Q1 Project Duration

19
EST A EFT EST A EFT Q2 Critical Path
Total Float Free Float Total Float LST-EST Free Float LFT-EFT ' Start > A > B > D> G > H > Finish
LST Durations LFT LST Durations LFT Q3 Near Critical Path
' Start > A > C > E> G > H > Finish
Q4 Free Float of Each Activity
A B C D E F G H
0 0 0 0 6 9 0 0
Q5 Total Float of each activity
A B C D E F G H
0 0 6 0 6 9 0 0

0 A 3 3 B 7 7 D 12 12 G 16
0 0 0 0 0 0 0 0 0 0 0
0 3 3 3 4 7 7 5 12 12 4 16

3 3 C 5 5 E 6 16 H 19
6 0 6 6 6 6 0 0
9 2 11 11 1 12 16 3 19

5 F 7
9 9 9
14 2 16

Path _1 A B D G H 19 Critical Path


3 4 5 4 3
Path _2 A C E G H 13 Near Critical Path
3 2 1 4 3
Path _3 A C F H 10
3 2 2 3
EST +
Duration
Activity No. of Pred Duration EST EFT
A 0 3 0 3
B 1 4 A 3 7
C 1 2 A 3 5
D 1 5 B 7 12
E 1 1 C
F 1 2 C
G 2 4 E E 12 16
H 2 3 F G 16 19
LFT-
Duration
LST LFT Critical Near Critical Total Float Free Float
0 3 x
3 7 x

7 12 x

12 16 x
16 19 x