Professional Documents
Culture Documents
Check List For Slab Steel Checking.: I) Form Work
Check List For Slab Steel Checking.: I) Form Work
Check List For Slab Steel Checking.: I) Form Work
i) Form Work::______
1) Sufficient number of vertical supports.
2) No hanging of vertical supports.
3) Cross bracing of vertical supports.
4) No gaps in centring plates.
5) No openings at column and beam junctions.
6) Extra supports should be spared for emergency use.
7) Soil below posts should be well settled/ CC blocks/ Horizontal beams/ Centring plates
8) Different levels of slab bottoms for different thickness of Slabs.
9) Stair case form should checked for Slope
iii) Beams::_______
1) Stirrup/ Ring External dimension should be checked and verify the clear cover available
at slab top.( This check should be done during cutting and bending of rings).
2) Stirrups should be bent to 135 degrees.
3) Bar Bending Schedule should be prepared for all RCC members.
4) Main STEEL dia and number of rods.
5) Spliced lap length w.r.t. approved drawing.
6) Staggering of laps.
7) Cover to Steel w.r.t. approved drawing.
8) Stirrups spacing.
9) Stirrups bending and binding.
10) Each Steel bar going to end shall have 'L’ bend.
11) Depth of Beam w.r.t. approved drawing.
12) Required cover at top of beam and slab at top.
13) Beam ends should have cantering plates, no open end.
14) Expansion joints should be checked with approved drawings.
v) Coarse Aggregate::________
1) Check the Mix design.
2) Check gradation of Aggregate by blending 20 mm, 12 mm and 6 mm size metal as specified
in mix design.
3) Over Size Aggregate should not be permitted.
4) Flaky and Elongated Aggregate should not be permitted.
5) Sufficient quantity of each size metal should be stacked before hand.
6) Aggregate should be wet with water.
viii) CEMENT::_________
1) Approved brand cement.
2) Latest stock as seen on bags.
3) Only OPC. Never use other than OPC 43 or OPC 53 grade cements.
4) Admixture should be as per approved mix design.
ix) Concrete::_______
1) Concrete Aggregate should be measured by weighing.
2) If volume is allowed, calculate volume of each Aggregate as per approved mix design.
3) Volume should be measured with Boxes only. Never by steel pans.
4) Each Box volume should be exactly equal to the volume of a single cement
bag.(50/1440=0.03472 cum.)
5) Concrete should not be laid at a temperature more than 30 degrees centigrade.
V. VENKATA NARAYANA,
EXECUTIVE ENGINEER