Professional Documents
Culture Documents
However, Before The Handing Over, The Following Processes Were Involved
However, Before The Handing Over, The Following Processes Were Involved
However, before the handing over, the following processes were involved;
• the Contractor issued a letter for joint site inspection to the site which includes the
representatives of the SPIU, Contractor and Consultants so as to check any outstanding
works;
• the Team conducted a site review to identify and verify outstanding issues;
• The Consultant compiles a final snag list of all outstanding items requiring resolution, with
input from SPIU and forward the list to the Contractor for necessary rectification;
• the Contractor then reviews the list of outstanding items with the team and set priorities
considering criticality, timelines and in line with client needs;
• the Contractor prepared and submitted a schedule of how the outstanding items will be
coordinated and procedures to be employed during the rectification work;
• the Contractor notified SPIU and Consultant when the works were completed;
• the Contractor together with the Resident Engineer coordinated a review of the completed
work and the Contractor submitted a Letter of Completion to the Supervising Consultant and
SPIU on confirmation by the team that all snags identified have been resolved and ensured
that all other project deficiencies and prerequisites have been achieved.
Finally, it has been a great achievement by the Contractor to complete the project on time in
line with project scope and specifications. We are pleased to inform you that the construction
work at the site is completed at the desired time. We request you to have a project
completion ceremony in your good office so that we depart our ways with a smile on our
faces.
Please see the attached templates for the checklists/snag list used on the site for the
supervision.