Saudi Electricity Company: Revisions
Saudi Electricity Company: Revisions
Saudi Electricity Company: Revisions
The CONTRACTOR shall perform on Lump Sum Turnkey basis, the detailed engineering
design, material procurement, quality management, fabrication, manufacture, factory
testing and inspection, supply and delivery of all the materials to WORK SITE, install, test,
commission, and perform all associated WORK to put into service with guarantee the
DESCRIPTION
A. 380kV Double Circuit O/H T/L between Juaymah BSP to Dhahran Home
PREP. BY: ROL
Ownership BSP:
DATE: July 27, 2015
1. Design and construct one (1) 380kV overhead transmission line double circuit,
vertical configuration, on COMPANY provided standard family of latticed steel
towers, approximately 93.13 kilometers long (total) from Juaymah BSP-
Dhahran Home Ownership to Dhahran Home Ownership BSP, using four
(4)X1080.6 KCMIL ACAR conductor per phase with two (2) OPGW, 120kN
APPROVED rated strength with 24kA fault current for 0.3 sec. at 55C initial temperature.
Refer to the following Route Maps:
a. TCD-E0390 Portion-1 approximately 12.32 kilometers
BY: Cipriano S. Mauricio
latticed steel towers, from the existing tower at PT-D up to Dhahran Home
CHK’D
APPROVED
8. Connect the grounding of the last tower of the proposed 380kV OHTL (at two
locations on the tower) before the substation gantry structure to the grounding
BY: Cipriano S. Mauricio grid of Juaymah BSP and Dhahran Home Ownership BSP.
DATE: July 27, 2015
9. CONTRACTOR shall provide line identification of the proposed Juaymah BSP-
Dhahran Home Ownership BSP 380kV OHTL.
10. CONTRACTOR shall perform full-scale load test on prototype foundations for
one (1) Tangent type structure and one (1) Heavy Angle type structure for all
CERTIFIED types of foundations to be used in the PROJECT (Juaymah BSP-Dhahran
Home Ownership-Dhahran South Transition Yard) before proceeding with the
final construction of the foundations. The two uplift tests will be for the entire
Juaymah BSP-Dhahran Home Ownership BSP and Dhahran Home Ownership
BY: Mohammad A. Al-Saffar
12. The above O/H T/L WORK will establish the following 380kV OHTL circuit
connections:
B. 380kV Double Circuit O/H T/L between Dhahran Home Ownership BSP to
CHK’D
1. Design and construct one (1) 380kV overhead transmission line double circuit,
vertical configuration, on COMPANY provided standard family of latticed steel
towers, approximately 20.19 kilometers long from Dhahran Home Ownership
DESCRIPTION
REVISIONS 3. Connect the grounding of the last tower of the proposed 380kV OHTL (at two
locations on the tower) before the substation and Transition gantry structure to
the grounding grid of Dhahran Home Ownership BSP and Dhahran South
BSP Transition Yard.
DEPT.: EHV-EDD/ESD
4. CONTRACTOR shall provide line identification of the proposed Dhahran
PREP. BY: ROL
Home Ownership BSP- Dhahran South BSP Transition Yard 380kV OHTL
DATE: July 27, 2015
5. The above O/H T/L WORK will establish the following 380kV OHTL circuit
connections:
a. Dhahran Home Ownership BSP to Dhahran South BSP Transition Yard
circuits 1 and 2.
ground wire arm to carry the proposed OPGW. CONTRACTOR shall only
BY: Mohammad A. Al-Saffar provide OPGW, which are compatible to the original design of the tower.
DATE: July 27, 2015 CONTRACTOR shall provide two (2) additional OPGW between the gantry and
last tower for shielding purposes. The steel tower drawings provided by the
COMPANY shall be provided with new drawing number. Tower with SP series
shall only be used if the normal towers S1N, TA1N, TA2N, TA3N and DE
cannot be used.
All other or new overhead transmission line structures/gantry, other than
COMPANY provided structures, which are required to complete the PROJECT,
shall be designed, fabricated, and erected by the CONTRACTOR in
THIS DOCUMENT IS
NOT TO BE USED FOR accordance with the requirement of the COMPANY Standards. One (1) type of
CONSTRUCTION
FOR
OR
ORDERING tower shall be tower tested in accordance with the COMPANY requirement.
MATERIALS UNTIL
CERTIFIED AND DATED
The COMPANY shall identify the type of tower to be tested.
CA-090923 sheets 30, 31, 33, 42 and 47. CONTRACTOR shall check the
existing tower members and submit the design calculations for COMPANY
review and approval. In the calculation of the slenderness ratio L/r, length L in
the plane of bending shall be taken as the distance between support and not at
the intersection of the cross bracing.
4. CONTRACTOR shall reinforce the horizontal diaphragm of the 380kV family of
tower (S1N, TA1N, TA2N, TA3N, DE and all SP type towers) provided by SEC.
NO.
REVISIONS The horizontal diaphragm of the lower level of the basic body (between the
basic body and the leg/body extension) and the diaphragm of the body
extension shall be provided with additional reinforcements as shown on drawing
WT-913734. CONTRACTOR shall revise the affected fabrication drawings and
DEPT.: EHV-EDD/ESD submitted to the COMPANY for review and approval.
D. CONTRACTOR shall design, fabricate and install the required structures crossing
existing lines, wadis, farms, hills, valleys, pipeline, paved road, tracks and any other
facilities or for any valid reasons and requirements so as to complete the WORK
successfully to the satisfaction of COMPANY.
E. Line Crossings:
THIS DOCUMENT IS
NOT TO BE USED FOR Unless other means of crossing, i.e. using GIL or Underground cable is specified in
CONSTRUCTION OR
FOR ORDERING the scope of work, the following requirements and details shall be considered:
MATERIALS UNTIL
CERTIFIED AND DATED
1. Crossing below the existing 380kV O/H T/L. CONTRACTOR shall design and
construct all required gantry structures that will be used in crossing below the
existing lines. Crossing below the existing/proposed line shall use latticed steel
CHK’D
REVISIONS can propose the crossing arrangement using rigid bus with all supporting
structures.
2. Crossing above the existing 380kV OHTL when security and class of importance
of lines allow such type of crossing. Under no condition that this option is
allowed when it jeopardize the safety, security and reliability of the existing lines.
DEPT.: EHV-EDD/ESD
4. CONTRACTOR shall route the proposed O/H T/L crossing such that it will
satisfy all clearance requirement. If crossing will be below the existing OH TL,
APPROVED CONTRACTOR shall provide Type-I fence around the entire gantry crossing
with two 6 meter wide drive gate with access road connected to the OH TL
BY: Cipriano S. Mauricio access road, and warning signs. Fence shall be 7 meters away from the edge of
the gantry/structure. The entire area shall be developed similar to the
DATE: July 27, 2015
requirement of TES-P-122.11.
5. CONTRACTOR shall prepare separate drawings with full details for each
crossing. Drawing shall show all vertical and horizontal clearances, elevation of
the existing conductor (including the temperature considered in the sag of the
CERTIFIED
conductor). Drawing should also show the stringing sag and tension of the
proposed conductor and OPGW/OGW.
BY: Mohammad A. Al-Saffar
6. It is the CONTRACTOR's responsibility to obtain all data and information
DATE: July 27, 2015 pertaining to the existing OH TL, existing facilities, and perform all necessary
survey works at crossing points/area. Above WORK shall be done by the
CONTRACTOR at no additional cost to the COMPANY. CONTRACTOR shall
identify the location of the line crossings, if any, in the route map.
CONTRACTOR shall propose the method of crossing subject to COMPANY‟s
approval.
7. When the proposed OHTL is crossing above the existing OHTL, and there are
THIS DOCUMENT IS
NOT TO BE USED FOR
no restrictions in spotting or locating the proposed towers, in such case, as
CONSTRUCTION OR much as possible, the existing OHTL shall be located near the middle of the
FOR ORDERING
MATERIALS UNTIL span (between the proposed towers).
CERTIFIED AND DATED
CONTRACTOR considering all the above requirements and the security and
importance of each line crossing.
G. Conduct soil investigation and soil resistivity test at every location of the proposed
structures.
H. Live line washing accessories are not required, however, one (1) level platform
located at the mid cross arms shall be provided when overhead transmission line
tower height is more than 65 meters or higher.
NO.
REVISIONS
I. CONTRACTOR shall coordinate with MODA, Saudi Aramco and other concerned
authorities if spherical markers, conductor lights and warming lights (beacon lights),
tower painting (red and white) within the vicinity of airports and airstrips are
DEPT.: EHV-EDD/ESD required. Such requirement shall be installed by the CONTRACTOR if required in
accordance with the requirements of TES-P-122.01 and 12-TMSS-03.
PREP. BY: ROL
DATE: July 27, 2015 J. Manufacturer shall carry out the analytical damping study for the phase conductor
and OPGW for the proposed dampers based on the design data specified for this
T/L and in accordance with the requirements of 12-TMSS-01 and TES-P-122.04,
and submit to the COMPANY for review and approval.
K. The location/routing of the proposed 380kV overhead transmission lines are shown
APPROVED
in drawings TCD-E0390, TCD-E0396, TCD-E0401, TCD-E0443. CONTRACTOR
shall conduct all survey WORKS and shall prepare all Plan and Profile drawings.
Survey and Plan and Profile drawings shall be from the gantry of the source BSP to
the gantry of the destination BSP/Transition Yard. PI numbering shall start from the
BY: Cipriano S. Mauricio
DATE: July 27, 2015 gantry of the source station and increase towards the destination station. Survey
shall include all crossing points and the elevations of all existing lines that will be
crossed.
L. The following WORKS are included, but not limited to the following:
CERTIFIED
1. Mobilization.
2. Soil investigation and soil resistivity measurements.
BY: Mohammad A. Al-Saffar 3. Line route survey checks and structures staking.
DATE: July 27, 2015
4. Development of Plan and Profile drawings.
5. Structure spotting.
6. Design, fabrication, and erection of latticed steel tower.
7. Design, construction, and testing of foundations for latticed steel tower.
8. Conductor and OPGW/OGW field vibration measurements in accordance with
the requirements of 12-TMSS-01.
9. Supply, procurement, inspection, testing, storage, handling of all the required
material and equipment.
THIS DOCUMENT IS 10. Transportation, delivery, and storage of all materials to the WORK SITE.
NOT TO BE USED FOR
CONSTRUCTION OR 11. Construction of access roads and structure pads along the proposed overhead
transmission lines.
FOR ORDERING
MATERIALS UNTIL
CERTIFIED AND DATED
12. Installation of insulators and associated hardware and fittings.
accessories.
14. Supply, installation and testing of OPGW/OGW, U/G non-metallic fiber optic
cables, joint boxes and all necessary associated hardware and accessories.
15. Installation and testing of structure‟s grounding system.
16. Conduct line impedance measurements to determine the positive and zero
DESCRIPTION
REVISIONS
M. Refer to Appendix VI for the requirement of the communication WORKS.
N. CONTRACTOR shall provide and install signboard with electronic counter. Refer to
DEPT.: EHV-EDD/ESD drawing no. ET-907744 for the Scope of Work and specifications. CONTRACTOR
shall install the signboard within thirty days (30) from the project start date. The
PREP. BY: ROL
Electronic Counter shall show the number of days remaining for the project
DATE: July 27, 2015
completion”. Separate signboard shall be provided for each line. The number of
signboards shall be determined in consultation with the COMPANY.
P. CONTRACTOR shall strictly comply with the requirements of the Right of Way
approvals. CONTRACTOR shall comply with the following.
DATE: July 27, 2015 2. CONTRACTOR shall provide interference free access for the COMPANY
maintenance personnel, SAUDI ARAMCO and other concerned personnel.
5. CONTRACTOR shall protect and relocate (if necessary) all utilities, which may
CHK’D
6. The WORK within the jurisdiction of related agencies should be carried out
under the supervision of their representatives.
REVISIONS satisfy himself as to the extent of WORK location and all the condition under
which the WORK will be carried out. No claims based on the lack of any such
knowledge shall be entertained.
DEPT.: EHV-EDD/ESD 8. Approval of final location of spotted structures on the transmission line route
drawings shall be obtained from MOT, MODA, Municipality,, SAUDI ARAMCO
PREP. BY: ROL and other concerned agencies in writing prior to commencement of WORK.
DATE: July 27, 2015 Any changes or deviations from the approval condition stated in the approved
letters shall be specifically approved by the MOT, MODA, Municipality, SAUDI
ARAMCO and the concerned agency.
1. 380kV Double Circuit O/H T/L between Juaymah BSP to Dhahran Home
CERTIFIED
Ownership BSP:
BY: Mohammad A. Al-Saffar CONTRACTOR shall prepare the complete As Built drawings from Juaymah
DATE: July 27, 2015
BSP to Dhahran Home Ownership BSP. The existing drawings (such as string
insulators, foundations, erection & fabrication of towers, conductors, etc) of
Jubail Residential BSP (Fadhili)-Juaymah BSP 380kV O/H T/L related to the
proposed 380kV OHTL shall be included and assigned with new drawing
number. Design drawings, calculations and drawings listed under Section 3.03
shall be included under this line circuit. The CONTRACTOR shall acquire all
necessary information required to complete the drawings. CONTRACTOR shall
coordinate with the COMPANY. All existing drawings which are to be included
THIS DOCUMENT IS under this line circuit not drawn to SEC Standard requirements shall be re
NOT TO BE USED FOR
CONSTRUCTION OR drawn by the CONTRACTOR.
FOR ORDERING
MATERIALS UNTIL
CERTIFIED AND DATED 2. 380kV Double Circuit O/H T/L between Dhahran Home Ownership BSP to
Dhahran South Transition Yard:
3. 380kV Double Circuit O/H T/L between Juaymah BSP to Jubail 2 BSP:
Dhahran Home Ownership BSP. The new drawings (such as string insulators,
3
REVISIONS foundations, erection & fabrication of towers, conductors, etc) of the new
380kV O/H T/L related to Jubail 2-Juaymah BSP 380kV OHTL shall be included
and assigned with new drawing number. Design drawings, calculations and
drawings listed under Section 3.03 shall be included under this line circuit. The
DEPT.: EHV-EDD/ESD CONTRACTOR shall acquire all necessary information required to complete
the drawings. CONTRACTOR shall coordinate with the COMPANY. All existing
PREP. BY: ROL
drawings which are to be included under this line circuit not drawn to SEC
DATE: July 27, 2015
Standard requirements shall be re drawn by the CONTRACTOR..
CONTRACTOR shall coordinate with SEC when preparing the As Built
drawings. New drawing control sheet shall be prepared by the CONTRACTOR.
4. 380kV Double Circuit O/H T/L between Juaymah BSP to Jubail Residential
BSP (Fadhili):
APPROVED
Refer to Appendix VI
THIS DOCUMENT IS
NOT TO BE USED FOR
CONSTRUCTION OR
FOR ORDERING
MATERIALS UNTIL
CERTIFIED AND DATED