Saudi Electricity Company: Revisions

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

CERT.

SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬


APP’D

SECTION III – SCOPE OF WORK


CHK’D

The CONTRACTOR shall perform on Lump Sum Turnkey basis, the detailed engineering
design, material procurement, quality management, fabrication, manufacture, factory
testing and inspection, supply and delivery of all the materials to WORK SITE, install, test,
commission, and perform all associated WORK to put into service with guarantee the
DESCRIPTION

overhead transmission line and communication WORKS, as described in this Scope of


Work and Technical Specifications. CONTRACTOR shall reinstate to its original condition
or better the existing facilities damaged or affected during construction. Refer to Section
1.02 “Project Description” and Section 3.04 “Project Interface” for additional information
and requirements.

Following is the detailed Scope of Work:


NO.

REVISIONS 3.01 OVERHEAD TRANSMISSION LINE WORK

Refer to drawing number ET-914565 for the overhead transmission lines


arrangement plan.
DEPT.: EHV-EDD/ESD

A. 380kV Double Circuit O/H T/L between Juaymah BSP to Dhahran Home
PREP. BY: ROL
Ownership BSP:
DATE: July 27, 2015

1. Design and construct one (1) 380kV overhead transmission line double circuit,
vertical configuration, on COMPANY provided standard family of latticed steel
towers, approximately 93.13 kilometers long (total) from Juaymah BSP-
Dhahran Home Ownership to Dhahran Home Ownership BSP, using four
(4)X1080.6 KCMIL ACAR conductor per phase with two (2) OPGW, 120kN
APPROVED rated strength with 24kA fault current for 0.3 sec. at 55C initial temperature.
Refer to the following Route Maps:
a. TCD-E0390 Portion-1 approximately 12.32 kilometers
BY: Cipriano S. Mauricio

TCD-E0401 Portion-2 approximately 62.93 kilometers


DATE: July 27, 2015
b.
c. TCD-E0396 Portion-3 approximately 17.88 kilometers
2. As shown on drawing ET-914566, CONTRACTOR shall perform the following
work to complete the proposed 380kV OHTL from Juaymah BSP-Dhahran
CERTIFIED Home Ownership BSP:
a. Disconnect the existing conductors and OPGW from tower PT-A of the
BY: Mohammad A. Al-Saffar existing Juaymah BSP-Jubail 2 380kV OHTL, and re-connect the same to
DATE: July 27, 2015
the proposed tower at PT-B. From the proposed tower PT-B, construct the
proposed 380kV OHTL up to Juaymah BSP as mentioned under PTS-
14EO335 clause 3.01.A. After completion of the above swapping work,
this will create the new 380kV OHTL connection between Juaymah BSP-
Jubail 2.
b. Disconnect the existing conductors and OPGW from tower PT-D of the
existing Juaymah BSP-Jubail Residential (Fadhili) 380kV OHTL, and re-
connect the same to the proposed tower at PT-A. After completion of the
THIS DOCUMENT IS
NOT TO BE USED FOR
above swapping work, this will create the new 380kV OHTL connection
CONSTRUCTION
FOR
OR
ORDERING
between Juaymah BSP-Jubail Residential (Fadhili).
MATERIALS UNTIL
CERTIFIED AND DATED c. Design and construct one (1) 380kV overhead transmission line double
circuit, vertical configuration, on COMPANY provided standard family of

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
33
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

latticed steel towers, from the existing tower at PT-D up to Dhahran Home
CHK’D

Ownership BSP as mentioned under PTS-14EO335 clause 3.01.A.


3. Provide and install two (2) heavy angle towers near the proposed Dammam
North BSP as shown on drawing ET-914565. Cross arms shall be designed to
provide the required clearances considering the OHTL will be cut and loop in
and out of the proposed Dammam North BSP.
DESCRIPTION

4. Refer to drawings TCD-E0401 sheet 2 of 4: At the location of PI-2,


CONTRACTOR shall investigate and survey the actual location and
configuration of the existing towers adjacent to PI-2. If necessary,
CONTRACTOR shall adjust the location of the proposed PI-2 to provide the
necessary clearances.
5. The proposed 380kV overhead transmission line (Juaymah BSP-Dhahran
NO.

BSP) shall be transposed as per the requirement of TES-P-122.01, Section 16.


REVISIONS Phasing arrangement of the line shall be as per the requirement of TES-P-
122.01, Section 7 and Section 16. CONTRACTOR shall submit the
transposition and phasing arrangement drawing for COMPANY review and
approval.
DEPT.: EHV-EDD/ESD

6. CONTRACTOR shall change/update the existing line identification of Juaymah


PREP. BY: ROL BSP-Jubail 2 380kV O/H T/L and Juaymah BSP-Jubail Residential (Fadhili)
DATE: July 27, 2015 380kV O/H T/L affected by this PROJECT to conform to the new circuit
connections.
7. Provide and install two (2) additional OPGW, 24kA fault current capacity at
0.30 sec. at 55C initial temperature between the last tower and gantry for
shielding purposes at Juaymah BSP and Dhahran Home Ownership BSP.

APPROVED
8. Connect the grounding of the last tower of the proposed 380kV OHTL (at two
locations on the tower) before the substation gantry structure to the grounding
BY: Cipriano S. Mauricio grid of Juaymah BSP and Dhahran Home Ownership BSP.
DATE: July 27, 2015
9. CONTRACTOR shall provide line identification of the proposed Juaymah BSP-
Dhahran Home Ownership BSP 380kV OHTL.

10. CONTRACTOR shall perform full-scale load test on prototype foundations for
one (1) Tangent type structure and one (1) Heavy Angle type structure for all
CERTIFIED types of foundations to be used in the PROJECT (Juaymah BSP-Dhahran
Home Ownership-Dhahran South Transition Yard) before proceeding with the
final construction of the foundations. The two uplift tests will be for the entire
Juaymah BSP-Dhahran Home Ownership BSP and Dhahran Home Ownership
BY: Mohammad A. Al-Saffar

DATE: July 27, 2015


BSP-Dhahran South BSP Transition Yard.

11. Refer to Appendix VI for the requirement of the communication WORKS.

12. The above O/H T/L WORK will establish the following 380kV OHTL circuit
connections:

a. Juaymah BSP to Dhahran Home Ownership 380kV BSP circuits 1 and 2.


THIS DOCUMENT IS
NOT TO BE USED FOR
CONSTRUCTION OR
FOR ORDERING
MATERIALS UNTIL
CERTIFIED AND DATED

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
34
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

B. 380kV Double Circuit O/H T/L between Dhahran Home Ownership BSP to
CHK’D

Dhahran South BSP Transition Yard:

1. Design and construct one (1) 380kV overhead transmission line double circuit,
vertical configuration, on COMPANY provided standard family of latticed steel
towers, approximately 20.19 kilometers long from Dhahran Home Ownership
DESCRIPTION

BSP-Dhahran South BSP Transition Yard, using four (4)X1080.6 KCMIL


ACAR conductor per phase with two (2) OPGW, 120kN rated strength with
24kA fault current for 0.3 sec. at 55C initial temperature. Refer to drawing
TCD-E0443 Route Maps.
2. Provide and install two (2) additional OPGW, 24kA fault current capacity at
0.30 sec. at 55C initial temperature between the last tower and gantry for
shielding purposes at Transition Yard.
NO.

REVISIONS 3. Connect the grounding of the last tower of the proposed 380kV OHTL (at two
locations on the tower) before the substation and Transition gantry structure to
the grounding grid of Dhahran Home Ownership BSP and Dhahran South
BSP Transition Yard.
DEPT.: EHV-EDD/ESD
4. CONTRACTOR shall provide line identification of the proposed Dhahran
PREP. BY: ROL
Home Ownership BSP- Dhahran South BSP Transition Yard 380kV OHTL
DATE: July 27, 2015
5. The above O/H T/L WORK will establish the following 380kV OHTL circuit
connections:
a. Dhahran Home Ownership BSP to Dhahran South BSP Transition Yard
circuits 1 and 2.

APPROVED C. 380kV Tower:

BY: Cipriano S. Mauricio


1. The tower design drawings of the 380kV latticed steel towers (double circuit
vertical configuration) type "S1N" (WT-908471), "TA1N" (WT-908472), "TA2N"
DATE: July 27, 2015
(WT-908473), "TA3N" (WT-908474), "DE" (WT-908475), S1N/SP, TA1N/SP,
TA2N/SP, and TA3N/SP" provided by the COMPANY are included in this PTS
(Refer to drawing control sheet). CONTRACTOR shall determine the required
height and weight of towers to be used. The COMPANY will provide the final
fabrication drawings of latticed steel towers in CD, to the successful
CONTRACTOR only. CONTRACTOR shall fabricate and erect the latticed steel
structure. CONTRACTOR shall also check the adequacy of the overhead
CERTIFIED

ground wire arm to carry the proposed OPGW. CONTRACTOR shall only
BY: Mohammad A. Al-Saffar provide OPGW, which are compatible to the original design of the tower.
DATE: July 27, 2015 CONTRACTOR shall provide two (2) additional OPGW between the gantry and
last tower for shielding purposes. The steel tower drawings provided by the
COMPANY shall be provided with new drawing number. Tower with SP series
shall only be used if the normal towers S1N, TA1N, TA2N, TA3N and DE
cannot be used.
All other or new overhead transmission line structures/gantry, other than
COMPANY provided structures, which are required to complete the PROJECT,
shall be designed, fabricated, and erected by the CONTRACTOR in
THIS DOCUMENT IS
NOT TO BE USED FOR accordance with the requirement of the COMPANY Standards. One (1) type of
CONSTRUCTION
FOR
OR
ORDERING tower shall be tower tested in accordance with the COMPANY requirement.
MATERIALS UNTIL
CERTIFIED AND DATED
The COMPANY shall identify the type of tower to be tested.

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
35
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

2. Leg extension shall be limited to a maximum of 10 meters (For tower S1N,


CHK’D

TA1N, TA2N, TA3N and DE).


3. The deflection of the diagonal/redundant members of the Body extension and
Leg extension of tower S1N, TA1N, TA2N, TA3N, DE, S1N/SP, TA1N/SP,
TA2N/SP, and TA3N/SP shall not exceed L/130. If the deflection exceeds the
above limit, CONTRACTOR shall provide hangers/supports similar to drawings
DESCRIPTION

CA-090923 sheets 30, 31, 33, 42 and 47. CONTRACTOR shall check the
existing tower members and submit the design calculations for COMPANY
review and approval. In the calculation of the slenderness ratio L/r, length L in
the plane of bending shall be taken as the distance between support and not at
the intersection of the cross bracing.
4. CONTRACTOR shall reinforce the horizontal diaphragm of the 380kV family of
tower (S1N, TA1N, TA2N, TA3N, DE and all SP type towers) provided by SEC.
NO.

REVISIONS The horizontal diaphragm of the lower level of the basic body (between the
basic body and the leg/body extension) and the diaphragm of the body
extension shall be provided with additional reinforcements as shown on drawing
WT-913734. CONTRACTOR shall revise the affected fabrication drawings and
DEPT.: EHV-EDD/ESD submitted to the COMPANY for review and approval.

PREP. BY: ROL


5. S1N tower and S1N/SP shall be type tested if the fabricator or supplier
DATE: July 27, 2015
proposed by the CONTRACTOR has not done the Full Scale test on the above
mentioned COMPANY 380kV tower. Full scale loading test shall be in
accordance with the requirements of 20-TMSS-01. If the Full scale loading test
has been done by the proposed fabricator or supplier, then the CONTRACTOR
shall submit the test report for COMPANY review and approval.
In case of tower failure during testing, Contractor has to carry out the
APPROVED
necessary Work such as engineering, design and modifications to towers and
re-testing at no additional cost to the COMPANY.
BY: Cipriano S. Mauricio 6. Stub angle shall be tested for mechanical and chemical properties to verify the
mill certificate proposed by the CONTRACTOR. Minimum of two (2) samples
DATE: July 27, 2015
for every batch/lot are required to be tested for mechanical and chemical
properties and to verify the mill certificate. Testing shall be witnessed by a
Company approved Third party inspector.
7. No change of the materials shall be permitted unless it is proven by several
suppliers that the original material is not available. The suitability of the
CERTIFIED
proposed materials shall be verified by calculation and testing.
8. Gusset plates and splice plates shall be high tensile steel. COMPANY provided
BY: Mohammad A. Al-Saffar
tower design of gusset plates and splice plates shall be changed to high tensile
DATE: July 27, 2015 steel.

D. CONTRACTOR shall design, fabricate and install the required structures crossing
existing lines, wadis, farms, hills, valleys, pipeline, paved road, tracks and any other
facilities or for any valid reasons and requirements so as to complete the WORK
successfully to the satisfaction of COMPANY.

E. Line Crossings:
THIS DOCUMENT IS
NOT TO BE USED FOR Unless other means of crossing, i.e. using GIL or Underground cable is specified in
CONSTRUCTION OR
FOR ORDERING the scope of work, the following requirements and details shall be considered:
MATERIALS UNTIL
CERTIFIED AND DATED
1. Crossing below the existing 380kV O/H T/L. CONTRACTOR shall design and
construct all required gantry structures that will be used in crossing below the

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
36
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

existing lines. Crossing below the existing/proposed line shall use latticed steel
CHK’D

gantry structures, horizontal configuration. CONTRACTOR shall design,


fabricate and install the required latticed steel gantry structures which shall also
be designed as full dead end structure (all conductors and OPGW on one side
only). The height of the latticed steel gantry shall be such that the shielding
angle shall cover all the circuits. The portion of the proposed line crossing below
DESCRIPTION

the existing/proposed line shall be fully shielded. OPGW shall be continuous. In


the event the OPGW cannot be continuous, then the CONTRACTOR shall
provide an Underground Non Metallic Fiber Optic Cable (in concrete encased
ductbank), and the grounding to the next structures shall be connected at
minimum of two locations. If two circuits cannot cross on the same span due to
the available clearance restriction, then CONTRACTOR shall determine an
alternate route at no additional cost to the COMPANY. Also, in case the
available clearance will limit the use of normal conductor, then the Contractor
NO.

REVISIONS can propose the crossing arrangement using rigid bus with all supporting
structures.
2. Crossing above the existing 380kV OHTL when security and class of importance
of lines allow such type of crossing. Under no condition that this option is
allowed when it jeopardize the safety, security and reliability of the existing lines.
DEPT.: EHV-EDD/ESD

PREP. BY: ROL


This option can only be implemented upon approval of the COMPANY.
DATE: July 27, 2015
3. Crossing line shall be arranged so that the higher voltage line or line of higher
security shall be over the line of lower voltage or lower security. All methods of
crossings shall be subject to approval and review of the COMPANY.

4. CONTRACTOR shall route the proposed O/H T/L crossing such that it will
satisfy all clearance requirement. If crossing will be below the existing OH TL,
APPROVED CONTRACTOR shall provide Type-I fence around the entire gantry crossing
with two 6 meter wide drive gate with access road connected to the OH TL
BY: Cipriano S. Mauricio access road, and warning signs. Fence shall be 7 meters away from the edge of
the gantry/structure. The entire area shall be developed similar to the
DATE: July 27, 2015
requirement of TES-P-122.11.

5. CONTRACTOR shall prepare separate drawings with full details for each
crossing. Drawing shall show all vertical and horizontal clearances, elevation of
the existing conductor (including the temperature considered in the sag of the
CERTIFIED
conductor). Drawing should also show the stringing sag and tension of the
proposed conductor and OPGW/OGW.
BY: Mohammad A. Al-Saffar
6. It is the CONTRACTOR's responsibility to obtain all data and information
DATE: July 27, 2015 pertaining to the existing OH TL, existing facilities, and perform all necessary
survey works at crossing points/area. Above WORK shall be done by the
CONTRACTOR at no additional cost to the COMPANY. CONTRACTOR shall
identify the location of the line crossings, if any, in the route map.
CONTRACTOR shall propose the method of crossing subject to COMPANY‟s
approval.

7. When the proposed OHTL is crossing above the existing OHTL, and there are
THIS DOCUMENT IS
NOT TO BE USED FOR
no restrictions in spotting or locating the proposed towers, in such case, as
CONSTRUCTION OR much as possible, the existing OHTL shall be located near the middle of the
FOR ORDERING
MATERIALS UNTIL span (between the proposed towers).
CERTIFIED AND DATED

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
37
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

8. Reviewer (COMPANY) shall review the method submitted by the


CHK’D

CONTRACTOR considering all the above requirements and the security and
importance of each line crossing.

F. CONTRACTOR shall check the conductor/insulator clearances to the tower body of


the drawings provided by the COMPANY. If necessary, the tower shall be modified
DESCRIPTION

to provide the required clearances.

G. Conduct soil investigation and soil resistivity test at every location of the proposed
structures.

H. Live line washing accessories are not required, however, one (1) level platform
located at the mid cross arms shall be provided when overhead transmission line
tower height is more than 65 meters or higher.
NO.

REVISIONS
I. CONTRACTOR shall coordinate with MODA, Saudi Aramco and other concerned
authorities if spherical markers, conductor lights and warming lights (beacon lights),
tower painting (red and white) within the vicinity of airports and airstrips are
DEPT.: EHV-EDD/ESD required. Such requirement shall be installed by the CONTRACTOR if required in
accordance with the requirements of TES-P-122.01 and 12-TMSS-03.
PREP. BY: ROL

DATE: July 27, 2015 J. Manufacturer shall carry out the analytical damping study for the phase conductor
and OPGW for the proposed dampers based on the design data specified for this
T/L and in accordance with the requirements of 12-TMSS-01 and TES-P-122.04,
and submit to the COMPANY for review and approval.

K. The location/routing of the proposed 380kV overhead transmission lines are shown
APPROVED
in drawings TCD-E0390, TCD-E0396, TCD-E0401, TCD-E0443. CONTRACTOR
shall conduct all survey WORKS and shall prepare all Plan and Profile drawings.
Survey and Plan and Profile drawings shall be from the gantry of the source BSP to
the gantry of the destination BSP/Transition Yard. PI numbering shall start from the
BY: Cipriano S. Mauricio

DATE: July 27, 2015 gantry of the source station and increase towards the destination station. Survey
shall include all crossing points and the elevations of all existing lines that will be
crossed.

L. The following WORKS are included, but not limited to the following:
CERTIFIED
1. Mobilization.
2. Soil investigation and soil resistivity measurements.
BY: Mohammad A. Al-Saffar 3. Line route survey checks and structures staking.
DATE: July 27, 2015
4. Development of Plan and Profile drawings.
5. Structure spotting.
6. Design, fabrication, and erection of latticed steel tower.
7. Design, construction, and testing of foundations for latticed steel tower.
8. Conductor and OPGW/OGW field vibration measurements in accordance with
the requirements of 12-TMSS-01.
9. Supply, procurement, inspection, testing, storage, handling of all the required
material and equipment.
THIS DOCUMENT IS 10. Transportation, delivery, and storage of all materials to the WORK SITE.
NOT TO BE USED FOR
CONSTRUCTION OR 11. Construction of access roads and structure pads along the proposed overhead
transmission lines.
FOR ORDERING
MATERIALS UNTIL
CERTIFIED AND DATED
12. Installation of insulators and associated hardware and fittings.

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
38
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

13. Installation of conductors and all necessary associated hardware and


CHK’D

accessories.
14. Supply, installation and testing of OPGW/OGW, U/G non-metallic fiber optic
cables, joint boxes and all necessary associated hardware and accessories.
15. Installation and testing of structure‟s grounding system.
16. Conduct line impedance measurements to determine the positive and zero
DESCRIPTION

sequence of the transmission line in coordination with the COMPANY


REPRESENTATIVE, and result shall be furnished to the COMPANY.
17. Tower and foundation testing if required, shall be witnessed by two (2) designated
COMPANY REPRESENTATIVES at the full expense of the CONTRACTOR.
CONTRACTOR shall submit the load test procedure for COMPANY review and
approval.
18. Testing and commissioning.
NO.

19. Demobilization and clean up.


3

REVISIONS
M. Refer to Appendix VI for the requirement of the communication WORKS.

N. CONTRACTOR shall provide and install signboard with electronic counter. Refer to
DEPT.: EHV-EDD/ESD drawing no. ET-907744 for the Scope of Work and specifications. CONTRACTOR
shall install the signboard within thirty days (30) from the project start date. The
PREP. BY: ROL
Electronic Counter shall show the number of days remaining for the project
DATE: July 27, 2015
completion”. Separate signboard shall be provided for each line. The number of
signboards shall be determined in consultation with the COMPANY.

O. All removed and dismantled materials shall be transported by the CONTRACTOR to


one of the COMPANY warehouses as specified by the COMPANY
REPRESENTATIVE. The removed hardware shall be kept inside wooden box,
APPROVED labeled with its quantities and material descriptions. Conductors and OPGW shall
be reeled on cable reels and labeled with its length and material description.
BY: Cipriano S. Mauricio
CONTRACTOR shall provide the cable reels and boxes. CONTRACTOR shall
prepare all the necessary documentations for turnover of materials to the
DATE: July 27, 2015
COMPANY designated warehouse.

P. CONTRACTOR shall strictly comply with the requirements of the Right of Way
approvals. CONTRACTOR shall comply with the following.

1. It is the responsibility of the CONTRACTOR to coordinate with MOT, MODA,


Municipality, SAUDI ARAMCO and other concerned agencies to obtain the
CERTIFIED

necessary approvals and work permits.


BY: Mohammad A. Al-Saffar

DATE: July 27, 2015 2. CONTRACTOR shall provide interference free access for the COMPANY
maintenance personnel, SAUDI ARAMCO and other concerned personnel.

3. CONTRACTOR shall ensure strict compliance to the approval conditions of the


MOT, MODA, Municipality, SAUDI ARAMCO and other concerned agencies.

4. CONTRACTOR shall protect the existing facilities/utilities and shall be


responsible for repairing any damage to the existing facilities/utilities including,
THIS DOCUMENT IS but not limited to, roads, buried telephone cables, underground water/sewage
NOT TO BE USED FOR
CONSTRUCTION OR lines, underground pipelines, underground power cables etc. at no cost to the
FOR
MATERIALS
ORDERING
UNTIL
COMPANY if such damage is caused during the course of execution by the
CERTIFIED AND DATED CONTRACTOR or his SUB-CONTRACTOR. CONTRACTOR shall verify the
exact locations of these facilities.

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
39
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

5. CONTRACTOR shall protect and relocate (if necessary) all utilities, which may
CHK’D

be uncovered or otherwise, are affected by the WORK. The CONTRACTOR


shall exercise caution, familiarize himself, and investigate the WORKSITE
thoroughly prior to the actual commencement of WORK.

If any utility is encountered unexpectedly, the COMPANY REPRESENTATIVE


DESCRIPTION

shall be notified immediately. Emergency rectification WORK as deemed


necessary shall be put in hand without delay and without prejudice to the
indemnity of the COMPANY.

6. The WORK within the jurisdiction of related agencies should be carried out
under the supervision of their representatives.

7. It is the responsibility of the CONTRACTOR to visit the WORKSITE and to


NO.

REVISIONS satisfy himself as to the extent of WORK location and all the condition under
which the WORK will be carried out. No claims based on the lack of any such
knowledge shall be entertained.

DEPT.: EHV-EDD/ESD 8. Approval of final location of spotted structures on the transmission line route
drawings shall be obtained from MOT, MODA, Municipality,, SAUDI ARAMCO
PREP. BY: ROL and other concerned agencies in writing prior to commencement of WORK.
DATE: July 27, 2015 Any changes or deviations from the approval condition stated in the approved
letters shall be specifically approved by the MOT, MODA, Municipality, SAUDI
ARAMCO and the concerned agency.

9. CONTRACTOR shall avoid the location of structures at the intersection of


existing roads, existing/proposed roads and at the cuts/opening in the proposed
APPROVED
roads. The final layout of proposed roads if any shall be considered during the
time of execution. It is the responsibility of the CONTACTOR to coordinate and
ascertain with MOT, MODA, Municipality, SAUDI ARAMCO and other
BY: Cipriano S. Mauricio
concerned agencies during the implementation/construction stage.
DATE: July 27, 2015

Q. The CONTRACTOR shall prepare the overhead transmission line drawings


including separate drawing control sheet for the O/H T/L as described below. All
existing 380kV O/H T/L drawings shall remain including its Drawing Control Sheet.

1. 380kV Double Circuit O/H T/L between Juaymah BSP to Dhahran Home
CERTIFIED
Ownership BSP:

BY: Mohammad A. Al-Saffar CONTRACTOR shall prepare the complete As Built drawings from Juaymah
DATE: July 27, 2015
BSP to Dhahran Home Ownership BSP. The existing drawings (such as string
insulators, foundations, erection & fabrication of towers, conductors, etc) of
Jubail Residential BSP (Fadhili)-Juaymah BSP 380kV O/H T/L related to the
proposed 380kV OHTL shall be included and assigned with new drawing
number. Design drawings, calculations and drawings listed under Section 3.03
shall be included under this line circuit. The CONTRACTOR shall acquire all
necessary information required to complete the drawings. CONTRACTOR shall
coordinate with the COMPANY. All existing drawings which are to be included
THIS DOCUMENT IS under this line circuit not drawn to SEC Standard requirements shall be re
NOT TO BE USED FOR
CONSTRUCTION OR drawn by the CONTRACTOR.
FOR ORDERING
MATERIALS UNTIL
CERTIFIED AND DATED 2. 380kV Double Circuit O/H T/L between Dhahran Home Ownership BSP to
Dhahran South Transition Yard:

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
40
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95
CERT.
SAUDI ELECTRICITY COMPANY ‫الشركة السعودية للكهرباء‬
APP’D

CONTRACTOR shall prepare the complete As Built drawings from Dhahran


CHK’D

Home Ownership BSP to Dhahran South Transition Yard. Design drawings,


calculations and drawings listed under Section 3.03 shall be included under this
line circuit. The CONTRACTOR shall acquire all necessary information required
to complete the drawings. CONTRACTOR shall coordinate with the
COMPANY. All existing drawings which are to be included under this line circuit
DESCRIPTION

not drawn to SEC Standard requirements shall be re drawn by the


CONTRACTOR.

3. 380kV Double Circuit O/H T/L between Juaymah BSP to Jubail 2 BSP:

CONTRACTOR shall prepare the complete As Built drawings from Jubail 2 to


Juaymah BSP affected by the construction of the proposed Juaymah BSP to
NO.

Dhahran Home Ownership BSP. The new drawings (such as string insulators,
3

REVISIONS foundations, erection & fabrication of towers, conductors, etc) of the new
380kV O/H T/L related to Jubail 2-Juaymah BSP 380kV OHTL shall be included
and assigned with new drawing number. Design drawings, calculations and
drawings listed under Section 3.03 shall be included under this line circuit. The
DEPT.: EHV-EDD/ESD CONTRACTOR shall acquire all necessary information required to complete
the drawings. CONTRACTOR shall coordinate with the COMPANY. All existing
PREP. BY: ROL
drawings which are to be included under this line circuit not drawn to SEC
DATE: July 27, 2015
Standard requirements shall be re drawn by the CONTRACTOR..
CONTRACTOR shall coordinate with SEC when preparing the As Built
drawings. New drawing control sheet shall be prepared by the CONTRACTOR.

4. 380kV Double Circuit O/H T/L between Juaymah BSP to Jubail Residential
BSP (Fadhili):
APPROVED

CONTRACTOR shall prepare the complete As Built drawings from Jubail


BY: Cipriano S. Mauricio Residential BSP (Fadhili) to Juaymah BSP affected by the construction of the
proposed Juaymah BSP to Dhahran Home Ownership BSP. The new drawings
DATE: July 27, 2015
(such as string insulators, foundations, erection & fabrication of towers,
conductors, etc) of the new 380kV O/H T/L related to Jubail Residential BSP-
Juaymah BSP 380kV OHTL shall be included and assigned with new drawing
number. Design drawings, calculations and drawings listed under Section 3.03
shall be included under this line circuit. The CONTRACTOR shall acquire all
CERTIFIED
necessary information required to complete the drawings. CONTRACTOR shall
coordinate with the COMPANY. All existing drawings which are to be included
under this line circuit not drawn to SEC Standard requirements shall be re
BY: Mohammad A. Al-Saffar
drawn by the CONTRACTOR. CONTRACTOR shall coordinate with SEC when
DATE: July 27, 2015 preparing the As Built drawings. New drawing control sheet shall be prepared
by the CONTRACTOR.

3.02 COMMUNICATION WORK

Refer to Appendix VI
THIS DOCUMENT IS
NOT TO BE USED FOR
CONSTRUCTION OR
FOR ORDERING
MATERIALS UNTIL
CERTIFIED AND DATED

PTS-14EO335 (Final), Rev. 03: ROL/CSM/MAS: (July 27, 2015)


DRAWING CONTROL SHEET CONSTRUCTION OF (1) D/C 380kV OHTL BETWEEN JUAYMAH PLANT NO. INDEX DOCUMENT NO. PAGE NO. REV.
BSP AND DHAHRAN HOME OWNERSHIP BSP AND (1) D/C
ET-914564
JOB ORDER NO.
380kV OHTL BETWEEN DHAHRAN HOME OWNERSHIP BSP
AND DHAHRAN SOUTH BSP TRANSITION YARD
41
SE0049 A PTS-14EO335 OF 03
DHAHRAN/JUAYMAH SAUDI ARABIA 95

You might also like