begin and it will end on end plates. Sudarea va incepe si se va termina obligatoriu pe
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 23 of 31

placutele terminale.
Welding layers will be deposited one after the Straturile de sudura se vor depune unul dupa altul
other, before the joining area to be cooled. fara ca zona imbinarii sa se raceasca.
However previously deposited layer temperature Totusi temperatura stratului depus anterior nu va
will not exceed 200 ° C; short joints will leave for depasi 200°C; la imbinarile scurte, se va lasa
5-6 minutes cooling time between two layers of pentru racire un timp de 5-6 minute intre doua
welding. straturi succesive de sudura.
6.10.6 CHECKING THE WELDING 6.10.6 CONTROLUL OPERATIILOR DE
OPERATIONS AND THE WELDED SUDARE SI A IMBINARILOR SUDATE
FITTING
The welds should be checked according to table 5 Sudurile se vor verifica in conformitate cu tabelul
from C150-99: 5 din C150-99:
Examination of the visual appearance is 100% for Examinarea vizuala se va face in proportie de
all laminates, parts and welded joints, the entire 100% pentru toate laminatele, partile si imbinarile
length and their surface, before corrosion sundate, pe intreaga lungime si suprafata, inainte
protection, as provided in table 5 of C150-99. de protectia anticoroziva, verifica in conformitate
cu tabelul 5 din C150-9.
Control of the welding operations and of the Controlul operatiilor de sudare si a imbinarilor
welded fitting is performed in the main phases of sudate se executa in fazele principale ale
the welding process, as follows: procesului de sudare, dupa cum urmeaza:
 Filler materials control - they will need to meet  Controlul materialelor de adaos - acestea vor
the requirements of standards and according trebui sa corespunda prescriptiilor
norms; standardelor si normativelor in vigoare.
 During the execution of the will follow the  In timpul executiei se va urmari folosirea
correct use of the materials, storage and corecta a materialelor de adaos, pastrarea si
drying them in good conditions; uscarea lor in bune conditiuni.
 Improper materials or those that have doubts  Materialele necorespunzatoare sau cele care
will not be used for welding. prezinta dubii nu vor fi folosite la sudare.
 Welding process control-during the welding  Controlul procesului de sudare - in timpul
process will verify compliance with the legal procesului de sudare se va verifica
prescriptions of the technological process and respectarea intocmai a prescriptiilor din
project execution. procesul tehnologic si proiectul de executie.
 It will verify the correct application of the  Se va verifica respectarea aplicarii corecte a
processes specified, the order of assembly procedeelor indicate, a ordinei de asamblare
and welding, welding procedure. si sudare, a regimului de sudare.
6.10.7 PROCESSING AFTER WELDING 6.10.7 PRELUCRAREA DUPA SUDARE
After welding, the weldings will be processed Dupa sudare, cordoanele de sudura se vor
according to the instructions of the project and prelucra conform indicatiilor din proiect si procesul
technological specs tehnologic.
The processing will be done generally through Prelucrarea se va face in general prin polizare
grinding or chipping followed by polishing. sau aschiere urmata de polizare.
Seam resulting from the grinding will be parallel to Rizurile rezultate din polizare vor fi paralele in
the direction of the effort in this piece. directia efortului in piesa respectiva.
It is forbidden to end at right angles to the Este interzisa prelucrarea finala perpendicular pe
direction of processing effort. directia efortului.

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 24 of 31

6.10.8 CONDITIONS OF QUALITY OF THE 6.10.8 CONDITII DE CALITATE ALE


PARTS, COMPONENTS, SUB- PIESELOR, ELEMENTELOR,
ASSEMBLIES AND STITCHING SUBANSAMBLURILOR SI
TECHNOLOGY WELDED CORDOANELOR DE SUDURA
Dimensional deviations of welded components Abateri dimensionale ale pieselor elementelor si
and subassemblies. subansamblurilor sudate
The dimensions specified on the drawings Dimensiunile specificate pe desenele de executie
correspond to temperature of + 20°C. corespund temperaturii de + 20°C.
For measurements made at other temperatures Pentru masuratori facute la alte temperaturi se vor
will make the necessary corrections, the face corecturile necesare, coeficientul de dilatare
coefficient of linear thermal expansion is α = 12 x termica liniara fiind α = 12 x 10-6/°C.
10-6/°C.
Limit deviations of the shape and dimensions of Abaterile limita de la forma si dimensiunile
parts and welded sub-assemblies are those pieselor si subansamblurilor sudate sunt cele
specified in STAS 767-0/88 item 2.3.1 ... 2.3.5 specificate in STAS 767-0/88 pct. 2.3.1 ... 2.3.5 si
namely tables 1, 2 and 3, with the following anume tabelele 1, 2 si 3, cu urmatoarele limitari si
limitations and issues: precizari :
 deviations from limit the length of the stifners  abateri limita la lungimea guseelor si
and plates is : + 2 ... 4 mm; rigidizarilor : +2 ... -4 mm;
 deviations from the main beam length limit:  abateri limita la lungimea grinzilor principale :
 up to 9 m openings including: + 0-4 mm;  pana la deschideri de 9 m inclusiv : +0 ... -
4 mm
 the openings greater than 9 m: + 0-6 mm.  la deschideri mai mari de 9 m : +0 ... -6
mm
 deviations from limit milling poles (with a  abateri limita la stalpi cu capete frezate (cu
length between 4, 5 and 9 m): ± 2 mm; lungimea intre 4, 5 si 9 m) : ± 2 mm.
 limit deviations from the ends of the Poles, but  abateri limita la stalpi cu capetele nefrezate,
processed for unmilling welding: + 2-4 mm. insa prelucrate pentru sudare : +2 ... -4 mm.
The lengths of the above points are measured Lungimile de la punctele de mai sus sunt
between the outer skins of the girls welds, which masurate intre fetele exterioare prelucrate ale
will have the shapes and sizes of SR EN ISO sudurilor, care vor avea formele si dimensiunile
9692-1/2004 or in the technological processes din SR EN ISO 9692-1/2004 sau din procesele
with prescribed tolerances in these. tehnologice, cu tolerantele prescrise in acestea.
If the result is greater lengths, they will process Daca lungimile rezulta mai mari, ele se vor
with abrasive discs, and if the result is smaller, it prelucra cu discuri abrazive, iar daca rezulta mai
will proceed in accordance with paragraph mici, se va proceda conform pct. 4.7.1.4. d si art.
4.7.1.4. d and art. 2.3.5.2 of STAS 767-0/88, 2.3.5.2 din STAS 767-0/88, si anume:
namely:
 tilt your upper limit of Δ1 to double T beams  inclinarea limita Δ1 a talpii superioare a
according to number 1 in the table 1 of 767- grinzilor dublu T conform numarului 1 din
STAS 0/88; tabel 1 din STAS 767-0/88 ;
 on the welds on folded cards or the right  pe portiunea pe care se sudeaza placile
combination with other components placed on cutate sau in dreptul imbinarilor cu alte piese
top: asezate deasupra:
 Δmax = 0,005 B, but not more than 1 mm;  Δmax = 0,005 B dar cel mult 1 mm;
 in other portions of the beams: B/40 but  in celelalte portiuni ale grinzilor : B/40 dar cel
not more than 5 mm. mult 5 mm;
 allowable deformation limit "fungus",  deformatia limita “in ciuperca” Δ1, conform

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 25 of 31

according to the number 2 Δ1 in table B; numarului 2 din tabel B;


 in other portions of the beams: 0,025 B but not  in celelalte portiuni ale grinzilor : 0,025 B dar
more than 5 mm cel mult 5 mm.
To observe deformation tolerance "fungus" is Pentru a respecta toleranta la deformarea "in
recommended as the soles of the main beams to ciuperca" se recomanda ca talpile superioare ale
be predeformate Conversely, cold welding. grinzilor principale sa fie predeformate invers la
rece, inainte de sudare.
In order to achieve proper fitting joints between In vederea realizarii corespunzatoare a rosturilor
parts and sections, variations in height and width de montaj intre subansambluri si tronsoane,
on the Assembly areas will be under the number abaterile la inaltimea si latimea acestora pe
13 and 14 in the table B: + 2-3 mm. zonele de montaj va fi conform numarului 13 si 14
din tabel B : +2 ... -3 mm.
Exceptions are the distances between the inner Exceptie fac distantele dintre fetele interioare ale
faces of the poles between which can be mounted stalpilor intre care se monteaza grinzi fara rosturi
without joints along the beams, which must not in lungul lor, care trebuie sa fie de cel mult ±2mm;
exceed ± 2 mm; these tolerances must be aceste tolerante trebuiesc respectate pe inaltimea
observed on the height that is a mixture between pe care se face imbinarea intre stalpi si grinzi.
the pillars and beams.
Limit deviations for the remainder of the Pentru restul abaterilor limita se respecta
provisions in respect of table 3, and alignment prevederile din tabelul 3.a, iar pentru tolerantele
tolerances for the SR EN ISO 13920-1998. de aliniere cele din SR EN ISO 13920 – 1998.
6.10.9 THE QUALITY CONDITIONS OF THE 6.10.9 CONDITII DE CALITATE ALE
WELDED JOINTS TECHNOLOGY CORDOANELOR DE SUDURA
For any type of welded joints and any quality or Indiferent de tipul imbinarilor si de forma
shape the welded joints will be verified using cordoanelor de sudura, calitatea cordoanelor de
direct measurement, by visual examination and sudura se verifica dimensional, vizual prin
with the magnifying devices, by tapping, by examinare exterioara si cu lupa, prin ciocanire, cu
penetrant liquid methods. lichide penetrante.
The butt welds having the acceptance level B or Sudurile cap la cap avand nivelul B de receptie a
the welds indicated in the NDT plan, the quality of sudurilor sau la acelea indicate in planul de
the welds is also verified by non-destructive radiografiere, calitatea cusaturilor se verifica si
methods prin metode nedistructive

Quality conditions for cutting the edges and joints, Conditiile de calitate pentru taierea marginilor si
proper processing quality classes in your project, prelucrarea rosturilor, corespunzatoare claselor
those in table 3 of the standard C 150-99. de calitate din proiect, sunt cele din tabelul 3 din
Normativul C 150 -99.
Acceptance levels of welded joints with defects Nivelurile de receptie a defectelor in imbinarile
are indicated in table 6 of the Norm C150-99 for sudate sunt cele din Tabelul 6 din Normativul
any type of welds. C150-99 pentru toate tipurile de sudura.
6.10.10 QUALITY CONTROL 6.10.10 CONTROLUL CALITATII
Quality control of sub-assemblies and welded Controlul de calitate al subansamblurilor si al
fitting is made by the attested personel of the imbinarilor sudate se face de catre organele
supplier. competente ale furnizorului.
Monitoring will be done through visual and also Controlul se va face vizual si prin masuratori
with dimensional measurements. dimensionale.
This control should not be exceeded the allowable La acest control nu trebuie depasite tolerantele
tolerances of STAS 767-0/88. admisibile din STAS 767-0/88.
It will give particular attention to compliance with Se va da o deosebita atentie la respectarea
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 26 of 31

tolerantelor in combination with other elements. tolerantelor in locurile de imbinare cu alte


elemente.
The supplier will perform random tests using Furnizorul va efectua teste aleatorii folosind probe
welded samples and steel pieces from the same sudate și piese din oțel din același material și va
material and will compare the results in order to compara rezultatele pentru a certifica calitatea
certify the quality of welded joints according to SR îmbinărilor sudate conform SR EN ISO
EN ISO 4136/2013. 4136/2013.
6.10.11 MARKING 6.10.11 MARCARE
Each sub assembly or steel elements ready to be Fiecare subansamblu sau element de constructie
shipped to the construction site, will be marked gata de a fi expediat la santier, se va marca cu
with paint resistance. vopsea rezistenta.
Sub-assemblies or metallic constructions Subansamblurile sau elementele constructiilor
elements will be marked as following: metalice vor avea notate:
 type of item-according to the project name;  tipul elementului - conform denumirii din
proiect;
 number of manufacturing orders (numbered  numarul de ordine de fabricatie (numerotat de
from 1 to the total number); la 1 la numarul total);
 position of part or subassembly in the  pozitia piesei sau subansamblului in
assembly piece (left, right, center, edge); ansamblul piesei (stanga, dreapta, centrala,
marginala);
 mark the mounting site (where noted)  semnul de montaj la santier (acolo unde este
notat).
For small pieces that will be delivered, it will be Pentru piesele mici care se livreaza detasat se va
marked the element type, and also the single part nota tipul elementului, numarul de pozitie al piesei
name (according to single part list) and the name (in extrasul de laminate) si eventual plansa cu
of the detail drawing. detalii.
6.10.12 PRE - ASSEMBLING 6.10.12 PREASAMBLAREA
Each main steel element will be pre-assembled in Fiecare element al structurii va fi preasamblat in
the workshop, it will be checked their collinearity, atelier, se va verifica colinearitatea barelor,
the assembly tolerances and then it will be respectarea tolerantelor de asamblare, se va
delivered on site after disassembly and marca si apoi se va expedia dupa dezasamblare
packaging. si coletare.
The packaging will take account of the La impachetare se va tine seama de gabaritele de
dimensions of truck transport. transport CF sau AUTO.
6.10.13 COATING 6.10.13 PROTECTIE ANTICOROZIVA
This chapter specifies minimum technical Acest capitol specifică cerințele tehnice minime şi
requirements and requirements for base surface cerinţele pentru pregătirea suprafeţelor de bază,
preparation, coating application in workshop and aplicarea protectiei anticorozive în atelier şi pe
on site, implementation, operation and santier, aplicarea, funcționarea și întreținerea
maintenance of corrosion protection for steel sistemului de protectie anticorozivă pentru
construction. constructiile metalice.
Corrosion protection systems for steel Sistemele de protectie anticorozivă pentru
construction will be chosen depending on the construcţii metalice vor fi alese în funcţie de clasa
corrosivity class of environment, the estimated de corozivitate a mediului, durabilitatea estimată
protection durability and economic considerations. de protecţie şi considerente economice.
Protection against corrosion is usually, the more Protectia anticoroziva este, de regula, mai
economical, the more has a high durability, as the economica si durabila daca pe parcursul executiei
maintenance / restoration service protection is se reduc activitatile de intretinere/reparatii.
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 27 of 31

minimalized during the construction.


Corrosion protection in factory or assembly Protectia anticoroziva aplicata in fabrica sau in
workshops construction units, for all metal atelier, pentru toate constructiile metalice din
construction of the project will be executed cadrul proiectului se va realiza conform proiectului
according to the project drawings and si desenelor de executie
documentation
Execution technology of the corrosion protection, , Tehnologia de executie a protecţiei anticorozive,
will be detailed in the technology sheet provided va fi detaliata în fişa de tehnologie furnizate de
by the unit, the sheet will be attached to the fabricant, fisa va fi ataşata la documentaţia
technical documentation referred to item 1.4.2 tehnică prevăzută la pct. 1.4.2 STAS 767 / 0-88
STAS 767 / 0-88.
Steel Surfaces Preparation Prepararea suprafetelor metalice
Criteria and performance levels for substrate will Criteriile si nivelele de performanta pentru stratul
be according to table 4.2 of GP 121-2013. support vor fi in concordanta cu tabelul 4.2 din GP
121-2013.
Regarding the readiness of welds, edges and In ceea ce priveste gradul de pregatire a
other surface imperfections, this it is chosen sudurilor, marginilor si altor imperfectiuni ale
according to table 4.3 of GP121-2013 (P2, for a suprafetelor, aceastra este ales in concordanta cu
corrosion durability protection > 15 years). tabelul 4.3 din GP 121-2013: P2 pentru o
durabilitate a sistemului de acoperire > de 15 ani.
Preparation of the surface to be covered shall be Pregatirea suprafetei care trebuie acoperita cu
performed in accordance with manufacturer's vopsea trebuie sa fie facuta in concordanta cu
requirements as follows: cerintele fabricantului dupa cum urmeaza:
 Uncoated steel and steel surfaces: Remove all  Otelul neacoperit si suprafetele metalice: Se
grease, slag grinding, welding splatter, dirt va indeparta toata grasimea, zgura, stropii de
and rust. sudura, murdărie și rugină.
 The first coating of steel surfaces: surface  Prima vopsire a suprafetelor metalice:
shot blasting to remove possible rust. The Suprafata se va sabla pentru a se indeparta
edges will be finished by adding material to eventuala rugina. Marginile vor fi finisate prin
remedy defects. material de adaos pentru remedierea
defectelor.
Surfaces Coating Acoperirea Suprafetelor
Coating system chosen is the alchidic paint, Sistemul de acoperire are durata de viata mare
epoxy paint with lifetime- (years): >15 years >15 ani tabel 5.5 din GP 121-2013.
(Table 5.5 of GP 121-2013). Tipul de acoperire a suprafetelor este indicat
. The type of anticorozive layer is indicated for pentru fiecare element metalic in detaliile de
each steel element in the detail drawings. executie.
Overall thickness of the coating is indicated in GP Grosime totala a acoperirii este indicate in
121-2013. normativul GP 121-2013.
Performance levels of corrosion class will be Nivelul de performanta a sistemului de acoperire
chosen according to Table 4.4 of GP 121-2013. anticoroziva se allege conform Tabelului 4.4. din
GP 121-2013
All bolt assemblies (bolts, nuts and washers) will Toate ansamblurile cu suruburi (suruburi, piulite si
be hot dip galvanized according to SR EN ISO saibe) vor fi zincate la cald conform cu SR EN
10684 ISO 10684.
7.0 CERTIFICATE OF QUALITY 7.0 CERTIFICAT DE CALITATE
For each part, or subassembly that leaves the Pentru fiecare piesa sau subansamblu care este
workshop, will be issued a certificate attesting that expediat din atelier se va emite un certificat care
the subassembly is qualitative and timely project sa ateste ca subansamblul/piesa corespunde din
and dimensional specification. punct de vedere calitativ si corespunde
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 28 of 31

prescriptiilor tehnice de proiect privind


dimensiunile.
Will not receive any subassembly without being Nu se va receptiona niciun subansamblu care nu
accompanied by the certificate of quality. este insotit de certificatul de calitate.
8.0 STORAGE AND TRANSPORT 8.0 DEPOZITARE SI TRANSPORT
Storage and transport of subassemblies or parts Depozitarea si transportul subansamblurilor sau a
of finished shapes, it will do so at the workshop or pieselor detasate finite, se va face atat la atelier
the construction site, in such a way that they don't cat si pe santier, in asa fel incat acestea sa nu se
get deformations, water does not stagnate on the deformeze, apa sa nu stagneze pe piesele
metal parts and the non- coated parts to be metalice iar partile neprotejate prin vopsire sa fie
adequately protected against rust. aparate de rugina.
During transport the parts and sub-assemblies, it Pe timpul transportului pieselor si
will take care that they do not get deformations. subansamblurilor, se va avea grija de asemenea
ca acestea sa nu se deformeze.
During transport and handling, metal structures Pe durata transportului si manipularii, constructiile
will be stiffened and ensured by bracing and metalice se vor rigidiza si asigura prin
unremovable elements. contravantuiri si elemente amovibile.
The structure will be equipped with lifting lugs in Structura va fi prevazuta cu urechi de agatare
order to the manipulate it safely. pentru ca manipularea sa se desfasoare in
conditii de siguranta
The acceptance of steel structures it will be done Receptionarea constructiilor metalice in uzina se
according to OMV Petrom procedures as fallows: face dupa cum urmeaza:
- after manufacturing of steel structure, before - dupa executarea structurii metalice si inainte de
applying anticorozive protection layers aplicarea straturilor de protective anticoroziva
- inspection of steel structure after applying - inspectia structurii metalice dupa aplicarea
anticorozive protection protectiei anticorozive
Acceptance of steel structure in site is made as Receptionarea constructiilor metalice in santier se
fallowing: face dupa cum urmeaza:
- after delivery of steel structure on site, only after - dupa livrarea elementelor metalice in santier,
the unloading and storage of steel elements in the numai dupa descarcare si depozitarea
area indicated elementelor in locurile indicate
- Acceptance at the end of the mounting activity - receptia la terminarea montajului
- Final acceptance of steel structure - receptia finala
Acceptance of steel structures is done according Activitatea de receptie a structurilor metalice se
to the requierements of this document and executa conform cerintelor din prezentul caiet de
inspection test plan (ITP) issued by the sarcini si in conformitate cu planul de inspectie si
constructor and prior approved by OMV testare intocmit de catre executant si aprobat in
PETROM. prealabil de catre OMV Petrom.

The technical control of the supplier, beneficiary Organele de control tehnic ale furnizorului,
and by case the designer shall check on shop, beneficiarului si dupa caz proiectantul vor verifica
randomly, the quality of the manufactured steel prin sondaj calitatea pieselor metalice
elements. confectionate in uzina.
9.0 TECHNICAL REQUIREMENTS FOR SITE 9.0 CERINTE TEHNICE PENTRU MONTAJ IN
MOUNTING TEREN

9.1 CONSTRUCTOR’S RESPONSIBILITIES 9.1 OBLIGATII ALE EXECUTANTULUI


The supplier of the steel structure shall have the Furnizorul structurilor metalice are obligatiile şi
duties and responsibilities provided by Art. 23 of raspunderile prevazute la art. 23 din legea 10/95

GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL


TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 29 of 31

Law 10/95, the regulations regarding the şi regulamentele privind conducerea şi asigurarea
management and quality assurance for calitati în constructii, aprobate cu H.G.R. 766/97 si
construction works approved by GO 766/97 and reglementarile privind receptia lucrarilor de
the regulations for the acceptance of construction constructii si a instalatiilor si echipamentelor
works and related systems and facilities, as aferente aprobate cu HG 273/94.
approved by GO 273/94.
The supplier of the steel structure shall notify the Fabricantul trebuie să sesizeze proiectantului
designer of all the non-conformities found in the toate neclarităţile sesizate în proiect
project.
The constructor shall comply with the project Executantul va respecta prevederile proiectului
provisions (drawings, written notes on drawings, (desene, note scrise, caiet de sarcini) pe
scope of work) during construction parcursul executiei.
The constructor shall notify the designer and Executantul va notifica proiectantul si beneficiarul
beneficiary of the fabrication start and will issue privind inceperea executiei si va intocmi planul de
ITP which will be sent for approval at the the inspectie si testare care va fi supus aprobarii
beneficiary and designer beneficiarului si proiectantului
The constructor shall ensure a proper quality level Executantul va asigura un nivel de calitate
in accordance with Law 10/95, the regulations for corespunzător cerinţelor legii 10/95, a
proof engineering and expert inspection of works regulamentului de verificare, expertizare şi
as approved by GO 925/95. execuţie a lucrărilor, aprobat de HGR 925/95,
The constructor shall also have an own inspection Executantul va avea un sistem propriu de control
system and a M.L.P.A.T. certified Construction şi un responsabil tehnic, cu execuţia, atestat de
Inspector. M.L.P.A.T
The constructor shall prepare in due time the Executantul va pregati din timp documentele
documents required for the Construction Book necesare pentru CARTEA CONSTRUCŢIEI
according to Annex 6, ch. B of the acceptance conform cu anexa 6, cap. B din regulamentul de
regulations approved by GO 273/94 and will recepţie aprobat cu HG 273/94 şi să le predea
deliver such documents to the site supervisor. dirigintelui de şantier.
9.2 QUALITY REQUIREMENTS FOR THE 9.2 CONDIŢII DE CALITATE PENTRU
CONSTRUCITON SITE SANTIER
Only the materials specified in the project shall be Se vor utiliza numai materialele (tipuri, calitate şi
used for fabrication (type, quality, quantity). cantitate) înscrise în proiect.
Such materials shall comply with STAS 767/0-88 Materialele trebuie să respecte condiţiile din
for steel structures. STAS 767/0-88 pentru confectii metalice.
It is not allowed any modification of the execution Nu este permisa modificarea proiectului fara
details without the designer’s and OMV Petrom aprobarea scrisă a proiectantului si al OMV
written approval. The modifications of the Petrom. Modificarile proiectului de executie vor fi
executions details will be performed in facute in conformitate cu procedura OMV Petrom
accordance with OMV Petrom MoC procedure. MoC.
Allowed tolerances for mounting are shown in Abaterile limită admise la montaj sunt cele din
STAS 767/0-88 Art. 2.3.5 unless otherwise STAS 767/0-88, pct.2.3.5, dacă proiectul nu
specified in the project. prevede altfel.
Mounting on the construction site shall be done Montajul în şantier se va face conform
according to the project, the specifications under proiectului, prescripţiilor de la cap. 6.2 şi a
Art. 6.2 and the inhouse technology mentioned tehnologiei proprii, din documentaţia
under Art. 9.1.. menţionată la pct. 9.1
9.3 INSPECTION AND ACCEPTANCE OF 9.3 VERIFICAREA ŞI RECEPŢIA
MOUNTED ELEMENTS ELEMENTELOR MONTATE
All the inspection and acceptance requirements Vor fi respectate şi îndeplinite toate condiţiile de
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 30 of 31

from the documents below shall be complied with: verificare şi recepţie înscrise în:
 QC program attached to the project  programul pentru controlul calităţii, anexat
documentation; caietului de sarcini
 C 56-85 -book XIX steel structures;  C 56-85 -caietul XIX constructii metalice
Methods for verification of the quality of pieces Metode de verificare a calitatii pieselor si
and elements: elementelor
- Checking on each execution phases - Control pe faze de executie
- Visual checking - Verificarea aspectului
- Non-distructive tests - Controlul nedistructiv
- Marking, storage, manipulation, transport and - Marcare, depozitare, manipulare, transport,
anticorozive protection layer protectia contra coroziunii
- Quality checking on site - Verificarea calitatii la primirea pe santier
- Quality checking after mounting works - Verificarea calitatii a lucrarilor la montare
- Preliminary acceptance of the structure - Receptia preliminara a obiectului
 STAS 767/0-88 Art.5.3. For each inspection or  STAS 767/0-88 pct.5.3. Pentru fiecare
acceptance legal documents shall be verificare sau recepţie se vor întocmi
prepared and signed by attendants; such documente legale semnate de participanţi,
documents shall be part of the Construction documente care vor fi componente ale
Book. CĂRŢII CONSTRUCŢIEI
The final acceptance shall be carried out upon Recepţia la terminarea tuturor lucrărilor se va face
beneficiary’s notice in accordance with the conform regulamentului de recepţie a lucrărilor de
regulations for the acceptance of construction construcţii şi instalaţii aferente acestora, aprobat
works and related systems and facilities, as cu HG 273/94, la convocarea investitorului
approved by GO HGR 273/94.
9.4 MISCELLANEOUS 9.4 DIVERSE
The regulations and specifications mentioned Legislaţia şi prescripţiile menţionate la cap. 1 nu
under ch. 2 are not limitative, they can be sunt limitative. Ele pot fi completate, după
completed by stakeholders, as needed, during the necesitate, pe timpul realizării investiţiei de către
project performance. factorii interesaţi.
In case of concerns, discrepancies, changes or Pentru nelămuriri, nepotriviri, schimbări de soluţii
remedies the designer shall be mandatorily sau remedieri va fi solicitat obligatoriu,
contacted. proiectantul.
The beneficiary shall supervise and follow up the Investitorul va supraveghea şi urmări construcţia
structure behaviour in time according to the în timp conform Normativului pentru urmărirea
Normative for the behaviour of structures in time comportării în timp a construcţiilor P130-99.
P130-99.
10.0 HEALTH AND SAFETY AT WORK 10.0 SECURITATEA SI SANATATEA IN
MUNCA
This project was developed in compliance with HS Proiectul a fost elaborat cu respectarea
Law 319/2006, Decision 1425/2006 for the prevederilor Legii securitatii si sanatatii in munca
approval of the methodogy for HS Law 319/2006; Hotararea 1425/2006 pentru aprobarea
implementation. Normelor metodologice de aplicare a prevederilor
Legii securitatii si sanatatii in munca.
The regulations below shall also be complied De asemenea se vor respecta prevederile :
with:
 HG 971/2006 : minimum requirements for  HG 971/2006 : cerintele minime pentru
health and safety signs; semnalizarea de securitate si sanatate
 HG 1048/2006 : minimum health and safety  HG 1048/2006 : cerintele minime de securitate
requirements for the use of personal si sanatate pentru utilizarea de catre lucratori
GENERAL SPECIFICATION FOR STEEL WORKS EXECUTION_CIVIL
TYP-E-E_PETRO-
Client
Doc.no.: C-XG-002
GENERAL SPECIFICATION
FOR STEEL WORKS
EXECUTION _CIVIL Doc.no.:

CAIET DE SARCINI
LUCRARI CONSTRUCTII Rev. no.:
METALICE
Page no. 31 of 31

protection equipment by workers at the work a echipamentelor individuale de protectie la


place; locul de munca
 HG 1051/2006 minimum health and safety  HG 1051/2006 cerintele minime de securitate
requirements for the manual handling of loads si sanatate pentru manipularea manuala a
where there is a risk particularly of back injury maselor care prezinta riscuri pentru lucratori,
to workers; in special de afectiuni dorsolombare
 HG 1091/2006 minimum health and safety  HG 1091/2006 : cerintele minime de securitate
requirements for the work place; si sanatate pentru locul de munca
 HG 1146/2006 minimum health and safety  HG 1146/2006 : cerintele minime de securitate
requirements for the use of work equipment by si sanatate pentru utilizarea in munca de catre
workers; lucratori a echipamentelor de munca
 HG 1058/2006 : Minimum requirements for  HG 1048/2006 : cerintele minime pentru
improving the safety and health protection of imbunatatirea securitatii si protectiei sanatatii
workers potentially at risk from explosive lucratorilor care pot fi expusi riscului datorat
atmospheres; atmosferelor explozive
The employers shall take the required actions to: Angajatorii au obligatia sa ia masurile necesare
pentru :
 Ensure the safety and health protection of  asigurarea securitatii si protectia sanatatii
workers; lucratorilor;
 Prevent professional risks;  prevenirea riscurilor profesionale;
 Inform and train the workers;  informarea si instruirea lucratorilor;
 Ensure the required organizational framework  asigurarea cadrului organizatoric si a
and means for health and safety at work. mijloacelor necesare securitatii si sanatatii in
munca.
To meet the safety and health requirements at In vederea asigurarii conditiilor de securitate si
work and prevent work accidents and professional sanatate in munca si pentru prevenirea
diseases, the employers, the designer, and the accidentelor de munca si a bolilor profesionale,
constructor shall comply with Ch. 3 of Law angajatorii - proiectantul, executantul si
319/2006. beneficiarul, trebuie sa respecte prevederile
cuprinse in cap.3 din Legea 319/2006.
During construction H.G. nr. 971/2006 shall be Pe toata durata executiei, se va respecta H.G. nr.
complied with for safety and/or health signs at 971/2006 privind cerintele minime pentru
work and the site management shall check the semnalizarea de securitate si/sau de sanatate la
compliance with such provisions. locul de munca, iar personalul de conducere al
punctului de lucru, va verifica respectarea acestor
prevederi.
The health and safety provisions shall not be Masurile de securitate si sanatate in munca
limited to the above ones but shall be mentionate nu sunt limitative. Ele trebuie
supplemented by the employer and constructor completate de catre beneficiar si executant cu
with their own safety and prevention measures masuri de prevenire si protectie stabilite in functie
subject to their means of production, work de mijloacele de productie, mediul de munca,
environment, assigned tasks and related risks. sarcina de munca, executant si de riscurile induse
de acestea.
Also the necessary measures shall be taken Vor fi luate toate masurile necesare tinand cont
subject to the equipment used and type of work to de echipamentele pe care le utilizeaza si tipul de
prevent human and technical accidents and limit lucrari executate pentru prevenirea accidentelor
their effects if any. tehnice, umane si limitarea efectelor lor in cazul in
care s-au produs.