A B C D E F G H: Q1 Project Duration Q2 Critical Path Q3 Near Critical Path Q4 Free Float of Each Activity

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

Q1 Project Duration

19
EST A EFT EST A EFT Q2 Critical Path
Total Float Free Float Total Float LST-EST Free Float LFT-EFT ' Start > A > B > D> G > H > Finish
LST Durations LFT LST Durations LFT Q3 Near Critical Path
' Start > A > C > E> G > H > Finish
Q4 Free Float of Each Activity
A B C D E F G H
0 0 0 0 6 9 0 0
Q5 Total Float of each activity
A B C D E F G H
0 0 6 0 6 9 0 0

0 A 3 3 B 7 7 D 12 12 G 16
0 0 0 0 0 0 0 0 0 0 0
0 3 3 3 4 7 7 5 12 12 4 16

3 3 C 5 5 E 6 16 H 19
6 0 6 6 6 6 0 0
9 2 11 11 1 12 16 3 19

5 F 7
9 9 9
14 2 16

Path _1 A B D G H 19 Critical Path


3 4 5 4 3
Path _2 A C E G H 13 Near Critical Path
3 2 1 4 3
Path _3 A C F H 10
3 2 2 3
EST +
Duration
Activity No. of Pred Duration EST EFT
A 0 3 0 3
B 1 4 A 3 7
C 1 2 A 3 5
D 1 5 B 7 12
E 1 1 C
F 1 2 C
G 2 4 E E 12 16
H 2 3 F G 16 19
LFT-
Duration
LST LFT Critical Near Critical Total Float Free Float
0 3 x
3 7 x

7 12 x

12 16 x
16 19 x