BOQ for electrical wiring and lighting work for Mr.

Varadrajan Bungalow at
Khandala Valley

SN Description Qnty Unit Rate Amount


1 Point wiring for primary light point / fan point / exhaust fan point /
call bell point with with 3 x 1.0 sq.mm copper wire in concealed
PVC conduit, with 10 Amp modular switch, modular plate, suitable
GI box in concealed manner complete in all respect including
required civil work like dutting, chiselling and making it good using
cement and sand mortar. One point controlled by one switch. (Switch
board to point) Nos.
2 Point wiring for secondary light point point same as above but
without switch and board. (Light point to Light point) Nos.
3
Point wiring for two way light point / fan point / exhaust fan point
with with 3 x 1.0 sq.mm copper wire in concealed PVC conduit,
with 10 Amp modular switch, modular plate, suitable GI box in
concealed manner complete in all respect including required civil
work like dutting, chiselling and making it good using cement and
sand mortar. One point controlled by two switches. (Two way point)
Nos.
4 Point wiring for primary light point / fan point / exhaust fan point /
call bell point with with 3 x 1.0 sq.mm copper wire in concealed
PVC conduit, with 10 Amp modular switch, modular plate, suitable
GI box in concealed manner complete in all respect including
required civil work like dutting, chiselling and making it good using
cement and sand mortar. Point(s) controlled by motion sensors Nos.
5 Power point wiring for power socket outlets with 2 x 4 sqmm FRLS
copper wire (P&N) + 1 x 2.5 sqmm FRLS copper wire (earth) in
concealed PVC conduit, with 10/20A Modular Switch and socket on
suitable modular plate & metal concealed box complete in all respect
including required civil work like cutting, chiselling and making it
good using cement and sand mortar. Nos,
6 Power point wiring for power socket outlets with 2 x 2.5 sqmm
FRLS copper wire (P&N) + 1 x 1.5 sqmm FRLS copper wire (earth)
in concealed PVC conduit, with 10/20A Modular Switch and socket
on suitable modular plate & metal concealed box complete in all
respect including required civil work like cutting, chiselling and
making it good using cement and sand mortar. Nos,
7 Point wiring for 10A socket point to be provided on same lighting
switch board with modular switch and socket Nos.
8 Laying of power circuit from MCB DB / Switch Board to Switch
Board using 3 x 1.5 Sq.mm. copper wires in PVC conduit laid
concealled in wall/ceiling/floor etc complete in all respect (including
requried civil work) RMtr
9 Laying of power circuit from MCB DB / Switch Board to Switch
Board using 2 x 2.5 + 1 x 1.5 Sq.mm. copper wires in PVC conduit
laid concealled in wall/ceiling/floor etc complete in all respect
(including requried civil work) RMtr
10 Laying of power circuit from MCB DB / Switch Board to Switch
Board using 2 x 4.0 + 1 x 2.5 Sq.mm. copper wires in PVC conduit
laid concealled in wall/ceiling/floor etc complete in all respect
(including requried civil work) RMtr
11 Laying of power circuit from MCB DB / Switch Board to Switch
Board using 2 x 6.0 + 1 x 2.5 Sq.mm. copper wires in PVC conduit
laid concealled in wall/ceiling/floor etc complete in all respect
(including requried civil work) RMtr
12 Laying of 1 x 1.5 sq.mm. inverter circuit from DB to individual
switch boards / switch board to switch board RMtr
13 Laying of telephone wire/Cat6 wire/RG6 TV / CCTV wire in
concealled PVC conduit including all civil work and accessories as
rrequried and incudling termination of wire in respective outlets RMtr
14
Installation of concealled switch board complete with modular plate,
switches and sockets and respective connections (upto 8 Mod) Nos.
15 Installation of TPN MCB DB concealled in wall complete with all
accessories, cable/wire terminations etc 1 No.
16 Installation of downlight / spot light / wall light etc in false ceiling or
surface mounted Nos.
17 Installation of decorative hanging lights Nos.
18
Installation of LED strip light / profile light flush or surface mounted Mtr
19 Installation of outdoor landscape lights / focus lights etc, flush or
surface mounted Nos.
20 Installation of Ex. Fan / Ceiling fan complete with fixing of U bolt
on ceiling / sloping roof etc. Nos.
21 Laying of main cable 4C x 25 Sq.mm. Al. arm cable from nearby
miniplillar to meter box to MCB DB. RMtr
22 Termiantion of above main cable using single compression cable
gland and Al. lugs 4 Nos.
23
Providng Chemical earthing using 76mm dia 3 Mtr long PIP GI earth
electrode with 50 KGs of Back Fill Compound complete with drilling
of 4"/6" hole and making chamber with 450 x 450 mm CI cover 2 Nos,
24 Supply and installation of 25 x 3 mm GI patti from earth pit to main
meter / MCB DB complete with requried hardware etc. (patti to be
joint with two SS nutbolts to earth electrode and patti to patti joint) 20 Mtrs

Notes & Terms

1) Lighting Mains from DB to first switchboard will be paid seperately. Mains from SB to SB to be
incorporated within point wiring
2) Rate for telephione / TV / Data (CAT6) wiring is inclusive of termination / connections in outlets
3) Material will be provided on site / your office as per your demand. You will have to give requisition atleast
a week in advance to arrange the material on site.
4) Security of Material, once handed over to you, will be in your scope. Material inventory will be tallied at
regular intervals and after work completion
5) Bill to be prepared after proper varification of quantity from electrical consultant
6) Payment will be released after verification of the same by consultant

You might also like