Estimate For Construction of RCC Retaining Wall Analysis For 1.00 M Length Wall
Estimate For Construction of RCC Retaining Wall Analysis For 1.00 M Length Wall
Estimate For Construction of RCC Retaining Wall Analysis For 1.00 M Length Wall
technical specification clause 305.1, including setting out, construction of shoring and bracing, removal
Item No.-1/11.1/305.1
of stumps and other deleterious matter, dressing of sides and bottom and backfilling with approved
material.
I. Ordinary soil, (i) Up to 3.00 m depth
Total 11.52 M3
Sand Filling in Foundation Trenches as per Drawing & Technical Specification Clause 305.3.9
Item No.-2/11.2/305.3.9
I. Sand filling
Total 2.39 M3
Total 0.34 M3
Total 1.44 M3
@ Rs. 6,113.00 / M3 Rs. 8,802.72
Plain/Reinforced cement concrete in Substructure complete as per drawing and technical specification
Total 1.56 M3
Reinforcement in Foundation: Supplying, fitting and placing HYSD bar reinforcement in foundation
complete as per drawing and technical specifications clause 1000 & 1202
Total 0.11 MT
Total 0.21 MT
(Rupees Forty Seven Thousand Four Hundred Forty Five and Sixty Four Paise ) Only
Asstt. Executive Engineer, P.W.D.
Executive Engineer, P.W.D.
Silchar Rural Road Sub Division-II Silchar Rural Road Division