Professional Documents
Culture Documents
At The Gate
At The Gate
At The Gate
Corporate Standard
At The Gate
Rev 0, issued for comment
14/01/2009
At The Gate
Sponsor Richard Thompson
(approving
document)
[Title]
(maintaining
document )
[Title]
[ Page 1 of 9
At The Gate
List of Contents
1.0 Introduction..................................................................................................................... 3
2.0 Roles & Responsibilities ................................................................................................. 5
3.0 Risk Analysis & Mitigation .............................................................................................. 6
4.0 Change Management Interface ...................................................................................... 6
5.0 Cost Estimate ................................................................................................................. 7
6.0 Schedules, Plans & Milestones ...................................................................................... 8
Appendix 1.0 Typical Risk Database .................................................................................... 9
Page 2 of 9
At The Gate
1.0 Introduction
Project management is the delivery of a project within time, cost, SHE and quality
constraints to a stakeholder(s). Each project is implemented as it will deliver value to
the stakeholder(s) – the use of a gated project approval system ensures that these
benefits are realised.
To realise the maximum amount of value from its projects, and allow it to weed out
projects that do not meet economic and/or SHE criteria at an early stage as possible,
most businesses include a stage process to their decision making. This stage process
involves gathering appropriate levels of information as early as possible in the project
life-cycle, which allows the organisation to either approve, reject or modify a projects’
goals before significant resources are applied to it. The figure below shows the
passage of influence value versus time, and demonstrates that at an early stage in a
project influence value is high, whilst definition and resource spend is low. Conversely
towards the end of a project influence value is low, whilst spend and definition is very
high.
Page 3 of 9
At The Gate
Each gate acts as a project review hold point where the business and technical
integrity of a project is assessed before it can proceed to the next phase. At all of
these hold points the business can assess risk and the level of definition to decide
whether the project can still deliver the required value, before additional resources
(time, budget, personnel, etc.) are released.
Each project phase must meet defined objectives before the proposal can progress
through the next gate, these are diagrammatically shown below;
Page 4 of 9
At The Gate
To assess risk and value each gate will require a minimum level of review and
information before a decision to proceed still further can be made, this is detailed in
the figure below;
P r o b le m o r
O p p o r tu n ity
Is t h e c h a n g e v a lid ? P r o b le m / O p p o r tu n i t y D e f in it io n
Is t h e s c o p e c le a r ? B u s in e s s Im p a c t , t y p e & q u a n tifi c a tio n
G a te 1 D o e s it w a r ra n t a s tu d y ? P o t e n t ia l S o lu tio n
A p p ro v a l f o r s tu d y / f a s t - t ra c k
P r io r itis e d S o lu t i o n
SoR Is t h e b u s in e s s c a s e P F D 's
v a lid ? P la n , m il e s t o n e s a n d lo n g -l e a d s
H a v e a ll t h e o p ti o n s b e e n
G a te 2 C o s t e s t im a t e ( f u ll jo b + / - 5 0 % ; n e x t
id e n t if ie d & s e le c te d ? s t a g e + / -1 0 % )
B u d g e t C o d e a n d /o r A F E
F E E D S tu d y
S tu d y R e p o r t t o c o n t a i n ;
I s th e b u s in e s s c a s e s t ill - s c o p e d e f i n i t io n
G a te 3 v a lid ? - ris k e d c o s t e s tim a t e
I s th e jo b s a n c t io n a b le ? - F u ll D D & I m p le m e n ta t io n S c h e d u l e
H a s it s re la tiv e p r io r it y ( ris k e d p l a n )
D e s ig n a n d b e e n a g re ed ? - P & D I 's + C & E 's + S C E 's
- S a f e t y S c re e n in g ( i.e . H A Z O P )
Im p le m e n ta tio n
- R is k r e v ie w & p l a n
H a v e c e r t' s b e e n s ig n e d
o f f?
A r e a l l p u n c h - lis t ite m s - I V B 's , S C E ' s , P S 's & W S E 's
H a n d-o v e r c le a r? - M MS
S y s te m C o m m i s s io n e d ? - S p a r e s & s p e c ia l to o ls
O p e ra tio n s a n d D o c s & M M S u p d a te d ? - D o c s & d ra w in g s a s - b u ilt
C o m m e rc i a l c lo s e - o u t ? - T ra in in g
C lo s e - o u t - O & M m a n u a ls
- le s s o n s le a r n t
- c o m m e r c ia ls / K P I 's
The following table summarises the roles and responsibilities with respect to the Gate
system within Fairfield Energy and its key stakeholders;
Page 5 of 9
At The Gate
All projects shall be subjected to an appropriate level of risk assessment, these can
occur through all stages of the project life cycle and can roughly be divided into the
following 4 elements;
Throughout the project life-cycle a risk register should be maintained, along with
mitigation strategies and identified owners.
Modelling software should be used to develop S-curves for schedule and cost P10,
P50 & P90 out-turn estimates. These will then allow the organization to make informed
decisions on project priorities, growth and contingencies (refer to Cost Risk
Management Procedure).
Page 6 of 9
At The Gate
The dutyholder MoC process is controlled using a series of consultation forms, these
are discussed in the Amec procedure (0052-01-000-PRO-001) and can be
summarizsed as follows;
Change Description
Proposal Form
CP1 Change Proposal Initiation
CP2 Technical Change Review/Comment
CP3 Hazard Identification
CP4 Justification/Comment
CP5 Instruction to implement
CP6 Confirmation of completion
As the proposed project moves through various phases of technical definition, the
accuracy of the cost estimate should become more refined and the risks to the project
more quantifiable. It is important to distinguish between the estimated overall cost for
the project and the actual cost that is risked by implementing the next phase of the
work – the stage cost. The level of accuracy for each stage cost should be +/-10%, if it
is greater than that then more definition is still required before it is progressed.
All estimates must include dutyholder costs (onshore TA’s, offshore support, logistics,
beds, flights, etc.).
Every project must be charged to an approved budget. If one does not exist for the
work then an AFE must be raised and approved.
Page 7 of 9
At The Gate
All projects will require plans so that they can be included in the 5 year, 2 year and 90
day management plans. No modification should appear within the 28 day plan without
notice, unless there is an urgent business requirement – this will require specific
General Manager approval.
Forward Planning
The asset 2 year plan will show all known significant engineering modifications and
projects, that are approved or could potentially be initiated during this period. This plan
is regularly updated and will reflect existing budgets. It will be used to indicate potential
work to key contractors and as such requires their input (particularly when estimating
engineering, equipment delivery and implementation periods).
It should also be noted that no project activity can enter the 28 day plan without an
approved workpack and available materials to implement the workscope.
Page 8 of 9
At The Gate
Page 9 of 9