Hatchery Kasolwe Phase 2
Hatchery Kasolwe Phase 2
TOTAL 1 #REF!
PRELIMINARIES % 5 #REF!
TOTAL 4 #REF!
BILLS OF QUANTITIES
COUNTRY: UGANDA
GANDA
TITIES
CTION OF HATCHERY IN
TRICAL INSTALLATIONS.
OURCES CENTER AND DATA
No. Description Unit Qty Total UShs
TOTAL 1 #REF!
TOTAL 3 #REF!
FOR
FOR
PRELIMINARIES % 5 #REF!
TOTAL #REF!
Site preparation
Filling pits
Earthworks
Strip top vegetable soil average 250mm thick,
E store on site approved wanted usable material
for later re-use, load and Cart away unwanted
spoil from site S.M ### 5,000 1,320,000
G Ditto over 1.5m but not exceeding 3.0m deep C.M 66 12,000 792,000
Allow for excavation in rock as specified
H ( Provisional ) C.M 20 30,000 600,000
A DEFINITION OF TERMS
'Works' shall mean all or any portion of the work, materials and
articles, wherever the same are being manufactured or prepared,
which are to be used in the execution of this Contract and whether
the same may be on the site or not.
A GROUP SIZES
Girths, depths or sizes grouped together in the Bills of Quantities
item descriptions by means of hyphenated upper and lower limits
shall be interpreted as 'exceeding' the lower limits and 'not
exceeding' the upper limit.
B DESCRIPTION OF SITE
The project is located in BUGABULA, KAMULI DISTRICT on the
premises of NATIONAL ANIMAL GENETIC RESOURCE CENTER
AND DATABANK
All materials for incorporation in the works must be stored on the site
before payment is effected unless specifically exempted by the
Project Manager.
-
The Contractor shall price the below mentioned items:
h) Police regulations;
i) Traffic regulations;
6,000,000
The Contractor is also to make allowance for the following particular
items:
A SITE OFFICES
The Contractor must allow for establishment or hire of space for site
offices for his use in such positions as may be adequate and
6,000,000
convenient for use by his own site staff and removing same at
completion and making good all areas disturbed.
The Contractor shall also provide an adequate refuse collection
service for all offices, to the satisfaction of the Project Manager.
The Contractor shall also maintain all furniture and equipment
provided by him in a reasonable state of repair and usable condition
and shall replace promptly any item which becomes unserviceable
or is lost, to the satisfaction of the Project Manager.
B SECURITY OF WORKS
The Contractor shall provide adequate security by day and by night
for the entire site together with any related materials and facilities
but in collaboration with the Client's security establishment. This
shall include the provision of suitable gates and fencing and the full
time attendance of permanent watchmen, all to the satisfaction of
the Project Manager.
The Contractor shall provide one fully lockable furnished office for
the Project Manager's representatives at the Site.
C ACCESS TO SITE
Access to the site shall be agreed with the Engineer prior to the
commencement of the works and the contractor must allow for
providing, forming and maintaining all temporary crossings and
access roads onto the site, removing the same on completion and
making good any damaged or disturbed surfaces as directed by and
to the approval of the Engineer.
The Contractor shall allow for providing the necessary latrines for
the employees on the works, including those employed by Sub-
Contractors, to the satisfaction of the Health and Medical Authorities
and for maintaining the same in a thoroughly clean and sanitary
condition and paying all conservancy fees.
The Contractor shall allow for removing the said latrines and leaving
the ground clean and free from pollution upon completion to the
satisfaction of the Health and Medical Authorities.
3,500,000
The Contractor shall be required to provide a brief methodology of
work and approach to the safety requirements, safety audit and fire
protection facilities he proposes to use during the works. He should
specifically put a price to the safety requirements for his operations
during construction including any test equipment.
A AS BUILT DRAWINGS
The Contractor must allow for removing and clearing away all plant,
rubbish and unused materials, and leaving the whole of the site of
the works in a clean and tidy state at all times and at completion to
the satisfaction of the Engineer.
B SIGNBOARD
The Contractor must allow for providing, erecting and maintaining a
site signboard, the size, type of construction and lettering of which
shall be to the Engineer's design. The board is to be fixed in an
elevated position on the site where indicated by the Project
Manager. On completion of the works, the sign board shall be
removed and disturbed areas made good.
A SPECIFICATIONS
Reference within Bills of Quantities descriptions are to
Specifications, reproduced in full elsewhere. The Contractor will be
deemed to have allowed for all Specification requirements in his
rates and prices and must resolve any queries or misunderstanding
regarding Specification requirements with the Project Manager prior
to the return of tenders. No extra claim will be admitted nor claims
allowed in respect of material and workmanship requirements or
other matters relating to these Specifications for any reason
whatsoever.
B MEASUREMENTS
These Bills of Quantities shall be deemed to generally follow
principals laid down in the Standard Method of Measurement of
Building Works for the Republic of Uganda, with the following
exceptions:
Clause D18 (a) and (b) of the Standard Method of Measurement
shall be deleted and the following working substituted:-
A SAMPLES
SUMMARY PAGE
-
Total BF from Page 2
Total BF from Page 3
Total BF from Page 4 6,000,000
Total BF from Page 5 -
Total BF from Page 6 -
Total BF from Page 7 3,500,000
Total BF from Page 8 -
Total BF from Page 9 -
Total BF from Page 10 -
P & G 10 / 10
Item Description Unit Qty Rate UShs Total UShs
Finishes to Windows
Cement and sand (1:3)
15mm plaster to reveals : average 200-300mm wide:
I L.M 151 5,000 755,000
trowelled smooth:external.
Superstructure 573803137.xls
Item Description Unit Qty Rate UShs Total UShs
ELEMENT NO. 5
DOORS
Precast concrete class 25 reinforced in
230 x 200mm Lintel laid including 4No. 12mm diameter
A bars and 8mm stirrups at 150mm centers L.M -
Steel Casement Doors
Supply and Fix the following Purpose made mild steel door
all members in 3mm thick steel sections (where thickness
is not stated); complete with mild steel frame, burglar
proofing grilles, all ironmongery, fixing lugs and a single
coat of red oxide primer; all fixed as per Architect's details
B Size 2700mm x 2750mm high as D 1 No -
C Size 2500mm x 3200mm high as D2 No -
D Size 1200mm x 2400mm high as D3 No -
E Size 1200mm x 2400mm high sliding door as D4 No -
Superstructure 573803137.xls
Item Description Unit Qty Rate UShs Total UShs
Facing Bricks
Approved Facing bricks; bedded and jointed in c/s morta
G L.M 88 20,000 1,760,000
mix to external walls all to architect's detail
Ceiling Eaves
Expanded Metal Lath Plastered ceiling comprising, 100 x
50mm softwood framing ceiling joists at 600mm centres; 100
H x 50mm branderings at 600mm c/c; metal lath nailed onto S.M 66 82,000 5,412,000
framework; 10mm cement sand (1:4) pricking course,
including 12mm lime plaster (m/s)
Splash apron
Prepare and compact previously levelled ground and lay
75mm thick concrete (Class 20) bed 600mm wide with top
and edge surface trowelled smooth to gentle falls in 25mm
M thick cement and sand (1:3) screed on and including 100mm S.M 66 120,000 7,920,000
thick bed of well compacted and blinded hardcore and
150mm thick brick edge wall 300mm deep including all
excavations and formwork to edges
Superstructure 573803137.xls
Item Description Unit Qty Rate UShs Total UShs
ELEMENT NO. 7
INTERNAL FINISHES
Wall finishes
20mm Cement :lime : sand (1:3:4) plaster steel
trowelled on blockwork to receive:
A Paint S.M 1,323 12,000 15,876,000
B Ceramic wall tiles S.M 118 12,000 1,416,000
Floor finishes
Lay 20mm thick Cement and sand (1:4) screed
on concrete floor finished to receive Terrazo on ;
E Floors generally S.M 449 15,000 6,735,000
F Skirting L.M 369 5,000 1,845,000
Ceiling finishes
Reinforce the ceiling for Incubating room,Transfer room
and Drawer/Trolley storage and wash room with IPE
200X100X12M steel sections from Roofings Ltd.Provide
I KG 800.0 12,000 9,600,000
2No.Internal supports spanning the icubating room and
Transfer room,and 1No.Internal support spanning the
drawer/Trolley storage room
Take up the solid 230mm wall separating the male and
female washrooms to the ceiling level with hoop iron every S.M 10.0 20,000 200,000
two courses
Expanded Metal Lath Plastered ceiling comprising, 100 x
50mm softwood framing ceiling joists at 600mm centres;
J 100 x 50mm branderings at 600mm c/c; metal lath nailed SM 449.0 65,000 29,185,000
onto framework; 10mm cement sand (1:4) pricking
course, including 12mm lime plaster (m/s)
Superstructure 573803137.xls
Item Description Unit Qty Rate UShs Total UShs
TOTAL CARRIED TO SUMMARY 160,531,000
Superstructure 573803137.xls
Item Description Unit Qty Rate UShs Total UShs
ELEMENT NO. 8
FITTINGS
SUMMARY PAGE
DOORS 42,601,400
FITTINGS 9,000,000
Superstructure 573803137.xls
Item Description Unit Qty Rate UShs
BILL 5: ROOF
Rainwater collection
O 150mm diameter PVC gutter complete with holderbats L.M 106 25,000
P 100mm PVC down pipe complete with holder bats L.M 45 20,000
2,650,000
900,000
200,000
200,000
200,000
200,000
4,350,000
FOR
FOR
MAIN SUMMARY
1 Electrical Installations
3,650,000
Connection 755,000 400,000
2 Mechanical Installations
Electrical Installations
A Lighting points wired by 3 x 1.5mm2 SC PVC copper No 63 80,000
cables in 25mm heavy guage PVC conduit
surface/concealed conduit with drops concealed in walls
to switch positions complete with MK steel boxes
complete with all accessories.
Light Fittings
A Decorative LED Poultry lighting pendant pulsa with No. 16 65,000
plastic housing on single wire for 9W, with 90-100lm/w
Lumens dimable IP67 and Diameter 151xH242MM
(Light Type R)
D LED pendant Poultry lighting with 7W/9W LED bulb, No. 31 25,000
90-100lm/w Lumens dimable IP65 or equall
APPROVED
(Light Type B)
Switches
E 6A 1 gang 2way light switch as MK or equal approved No 26 20,000
complete with all accessories.
E Earth Electrodes made from hard drawn copper 16mm No. 2 150,000
diameter, 1200mm long, complete with cap, earth clamp,
and all accessories as made by FURSE or equal
approved.
F 400x400 mm Earth Mate made from hard drawn copper No. 1 200,000
16mm diameter, 1200mm long, complete with cap, earth
clamp, and all accessories as made by FURSE or equal
approved.
Power Supply
A Allow a lump sum of UGX 300000 for UMEME to Item 1 300,000
connect power Complete with Umeme metering Unit.
Energy Meters
C Three phase Electronic Energy Check Meters complete No 1 800,000
with a MOD-BUS interface, and all accessories and to
UMEME Standards and approval.
COLLECTION
FROM PAGE 02
FROM PAGE 03
FROM PAGE 04
FROM PAGE 05
5,040,000
715,000
800,000
1,800,000
600,000
1,250,000
10,205,000
1,040,000
2,400,000
800,000
775,000
520,000
200,000
120,000
220,000
150,000
6,225,000
1,500,000
250,000
100,000
300,000
200,000
200,000
400,000
500,000
3,450,000
300,000
30,000
800,000
1,000,000
800,000
2,930,000
10,205,000
6,225,000
3,450,000
2,930,000
22,810,000
BILLS OF QUANTITIES: MECHANICAL INSTALLATIONS
Rate (Ugx)
Item Description Unit Qty
Mechanical Installations
Sanitary Fittings
E Surface shower pipe con wall complete with Shower set No 2 500,000
with slide rail, multi function shower head, hand set,
Matrix mixer valve and a diverter As JAQUAR SHA-
CHR-1215FSHK , complete or equal approved.
F Toilet roll holder with flap as JAQUAR AKP-CHR- No 2 150,000
35753P complete with fixing to the wall.
PIPE WORK
A 25mm PPR cold water Pipe work complete. m 15 25,000
F 110mm Upvc PN6 soil waste pipe buried in the ground to m 65 30,000
a fall of 1:60 complete with all accessories.
G 50mm uPVC soil waste pipe in wall complete with all m 25 30,000
accessories.
H 40mm uPVC soil waste pipe in wall complete with all m 20 10,000
accessories.
TOTAL CARRIED TO COLLECTION
FROM PAGE 02
TOTAL CARRIED TO COLLECTION
Water Supply
Sewer System
D Excavate for and construct manhole size No 10 600,000
450mmx600mmm depth to invert level (average) 600mm
built in 200mm thick concrete block walling in 1:4
cement mortar walls plastered inside with approved water
proofing additive in two coats:150mm concrete mix
(1:3:6-20mm aggregate) base 1000mmx150mm (average)
thick benching including 2No straight and curved 150mm
half round main channel:150mm thick slab,
610mmx450mm rebate opening and double seal heavy
duty cast iron cover including all accessories as per
drawing.
COLLECTION
FROM PAGE 01
FROM PAGE 02
FROM PAGE 03
Amount (Ugx)
760,000
760,000
4,800,000
1,800,000
1,000,000
300,000
200,000
9,620,000
375,000
400,000
75,000
200,000
300,000
1,950,000
750,000
200,000
4,250,000
4,250,000
4,250,000
500,000
5,000,000
3,000,000
6,000,000
1,200,000
1,200,000
6,000,000
22,900,000
9,620,000
4,250,000
22,900,000
36,770,000
Item Description Unit Qty Rate UShs Total UShs
BILL NO. 6
General excavations and earthworks ( Provisional )
Paving
B Trim , level and compact previously excavated surfaces S.M 214 2,000 428,000
D Supply and lay lime stabilised murram 300mm thick; compact S.M 214 20,000 4,280,000
mechanically at approved optimum moisture content and
MDD values in layer not exceeding 150mm thick to the
entire satisfaction of the Engineer
F Provide and lay 60mmthick concrete block paviours; light duty S.M 214 60,000 12,840,000
type, laid to approved falls and cross falls on and
including 50mmthick bed of course sand