SV-COMM-TEP-023 - Preservation Comments / Remarks
YES / NO / NA
GENERAL
SPECIFIC
Have the preservation elements been assigned correctly and in line with
Vendors requirements?
6 Yes as per Vendor requirement YES
Apakah perencanaan kegiatan preservasi dilakukan sesuai dengan
persyaratan vendor?
Has the preservation work been carried out as planned and in line with
7 Vendors requirements? Yes man power allocation is aligned with preservation procedure YES
Apakah kegiatan preservasi dilakukan sesuai dengan persyaratan vendor?
Has preservation inspection been carried out as planned? Regular inspection is carried out as per planned and instruction from CSTS
8 YES
Apakah preservasi dilakukan sesuai dengan perencanaan? Preservation team
Has the preservation work been recorded in WinPCS and preservation label
(equipment) correctly?
9 Regular preservation are recorded and reported to WinPCS Administrator YES
Apakah catatan preservasi telah diinput ke WinPCS dan label preservasi
tepat?
For the case of preservation handover between CONST and COMM, is the
handover document available and signed by all parties?
10 Not yet started NA
Untuk kasus handover preservasi dengan COMM/CONST,apalah dokumen
handover tersedia dan ditandatangani?